The U.S. Nuclear Regulatory Commission (NRC) has determined that Korea Hydro and Nuclear Power Co., Ltd. (KHNP) and Korea Electric Power Corporation (KEPCO) have submitted information for a standard design certification of the APR1400 Standard Plant Design that is acceptable for docketing. The docket number established is 52-046.

Federal Register, Volume 80 Issue 48 (Thursday, March 12, 2015)
[Federal Register Volume 80, Number 48 (Thursday, March 12, 2015)]
[Notices]
[Pages 13035-13036]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-05579]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 52-046; NRC-2015-0021]


Korea Hydro and Nuclear Power Co., Ltd., and Korea Electric Power 
Corporation

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice of docketing.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has determined 
that Korea Hydro and Nuclear Power Co., Ltd. (KHNP) and Korea Electric 
Power Corporation (KEPCO) have submitted information for a standard 
design certification of the APR1400 Standard Plant Design that is 
acceptable for docketing. The docket number established is 52-046.

DATES: March 12, 2015.

ADDRESSES: Please refer to Docket ID NRC-2015-0021 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2015-0021. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC'S Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced in this document 
(if that document is available in ADAMS) is provided the first time 
that the document is referenced. The application is available in ADAMS 
under Accession No. ML15006A037.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Jeffrey Ciocco, Office of New 
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC, 20555-
0001; telephone: 301-415-6391; email: [email protected].

SUPPLEMENTARY INFORMATION: By letter dated December 23, 2014, KHNP and 
KEPCO filed with the NRC, pursuant to Section 103 of the Atomic Energy 
Act and part 52 of Title 10 of the Code of Federal Regulations (10 
CFR), ``Licenses, Certifications, and Approvals for Nuclear Power 
Plants,'' an application for standard design certification of the 
APR1400 Standard Plant Design. A notice of receipt for this application 
was previously published in the Federal Register on February 3, 2015 
(80 FR 5792).
    The APR1400 stands for Advanced Power Reactor with a 1,400 
megawatts electrical power and two-loop pressurized water reactor, 
developed in the Republic of Korea. According to the applicant, based 
on the self-reliant technologies and experiences from the design, 
construction, operation and maintenance of the Optimized Power Reactor 
1000 (OPR1000), the APR1400 adopts advanced design features to enhance 
plant safety, economical efficiency, and convenience of operation and 
maintenance. The APR1400 application includes the entire power 
generation complex, except those elements and features considered site-
specific.
    The NRC staff has determined that KHNP and KEPCO have submitted 
information in accordance with 10 CFR

[[Page 13036]]

part 2, ``Rules of Practice for Domestic Licensing Proceedings and 
Issuance of Orders,'' and 10 CFR part 52 that is acceptable for 
docketing. The docket number established for this application is 52-
046.
    The NRC staff will perform a detailed technical review of the 
design certification application. Docketing of the design certification 
application does not preclude the NRC from requesting additional 
information from the applicant as the review proceeds, nor does it 
predict whether the NRC will grant or deny the application. A notice 
related to the rulemaking pursuant to 10 CFR 52.51 for design 
certification, including provisions for participation of the public and 
other parties, will be the subject of a subsequent Federal Register 
notice.

    Dated at Rockville, Maryland, this 3rd day of March, 2015.

    For the Nuclear Regulatory Commission.
Jeffrey A. Ciocco,
Senior Project Manager, Licensing Branch 2, Division of New Reactor 
Licensing, Office of New Reactors.
[FR Doc. 2015-05579 Filed 3-11-15; 8:45 am]
 BILLING CODE 7590-01-P



                                                                                        Federal Register / Vol. 80, No. 48 / Thursday, March 12, 2015 / Notices                                            13035

                                                     ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE
                                                                   UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING—Continued
                                                           Day                                                                                  Event/Activity

                                                    20 .................     U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for ac-
                                                                                cess provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs
                                                                                any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.)
                                                                                If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (prepara-
                                                                                tion of redactions or review of redacted documents).
                                                    25 .................     If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to
                                                                                reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Ad-
                                                                                ministrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party
                                                                                to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a
                                                                                motion seeking a ruling to reverse the NRC staff’s grant of access.
                                                    30 .................     Deadline for NRC staff reply to motions to reverse NRC staff determination(s).
                                                    40 .................     (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and
                                                                                file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agree-
                                                                                ment for SUNSI.
                                                    A ...................    If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access to
                                                                                sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final ad-
                                                                                verse determination by the NRC staff.
                                                    A + 3 ............       Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective
                                                                                order.
                                                    A + 28 ..........        Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days re-
                                                                                main between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as es-
                                                                                tablished in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later dead-
                                                                                line.
                                                    A + 53 ..........        (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
                                                    A + 60 ..........        (Answer receipt +7) Petitioner/Intervener reply to answers.
                                                    >A + 60 ........         Decision on contention admission.



                                                    [FR Doc. 2015–05679 Filed 3–11–15; 8:45 am]                    Gallagher; telephone: 301–415–3463;                   telephone: 301–415–6391; email:
                                                    BILLING CODE 7590–01–P                                         email: Carol.Gallagher@nrc.gov. For                   Jeff.Ciocco@nrc.gov.
                                                                                                                   technical questions, contact the                      SUPPLEMENTARY INFORMATION:      By letter
                                                                                                                   individual listed in the FOR FURTHER                  dated December 23, 2014, KHNP and
                                                    NUCLEAR REGULATORY                                             INFORMATION CONTACT section of this
                                                                                                                                                                         KEPCO filed with the NRC, pursuant to
                                                    COMMISSION                                                     document.                                             Section 103 of the Atomic Energy Act
                                                    [Docket No. 52–046; NRC–2015–0021]                                • NRC’S Agencywide Documents                       and part 52 of Title 10 of the Code of
                                                                                                                   Access and Management System                          Federal Regulations (10 CFR),
                                                    Korea Hydro and Nuclear Power Co.,                             (ADAMS): You may obtain publicly-                     ‘‘Licenses, Certifications, and Approvals
                                                    Ltd., and Korea Electric Power                                 available documents online in the                     for Nuclear Power Plants,’’ an
                                                    Corporation                                                    ADAMS Public Documents collection at                  application for standard design
                                                    AGENCY: Nuclear Regulatory                                     http://www.nrc.gov/reading-rm/                        certification of the APR1400 Standard
                                                    Commission.                                                    adams.html. To begin the search, select               Plant Design. A notice of receipt for this
                                                    ACTION: Notice of docketing.                                   ‘‘ADAMS Public Documents’’ and then                   application was previously published in
                                                                                                                   select ‘‘Begin Web-based ADAMS                        the Federal Register on February 3,
                                                    SUMMARY:    The U.S. Nuclear Regulatory                        Search.’’ For problems with ADAMS,                    2015 (80 FR 5792).
                                                    Commission (NRC) has determined that                           please contact the NRC’s Public                          The APR1400 stands for Advanced
                                                    Korea Hydro and Nuclear Power Co.,                             Document Room (PDR) reference staff at                Power Reactor with a 1,400 megawatts
                                                    Ltd. (KHNP) and Korea Electric Power                           1–800–397–4209, 301–415–4737, or by                   electrical power and two-loop
                                                    Corporation (KEPCO) have submitted                             email to pdr.resource@nrc.gov. The                    pressurized water reactor, developed in
                                                    information for a standard design                              ADAMS accession number for each                       the Republic of Korea. According to the
                                                    certification of the APR1400 Standard                          document referenced in this document                  applicant, based on the self-reliant
                                                    Plant Design that is acceptable for                            (if that document is available in                     technologies and experiences from the
                                                    docketing. The docket number                                   ADAMS) is provided the first time that                design, construction, operation and
                                                    established is 52–046.                                         the document is referenced. The                       maintenance of the Optimized Power
                                                    DATES: March 12, 2015.                                         application is available in ADAMS                     Reactor 1000 (OPR1000), the APR1400
                                                    ADDRESSES: Please refer to Docket ID                           under Accession No. ML15006A037.                      adopts advanced design features to
                                                    NRC–2015–0021 when contacting the                                                                                    enhance plant safety, economical
                                                                                                                      • NRC’s PDR: You may examine and
                                                    NRC about the availability of                                                                                        efficiency, and convenience of operation
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                   purchase copies of public documents at
                                                    information regarding this document.                                                                                 and maintenance. The APR1400
                                                                                                                   the NRC’s PDR, Room O1–F21, One
                                                    You may obtain publicly-available                                                                                    application includes the entire power
                                                                                                                   White Flint North, 11555 Rockville
                                                    information related to this document                                                                                 generation complex, except those
                                                                                                                   Pike, Rockville, Maryland 20852.
                                                    using any of the following methods:                                                                                  elements and features considered site-
                                                      • Federal Rulemaking Web site: Go to                         FOR FURTHER INFORMATION CONTACT:                      specific.
                                                    http://www.regulations.gov and search                          Jeffrey Ciocco, Office of New Reactors,                  The NRC staff has determined that
                                                    for Docket ID NRC–2015–0021. Address                           U.S. Nuclear Regulatory Commission,                   KHNP and KEPCO have submitted
                                                    questions about NRC dockets to Carol                           Washington, DC, 20555–0001;                           information in accordance with 10 CFR


                                               VerDate Sep<11>2014          17:40 Mar 11, 2015   Jkt 235001   PO 00000   Frm 00062   Fmt 4703   Sfmt 4703   E:\FR\FM\12MRN1.SGM   12MRN1


                                                    13036                        Federal Register / Vol. 80, No. 48 / Thursday, March 12, 2015 / Notices

                                                    part 2, ‘‘Rules of Practice for Domestic                ADDRESSES:   Please refer to Docket                   application, as supplemented, was
                                                    Licensing Proceedings and Issuance of                   Number 50–608 or Docket ID NRC–                       accepted for docketing on December 2,
                                                    Orders,’’ and 10 CFR part 52 that is                    2013–0053 when contacting the NRC                     2013 (78 FR 73897). The docket number
                                                    acceptable for docketing. The docket                    about the availability of information                 established for this application is 50–
                                                    number established for this application                 regarding this document. You may                      608.
                                                    is 52–046.                                              obtain publicly-available information                   The NRC is considering issuance of a
                                                       The NRC staff will perform a detailed                related to this document using any of                 construction permit to SHINE for
                                                    technical review of the design                          the following methods:                                construction of the SHINE medical
                                                    certification application. Docketing of                    • NRC’s Agencywide Documents                       radioisotope production facility, to be
                                                    the design certification application does               Access and Management System                          located in Rock County, Wisconsin.
                                                    not preclude the NRC from requesting                    (ADAMS): You may obtain publicly                      II. Hearing
                                                    additional information from the                         available documents online in the
                                                    applicant as the review proceeds, nor                   ADAMS Public Documents collection at                     Pursuant to the Atomic Energy Act of
                                                    does it predict whether the NRC will                    http://www.nrc.gov/reading-rm/                        1954, as amended, and parts 2 and 50
                                                    grant or deny the application. A notice                 adams.html. To begin the search, select               of Title 10 of the Code of Federal
                                                    related to the rulemaking pursuant to 10                ‘‘ADAMS Public Documents’’ and then                   Regulations (10 CFR), ‘‘Rules of Practice
                                                    CFR 52.51 for design certification,                     select ‘‘Begin Web-based ADAMS                        for Domestic Licensing Proceedings and
                                                    including provisions for participation of               Search.’’ For problems with ADAMS,                    Issuance of Orders,’’ and ‘‘Domestic
                                                    the public and other parties, will be the               please contact the NRC’s Public                       Licensing of Production and Utilization
                                                    subject of a subsequent Federal Register                Document Room (PDR) reference staff at                Facilities,’’ notice is hereby given that a
                                                    notice.                                                 1–800–397–4209, 301–415–4737, or by                   hearing will be held, at a time and place
                                                                                                            email to pdr.resource@nrc.gov. The                    to be set in the future by the
                                                      Dated at Rockville, Maryland, this 3rd day                                                                  Commission or designated by the
                                                    of March, 2015.                                         ADAMS accession number for each
                                                                                                                                                                  Atomic Safety and Licensing Board
                                                      For the Nuclear Regulatory Commission.                document referenced in this document
                                                                                                                                                                  (Board).
                                                                                                            (if that document is available in
                                                    Jeffrey A. Ciocco,                                                                                               The hearing on the application for a
                                                                                                            ADAMS) is provided the first time that                construction permit filed by SHINE
                                                    Senior Project Manager, Licensing Branch 2,
                                                    Division of New Reactor Licensing, Office of
                                                                                                            a document is referenced.                             pursuant to 10 CFR part 50 will be
                                                    New Reactors.                                              • NRC’s PDR: You may examine and                   conducted by a Board that will be
                                                    [FR Doc. 2015–05579 Filed 3–11–15; 8:45 am]
                                                                                                            purchase copies of public documents at                designated by the Chief Judge of the
                                                                                                            the NRC’s PDR, Room O1–F21, One                       Atomic Safety and Licensing Board
                                                    BILLING CODE 7590–01–P
                                                                                                            White Flint North, 11555 Rockville                    Panel or will be conducted by the
                                                                                                            Pike, Rockville, Maryland 20852.                      Commission. Notice as to the
                                                    NUCLEAR REGULATORY                                      FOR FURTHER INFORMATION CONTACT:                      membership of the Board will be
                                                    COMMISSION                                              Steven Lynch, Office of Nuclear Reactor               published in the Federal Register at a
                                                                                                            Regulation, U.S. Nuclear Regulatory                   later date. The NRC staff will complete
                                                    [Docket No. 50–608; NRC–2013–0053]                      Commission, Washington, DC 20555–                     a detailed technical review of the
                                                    SHINE Medical Technologies, Inc.;                       0001; telephone: 301–415–1524, email:                 application and will document its
                                                    Notice of Hearing, Opportunity To                       Steven.Lynch@nrc.gov.                                 findings in a safety evaluation report.
                                                    Intervene, Order Imposing Procedures                    SUPPLEMENTARY INFORMATION:                            The Commission will refer a copy of the
                                                                                                            I. Introduction                                       application to the Advisory Committee
                                                    AGENCY:  Nuclear Regulatory                                                                                   on Reactor Safeguards (ACRS) in
                                                    Commission.                                                By letters dated March 26, 2013                    accordance with 10 CFR 50.58,
                                                    ACTION: Construction permit                             (ADAMS Accession No. ML13088A192),                    ‘‘Hearings and Report of the Advisory
                                                    application; hearing, opportunity to                    and May 31, 2013 (ADAMS Accession                     Committee on Reactor Safeguards,’’ and
                                                    petition for leave to intervene; order                  No. ML13172A361), and supplemented                    the ACRS will report on those portions
                                                    imposing procedures for access to                       by letter dated September 25, 2013                    of the application that concern safety.
                                                    Sensitive Unclassified Non-Safeguards                   (ADAMS Accession No. ML13269A378),                    The NRC staff will also complete an
                                                    Information (SUNSI).                                    SHINE requested approval of a                         environmental review of the application
                                                                                                            construction permit application for a                 and will document its findings in an
                                                    SUMMARY:   The U.S. Nuclear Regulatory                  medical radioisotope production facility              environmental impact statement in
                                                    Commission (NRC) has received a                         (ADAMS Accession No. ML13172A324).                    accordance with the National
                                                    construction permit application from                    SHINE’s medical radioisotope                          Environmental Policy Act of 1969, as
                                                    SHINE Medical Technologies, Inc.                        production facility would include an                  amended, and the Commission’s
                                                    (SHINE), for approval of a proposed                     irradiation facility and a radioisotope               regulations in 10 CFR part 51.
                                                    medical radioisotope production facility                production facility collocated in a single
                                                    for the production of molybdenum-99                     building. The irradiation facility would              III. Opportunity To Petition for Leave
                                                    (Mo-99) at a site located in Janesville,                consist of accelerator-driven subcritical             To Intervene
                                                    Wisconsin. The NRC is currently                         operating assemblies used for the                        Within 60 days after the date of
                                                    conducting a detailed technical review                  irradiation of a uranium solution to                  publication of this Federal Register
                                                    of the construction permit application.                 produce molybdenum-99 and other                       notice, any person whose interest may
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    If the construction permit application is               fission products. The radioisotope                    be affected by this proceeding and who
                                                    approved, the applicant would be                        production facility would consist of hot              desires to participate as a party in this
                                                    authorized to construct its proposed                    cell structures used for the extraction of            proceeding must file a written petition
                                                    medical radioisotope production facility                radioisotopes. Part one of the                        for leave to intervene with respect to
                                                    in accordance with the provisions of the                application was accepted for docketing                issuance of the construction permit to
                                                    construction permit.                                    on June 25, 2013 (78 FR 39342). The                   SHINE in accordance with the NRC’s
                                                    DATES: A petition for leave to intervene                second and final portion of SHINE’s                   ‘‘Agency Rules of Practice and
                                                    must be filed by May 11, 2015.                          two-part construction permit                          Procedure’’ in 10 CFR part 2. Interested


                                               VerDate Sep<11>2014   17:40 Mar 11, 2015   Jkt 235001   PO 00000   Frm 00063   Fmt 4703   Sfmt 4703   E:\FR\FM\12MRN1.SGM   12MRN1



Document Created: 2018-02-21 09:35:55
Document Modified: 2018-02-21 09:35:55
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of docketing.
DatesMarch 12, 2015.