Document

NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization

[Federal Register Volume 63, Number 251 (Thursday, December 31, 1998)] [Notices] [Page 72297] From the Federal Register Online via the Government Publishing Office [ www.gpo.gov...

[Federal Register Volume 63, Number 251 (Thursday, December 31, 1998)]
[Notices]
[Page 72297]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-34599]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP99-126-000]


NorAm Gas Transmission Company; Notice of Request Under Blanket 
Authorization

December 24, 1998.
    Take notice that on December 18, 1998, NorAm Gas Transmission 
Company (NGT), 1111 Louisiana, Houston, Texas 77002-5231, filed in 
Docket No. CP99-126-000 a request pursuant to Sections 157.205 and 
157.211 of the Commission's Regulations under the Natural Gas Act (18 
CFR 157.205 and 157.211) for authorization to construct and operate 
certain facilities in Oklahoma under NGT's blanket certificate issued 
in Docket No. CP82-384-000 and CP82-384-001 pursuant to Section 7 of 
the Natural Gas Act, all as more fully set forth in the request that is 
on file with the Commission and open to public inspection.
    NGT specifically proposes to construct and operate two 2-inch 
delivery taps, first-cut regulators and one 4-inch meter station to 
serve ARKLA, a division of NorAm Energy Corp. (ARKLA). The proposed 
facilities will be located on NGT's lines 10 and 10-1 in Stephens 
County, Oklahoma. The total estimated volume to be delivered to this 
meter station is 400,000 Dth annually and 4,000 Dth on a peak day. The 
facilities will be constructed at an estimated cost of $42,872 and 
ARKLA will reimburse NGT the construction costs.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
the request. If no protest is filed within the time allowed therefor, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-34599 Filed 12-30-98; 8:45 am]
BILLING CODE 6717-01-M


Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

63 FR 72297

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization,” thefederalregister.org (December 31, 1998), https://thefederalregister.org/documents/98-34599/noram-gas-transmission-company-notice-of-request-under-blanket-authorization.