Air Plan Approval; Arkansas; Update to Materials Incorporated by Reference

The Environmental Protection Agency (EPA) is updating the materials that are incorporated by reference (IBR) into the Arkansas State Implementation Plan (SIP). The regulations a...

Environmental Protection Agency
  1. 40 CFR Part 52
  2. [EPA-R06-OAR-2026-8383; FRL-13644-01-R6]

AGENCY:

Environmental Protection Agency (EPA).

ACTION:

Final rule; administrative change.

SUMMARY:

The Environmental Protection Agency (EPA) is updating the materials that are incorporated by reference (IBR) into the Arkansas State Implementation Plan (SIP). The regulations affected by this update have been previously submitted by the State of Arkansas and approved by the EPA. This update affects the materials that are available for public inspection at the EPA Regional Office and the National Archives and Records Administration.

DATES:

This rule is effective on November 20, 2026.

( printed page 75220)

ADDRESSES:

The SIP materials for which incorporation by reference into 40 Code of Federal Regulations (CFR) part 52 is finalized through this action are available for inspection at the following locations: Environmental Protection Agency, Region 6, 1201 Elm Street, Suite 500, Dallas, TX 75202; and on the www.regulations.gov website at Docket ID: EPA-R06-OAR-2026-8383.

FOR FURTHER INFORMATION CONTACT:

Adina Wiley, EPA Region 6 Office, Air Permits Section; telephone number: (214) 665-2115; email address: .

SUPPLEMENTARY INFORMATION:

Throughout this document “we,” “us,” and “our” means the EPA. We use multiple abbreviations and terms in this proposed rule. While this list may not be exhaustive, for ease of reading and for reference purposes, the EPA defines the following terms and acronyms here:

APA—Administrative Procedures Act

CAA—Clean Air Act

CFR—Code of Federal Regulations

IBR—Incorporation by Reference

NAAQS—National Ambient Air Quality Standards

SIP—State Implementation Plan

Table of Contents

I. Executive Summary

A. What action is the EPA taking?

B. What is the legal authority and what are the requirements?

II. Background

III. Incorporation by Reference

IV. Statutory and Executive Order Reviews

I. Executive Summary

A. What action is the EPA taking?

In this action, the EPA is providing notification of an update to the materials incorporated by reference into the Arkansas SIP as of September 30, 2026, and identified in 40 CFR 52.170(c) and 40 CFR 52.170(d). This update includes SIP materials submitted by Arkansas and approved by the EPA since the most recent Arkansas SIP Compilation completed March 16, 2006.[1]

B. What is the legal authority and what are the requirements?

The EPA has determined that this action falls under the “good cause” exemption in section 553(b)(3)(B) of the Administrative Procedure Act (APA) which, upon finding “good cause,” authorizes agencies to dispense with public participation and APA section 553(d)(3) which allows an agency to make an action effective immediately (thereby avoiding the 30-day delayed effective date otherwise provided for in the APA). This administrative action simply codifies provisions which are already in effect as a matter of law in Federal and approved State programs, makes corrections and clarifying changes to the tables in the CFR, and makes ministerial changes to the prefatory heading to the tables in the CFR. Under section 553 of the APA, an agency may find good cause where procedures are “impracticable, unnecessary, or contrary to the public interest.” Public comment for this administrative action is “unnecessary” and “contrary to the public interest” since the codification (and corrections) only reflect existing law. Immediate notice of this action in the Federal Register benefits the public by providing the public notification of the updated Arkansas SIP Compilation and notification of corrections to the Arkansas “Identification of Plan” portion of the CFR. Further, pursuant to APA section 553(d)(3), making this action immediately effective benefits the public by immediately updating both the SIP Compilation and the CFR “Identification of plan” section (which includes table entry corrections).

II. Background

Each State has a SIP containing the control measures and strategies used to attain and maintain the national ambient air quality standards (NAAQS) and meet other Clean Air Act requirements. The SIP is extensive, containing such elements as air pollution control regulations, emission inventories, monitoring networks, attainment demonstrations, and enforcement mechanisms.

Each State must formally adopt the control measures and strategies in the SIP after the public has had an opportunity to comment on them and then submit the proposed SIP revisions to the EPA. Once these control measures and strategies are approved by the EPA, and after notice and comment, they are incorporated into the federally approved SIP and are identified in part 52, “Approval and Promulgation of Implementation Plans,” of title 40 of the Code of Federal Regulations (40 CFR part 52). The full text of the State regulation approved by the EPA is not reproduced in its entirety in 40 CFR part 52 but is “incorporated by reference.” This means that the EPA has approved a given State provision or specified changes to the given provision with a specific effective date. The public is referred to the location of the full text version should they want to know which measures are contained in a given SIP. The information provided allows the EPA and the public to monitor the extent to which a State implements a SIP and to take enforcement action for violations of the SIP.

The SIP is a living document which the State can revise as necessary to address the unique air pollution problems in the State. Therefore, the EPA from time to time must take action on proposed revisions containing new or revised State regulations. A submission from a State can revise one or more rules in their entirety, or portions of rules. The State indicates the changes in the submission (such as by using redline/strikethrough text) and the EPA then takes action on the requested changes. The EPA establishes a docket for its actions using a unique Docket Identification Number, which is listed in each action. These dockets and the complete submission are available for viewing on www.regulations.gov.

On May 22, 1997 (62 FR 27968), the EPA revised the procedures for incorporating by reference, into the CFR, materials approved by the EPA into each SIP. These changes revised the format for the identification of the SIP in 40 CFR part 52, streamlined the mechanisms for announcing the EPA approval of revisions to a SIP, and streamlined the mechanisms for the EPA's updating of the IBR information contained for each SIP in 40 CFR part 52. The revised procedures also called for the EPA to maintain “SIP Compilations” that contain the federally approved regulations and source specific permits submitted by each State agency.

The EPA generally updates these SIP Compilations every few years. Under the revised procedures, the EPA must periodically publish an informational document in the rules section of the Federal Register notifying the public that updates have been made to a SIP Compilation for a particular State. The EPA began applying the 1997 revised procedures to the Arkansas SIP on October 23, 1998 (63 FR 56824). The most recent SIP Compilation update was approved on March 16, 2006 (71 FR 13543). This update includes SIP materials submitted by Arkansas and approved by EPA since the March 16, 2006, SIP Compilation update.

III. Incorporation by Reference

In this rule, the EPA is finalizing regulatory text that includes incorporation by reference. In accordance with requirements of 1 CFR 51.5, the EPA is finalizing the incorporation by reference of previously EPA-approved regulations promulgated by Arkansas and federally effective prior to September 30, 2026. The EPA has ( printed page 75221) made, and will continue to make, these materials generally available through www.regulations.gov and at the EPA Region 6 Office (please contact the person identified in the FOR FURTHER INFORMATION CONTACT section of this preamble for more information).

V. Statutory and Executive Order Reviews

Under the Clean Air Act, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable Federal regulations (42 U.S.C. 7410(k); 40 CFR 52.02(a)). Thus, in reviewing SIP submissions, the EPA's role is to approve State choices, provided that they meet the criteria of the Clean Air Act. Accordingly, this action merely approves State law as meeting Federal requirements and does not impose additional requirements beyond those imposed by State law. For that reason, this action:

In addition, the SIP is not approved to apply on any Indian reservation land or in any other area where the EPA or an Indian Tribe has demonstrated that a Tribe has jurisdiction. In those areas of Indian country, the rule does not have Tribal implications and will not impose substantial direct costs on Tribal governments or preempt Tribal law as specified by Executive Order 13175 (65 FR 67249, November 9, 2000).

This action is subject to the Congressional Review Act, and the EPA will submit a rule report to each House of the Congress and to the Comptroller General of the United States. This action is not a “major rule” as defined by 5 U.S.C. 804(2).

The EPA also believes that the provisions of section 307(b)(1) of the CAA pertaining to petitions for judicial review are not applicable to this action. This is because prior EPA rulemaking actions for each individual component of the Arkansas SIP Compilation previously afforded interested parties the opportunity to file a petition for judicial review in the United States Court of Appeals for the appropriate circuit within 60 days of such rulemaking action. Thus, the EPA believes judicial review of this action under CAA section 307(b)(1) is not available.

List of Subjects in 40 CFR Part 52

  • Environmental protection
  • Air pollution control
  • Carbon monoxide
  • Incorporation by reference
  • Intergovernmental relations
  • Lead
  • Nitrogen dioxide
  • Ozone
  • Particulate matter
  • Reporting and recordkeeping requirements
  • Sulfur oxides
  • Volatile organic compounds

Dated: November 9, 2026.

Walter Mason,

Regional Administrator, Region 6.

For the reasons stated in the preamble, the Environmental Protection Agency amends 40 CFR part 52 as follows:

PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS

1. The authority citation for part 52 continues to read as follows:

Authority: 42 U.S.C. 7401 et seq.

Subpart E—Arkansas

2. Amend § 52.170 by revising and republishing paragraphs (b) through (d) to read as follows:

Identification of plan.
* * * * *

(b) Incorporation by reference. (1) Material listed in paragraphs (c) and (d) of this section with an EPA approval date prior to September 30, 2026, was approved for incorporation by reference by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. Material is incorporated as it exists on the date of the approval, and notice of any change in the material will be published in the Federal Register . Entries in paragraphs (c) and (d) of this section with EPA approval dates after September 30, 2026, will be incorporated by reference in the next update to the SIP compilation.

(2) EPA Region 6 certifies that the rules/regulations provided by the EPA in the SIP compilation at the addresses in paragraph (b)(3) of this section are an exact duplicate of the officially promulgated State rules/regulations that have been approved as part of the State Implementation Plan as of the dates referenced in paragraph (b)(1) of this section.

(3) Copies of the materials incorporated by reference may be inspected at the Environmental Protection Agency, Region 6 Office at 1201 Elm Street, Suite 500, Dallas, Texas 75270. If you wish to obtain material from the EPA Regional Office, please call (214) 665-7346. You may inspect the material with an EPA approval date prior to September 30, 2026, for Arkansas at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA email or go to www.archives.gov/​federal-register/​cfr/​ibr-locations.

(c) EPA approved regulations. ( printed page 75222)

EPA-Approved Regulations in the Arkansas SIP

State citation Title/subject State submittal/ effective date EPA approval date Explanation
Title 8. Environmental Law
Chapter I. Arkansas Pollution Control and Ecology Commission, Department of Energy and Environment
Subchapter B. Administration
Part 12. Permit Fee Rules
Subpart 1. General Provisions
8 CAR Section 12-101 Title 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-102 Purpose 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-103 Definitions 02/04/2025 01/26/2026, 91 FR 3037 The Arkansas SIP does NOT include the definitions of “Category”, “Certificate”, “Confined Animal Operation”, “Discretionary Major Facility”, “Evaluation”, “Laboratory”, “Major Municipal Facility”, “Non-Municipal Major Facility”, “Parameter”, and “Program”.
8 CAR Section 12-104 Applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-105 Severability 02/04/2025 01/26/2026, 91 FR 3037
Subpart 2. Permit Fee Payment
8 CAR Section 12-201 Permit fee payment 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-202 Refunds 02/04/2025 01/26/2026, 91 FR 3037
Subpart 4. Air Permit Fees
8 CAR Section 12-401 Applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-402 Terms used in fee formulas 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-403 Initial fees 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-404 Annual fees 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-405 Modification fees 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-406 Administrative permit amendments and renewal permits 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-407 General permits 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-408 Permit fees for certain small business subject to part 70 permitting requirements 02/04/2025 01/26/2026, 91 FR 3037
Subpart 8. Administrative Procedures
8 CAR Section 12-801 Division review of fees 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-802 Appeals 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 12-803 Effective date 02/04/2025 01/26/2026, 91 FR 3037
( printed page 75223)
Subchapter D. Air Quality
Part 41. Rules of the Arkansas Plan of Implementation for Air Pollution Control
Subpart 1. Title, Intent and Purpose—Definitions
8 CAR Section 41-101 Title 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-102 Applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-103 Intent and construction 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-104 Severability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-105 Incorporation by reference 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-106 Definitions 02/04/2025 01/26/2026, 91 FR 3037
Subpart 2. Protection of the National Ambient Air Quality Standards
8 CAR Section 41-201 Purpose 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-202 Division responsibilities 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-203 Regulated sources responsibilities 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-204 Delegated federal programs 02/04/2025 01/26/2026, 91 FR 3037
Subpart 3. Minor Source Review
8 CAR Section 41-301 General applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-302 Approval criteria 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-303 Owner/operator's responsibilities 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-304 Required information 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-305 Action on application 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-306 Public participation 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-307 Permit amendments 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-308 Exemption from permitting 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-309 [Reserved] 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-310 Permit revocation and cancellation 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-311 General permits 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-312 Dispersion modeling 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-313 Confidentiality 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-314 Operational flexibility—Applicant's duty to apply for alternative scenarios 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-315 Changes resulting in no emissions increases 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-316 Permit flexibility 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-317 Registration 02/04/2025 01/26/2026, 91 FR 3037
( printed page 75224)
Subpart 4. General Emissions Limitations Applicable to Equipment
8 CAR Section 41-401 Purpose 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-402 General rules 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-403 Visible emission rules 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-404 Stack height/dispersion rules 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-405 Revised emissions limitation 02/04/2025 01/26/2026, 91 FR 3037
Subpart 5. Upset and Emergency Conditions
8 CAR Section 41-501 Upset conditions 02/04/2025 01/26/2026, 91 FR 3037
Subpart 6. Sampling, Monitoring, and Reporting Requirements
8 CAR Section 41-601 Purpose 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-602 Air emissions sampling 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-603 Continuous emissions monitoring 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-604 Notice of completion 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-605 Recordkeeping and reporting requirements 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-606 Public availability of emissions data 02/04/2025 01/26/2026, 91 FR 3037
Subpart 8. Prevention of Significant Deterioration Rules of the Arkansas Plan of Implementation for Air Pollution Control
8 CAR Section 41-801 Title 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-802 Purposes 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-803 Definitions 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-804 Adoption of rules 02/04/2025 01/26/2026, 91 FR 3037
Subpart 9. Rules for the Control of Volatile Organic Compounds in Pulaski County
8 CAR Section 41-901 Title 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-902 Purpose 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-903 Definitions 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-904 [Reserved] 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-905 Provisions for specific processes 02/04/2025 01/26/2026, 91 FR 3037
Subpart 10. Major Source Permitting Requirements
8 CAR Section 41-1001 Permitting procedure for part 70 source 02/04/2025 01/26/2026, 91 FR 3037
Subpart 12. Stage 1 Vapor Recovery
8 CAR Section 41-1201 Purpose 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1202 Applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1203 Definitions 02/04/2025 01/26/2026, 91 FR 3037
( printed page 75225)
8 CAR Section 41-1204 Exemptions 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1205 Prohibited activities 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1206 Recordkeeping 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1207 Inspections 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1208 Vapor recovery systems 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1209 Gasoline delivery vessels 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1210 Owner/operator responsibility 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1211 Test methods 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1212 Effective date 02/04/2025 01/26/2026, 91 FR 3037
Subpart 13. [Reserved]
Subpart 14. Best Available Retrofit Technology
8 CAR Section 41-1401 Purpose 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1402 Definitions 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1403 [Reserved] 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1404 [Reserved] 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Sectio 41-1405 Best available retrofit technology requirements 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 41-1406 Compliance provisions 02/04/2025 01/26/2026, 91 FR 3037
Subpart 15. [Reserved]
Subpart 17. Effective Date
8 CAR Section 41-1701 Effective Date 02/04/2025 01/26/2026, 91 FR 3037
Appendix A. Insignificant Activities List
8 CAR Section 41, Appendix A Insignificant Activities List 02/04/2025 01/26/2026, 91 FR 3037
Appendix B. National Ambient Air Quality Standards List
8 CAR Section 41, Appendix B National Ambient Air Quality Standards List 02/04/2025 01/26/2026, 91 FR 3037
Part 42. Rules of the Arkansas Operating Air Permit Program
Subpart 2. Requirement for a Permit—Applicability
8 CAR Section 42-201 Requirement for a permit 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 42-202 Sources subject to permitting 02/04/2025 01/26/2026, 91 FR 3037
Subpart 3. Applications for Permits
8 CAR Section 42-301 Duty to apply 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 42-302 Standard application form and required information 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 42-307 Complete application 02/04/2025 01/26/2026, 91 FR 3037
( printed page 75226)
8 CAR Section 42-309 Applicant's duty to supplement or correct application 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 42-310 Certification by responsible official 02/04/2025 01/26/2026, 91 FR 3037
Subpart 4. Action on Applications
8 CAR Section 42-401 Action on part 70 permit applications 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 42-402 Final action on permit application 02/04/2025 01/26/2026, 91 FR 3037
Subpart 5. Permit Review by the Public, Affected States, and the Environmental Protection Agency
8 CAR 42-501 Applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 42-502 Public participation 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 42-503 Transmission of permit information to the Administrator of the Environmental Protection Agency 02/04/2025 01/26/2026, 91 FR 3037
8 CAR 42-504 Review of draft permit by affected states 02/04/2025 01/26/2026, 91 FR 3037
Part 43. Nonattainment New Source Review Requirements
Subpart 1. General Provisions
8 CAR Section 43-101 Title 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-102 Applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-103 Severability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-104 Definitions 02/04/2025 01/26/2026, 91 FR 3037
Subpart 2. Preconstruction Review
8 CAR Section 43-201 Requirement for a permit 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-202 Required information 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-203 Approval criteria 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-204 Offsets 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-205 Zones targeted for economic development 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-206 Control technology information 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-207 Approval to construct 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-208 Applicability to attainment or unclassifiable areas 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-209 Applicability of other rules 02/04/2025 01/26/2026, 91 FR 3037
Subpart 3. Applicability Tests
8 CAR Section 43-301 Actual-to-projected actual applicability test 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-302 Actual-to-potential test 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-303 [Reserved] 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-304 [Reserved] 02/04/2025 01/26/2026, 91 FR 3037
( printed page 75227)
8 CAR Section 43-305 Emission baseline credits 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-306 Relaxation of limitations 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-307 Modification to existing units 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-308 Public availability of information 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-309 Applicability to nitrogen oxides 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-310 Offset requirements 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-311 PM 10 precursors 02/04/2025 01/26/2026, 91 FR 3037
Subpart 4. [Reserved]
Subpart 5. [Reserved]
Subpart 6. [Reserved]
Subpart 7. Actual PALs
8 CAR Section 43-701 Applicability 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-702 Definitions 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-703 Permit application requirements 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-704 General requirements for establishing PALs 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-705 Public participation requirement for PALs 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-706 Setting the ten-year actuals PAL level 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-707 Contents of the PAL permit 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-708 Reopening of the PAL permit 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-709 PAL effective period 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-710 Expiration of a PAL 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-711 Renewal of a PAL 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-712 Increasing a PAL during the PAL effective period 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-713 Monitoring requirements for PALs 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-714 Recordkeeping requirements 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-715 Reporting and notification requirements 02/04/2025 01/26/2026, 91 FR 3037
8 CAR Section 43-716 Transition requirements 02/04/2025 01/26/2026, 91 FR 3037
Subpart 8. Effective Date
8 CAR Section 43-801 Effective Date 02/04/2025 01/26/2026, 91 FR 3037

(d) EPA-approved State source-specific requirements. ( printed page 75228)

EPA-Approved Arkansas Source-Specific Requirements

Name of source Permit or order No. State approval/ effective date EPA approval date Comments
Arkansas Electric Cooperative Corporation Carl E. Bailey Generating Station Administrative Order LIS No. 18-071 08/07/2018 09/27/2019, 84 FR 51033 Unit 1.
Arkansas Electric Cooperative Corporation John L. McClellan Generating Station Administrative Order LIS No. 18-071 08/07/2018 09/27/2019, 84 FR 51033 Unit 1.
Southwestern Electric Power Company Flint Creek Power Plant Administrative Order LIS No. 18-072 08/07/2018 09/27/2019, 84 FR 51033 Unit 1.
Entergy Arkansas, Inc. Lake Catherine Plant Administrative Order LIS No. 18-073 08/07/2018 09/27/2019, 84 FR 51033 Unit 4.
Entergy Arkansas, Inc. White Bluff Plant Administrative Order LIS No. 18-073 08/07/2018 09/27/2019, 84 FR 51033 Units 1, 2, and Auxiliary Boiler.
Entergy Arkansas, Inc. Independence Plant Administrative Order LIS No. 18-073 08/07/2018 09/27/2019, 84 FR 51033 Units 1 and 2.
Domtar Ashdown Mill Permit #0287-AOP-R22 08/01/2019 03/22/2021, 86 FR 15104 Approval of plantwide conditions 32 to 43 of section VI from the permit, addressing emission limits for SO 2 , NO X , and PM 10 and conditions for implementing the BART alternative for Power Boilers No. 1 and 2.
FutureFuel Chemical Company Administrative Order LIS No. 22-085 08/03/2022 08/27/2026, 91 FR 55268 Three boiler system (SN:6M01-01).
* * * * *

Footnotes

1.  71 FR 13543 (Mar. 16, 2006).

Back to Citation

[FR Doc. 2026-23686 Filed 11-19-26; 8:45 am]

BILLING CODE 6560-50-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

91 FR 75219

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Air Plan Approval; Arkansas; Update to Materials Incorporated by Reference,” thefederalregister.org (November 20, 2026), https://thefederalregister.org/documents/2026-23686/air-plan-approval-arkansas-update-to-materials-incorporated-by-reference.