Department of Energy
Federal Energy Regulatory Commission
- [Project No. 2756-068]
Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2756-068.
c. Date Filed: October 30, 2026.
d. Applicant: Burlington Electric Department (Burlington).
e. Name of Project: Chace Mill Hydroelectric Project.
f. Location: The project is located on the Winooski River in the cities of Burlington and Winooski in Chittenden County, Vermont.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: James Gibbons, Director of Policy and Planning, Burlington Electric Department, 585 Pine Street, Burlington, VT 05401; telephone at (802) 658-0300; email at jgibbons@burlingtonelectric.com.
i. FERC Contact: Joshua Dub, Project Coordinator, Great Lakes Branch, Division of Hydropower Licensing; telephone at (202) 502-8138; email at Joshua.Dub@ferc.gov.
j. The application is not ready for environmental analysis at this time.
k. Project Description: The project includes an approximately 252.6-foot-long, 29-foot-high dam that includes two spillway sections that are overtopped with inflatable rubber crest gates with maximum crest elevations of 136 feet National Geodetic Vertical Datum of 1929 (NGVD 29) and a powerhouse that includes an intake structure with a trashrack with 0.8-inch clear bar spacing for the upper 8 feet of the trashrack and 2-inch clear bar spacing on the bottom section, and three 2.485-MW Kaplan turbine-generator units, for a total installed capacity of 7.455 MW.
The dam creates an impoundment that has a normal surface area of 6.7 acres at 136.0 feet NGVD 29. From the impoundment, water flows through the powerhouse to a 190-foot-long tailrace, where it returns to the Winooski River. Water also flows through the intake structure to a downstream fishway that includes a collection chamber behind the trashracks and a 3-foot-diameter pipe that discharges to the tailrace on the east side of the powerhouse. The project creates an approximately 230-foot-long bypassed reach of the Winooski River.
The project includes an upstream fish passage facility that consists of a trap and truck facility with a concrete fish lift located on the west side of the powerhouse. Project recreation facilities include: (1) an approximately 660-foot-long paved walkway on the north shoreline of the impoundment; (2) an approximately 745-foot-long public access trail on the north shoreline of the Winooski River, to the west of the project dam; and (3) a public access and overlook area on top of the powerhouse. The project includes a 200-foot-long access road on the northern bank of the impoundment.
Electricity generated at the project is transmitted to the electric grid via an underground 400-foot-long, 13.8-kilovolt transmission line.
l. Locations of the Application: A copy of the application may be viewed on the Commission's website at www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). A copy is also available for inspection and reproduction at the address in item h above.
m. You may also register online at ferconline.ferc.gov/​eSubscription.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.
n. For public inquiries and assistance with making filings such as interventions, comments, or requests for ( printed page 73575) rehearing, contact the Office of Public Participation at (202) 502-6595 or OPP@ferc.gov.
o. Procedural Schedule: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate.
| Milestone | Target date |
|---|---|
| Notice of Acceptance/Notice of Ready for Environmental Analysis | May 2027. |
| Filing of recommendations, preliminary terms and conditions, and fishway prescriptions | July 2027. |
p. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.
(Authority: 18 CFR 2.1)
Dated: November 10, 2026.
Carlos D. Clay,
Deputy Secretary.