Department of Energy
Federal Energy Regulatory Commission
- [Docket No. CP26-556-000]
On July 22, 2026, Tres Palacios Gas Storage LLC (Tres Palacios) filed an application in Docket No. CP26-556-000, requesting Authorization pursuant to Section 7(c) of the Natural Gas Act to construct and operate the Tres Palacios Smith Cavern Expansion Project ( printed page 75852) (Project) that would add approximately 24.8 billion cubic feet of new working gas capacity and increase injection capabilities at the Tres Palacios Gas Storage Facility. The proposed Project would be located in Matagorda and Wharton Counties, Texas.
On July 31, 2026, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff's environmental document for the Project.
This notice identifies Commission staff's intention to prepare an environmental assessment (EA) for the Project and the planned schedule for the completion of the environmental review.[1]
Schedule for Environmental Review
Issuance of EA—February 26, 2027
90-day Federal Authorization Decision Deadline [2] —May 27, 2027
If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project's progress.
Project Description
Tres Palacios proposes to construct and operate (1) three new natural gas salt dome storage caverns, by converting three existing brine caverns, with a total working gas capacity of approximately 24.8 billion cubic feet (Bcf) and a base gas capacity of approximately 8.93 Bcf, equaling a total capacity of approximately 33.73 Bcf (Smith Caverns 5, 6, and 7); (2) 5.4 miles of new 36-inch-diameter pipeline loop; (3) three 1.7-mile-long, 16-inch-diameter pipeline cavern laterals; (4) the new El Campo Compressor Station, including four 5,500 horsepower (hp) reciprocating compressor units; (5) additional facilities at the existing Tres Palacios Gas Storage Facility, including three new 5,500 hp reciprocating compressor units, a new compressor building, six cooling bays, and one gas dehydration system; (6) modifications at three existing metering and regulation stations; and (7) associated appurtenant facilities, all located in Matagorda and Wharton Counties, Texas.
Background
On September 22, 2026, the Commission issued a Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Tres Palacios Smith Cavern Expansion Project (Notice of Scoping). The Notice of Scoping was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties; and local libraries and newspapers. We received comments from the U.S. Environmental Protection Agency (EPA) Region 6 and from a member of the public.
EPA's comments addressed water quality; National Pollutant Discharge Elimination System permit coverage, Clean Water Act section 402; and effects of construction on groundwater. The primary issues raised by the public include potential effects on ecosystems, water resources, vegetation, threatened and endangered species, air quality, and operational noise. All substantive comments will be addressed in the EA.
Additional Information
In order to receive notification of the issuance of the EA and to keep track of formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This service provides automatic notification of filings made to subscribed dockets, document summaries, and direct links to the documents. Go to www.ferc.gov/ferc-online/overview to register for eSubscription.
For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation at (202) 502-6595 or OPP@ferc.gov.
Additional information about the Project is available from the FERC website ( www.ferc.gov). Using the “eLibrary” link, select “General Search” from the eLibrary menu, enter the selected date range and “Docket Number” excluding the last three digits ( i.e., CP26-556), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings.
(Authority: 18 CFR 2.1)
Dated: November 18, 2026.
Debbie-Anne A. Reese,
Secretary.
Footnotes
1. For tracking purposes under the National Environmental Policy Act, the unique identification number for documents relating to this environmental review is EAXX-019-20-000-1790772608.
Back to Citation2. The Commission's deadline applies to the decisions of other federal agencies, and state agencies acting under federally delegated authority, that are responsible for federal authorizations, permits, and other approvals necessary for proposed projects under the Natural Gas Act. Per 18 CFR 157.22(a), the Commission's deadline for other agency's decisions applies unless a schedule is otherwise established by federal law.
Back to Citation[FR Doc. 2026-23835 Filed 11-23-26; 8:45 am]
BILLING CODE 6717-01-P