80_FR_22824 80 FR 22746 - Nuclear Innovation North America LLC; South Texas Project, Units 3 and 4

80 FR 22746 - Nuclear Innovation North America LLC; South Texas Project, Units 3 and 4

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 80, Issue 78 (April 23, 2015)

Page Range22746-22747
FR Document2015-09517

On September 20, 2007, South Texas Project Nuclear Operating Company (STPNOC) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for combined licenses (COLs) for two additional units (Units 3 and 4) at the South Texas Project (STP) Electric Generating Station site in Matagorda County near Bay City, Texas. The NRC published a notice of receipt and availability for this COL application in the Federal Register on December 5, 2007. In a letter dated January 19, 2011, STPNOC notified the NRC that, effective January 24, 2011, Nuclear Innovation North America LLC (NINA) became the lead applicant for STP, Units 3 and 4. This notice is being published to notify the public of the availability of the COL application for STP, Units 3 and 4.

Federal Register, Volume 80 Issue 78 (Thursday, April 23, 2015)
[Federal Register Volume 80, Number 78 (Thursday, April 23, 2015)]
[Notices]
[Pages 22746-22747]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-09517]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-012 and 52-013; NRC-2008-0091]


Nuclear Innovation North America LLC; South Texas Project, Units 
3 and 4

AGENCY: Nuclear Regulatory Commission.

ACTION: Combined license application; availability.

-----------------------------------------------------------------------

SUMMARY: On September 20, 2007, South Texas Project Nuclear Operating 
Company (STPNOC) submitted to the U.S. Nuclear Regulatory Commission 
(NRC) an application for combined licenses (COLs) for two additional 
units (Units 3 and 4) at the South Texas Project (STP) Electric 
Generating Station site in Matagorda County near Bay City, Texas. The 
NRC published a notice of receipt and availability for this COL 
application in the Federal Register on December 5, 2007. In a letter 
dated January 19, 2011, STPNOC notified the NRC that, effective January 
24, 2011, Nuclear Innovation North America LLC (NINA) became the lead 
applicant for STP, Units 3 and 4. This notice is being published to 
notify the public of the availability of the COL application for STP, 
Units 3 and 4.

DATES: The COL application is available on April 23, 2015.

ADDRESSES: Please refer to Docket ID NRC-2008-0091 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0091. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/

[[Page 22747]]

adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it available in 
ADAMS) is provided the first time that a document is referenced. For 
the convenience of the reader, the ADAMS accession numbers are provided 
in a table in the ``Availability of Documents'' section of this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Tom Tai, telephone: 301-415-8484, 
email: [email protected]; or Luis Betancourt, telephone: 301-415-6145, 
email: [email protected]. Both are staff of the Office of New 
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001.

SUPPLEMENTARY INFORMATION: On September 20, 2007, the NRC received a 
COL application from STPNOC, filed pursuant to Section 103 of the 
Atomic Energy Act of 1954, as amended, and Part 52 of Title 10 of the 
Code of Federal Regulations (10 CFR), ``Licenses, Certifications, and 
Approvals for Nuclear Power Plants,'' to construct and operate two 
additional units (Units 3 and 4) at the STP Electric Generating Station 
site in Matagorda County near Bay City, Texas. The additional units are 
based on the U.S. Advanced Boiling Water Reactor design, which is 
certified in 10 CFR part 52, appendix A. The NRC published a notice of 
receipt and availability for an application for a COL in the Federal 
Register on December 5, 2007 (72 FR 68597). In a letter dated January 
19, 2011, STPNOC notified the NRC that, effective January 24, 2011, 
NINA became the lead applicant for STP, Units 3 and 4. As such, NINA 
assumed responsibility for the design, construction and licensing of 
STP, Units 3 and 4. The application is currently under review by the 
NRC.
    An applicant may seek a COL in accordance with Subpart C of 10 CFR 
part 52. The information submitted by the applicant includes certain 
administrative information, such as financial qualifications submitted 
pursuant to 10 CFR 52.77, as well as technical information submitted 
pursuant to 10 CFR 52.79. This notice is being provided in accordance 
with the requirements in 10 CFR 50.43(a)(3).

Availability of Documents

    The documents identified in the following table are available to 
interested persons through the ADAMS Public Documents collection. A 
copy of the COL application is also available for public inspection at 
the NRC's PDR and at http://www.nrc.gov/reactors/new-reactors/col.html.

 
------------------------------------------------------------------------
                Document                       ADAMS  Accession No.
------------------------------------------------------------------------
South Texas Project, Units 3 and 4,       ML072830407.
 Combined License Application, Revision
 0, September 20, 2007.
South Texas Project, Units 3 and 4,       ML072740461.
 Supplement to Combined License
 Application ``Safeguards Information,''
 Part 8, Revision 0, September 26, 2007.
South Texas Project, Units 3 and 4,       ML072960352.
 Supplement to Combined License
 Application Revision 0, October 15,
 2007.
South Texas Project, Units 3 and 4,       ML072960489.
 Supplement to Combined License
 Application Revision 0, October 18,
 2007.
South Texas Project, Units 3 and 4,       ML073200992.
 Supplement to Combined License
 Application Revision 0, November 13,
 2007.
South Texas Project, Units 3 and 4,       ML073310616.
 Supplement to Combined License
 Application Revision 0, November 21,
 2007.
South Texas Project, Units 3 and 4,       ML080700399.
 Combined License Application, Revision
 1, January 31, 2008.
South Texas Project, Units 3 and 4,       ML080420090.
 Submittal of Supplement to Combined
 License Application ``Safeguards
 Information,'' Part 8, Revision 1,
 January 31, 2008.
South Texas Project, Units 3 and 4,       ML082830938.
 Combined License Application, Revision
 2, September 24, 2008.
South Texas Project, Units 3 and 4,       ML082730700.
 Submittal of Supplement to Combined
 License Application ``Safeguards
 Information,'' Part 8, Revision 2,
 September 24, 2008.
South Texas Project, Units 3 and 4,       ML083530131.
 Submittal of Combined License
 Application, ``Proprietary
 Information,'' Part 10, Revision 2,
 December 11, 2008.
South Texas Project, Units 3 and 4,       ML092930393.
 Combined License Application, Revision
 3, September 16, 2009.
South Texas Project, Units 3 and 4,       ML102010268.
 Submittal of Supplement to Combined
 License Application ``Safeguards
 Information,'' Part 8, Revision 3, July
 15, 2010.
South Texas Project, Units 3 and 4,       ML102861292.
 Combined License Application, Revision
 4, October 5, 2010.
South Texas Project, Units 3 and 4,       ML110400425.
 Submittal of Supplement to Combined
 License Application ``Safeguards
 Information,'' Part 8, Revision 4,
 February 3, 2011.
South Texas Project, Units 3 and 4,       ML110250369.
 Update to Change in Lead Applicant,
 January 19, 2011.
South Texas Project, Units 3 and 4,       ML110340451.
 Combined License Application, Revision
 5, January 26, 2011.
South Texas Project, Units 3 and 4,       ML11243A171.
 Submittal of Supplement to Combined
 License Application ``Safeguards
 Information,'' Part 8, Revision 5,
 August 30, 2011.
South Texas Project, Units 3 and 4,       ML11252A505.
 Combined License Application, Revision
 6, August 30, 2011.
South Texas Project, Units 3 and 4,       ML12048A714.
 Combined License Application, Revision
 7, February 1, 2012.
South Texas Project, Units 3 and 4,       ML12291A415.
 Combined License Application, Revision
 8, September 17, 2012.
South Texas Project, Units 3 and 4,       ML13115A094.
 Combined License Application, Revision
 9, April 17, 2013.
South Texas Project, Units 3 and 4,       ML13310A599.
 Combined License Application, Revision
 10, October 29, 2013.
South Texas Project, Units 3 and 4,       ML14307A876.
 Combined License Application, Revision
 11, October 21, 2014.
------------------------------------------------------------------------


    Dated at Rockville, Maryland, this 14th day of April 2015.

    For the Nuclear Regulatory Commission.
Samuel Lee,
Chief, Licensing Branch 2, Division of New Reactor Licensing, Office of 
New Reactors.
[FR Doc. 2015-09517 Filed 4-22-15; 8:45 am]
BILLING CODE 7590-01-P



                                                  22746                         Federal Register / Vol. 80, No. 78 / Thursday, April 23, 2015 / Notices

                                                  Radium-226 and -228, Selenium,                          Environmental Impacts of the                             For the Nuclear Regulatory Commission.
                                                  Thorium-230, and Uranium for the                        Alternatives to the Proposed Action                   Craig G. Erlanger,
                                                  Southwest Alluvium, Zone 1, and Zone                                                                          Deputy Director, Division of Fuel Cycle Safety,
                                                  3. No changes are proposed for the other                  As an alternative to the proposed                   Safeguards and Environmental Review, Office
                                                  constituents in License Condition 30.B                  action, the NRC staff considered denial               of Nuclear Material Safety and Safeguards.
                                                  (i.e., Beryllium, Total Trihalomethanes,                of the proposed action (i.e., the ‘‘no-               [FR Doc. 2015–09516 Filed 4–22–15; 8:45 am]
                                                  and Vanadium).                                          action alternative’’). Denial of the                  BILLING CODE 7590–01–P
                                                                                                          proposed license amendment would
                                                  Need for the Proposed Action                            result in no change in the currently
                                                    The proposed action is needed to                      approved ground water protection                      NUCLEAR REGULATORY
                                                  provide ground water protection                         standards. The proposed action is                     COMMISSION
                                                  standards for the Mill Site that are                    needed to revise the ground water                     [Docket Nos. 52–012 and 52–013; NRC–
                                                  consistent with 10 CFR part 40,                         protection standards to more accurately               2008–0091]
                                                  appendix A, paragraph 5B(1) and                         reflect current background conditions.
                                                  background ground water quality that is                 Both the No-Action alternative and the                Nuclear Innovation North America
                                                  protective of public health and safety.                 Proposed Action for the Mill Site are                 LLC; South Texas Project, Units 3
                                                                                                          consistent with appendix A, criterion 5,              and 4
                                                  Environmental Impacts of the Proposed
                                                                                                          paragraph 5B(1) and background ground                 AGENCY:  Nuclear Regulatory
                                                  Action
                                                                                                          water quality that is protective of public            Commission.
                                                     The NRC staff determined that, due to                health and safety.                                    ACTION: Combined license application;
                                                  the nature of the proposed action,                                                                            availability.
                                                                                                          Agencies and Persons Consulted
                                                  environmental impacts would be
                                                  limited to subsurface ground water                        The NRC staff determined that the                   SUMMARY:   On September 20, 2007,
                                                  resources, and that such impacts would                  proposed action would be limited to                   South Texas Project Nuclear Operating
                                                  be small and not significant. Staff                     impacts to subsurface ground water                    Company (STPNOC) submitted to the
                                                  expects no impacts to public health and                 resources and therefore is not expected               U.S. Nuclear Regulatory Commission
                                                  safety, ecological resources, or historical             to affect listed endangered and                       (NRC) an application for combined
                                                  and cultural resources. Therefore, the                                                                        licenses (COLs) for two additional units
                                                                                                          threatened species or their critical
                                                  NRC staff does not expect significant                                                                         (Units 3 and 4) at the South Texas
                                                                                                          habitat. As well, the proposed action is
                                                  impacts to result from the proposed                                                                           Project (STP) Electric Generating Station
                                                                                                          not expected to impact potential or
                                                  modification to the ground water                                                                              site in Matagorda County near Bay City,
                                                                                                          identified cultural or historical
                                                  protection standards in SUA–1475 and                                                                          Texas. The NRC published a notice of
                                                                                                          resources. Therefore, no further
                                                  considers that impacts from the                                                                               receipt and availability for this COL
                                                                                                          consultation was completed under                      application in the Federal Register on
                                                  proposed action would be protective of                  Section 7 of the Endangered Species Act
                                                  public health and safety and the                                                                              December 5, 2007. In a letter dated
                                                                                                          or under Section 106 of the National                  January 19, 2011, STPNOC notified the
                                                  environment.
                                                                                                          Historic Preservation Act.                            NRC that, effective January 24, 2011,
                                                     In conducting its assessment, the NRC
                                                                                                            During preparation of the EA, the                   Nuclear Innovation North America LLC
                                                  staff considered the following:
                                                                                                          NRC staff consulted with the following                (NINA) became the lead applicant for
                                                     • Information in the license                         federal, tribal, and state agencies: the              STP, Units 3 and 4. This notice is being
                                                  application and supporting                              U.S. Environmental Protection Agency                  published to notify the public of the
                                                  documentation;                                          (EPA) Regions 6 and 9, the U.S.                       availability of the COL application for
                                                     • Information in modeling reports                    Department of Energy, the Navajo                      STP, Units 3 and 4.
                                                  and NRC staff review reports;                           Nation EPA, and the New Mexico                        DATES: The COL application is available
                                                     • Information in land use and                        Environment Department. The purpose                   on April 23, 2015.
                                                  environmental monitoring reports;                       of this consultation was to request                   ADDRESSES: Please refer to Docket ID
                                                     • Information from NRC staff site                    comments on the proposed action;                      NRC–2008–0091 when contacting the
                                                  visits and inspections;                                 however, none of the agencies identified              NRC about the availability of
                                                     • 10 CFR part 40, appendix A,                        concerns with the proposed action.                    information regarding this document.
                                                  ‘‘Criteria Relating to the Operation of                                                                       You may obtain publicly-available
                                                                                                          III. Finding of No Significant Impact
                                                  Uranium Mills and the Disposition of                                                                          information related to this document
                                                  Tailings or Wastes Produced by the                         Based on its review of the UNC’s                   using any of the following methods:
                                                  Extraction or Concentration of Source                   license amendment request to revise                      • Federal Rulemaking Web site: Go to
                                                  Material From Ores Processed Primarily                  License Condition 30.B of SUA–1475,                   http://www.regulations.gov and search
                                                  for Their Source Material Content;’’                    the NRC staff expects there to be no                  for Docket ID NRC–2008–0091. Address
                                                                                                          significant environmental impacts in                  questions about NRC dockets to Carol
                                                     • NUREG–1620, Rev. 1, ‘‘Standard                                                                           Gallagher; telephone: 301–415–3463;
                                                  Review Plan for the Review of a                         connection with the proposed action as
                                                                                                          the proposed ground water protection                  email: Carol.Gallagher@nrc.gov. For
                                                  Reclamation Plan for Mill Tailings Sites                                                                      technical questions, contact the
                                                  Under Title II of the Uranium Mill                      standard values, conceptually, pose no
                                                                                                                                                                individual listed in the FOR FURTHER
                                                  Tailings Radiation Control Act of 1978’’                incremental hazards to public health
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                                                                INFORMATION CONTACT section of this
                                                  (ADAMS Accession No. ML031550522);                      and safety. Therefore, a Finding of No
                                                                                                                                                                document.
                                                  and                                                     Significant Impact (FONSI) is                            • NRC’s Agencywide Documents
                                                     • NUREG–1748, ‘‘Environmental                        appropriate and preparation of an                     Access and Management System
                                                  Review Guidance for Licensing Actions                   Environmental Impact Statement is not                 (ADAMS): You may obtain publicly
                                                  Associated with NMSS Programs, Final                    warranted.                                            available documents online in the
                                                  Report’’ (ADAMS Accession No.                             Dated at Rockville, Maryland, this 9th day          ADAMS Public Documents collection at
                                                  ML032540811).                                           of April 2015.                                        http://www.nrc.gov/reading-rm/


                                             VerDate Sep<11>2014   18:53 Apr 22, 2015   Jkt 235001   PO 00000   Frm 00046   Fmt 4703   Sfmt 4703   E:\FR\FM\23APN1.SGM   23APN1


                                                                                Federal Register / Vol. 80, No. 78 / Thursday, April 23, 2015 / Notices                                                    22747

                                                  adams.html. To begin the search, select                 of the Office of New Reactors, U.S.                    STP, Units 3 and 4. As such, NINA
                                                  ‘‘ADAMS Public Documents’’ and then                     Nuclear Regulatory Commission,                         assumed responsibility for the design,
                                                  select ‘‘Begin Web-based ADAMS                          Washington, DC 20555–0001.                             construction and licensing of STP, Units
                                                  Search.’’ For problems with ADAMS,                      SUPPLEMENTARY INFORMATION: On                          3 and 4. The application is currently
                                                  please contact the NRC’s Public                         September 20, 2007, the NRC received                   under review by the NRC.
                                                  Document Room (PDR) reference staff at                  a COL application from STPNOC, filed                      An applicant may seek a COL in
                                                  1–800–397–4209, 301–415–4737, or by                     pursuant to Section 103 of the Atomic                  accordance with Subpart C of 10 CFR
                                                  email to pdr.resource@nrc.gov. The                      Energy Act of 1954, as amended, and                    part 52. The information submitted by
                                                  ADAMS accession number for each                         Part 52 of Title 10 of the Code of Federal             the applicant includes certain
                                                  document referenced (if it available in                 Regulations (10 CFR), ‘‘Licenses,                      administrative information, such as
                                                  ADAMS) is provided the first time that                  Certifications, and Approvals for                      financial qualifications submitted
                                                  a document is referenced. For the                       Nuclear Power Plants,’’ to construct and               pursuant to 10 CFR 52.77, as well as
                                                  convenience of the reader, the ADAMS                    operate two additional units (Units 3                  technical information submitted
                                                  accession numbers are provided in a                     and 4) at the STP Electric Generating                  pursuant to 10 CFR 52.79. This notice
                                                  table in the ‘‘Availability of Documents’’              Station site in Matagorda County near                  is being provided in accordance with
                                                  section of this document.                               Bay City, Texas. The additional units                  the requirements in 10 CFR 50.43(a)(3).
                                                     • NRC’s PDR: You may examine and                     are based on the U.S. Advanced Boiling
                                                  purchase copies of public documents at                  Water Reactor design, which is certified               Availability of Documents
                                                  the NRC’s PDR, Room O1–F21, One                         in 10 CFR part 52, appendix A. The                        The documents identified in the
                                                  White Flint North, 11555 Rockville                      NRC published a notice of receipt and                  following table are available to
                                                  Pike, Rockville, Maryland 20852.                        availability for an application for a COL              interested persons through the ADAMS
                                                  FOR FURTHER INFORMATION CONTACT: Tom                    in the Federal Register on December 5,                 Public Documents collection. A copy of
                                                  Tai, telephone: 301–415–8484, email:                    2007 (72 FR 68597). In a letter dated                  the COL application is also available for
                                                  Tom.Tai@nrc.gov; or Luis Betancourt,                    January 19, 2011, STPNOC notified the                  public inspection at the NRC’s PDR and
                                                  telephone: 301–415–6145, email:                         NRC that, effective January 24, 2011,                  at http://www.nrc.gov/reactors/new-
                                                  Luis.Betancourt@nrc.gov. Both are staff                 NINA became the lead applicant for                     reactors/col.html.



                                                                                                                                                                                                        ADAMS
                                                                                                                    Document                                                                         Accession No.

                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 0, September 20, 2007 ........................................         ML072830407.
                                                  South Texas Project, Units 3 and 4, Supplement to Combined License Application ‘‘Safeguards Information,’’ Part 8, Revision                       ML072740461.
                                                    0, September 26, 2007.
                                                  South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, October 15, 2007 .....................                 ML072960352.
                                                  South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, October 18, 2007 .....................                 ML072960489.
                                                  South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, November 13, 2007 .................                    ML073200992.
                                                  South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, November 21, 2007 .................                    ML073310616.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 1, January 31, 2008 .............................................      ML080700399.
                                                  South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part                      ML080420090.
                                                    8, Revision 1, January 31, 2008.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 2, September 24, 2008 ........................................         ML082830938.
                                                  South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part                      ML082730700.
                                                    8, Revision 2, September 24, 2008.
                                                  South Texas Project, Units 3 and 4, Submittal of Combined License Application, ‘‘Proprietary Information,’’ Part 10, Revision                     ML083530131.
                                                    2, December 11, 2008.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 3, September 16, 2009 ........................................         ML092930393.
                                                  South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part                      ML102010268.
                                                    8, Revision 3, July 15, 2010.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 4, October 5, 2010 ...............................................     ML102861292.
                                                  South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part                      ML110400425.
                                                    8, Revision 4, February 3, 2011.
                                                  South Texas Project, Units 3 and 4, Update to Change in Lead Applicant, January 19, 2011 ......................................................   ML110250369.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 5, January 26, 2011 .............................................      ML110340451.
                                                  South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part                      ML11243A171.
                                                    8, Revision 5, August 30, 2011.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 6, August 30, 2011 ..............................................      ML11252A505.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 7, February 1, 2012 .............................................      ML12048A714.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 8, September 17, 2012 ........................................         ML12291A415.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 9, April 17, 2013 ..................................................   ML13115A094.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 10, October 29, 2013 ...........................................       ML13310A599.
                                                  South Texas Project, Units 3 and 4, Combined License Application, Revision 11, October 21, 2014 ...........................................       ML14307A876.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                    Dated at Rockville, Maryland, this 14th day             For the Nuclear Regulatory Commission.
                                                  of April 2015.                                          Samuel Lee,
                                                                                                          Chief, Licensing Branch 2, Division of New
                                                                                                          Reactor Licensing, Office of New Reactors.
                                                                                                          [FR Doc. 2015–09517 Filed 4–22–15; 8:45 am]
                                                                                                          BILLING CODE 7590–01–P




                                             VerDate Sep<11>2014   18:53 Apr 22, 2015   Jkt 235001   PO 00000   Frm 00047   Fmt 4703   Sfmt 9990   E:\FR\FM\23APN1.SGM   23APN1



Document Created: 2015-12-16 08:41:20
Document Modified: 2015-12-16 08:41:20
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionCombined license application; availability.
DatesThe COL application is available on April 23, 2015.
ContactTom Tai, telephone: 301-415-8484, email: [email protected]; or Luis Betancourt, telephone: 301-415-6145, email: [email protected] Both are staff of the Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555- 0001.
FR Citation80 FR 22746 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR