80_FR_21307 80 FR 21233 - Florida Gas Transmission, LLC; Notice of Application

80 FR 21233 - Florida Gas Transmission, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 74 (April 17, 2015)

Page Range21233-21234
FR Document2015-08871

Federal Register, Volume 80 Issue 74 (Friday, April 17, 2015)
[Federal Register Volume 80, Number 74 (Friday, April 17, 2015)]
[Notices]
[Pages 21233-21234]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-08871]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-144-000]


Florida Gas Transmission, LLC; Notice of Application

    Take notice that on March 31, 2015 Florida Gas Transmission 
Company, LLC (FGT), 1300 Main St., Houston, Texas 77002, filed in 
Docket No. CP15-144-000, an application pursuant to section 7(c) of the 
Commission's Regulations under the Natural Gas Act and Parts 157 of the 
Federal Energy Regulatory Commission's (Commission) regulations 
requesting authorization to construct, own, and operate: (1) 
Approximately 3.0 miles of 30-inch mainline loop extension (Branford 
Loop); (2) one new reciprocating 5,000 horsepower compressor unit and 
building at Compressor Station (CS) 16; (3) re-wheel an existing 
turbine compressor unit at CS 16; (4) approximately 5.7 miles of 20-
inch loop extension (Jacksonville Loop); and (5) a new regulator 
station and appurtenant auxiliary facilities, all known as its 
Jacksonville Expansion Project. The project will provide an initial 
60,000 MMBtu/d, and an expansion of 15,000 MMBtu/d of firm 
transportation to two existing delivery points for Peoples Gas System 
(PGS), a division of Tampa Electric Company all in Suwanee, Bradford, 
Columbia and Clay Counties, Florida, all as more fully set forth in the 
application which is on file with the Commission and open to public 
inspection. This filing may be viewed on the web at http://www.ferc.gov 
using the ``eLibrary'' link. Enter the docket number excluding the last 
three digits in the docket number field to access the document. For 
assistance, please contact FERC at [email protected] or call 
toll-free, (886) 208-3676 or TYY, (202) 502-8659.
    Any questions regarding this Application should be directed to 
Stephen Veatch, Senior Director of Certificates & Reporting, Florida 
Gas Transmission Company, LLC, 1300 Main St., Houston, Texas, 77002, or 
call (713) 989-2024, or fax (713) 989-1205,

[[Page 21234]]

or via eMail [email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 7 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with he Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentary, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and ill not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link.
    Comment Date: May 4, 2015.

    Dated: April 13, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-08871 Filed 4-16-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 80, No. 74 / Friday, April 17, 2015 / Notices                                                21233

                                                 j. Deadline for filing comments,                     at http://www.ferc.gov/docs-filing/                   accordance with 18 CFR 4.34(b) and
                                              motions to intervene, protests, and                     esubscription.asp to be notified via                  385.2010.
                                              recommendations is 15 days from the                     email of new filings and issuances                      Dated: April 13, 2015.
                                              issuance date of this notice by the                     related to this or other pending projects.            Kimberly D. Bose,
                                              Commission (April 28, 2015). The                        For assistance, call 1–866–208–3676 or
                                                                                                                                                            Secretary.
                                              Commission strongly encourages                          email FERCOnlineSupport@ferc.gov, for
                                              electronic filing. Please file motions to               TTY, call (202) 502–8659. A copy is also              [FR Doc. 2015–08876 Filed 4–16–15; 8:45 am]
                                              intervene, protests, comments, or                       available for inspection and                          BILLING CODE 6717–01–P

                                              recommendations using the                               reproduction at the address in item (h)
                                              Commission’s eFiling system at http://                  above.
                                              www.ferc.gov/docs-filing/efiling.asp.                      m. Individuals desiring to be included             DEPARTMENT OF ENERGY
                                              Commenters can submit brief comments                    on the Commission’s mailing list should
                                                                                                                                                            Federal Energy Regulatory
                                              up to 6,000 characters, without prior                   so indicate by writing to the Secretary
                                                                                                                                                            Commission
                                              registration, using the eComment system                 of the Commission.
                                              at http://www.ferc.gov/docs-filing/                        n. Comments, Protests, or Motions to
                                              ecomment.asp. You must include your                     Intervene: Anyone may submit                          [Docket No. CP15–144–000]
                                              name and contact information at the end                 comments, a protest, or a motion to
                                                                                                      intervene in accordance with the                      Florida Gas Transmission, LLC; Notice
                                              of your comments. For assistance,
                                                                                                      requirements of Rules of Practice and                 of Application
                                              please contact FERC Online Support at
                                              FERCOnlineSupport@ferc.gov, (866)                       Procedure, 18 CFR 385.210, .211, .214.                  Take notice that on March 31, 2015
                                              208–3676 (toll free), or (202) 502–8659                 In determining the appropriate action to              Florida Gas Transmission Company,
                                              (TTY). In lieu of electronic filing, please             take, the Commission will consider all                LLC (FGT), 1300 Main St., Houston,
                                              send a paper copy to: Secretary, Federal                protests or other comments filed, but
                                                                                                                                                            Texas 77002, filed in Docket No. CP15–
                                              Energy Regulatory Commission, 888                       only those who file a motion to
                                                                                                                                                            144–000, an application pursuant to
                                              First Street NE., Washington, DC 20426.                 intervene in accordance with the
                                                                                                                                                            section 7(c) of the Commission’s
                                              Please include the project number (P–                   Commission’s Rules may become a
                                                                                                                                                            Regulations under the Natural Gas Act
                                              184–246) on any comments, motions to                    party to the proceeding. Any comments,
                                                                                                                                                            and Parts 157 of the Federal Energy
                                              intervene, protests, or recommendations                 protests, or motions to intervene must
                                                                                                                                                            Regulatory Commission’s (Commission)
                                              filed.                                                  be received on or before the specified
                                                                                                                                                            regulations requesting authorization to
                                                 k. Description of Request: The                       comment date for the particular
                                                                                                                                                            construct, own, and operate: (1)
                                              licensee requests a modification of its                 application.
                                                                                                         o. Filing and Service of Responsive                Approximately 3.0 miles of 30-inch
                                              previous March 25, 2015 request for
                                                                                                      Documents: Any filing must (1) bear in                mainline loop extension (Branford
                                              temporary flow variance, which is
                                                                                                      all capital letters the title                         Loop); (2) one new reciprocating 5,000
                                              currently pending before the
                                                                                                      ‘‘COMMENTS’’, ‘‘PROTEST’’, or                         horsepower compressor unit and
                                              Commission. Specifically, the licensee
                                                                                                      ‘‘MOTION TO INTERVENE’’ as                            building at Compressor Station (CS) 16;
                                              requests an expanded temporary flow
                                                                                                      applicable; (2) set forth in the heading              (3) re-wheel an existing turbine
                                              variance at the South Fork American
                                                                                                      the name of the applicant and the                     compressor unit at CS 16; (4)
                                              River below Kyburz location, such that
                                                                                                      project number of the application to                  approximately 5.7 miles of 20-inch loop
                                              flows are reduced: from required 60
                                                                                                      which the filing responds; (3) furnish                extension (Jacksonville Loop); and (5) a
                                              cubic feet per second (cfs) to 45 cfs from
                                              May 1–15; from the required 60 cfs to                   the name, address, and telephone                      new regulator station and appurtenant
                                              30 cfs from May 16–31; from the                         number of the person protesting or                    auxiliary facilities, all known as its
                                              required 60 cfs to 18 cfs in June; from                 intervening; and (4) otherwise comply                 Jacksonville Expansion Project. The
                                              the required 40 cfs to 15 cfs in July; and              with the requirements of 18 CFR                       project will provide an initial 60,000
                                              from the required 18 cfs to 15 cfs in                   385.2001 through 385.2005. All                        MMBtu/d, and an expansion of 15,000
                                              August.                                                 comments, motions to intervene, or                    MMBtu/d of firm transportation to two
                                                 The licensee states that the revised                 protests must set forth their evidentiary             existing delivery points for Peoples Gas
                                              request is in response to worsening                     basis and otherwise comply with the                   System (PGS), a division of Tampa
                                              drought conditions in the project area,                 requirements of 18 CFR 4.34(b). All                   Electric Company all in Suwanee,
                                              including record low snowpack and                       comments, motions to intervene, or                    Bradford, Columbia and Clay Counties,
                                              accelerated spring runoff that has                      protests should relate to project works               Florida, all as more fully set forth in the
                                              occurred this year. The licensee also                   which are the subject of the variance.                application which is on file with the
                                              states that it maintains its previous                   Agencies may obtain copies of the                     Commission and open to public
                                              request for temporary flow variances in                 application directly from the applicant.              inspection. This filing may be viewed
                                              Caples Creek, Echo Creek, Silver Fork                   A copy of any protest or motion to                    on the web at http://www.ferc.gov using
                                              American River and Pyramid Creek.                       intervene must be served upon each                    the ‘‘eLibrary’’ link. Enter the docket
                                                 l. Locations of the Application: A                   representative of the applicant specified             number excluding the last three digits in
                                              copy of the application is available for                in the particular application. If an                  the docket number field to access the
                                              inspection and reproduction at the                      intervener files comments or documents                document. For assistance, please contact
                                              Commission’s Public Reference Room,                     with the Commission relating to the                   FERC at FERCOnlineSupport@ferc.gov
                                              located at 888 First Street NE., Room                   merits of an issue that may affect the                or call toll-free, (886) 208–3676 or TYY,
                                              2A, Washington, DC 20426, or by calling                 responsibilities of a particular resource             (202) 502–8659.
tkelley on DSK3SPTVN1PROD with NOTICES




                                              (202) 502–8371. This filing may also be                 agency, they must also serve a copy of                  Any questions regarding this
                                              viewed on the Commission’s Web site at                  the document on that resource agency.                 Application should be directed to
                                              http://www.ferc.gov/docs-filing/                        A copy of all other filings in reference              Stephen Veatch, Senior Director of
                                              elibrary.asp. Enter the docket number                   to this application must be accompanied               Certificates & Reporting, Florida Gas
                                              excluding the last three digits in the                  by proof of service on all persons listed             Transmission Company, LLC, 1300
                                              docket number field to access the                       in the service list prepared by the                   Main St., Houston, Texas, 77002, or call
                                              document. You may also register online                  Commission in this proceeding, in                     (713) 989–2024, or fax (713) 989–1205,


                                         VerDate Sep<11>2014   19:08 Apr 16, 2015   Jkt 235001   PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\17APN1.SGM   17APN1


                                              21234                            Federal Register / Vol. 80, No. 74 / Friday, April 17, 2015 / Notices

                                              or via eMail stephen.veatch@                            the party or parties directly involved in             that the Project involves: (i)
                                              energytransfer.com.                                     the protest.                                          Approximately 8.1 miles of new 36-inch
                                                 Pursuant to section 157.9 of the                        Persons who wish to comment only                   diameter pipeline looping in Tioga
                                              Commission’s rules, 18 CFR 157.9,                       on the environmental review of this                   County, Pennsylvania; (ii) pipeline
                                              within 90 days of this Notice the                       project should submit an original and                 modifications associated with the
                                              Commission staff will either: Complete                  two copies of their comments to the                   pipeline loops; (iii) modification to
                                              its environmental assessment (EA) and                   Secretary of the Commission.                          piping at three existing compressor
                                              place it into the Commission’s public                   Environmental commenters will be                      stations, which are Compressor Station
                                              record (eLibrary) for this proceeding; or               placed on the Commission’s                            315, Compressor Station 317, and
                                              issue a Notice of Schedule for                          environmental mailing list, will receive              Compressor Station 319; and (iv)
                                              Environmental Review. If a Notice of                    copies of the environmental documents,                increase in horsepower at two of the
                                              Schedule for Environmental Review is                    and will be notified of meetings                      three existing compressor stations.
                                              issued, it will indicate, among other                   associated with he Commission’s                       Tennessee estimates the cost of the
                                              milestones, the anticipated date for the                environmental review process.                         Project to be approximately $156.4
                                              Commission staff’s issuance of the final                Environmental commenters will not be                  million, all as more fully set forth in the
                                              environmental impact statement (FEIS)                   required to serve copies of filed                     application which is on file with the
                                              or EA for this proposal. The filing of the              documents on all other parties.                       Commission and open to public
                                              EA in the Commission’s public record                    However, the non-party commentary,                    inspection. The filing is available for
                                              for this proceeding or the issuance of a                will not receive copies of all documents              review at the Commission in the Public
                                              Notice of Schedule for Environmental                    filed by other parties or issued by the               Reference Room or may be viewed on
                                              Review will serve to notify federal and                 Commission (except for the mailing of                 the Commission’s Web site web at
                                              state agencies of the timing for the                    environmental documents issued by the                 http://www.ferc.gov using the
                                              completion of all necessary reviews, and                Commission) and ill not have the right                ‘‘eLibrary’’ link. Enter the docket
                                              the subsequent need to complete all                     to seek court review of the                           number excluding the last three digits in
                                              federal authorizations within 90 days of                Commission’s final order.                             the docket number field to access the
                                              the date of issuance of the Commission                     The Commission strongly encourages                 document. For assistance, contact FERC
                                              staff’s FEIS or EA.                                     electronic filings of comments, protests              at FERCOnlineSupport@ferc.gov or call
                                                 There are two ways to become                         and interventions in lieu of paper using              toll-free, (886) 208–3676 or TYY, (202)
                                              involved in the Commission’s review of                  the ‘‘eFiling’’ link at http://                       502–8659.
                                              this project. First, any person wishing to              www.ferc.gov. Persons unable to file                     Any questions concerning this
                                              obtain legal status by becoming a party                 electronically should submit an original              application may be directed to John E.
                                              to the proceedings for this project                     and 5 copies of the protest or                        Griffin, Assistant General Counsel,
                                              should, on or before the comment date                                                                         Tennessee Gas Pipeline Company,
                                                                                                      intervention to the Federal Energy
                                              stated below, file with the Federal                                                                           L.L.C., 1001 Louisiana Street, Houston,
                                                                                                      Regulatory Commission, 888 First Street
                                              Energy Regulatory Commission, 888                                                                             Texas 77002, phone: (713) 420–3624,
                                                                                                      NE., Washington, DC 20426. See, 18
                                              First Street NE., Washington, DC 20426,                                                                       facsimile: (713) 420–1601, email: John_
                                                                                                      CFR 385.2001(a)(1)(iii) and the
                                              a motion to intervene in accordance                                                                           Griffin2@kindermorgan.com.
                                                                                                      instructions on the Commission’s Web
                                              with the requirements of the                                                                                     Pursuant to section 157.9 of the
                                                                                                      site under the ‘‘e-Filing’’ link.
                                              Commission’s Rules of Practice and                                                                            Commission’s rules, 18 CFR 157.9,
                                                                                                         Comment Date: May 4, 2015.
                                              Procedure (18 CFR 385.214 or 385.211)                                                                         within 90 days of this Notice, the
                                              and the Regulations under the NGA (18                     Dated: April 13, 2015.                              Commission staff will either: Complete
                                              CFR 157.10). A person obtaining party                   Kimberly D. Bose,                                     its environmental assessment (EA) and
                                              status will be placed on the service list               Secretary.                                            place it into the Commission’s public
                                              maintained by the Secretary of the                      [FR Doc. 2015–08871 Filed 4–16–15; 8:45 am]           record (eLibrary) for this proceeding; or
                                              Commission and will receive copies of                   BILLING CODE 6717–01–P                                issue a Notice of Schedule for
                                              all documents filed by the applicant and                                                                      Environmental Review. If a Notice of
                                              by all other parties. A party must submit                                                                     Schedule for Environmental Review is
                                              7 copies of filings made with the                       DEPARTMENT OF ENERGY                                  issued, it will indicate, among other
                                              Commission and must mail a copy to                                                                            milestones, the anticipated date for the
                                              the applicant and to every other party in               Federal Energy Regulatory                             Commission staff’s issuance of the final
                                              the proceeding. Only parties to the                     Commission                                            environmental impact statement (FEIS)
                                              proceeding can ask for court review of                                                                        or EA for this proposal. The filing of the
                                                                                                      [Docket No. CP15–148–000]
                                              Commission orders in the proceeding.                                                                          EA in the Commission’s public record
                                                 However, a person does not have to                   Tennessee Gas Pipeline Company,                       for this proceeding or the issuance of a
                                              intervene in order to have comments                     L.L.C.; Notice of Application                         Notice of Schedule for Environmental
                                              considered. The second way to                                                                                 Review will serve to notify federal and
                                              participate is by filing with the                          Take notice that on April 2, 2015,                 state agencies of the timing for the
                                              Secretary of the Commission, as soon as                 Tennessee Gas Pipeline Company,                       completion of all necessary reviews, and
                                              possible, an original and two copies of                 L.L.C. (Tennessee), 1001 Louisiana                    the subsequent need to complete all
                                              comments in support of or in opposition                 Street, Houston, Texas 77002, filed an                federal authorizations within 90 days of
                                              to this project. The Commission will                    application pursuant to section 7(c) of               the date of issuance of the Commission
                                              consider these comments in                              the Natural Gas Act (NGA) requesting                  staff’s FEIS or EA.
tkelley on DSK3SPTVN1PROD with NOTICES




                                              determining the appropriate action to be                authorization to construct and operate                   There are two ways to become
                                              taken, but the filing of a comment alone                its Susquehanna West Project (Project)                involved in the Commission’s review of
                                              will not serve to make the filer a party                located in Pennsylvania. Tennessee                    this project. First, any person wishing to
                                              to the proceeding. The Commission’s                     asserts that the proposed Project will                obtain legal status by becoming a party
                                              rules require that persons filing                       increase east-to-west delivery capacity               to the proceedings for this project
                                              comments in opposition to the project                   in the region by approximately 145,000                should, on or before the comment date
                                              provide copies of their protests only to                dekatherms per day. Tennessee states                  stated below file with the Federal


                                         VerDate Sep<11>2014   19:08 Apr 16, 2015   Jkt 235001   PO 00000   Frm 00033   Fmt 4703   Sfmt 4703   E:\FR\FM\17APN1.SGM   17APN1



Document Created: 2015-12-18 11:20:30
Document Modified: 2015-12-18 11:20:30
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesMay 4, 2015.
FR Citation80 FR 21233 

2025 Federal Register | Disclaimer | Privacy Policy