80_FR_15256 80 FR 15201 - UGI Sunbury, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Sunbury Pipeline Project and Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting

80 FR 15201 - UGI Sunbury, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Sunbury Pipeline Project and Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 55 (March 23, 2015)

Page Range15201-15203
FR Document2015-06530

Federal Register, Volume 80 Issue 55 (Monday, March 23, 2015)
[Federal Register Volume 80, Number 55 (Monday, March 23, 2015)]
[Notices]
[Pages 15201-15203]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-06530]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF15-9-000]


UGI Sunbury, LLC; Notice of Intent To Prepare an Environmental 
Assessment for the Planned Sunbury Pipeline Project and Request for 
Comments on Environmental Issues, and Notice of Public Scoping Meeting

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Sunbury Pipeline Project 
(Project) involving the construction and operation of approximately 
34.5 miles of 20-inch diameter pipeline and related facilities by UGI 
Sunbury, LLC (Sunbury) in Snyder, Union, Northumberland, Montour, and 
Lycoming Counties, Pennsylvania. The Commission will use this EA in its 
decision-making process to determine whether the project is in the 
public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues they need to evaluate in the EA. Please note that 
the scoping period will close on April 17, 2015.
    You may submit comments in written form or verbally. Further 
details on how to submit written comments are in the Public 
Participation section of this notice. If you sent comments on this 
project to the Commission before the opening of this docket on December 
30, 2014, you will need to file those comments in Docket No. PF15-9-000 
to ensure they are considered as part of this proceeding. In lieu of or 
in addition to sending written comments, the Commission invites you to 
attend the public scoping meeting scheduled as follows:

------------------------------------------------------------------------
             Date and time                           Location
------------------------------------------------------------------------
April 7, 2015, 6:00 p.m. (Eastern Time)  James F. Baugher Elementary
                                          School, All Purpose Room, 60
                                          Brenda Rovenolt Circle,
                                          Milton, PA 17847.
------------------------------------------------------------------------

    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this planned 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses 
a number of typically asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings.

Summary of the Planned Project

    Sunbury plans to construct, own, and operate a new natural gas 
pipeline extending from Lycoming County, Pennsylvania to a gas-fired 
power plant,

[[Page 15202]]

Hummel Station LLC (Hummel), at the existing site of coal-fired Sunbury 
Generation LP facility near Shamokin Dam, in Snyder County, 
Pennsylvania. Hummel is planning to construct the power plant at the 
existing site of the coal-fired facility near Shamokin Dam. The project 
has a planned capacity to transport approximately 200,000 dekatherms of 
natural gas per day.
    The Sunbury Pipeline Project would consist of the following 
facilities:
     One new 34.5-mile, 20-inch-diameter pipeline; and
     associated aboveground facilities consisting of two new 
mainline vales, four meter stations, and two launcher and receivers.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the planned pipeline would disturb about 488 acres 
of land. Land disturbance for the planned above ground facilities would 
encompass an area of 3.7 acres, which would be reduced to 2.1 acres for 
operation of these facilities. Following construction, Sunbury would 
maintain about 209 acres for permanent operation of the project's 
pipeline facilities, and 2.1 acres for the above ground facilities. The 
remaining 279 acres would be used for temporary construction workspace 
and be restored and to former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the planned project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife, including migratory birds;
     air quality and noise;
     endangered and threatened species;
     socioeconomics;
     public safety; and
     cumulative impacts.
    We will also evaluate possible alternatives to the planned project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Although no formal application has been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders and to identify and resolve issues before 
the FERC receives an application. As part of our pre-filing review, we 
participated in public Open House meetings sponsored by Sunbury in the 
project area on February 24th and February 25th to explain the 
environmental review process to interested stakeholders. Also, we have 
begun to contact some federal and state agencies to discuss their 
involvement in the scoping process and the preparation of the EA.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before we make our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues 
related to this project to formally cooperate with us in the 
preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at title 40, Code of Federal 
Regulations, part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the Pennsylvania State Historic Preservation Office, and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation regulations 
are at title 36, Code of Federal Regulations, part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before April 
17, 2015.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number (PF15-9-000) with your submission. The Commission 
encourages electronic filing of comments and has expert staff available 
to assist you at (202) 502-8258 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. This is an easy method for interested 
persons to

[[Page 15203]]

submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address:

Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE., Room 1A, Washington, DC 20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
planned project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    Once Sunbury files its application with the Commission, you may 
want to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site. Please note that the Commission will not accept requests for 
intervenor status at this time. You must wait until the Commission 
receives a formal application for the project.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., PF15-
9). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: March 16, 2015.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-06530 Filed 3-20-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                Federal Register / Vol. 80, No. 55 / Monday, March 23, 2015 / Notices                                                  15201

                                                     Register online at http://                           DEPARTMENT OF ENERGY                                  and interested agencies on the project.
                                                  www.ferc.gov/docs-filing/                                                                                     Your input will help the Commission
                                                  esubscription.asp to be notified via                    Federal Energy Regulatory                             staff determine what issues they need to
                                                  email of new filings and issuances                      Commission                                            evaluate in the EA. Please note that the
                                                  related to this or other pending projects.              [Docket No. ER15–402–001; Docket No.                  scoping period will close on April 17,
                                                  For assistance, contact FERC Online                     ER15–817–000; Docket No. ER15–861–000]                2015.
                                                  Support.                                                                                                        You may submit comments in written
                                                                                                          California Independent System                         form or verbally. Further details on how
                                                     All filings must: (1) Bear in all capital
                                                                                                          Operator Corporation; Notice of FERC                  to submit written comments are in the
                                                  letters the title ‘‘COMMENTS,’’ ‘‘REPLY
                                                                                                          Staff Attendance                                      Public Participation section of this
                                                  COMMENTS,’’
                                                                                                                                                                notice. If you sent comments on this
                                                  ‘‘RECOMMENDATIONS,’’ ‘‘TERMS                               The Federal Energy Regulatory                      project to the Commission before the
                                                  AND CONDITIONS,’’ or                                    Commission (Commission) hereby gives                  opening of this docket on December 30,
                                                  ‘‘PRESCRIPTIONS’’; (2) set forth in the                 notice that on March 18, 2015 members                 2014, you will need to file those
                                                  heading the name of the applicant and                   of its staff will attend the California               comments in Docket No. PF15–9–000 to
                                                  the project number of the application to                Independent System Operator’s (CAISO)                 ensure they are considered as part of
                                                  which the filing responds; (3) furnish                  Market Performance and Planning                       this proceeding. In lieu of or in addition
                                                  the name, address, and telephone                        Forum. The agenda and other                           to sending written comments, the
                                                  number of the person submitting the                     documents for the meeting are available               Commission invites you to attend the
                                                  filing; and (4) otherwise comply with                   on CAISO’s Web site, www.caiso.com.                   public scoping meeting scheduled as
                                                  the requirements of 18 CFR 385.2001                        Sponsored by CAISO, the meeting is                 follows:
                                                  through 385.2005. All comments,                         open to all market participants and
                                                  recommendations, terms and conditions                   staff’s attendance is part of the                      Date and time              Location
                                                  or prescriptions must set forth their                   Commission’s ongoing outreach efforts.
                                                  evidentiary basis and otherwise comply                  The meeting may discuss matters at                    April 7, 2015,    James F. Baugher Elemen-
                                                  with the requirements of 18 CFR 4.34(b).                issue in the above captioned dockets.                   6:00 p.m.         tary School, All Purpose
                                                  Agencies may obtain copies of the                          For further information, contact Saeed               (Eastern          Room, 60 Brenda
                                                  application directly from the applicant.                Farrokhpay at saeed.farrokhpay@                         Time).            Rovenolt Circle, Milton, PA
                                                                                                                                                                                    17847.
                                                  Each filing must be accompanied by                      ferc.gov (916) 294–0322.
                                                  proof of service on all persons listed on                 Dated: March 16, 2015.                                This notice is being sent to the
                                                  the service list prepared by the                        Kimberly D. Bose,                                     Commission’s current environmental
                                                  Commission in this proceeding, in
                                                                                                          Secretary.                                            mailing list for this project. State and
                                                  accordance with 18 CFR 4.34(b) and                                                                            local government representatives should
                                                                                                          [FR Doc. 2015–06529 Filed 3–20–15; 8:45 am]
                                                  385.2010.                                                                                                     notify their constituents of this planned
                                                                                                          BILLING CODE 6717–01–P
                                                     n. Procedural Schedule:                                                                                    project and encourage them to comment
                                                     The application will be processed                                                                          on their areas of concern.
                                                  according to the following revised hydro                DEPARTMENT OF ENERGY                                    If you are a landowner receiving this
                                                  licensing schedule. Revisions to the                                                                          notice, a pipeline company
                                                  schedule may be made as appropriate.                    Federal Energy Regulatory                             representative may contact you about
                                                                                                          Commission                                            the acquisition of an easement to
                                                             Milestone                   Target date      [Docket No. PF15–9–000]                               construct, operate, and maintain the
                                                                                                                                                                planned facilities. The company would
                                                  Filing of recommendations,            May 2015.         UGI Sunbury, LLC; Notice of Intent To                 seek to negotiate a mutually acceptable
                                                     terms and conditions, and                            Prepare an Environmental Assessment                   agreement. However, if the Commission
                                                     prescriptions.                                       for the Planned Sunbury Pipeline                      approves the project, that approval
                                                  Commission issues Draft EA            December          Project and Request for Comments on                   conveys with it the right of eminent
                                                                                          2015.                                                                 domain. Therefore, if easement
                                                  Comments on Draft EA Due              January 2016.
                                                                                                          Environmental Issues, and Notice of
                                                                                                          Public Scoping Meeting                                negotiations fail to produce an
                                                  Commission Issues Final EA            May 2016.
                                                                                                                                                                agreement, the pipeline company could
                                                                                                            The staff of the Federal Energy                     initiate condemnation proceedings
                                                    o. Public notice of the filing of the                 Regulatory Commission (FERC or                        where compensation would be
                                                  initial development application, which                  Commission) will prepare an                           determined in accordance with state
                                                  has already been given, established the                 environmental assessment (EA) that will               law.
                                                  due date for filing competing                           discuss the environmental impacts of                    A fact sheet prepared by the FERC
                                                  applications or notices of intent. Under                the Sunbury Pipeline Project (Project)                entitled ‘‘An Interstate Natural Gas
                                                  the Commission’s regulations, any                       involving the construction and                        Facility On My Land? What Do I Need
                                                  competing development application                       operation of approximately 34.5 miles of              To Know?’’ is available for viewing on
                                                  must be filed in response to and in                     20-inch diameter pipeline and related                 the FERC Web site (www.ferc.gov). This
                                                  compliance with public notice of the                    facilities by UGI Sunbury, LLC                        fact sheet addresses a number of
                                                  initial development application. No                     (Sunbury) in Snyder, Union,                           typically asked questions, including the
                                                  competing applications or notices of                    Northumberland, Montour, and                          use of eminent domain and how to
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  intent may be filed in response to this                 Lycoming Counties, Pennsylvania. The                  participate in the Commission’s
                                                  notice.                                                 Commission will use this EA in its                    proceedings.
                                                    Dated: March 16, 2015.
                                                                                                          decision-making process to determine
                                                                                                          whether the project is in the public                  Summary of the Planned Project
                                                  Kimberly D. Bose,                                                                                               Sunbury plans to construct, own, and
                                                                                                          convenience and necessity.
                                                  Secretary.                                                This notice announces the opening of                operate a new natural gas pipeline
                                                  [FR Doc. 2015–06526 Filed 3–20–15; 8:45 am]             the scoping process the Commission                    extending from Lycoming County,
                                                  BILLING CODE 6717–01–P                                  will use to gather input from the public              Pennsylvania to a gas-fired power plant,


                                             VerDate Sep<11>2014   16:51 Mar 20, 2015   Jkt 235001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\23MRN1.SGM   23MRN1


                                                  15202                          Federal Register / Vol. 80, No. 55 / Monday, March 23, 2015 / Notices

                                                  Hummel Station LLC (Hummel), at the                     construction and operation of the                     provided under the Public Participation
                                                  existing site of coal-fired Sunbury                     planned project under these general                   section of this notice.
                                                  Generation LP facility near Shamokin                    headings:
                                                                                                                                                                Consultations Under Section 106 of the
                                                  Dam, in Snyder County, Pennsylvania.                       • Geology and soils;                               National Historic Preservation Act
                                                  Hummel is planning to construct the                        • land use;
                                                  power plant at the existing site of the                    • water resources, fisheries, and                    In accordance with the Advisory
                                                  coal-fired facility near Shamokin Dam.                  wetlands;                                             Council on Historic Preservation’s
                                                  The project has a planned capacity to                      • cultural resources;                              implementing regulations for section
                                                  transport approximately 200,000                                                                               106 of the National Historic
                                                                                                             • vegetation and wildlife, including
                                                  dekatherms of natural gas per day.                                                                            Preservation Act, we are using this
                                                                                                          migratory birds;
                                                     The Sunbury Pipeline Project would                                                                         notice to initiate consultation with the
                                                                                                             • air quality and noise;
                                                  consist of the following facilities:                                                                          Pennsylvania State Historic Preservation
                                                                                                             • endangered and threatened species;
                                                     • One new 34.5-mile, 20-inch-                                                                              Office, and to solicit their views and
                                                                                                             • socioeconomics;                                  those of other government agencies,
                                                  diameter pipeline; and
                                                     • associated aboveground facilities                     • public safety; and                               interested Indian tribes, and the public
                                                  consisting of two new mainline vales,                      • cumulative impacts.                              on the project’s potential effects on
                                                  four meter stations, and two launcher                      We will also evaluate possible                     historic properties.4 We will define the
                                                  and receivers.                                          alternatives to the planned project or                project-specific Area of Potential Effects
                                                     The general location of the project                  portions of the project, and make                     (APE) in consultation with the SHPO as
                                                  facilities is shown in appendix 1.1                     recommendations on how to lessen or                   the project develops. On natural gas
                                                                                                          avoid impacts on the various resource                 facility projects, the APE at a minimum
                                                  Land Requirements for Construction                      areas.                                                encompasses all areas subject to ground
                                                    Construction of the planned pipeline                     Although no formal application has                 disturbance (examples include
                                                  would disturb about 488 acres of land.                  been filed, we have already initiated our             construction right-of-way, contractor/
                                                  Land disturbance for the planned above                  NEPA review under the Commission’s                    pipe storage yards, compressor stations,
                                                  ground facilities would encompass an                    pre-filing process. The purpose of the                and access roads). Our EA for this
                                                  area of 3.7 acres, which would be                       pre-filing process is to encourage early              project will document our findings on
                                                  reduced to 2.1 acres for operation of                   involvement of interested stakeholders                the impacts on historic properties and
                                                  these facilities. Following construction,               and to identify and resolve issues before             summarize the status of consultations
                                                  Sunbury would maintain about 209                        the FERC receives an application. As                  under section 106.
                                                  acres for permanent operation of the                    part of our pre-filing review, we
                                                  project’s pipeline facilities, and 2.1                  participated in public Open House                     Public Participation
                                                  acres for the above ground facilities. The              meetings sponsored by Sunbury in the                     You can make a difference by
                                                  remaining 279 acres would be used for                   project area on February 24th and                     providing us with your specific
                                                  temporary construction workspace and                    February 25th to explain the                          comments or concerns about the project.
                                                  be restored and to former uses.                         environmental review process to                       Your comments should focus on the
                                                                                                          interested stakeholders. Also, we have                potential environmental effects,
                                                  The EA Process
                                                                                                          begun to contact some federal and state               reasonable alternatives, and measures to
                                                     The National Environmental Policy                    agencies to discuss their involvement in              avoid or lessen environmental impacts.
                                                  Act (NEPA) requires the Commission to                   the scoping process and the preparation               The more specific your comments, the
                                                  take into account the environmental                     of the EA.                                            more useful they will be. To ensure that
                                                  impacts that could result from an action                   The EA will present our independent                your comments are timely and properly
                                                  whenever it considers the issuance of a                 analysis of the issues. The EA will be                recorded, please send your comments so
                                                  Certificate of Public Convenience and                   available in the public record through                that the Commission receives them in
                                                  Necessity. NEPA also requires us 2 to                   eLibrary. Depending on the comments                   Washington, DC on or before April 17,
                                                  discover and address concerns the                       received during the scoping process, we               2015.
                                                  public may have about proposals. This                   may also publish and distribute the EA                   For your convenience, there are three
                                                  process is referred to as scoping. The                  to the public for an allotted comment                 methods you can use to submit your
                                                  main goal of the scoping process is to                  period. We will consider all comments                 comments to the Commission. In all
                                                  focus the analysis in the EA on the                     on the EA before we make our                          instances, please reference the project
                                                  important environmental issues. By this                 recommendations to the Commission.                    docket number (PF15–9–000) with your
                                                  notice, the Commission requests public                  To ensure we have the opportunity to                  submission. The Commission
                                                  comments on the scope of the issues to                  consider and address your comments,                   encourages electronic filing of
                                                  address in the EA. We will consider all                 please carefully follow the instructions              comments and has expert staff available
                                                  filed comments during the preparation                   in the Public Participation section.                  to assist you at (202) 502–8258 or
                                                  of the EA.                                                 With this notice, we are asking                    efiling@ferc.gov.
                                                     In the EA we will discuss impacts that               agencies with jurisdiction by law and/                   (1) You can file your comments
                                                  could occur as a result of the                          or special expertise with respect to the              electronically using the eComment
                                                                                                          environmental issues related to this                  feature located on the Commission’s
                                                    1 The appendices referenced in this notice will
                                                                                                          project to formally cooperate with us in              Web site (www.ferc.gov) under the link
                                                  not appear in the Federal Register. Copies of
                                                  appendices were sent to all those receiving this        the preparation of the EA.3 Agencies                  to Documents and Filings. This is an
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  notice in the mail and are available at www.ferc.gov    that would like to request cooperating                easy method for interested persons to
                                                  using the link called ‘‘eLibrary’’ or from the          agency status should follow the
                                                  Commission’s Public Reference Room, 888 First                                                                   4 The Advisory Council on Historic Preservation
                                                  Street NE., Washington, DC 20426, or call (202)
                                                                                                          instructions for filing comments
                                                                                                                                                                regulations are at title 36, Code of Federal
                                                  502–8371. For instructions on connecting to                                                                   Regulations, part 800. Those regulations define
                                                  eLibrary, refer to the last page of this notice.          3 The Council on Environmental Quality              historic properties as any prehistoric or historic
                                                    2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the            regulations addressing cooperating agency             district, site, building, structure, or object included
                                                  environmental staff of the Commission’s Office of       responsibilities are at title 40, Code of Federal     in or eligible for inclusion in the National Register
                                                  Energy Projects.                                        Regulations, part 1501.6.                             of Historic Places.



                                             VerDate Sep<11>2014   16:51 Mar 20, 2015   Jkt 235001   PO 00000   Frm 00017   Fmt 4703   Sfmt 4703   E:\FR\FM\23MRN1.SGM   23MRN1


                                                                                Federal Register / Vol. 80, No. 55 / Monday, March 23, 2015 / Notices                                                   15203

                                                  submit brief, text-only comments on a                   the proceeding by filing a request to                 Department of Energy (DOE) pursuant to
                                                  project;                                                intervene. Instructions for becoming an               § 201(d) of the Powerplant and
                                                     (2) You can file your comments                       intervenor are in the User’s Guide under              Industrial Fuel Use Act of 1978 (FUA),
                                                  electronically using the eFiling feature                the ‘‘e-filing’’ link on the Commission’s             as amended, and DOE regulations in 10
                                                  located on the Commission’s Web site                    Web site. Please note that the                        CFR 501.60, 61. FUA and regulations
                                                  (www.ferc.gov) under the link to                        Commission will not accept requests for               thereunder require DOE to publish a
                                                  Documents and Filings. With eFiling,                    intervenor status at this time. You must              notice of filing of self-certification in the
                                                  you can provide comments in a variety                   wait until the Commission receives a                  Federal Register. 42 U.S.C. 8311(d) and
                                                  of formats by attaching them as a file                  formal application for the project.                   10 CFR 501.61(c).
                                                  with your submission. New eFiling
                                                  users must first create an account by                   Additional Information                                ADDRESSES:    Copies of coal capability
                                                  clicking on ‘‘eRegister.’’ You must select                 Additional information about the                   self-certification filings are available for
                                                  the type of filing you are making. If you               project is available from the                         public inspection, upon request, in the
                                                  are filing a comment on a particular                    Commission’s Office of External Affairs,              Office of Electricity Delivery and Energy
                                                  project, please select ‘‘Comment on a                   at (866) 208–FERC, or on the FERC Web                 Reliability, Mail Code OE–20, Room
                                                  Filing’’; or                                            site (www.ferc.gov) using the eLibrary                8G–024, Forrestal Building, 1000
                                                     (3) You can file a paper copy of your                link. Click on the eLibrary link, click on            Independence Avenue SW.,
                                                  comments by mailing them to the                         ‘‘General Search’’ and enter the docket               Washington, DC 20585.
                                                  following address:                                      number, excluding the last three digits
                                                  Kimberly D. Bose, Secretary, Federal                    in the Docket Number field (i.e., PF15–               FOR FURTHER INFORMATION CONTACT:
                                                  Energy Regulatory Commission, 888                       9). Be sure you have selected an                      Christopher Lawrence at (202) 586–
                                                  First Street NE., Room 1A, Washington,                  appropriate date range. For assistance,               5260.
                                                  DC 20426.                                               please contact FERC Online Support at
                                                                                                                                                                SUPPLEMENTARY INFORMATION:       Title II of
                                                  Environmental Mailing List                              FercOnlineSupport@ferc.gov or toll free
                                                                                                          at (866) 208–3676, or for TTY, contact                FUA, as amended (42 U.S.C. 8301 et
                                                     The environmental mailing list                       (202) 502–8659. The eLibrary link also                seq.), provides that no new base load
                                                  includes federal, state, and local                      provides access to the texts of formal                electric powerplant may be constructed
                                                  government representatives and                          documents issued by the Commission,                   or operated without the capability to use
                                                  agencies; elected officials;                            such as orders, notices, and                          coal or another alternate fuel as a
                                                  environmental and public interest                       rulemakings.                                          primary energy source. Pursuant to FUA
                                                  groups; Native American Tribes; other                      In addition, the Commission offers a               in order to meet the requirement of coal
                                                  interested parties; and local libraries                 free service called eSubscription which               capability, the owner or operator of such
                                                  and newspapers. This list also includes                 allows you to keep track of all formal                a facility proposing to use natural gas or
                                                  all affected landowners (as defined in                  issuances and submittals in specific                  petroleum as its primary energy source
                                                  the Commission’s regulations) who are                   dockets. This can reduce the amount of                shall certify to the Secretary of Energy
                                                  potential right-of-way grantors, whose                  time you spend researching proceedings                (Secretary) prior to construction, or
                                                  property may be used temporarily for                    by automatically providing you with                   prior to operation as a base load electric
                                                  project purposes, or who own homes                      notification of these filings, document               powerplant, that such powerplant has
                                                  within certain distances of aboveground                 summaries, and direct links to the
                                                  facilities, and anyone who submits                                                                            the capability to use coal or another
                                                                                                          documents. Go to www.ferc.gov/docs-                   alternate fuel. Such certification
                                                  comments on the project. We will                        filing/esubscription.asp.
                                                  update the environmental mailing list as                                                                      establishes compliance with FUA
                                                                                                             Finally, public meetings or site visits            section 201(a) as of the date it is filed
                                                  the analysis proceeds to ensure that we                 will be posted on the Commission’s
                                                  send the information related to this                                                                          with the Secretary. 42 U.S.C. 8311.
                                                                                                          calendar located at www.ferc.gov/
                                                  environmental review to all individuals,                EventCalendar/EventsList.aspx along                      The following owner of a proposed
                                                  organizations, and government entities                  with other related information.                       new base load electric powerplant has
                                                  interested in and/or potentially affected                                                                     filed a self-certification of coal-
                                                  by the planned project.                                   Dated: March 16, 2015.
                                                                                                                                                                capability with DOE pursuant to FUA
                                                     If we publish and distribute the EA,                 Kimberly D. Bose,                                     section 201(d) and in accordance with
                                                  copies will be sent to the environmental                Secretary.                                            DOE regulations in 10 CFR 501.60, 61:
                                                  mailing list for public review and                      [FR Doc. 2015–06530 Filed 3–20–15; 8:45 am]
                                                  comment. If you would prefer to receive                                                                          Owner: NTE Ohio, LLC.
                                                                                                          BILLING CODE 6717–01–P
                                                  a paper copy of the document instead of                                                                          Capacity: 525 megawatts (MW).
                                                  the CD version or would like to remove                                                                           Plant Location: Cincinnati Dayton
                                                  your name from the mailing list, please                 DEPARTMENT OF ENERGY                                  Road, Middletown, Ohio.
                                                  return the attached Information Request
                                                                                                          [Certification Notice—232]                               In-Service Date: As early as January
                                                  (appendix 2).
                                                                                                                                                                2018.
                                                  Becoming an Intervenor                                  Notice of Filing of Self-Certification of
                                                                                                          Coal Capability Under the Powerplant                    Issued in Washington, DC, on March 17,
                                                    Once Sunbury files its application                                                                          2015.
                                                                                                          and Industrial Fuel Use Act
                                                  with the Commission, you may want to                                                                          Brian Mills,
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  become an ‘‘intervenor’’ which is an                    AGENCY: Office of Electricity Delivery
                                                  official party to the Commission’s                                                                            Director, Permitting and Siting, Office of
                                                                                                          and Energy Reliability, DOE.
                                                                                                                                                                Electricity Delivery and Energy Reliability.
                                                  proceeding. Intervenors play a more                     ACTION: Notice of Filing.                             [FR Doc. 2015–06559 Filed 3–20–15; 8:45 am]
                                                  formal role in the process and are able
                                                  to file briefs, appear at hearings, and be              SUMMARY:  On March 2, 2015, NTE Ohio,                 BILLING CODE 6450–01–P
                                                  heard by the courts if they choose to                   LLC, as owner and operator of a new
                                                  appeal the Commission’s final ruling.                   base load electric powerplant, submitted
                                                  An intervenor formally participates in                  a coal capability self-certification to the


                                             VerDate Sep<11>2014   16:51 Mar 20, 2015   Jkt 235001   PO 00000   Frm 00018   Fmt 4703   Sfmt 9990   E:\FR\FM\23MRN1.SGM   23MRN1



Document Created: 2018-02-21 09:47:27
Document Modified: 2018-02-21 09:47:27
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 15201 

2024 Federal Register | Disclaimer | Privacy Policy