80_FR_26191 80 FR 26104 - Nuclear Innovation North America LLC; South Texas Project, Units 3 and 4

80 FR 26104 - Nuclear Innovation North America LLC; South Texas Project, Units 3 and 4

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 80, Issue 87 (May 6, 2015)

Page Range26104-26105
FR Document2015-10492

On September 20, 2007, South Texas Project Nuclear Operating Company (STPNOC) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for combined licenses (COLs) for two additional units (Units 3 and 4) at the South Texas Project (STP) Electric Generating Station site in Matagorda County near Bay City, Texas. The NRC published a notice of receipt and availability for this COL application in the Federal Register on December 5, 2007. In a letter dated January 19, 2011, STPNOC notified the NRC that, effective January 24, 2011, Nuclear Innovation North America LLC (NINA) became the lead applicant for STP, Units 3 and 4. This notice is being published to notify the public of the availability of the COL application for STP, Units 3 and 4.

Federal Register, Volume 80 Issue 87 (Wednesday, May 6, 2015)
[Federal Register Volume 80, Number 87 (Wednesday, May 6, 2015)]
[Notices]
[Pages 26104-26105]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-10492]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-012 and 52-013; NRC-2008-0091]


Nuclear Innovation North America LLC; South Texas Project, Units 
3 and 4

AGENCY: Nuclear Regulatory Commission.

ACTION: Combined license application; availability.

-----------------------------------------------------------------------

SUMMARY: On September 20, 2007, South Texas Project Nuclear Operating 
Company (STPNOC) submitted to the U.S. Nuclear Regulatory Commission 
(NRC) an application for combined licenses (COLs) for two additional 
units (Units 3 and 4) at the South Texas Project (STP) Electric 
Generating Station site in Matagorda County near Bay City, Texas. The 
NRC published a notice of receipt and availability for this COL 
application in the Federal Register on December 5, 2007. In a letter 
dated January 19, 2011, STPNOC notified the NRC that, effective January 
24, 2011, Nuclear Innovation North America LLC (NINA) became the lead 
applicant for STP, Units 3 and 4. This notice is being published to 
notify the public of the availability of the COL application for STP, 
Units 3 and 4.

DATES: The COL application is available on May 6, 2015.

ADDRESSES: Please refer to Docket ID NRC-2008-0091 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0091. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it available in 
ADAMS) is provided the first time that a document is referenced. For 
the convenience of the reader, the ADAMS accession numbers are provided 
in a table in the ``Availability of Documents'' section of this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Tom Tai, telephone: 301-415-8484, 
email: [email protected]; or Luis Betancourt, telephone: 301-415-6145, 
email: [email protected]. Both are staff of the Office of New 
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001.

SUPPLEMENTARY INFORMATION: On September 20, 2007, the NRC received a 
COL application from STPNOC, filed pursuant to Section 103 of the 
Atomic Energy Act of 1954, as amended, and part 52 of Title 10 of the 
Code of Federal Regulations (10 CFR), ``Licenses, Certifications, and 
Approvals for Nuclear Power Plants,'' to construct and operate two 
additional units (Units 3 and 4) at the STP Electric Generating Station 
site in Matagorda County near Bay City, Texas. The additional units are 
based on the U.S. Advanced Boiling Water Reactor design, which is 
certified in 10 CFR part 52, appendix A. The NRC published a notice of 
receipt and availability for an application for a COL in the Federal 
Register on December 5, 2007 (72 FR 68597). In a letter dated January 
19, 2011, STPNOC notified the NRC that, effective January 24, 2011, 
NINA became the lead applicant for STP, Units 3 and 4. As such, NINA 
assumed responsibility for the design, construction and licensing of 
STP, Units 3 and 4. The application is currently under review by the 
NRC.
    An applicant may seek a COL in accordance with subpart C of 10 CFR 
part 52. The information submitted by the applicant includes certain 
administrative information, such as financial qualifications submitted 
pursuant to 10 CFR 52.77, as well as technical information submitted 
pursuant to 10 CFR 52.79. This notice is being provided in accordance 
with the requirements in 10 CFR 50.43(a)(3).

Availability of Documents

    The documents identified in the following table are available to 
interested persons through the ADAMS Public Documents collection. A 
copy of the COL application is also available for public inspection at 
the NRC's PDR and at http://www.nrc.gov/reactors/new-reactors/col.html.

------------------------------------------------------------------------
                                                        Adams Accession
                       Document                               No.
------------------------------------------------------------------------
South Texas Project, Units 3 and 4, Combined License         ML072830407
 Application, Revision 0, September 20, 2007.........
South Texas Project, Units 3 and 4, Supplement to            ML072740461
 Combined License Application ``Safeguards
 Information,'' Part 8, Revision 0, September 26,
 2007................................................
South Texas Project, Units 3 and 4, Supplement to            ML072960352
 Combined License Application Revision 0, October 15,
 2007................................................
South Texas Project, Units 3 and 4, Supplement to            ML072960489
 Combined License Application Revision 0, October 18,
 2007................................................
South Texas Project, Units 3 and 4, Supplement to            ML073200992
 Combined License Application Revision 0, November
 13, 2007............................................
South Texas Project, Units 3 and 4, Supplement to            ML073310616
 Combined License Application Revision 0, November
 21, 2007............................................
South Texas Project, Units 3 and 4, Combined License         ML080700399
 Application, Revision 1, January 31, 2008...........
South Texas Project, Units 3 and 4, Submittal of             ML080420090
 Supplement to Combined License Application
 ``Safeguards Information,'' Part 8, Revision 1,
 January 31, 2008....................................
South Texas Project, Units 3 and 4, Combined License         ML082830938
 Application, Revision 2, September 24, 2008.........
South Texas Project, Units 3 and 4, Submittal of             ML082730700
 Supplement to Combined License Application
 ``Safeguards Information,'' Part 8, Revision 2,
 September 24, 2008..................................
South Texas Project, Units 3 and 4, Submittal of             ML083530131
 Combined License Application, ``Proprietary
 Information,'' Part 10, Revision 2, December 11,
 2008................................................
South Texas Project, Units 3 and 4, Combined License         ML092930393
 Application, Revision 3, September 16, 2009.........

[[Page 26105]]

 
South Texas Project, Units 3 and 4, Submittal of             ML102010268
 Supplement to Combined License Application
 ``Safeguards Information,'' Part 8, Revision 3, July
 15, 2010............................................
South Texas Project, Units 3 and 4, Combined License         ML102861292
 Application, Revision 4, October 5, 2010............
South Texas Project, Units 3 and 4, Submittal of             ML110400425
 Supplement to Combined License Application
 ``Safeguards Information,'' Part 8, Revision 4,
 February 3, 2011....................................
South Texas Project, Units 3 and 4, Update to Change         ML110250369
 in Lead Applicant, January 19, 2011.................
South Texas Project, Units 3 and 4, Combined License         ML110340451
 Application, Revision 5, January 26, 2011...........
South Texas Project, Units 3 and 4, Submittal of             ML11243A171
 Supplement to Combined License Application
 ``Safeguards Information,'' Part 8, Revision 5,
 August 30, 2011.....................................
South Texas Project, Units 3 and 4, Combined License         ML11252A505
 Application, Revision 6, August 30, 2011............
South Texas Project, Units 3 and 4, Combined License         ML12048A714
 Application, Revision 7, February 1, 2012...........
South Texas Project, Units 3 and 4, Combined License         ML12291A415
 Application, Revision 8, September 17, 2012.........
South Texas Project, Units 3 and 4, Combined License         ML13115A094
 Application, Revision 9, April 17, 2013.............
South Texas Project, Units 3 and 4, Combined License         ML13310A599
 Application, Revision 10, October 29, 2013..........
South Texas Project, Units 3 and 4, Combined License         ML14307A876
 Application, Revision 11, October 21, 2014..........
------------------------------------------------------------------------


    Dated at Rockville, Maryland, this 29th day of April 2015.

    For the Nuclear Regulatory Commission.
Samuel Lee,
Chief, Licensing Branch 2, Division of New Reactor Licensing, Office of 
New Reactors.
[FR Doc. 2015-10492 Filed 5-5-15; 8:45 am]
 BILLING CODE 7590-01-P



                                              26104                                   Federal Register / Vol. 80, No. 87 / Wednesday, May 6, 2015 / Notices

                                                For the Nuclear Regulatory Commission.                                information regarding this document.                                    SUPPLEMENTARY INFORMATION:     On
                                              A. Louise Lund,                                                         You may obtain publicly-available                                       September 20, 2007, the NRC received
                                              Acting Director, Division of Operating Reactor                          information related to this document                                    a COL application from STPNOC, filed
                                              Licensing, Office of Nuclear Reactor                                    using any of the following methods:                                     pursuant to Section 103 of the Atomic
                                              Regulation.                                                                • Federal Rulemaking Web site: Go to                                 Energy Act of 1954, as amended, and
                                              [FR Doc. 2015–10494 Filed 5–5–15; 8:45 am]                              http://www.regulations.gov and search                                   part 52 of Title 10 of the Code of Federal
                                              BILLING CODE 7590–01–P                                                  for Docket ID NRC–2008–0091. Address                                    Regulations (10 CFR), ‘‘Licenses,
                                                                                                                      questions about NRC dockets to Carol                                    Certifications, and Approvals for
                                                                                                                      Gallagher; telephone: 301–415–3463;                                     Nuclear Power Plants,’’ to construct and
                                              NUCLEAR REGULATORY                                                      email: Carol.Gallagher@nrc.gov. For                                     operate two additional units (Units 3
                                              COMMISSION                                                              technical questions, contact the                                        and 4) at the STP Electric Generating
                                              [Docket Nos. 52–012 and 52–013; NRC–
                                                                                                                      individual listed in the FOR FURTHER                                    Station site in Matagorda County near
                                              2008–0091]                                                              INFORMATION CONTACT section of this                                     Bay City, Texas. The additional units
                                                                                                                      document.                                                               are based on the U.S. Advanced Boiling
                                              Nuclear Innovation North America                                           • NRC’s Agencywide Documents                                         Water Reactor design, which is certified
                                              LLC; South Texas Project, Units 3                                       Access and Management System                                            in 10 CFR part 52, appendix A. The
                                              and 4                                                                   (ADAMS): You may obtain publicly                                        NRC published a notice of receipt and
                                                                                                                      available documents online in the                                       availability for an application for a COL
                                              AGENCY:  Nuclear Regulatory                                             ADAMS Public Documents collection at                                    in the Federal Register on December 5,
                                              Commission.                                                             http://www.nrc.gov/reading-rm/                                          2007 (72 FR 68597). In a letter dated
                                              ACTION: Combined license application;                                   adams.html. To begin the search, select                                 January 19, 2011, STPNOC notified the
                                              availability.                                                           ‘‘ADAMS Public Documents’’ and then                                     NRC that, effective January 24, 2011,
                                                                                                                      select ‘‘Begin Web-based ADAMS                                          NINA became the lead applicant for
                                              SUMMARY:   On September 20, 2007,                                       Search.’’ For problems with ADAMS,                                      STP, Units 3 and 4. As such, NINA
                                              South Texas Project Nuclear Operating                                   please contact the NRC’s Public                                         assumed responsibility for the design,
                                              Company (STPNOC) submitted to the                                       Document Room (PDR) reference staff at                                  construction and licensing of STP, Units
                                              U.S. Nuclear Regulatory Commission                                      1–800–397–4209, 301–415–4737, or by                                     3 and 4. The application is currently
                                              (NRC) an application for combined                                       email to pdr.resource@nrc.gov. The                                      under review by the NRC.
                                              licenses (COLs) for two additional units                                ADAMS accession number for each                                            An applicant may seek a COL in
                                              (Units 3 and 4) at the South Texas                                      document referenced (if it available in                                 accordance with subpart C of 10 CFR
                                              Project (STP) Electric Generating Station                               ADAMS) is provided the first time that                                  part 52. The information submitted by
                                              site in Matagorda County near Bay City,                                 a document is referenced. For the                                       the applicant includes certain
                                              Texas. The NRC published a notice of                                    convenience of the reader, the ADAMS                                    administrative information, such as
                                              receipt and availability for this COL                                   accession numbers are provided in a                                     financial qualifications submitted
                                              application in the Federal Register on                                  table in the ‘‘Availability of Documents’’                              pursuant to 10 CFR 52.77, as well as
                                              December 5, 2007. In a letter dated                                     section of this document.                                               technical information submitted
                                              January 19, 2011, STPNOC notified the                                      • NRC’s PDR: You may examine and                                     pursuant to 10 CFR 52.79. This notice
                                              NRC that, effective January 24, 2011,                                   purchase copies of public documents at                                  is being provided in accordance with
                                              Nuclear Innovation North America LLC                                    the NRC’s PDR, Room O1–F21, One                                         the requirements in 10 CFR 50.43(a)(3).
                                              (NINA) became the lead applicant for                                    White Flint North, 11555 Rockville
                                              STP, Units 3 and 4. This notice is being                                Pike, Rockville, Maryland 20852.                                        Availability of Documents
                                              published to notify the public of the                                   FOR FURTHER INFORMATION CONTACT: Tom                                       The documents identified in the
                                              availability of the COL application for                                 Tai, telephone: 301–415–8484, email:                                    following table are available to
                                              STP, Units 3 and 4.                                                     Tom.Tai@nrc.gov; or Luis Betancourt,                                    interested persons through the ADAMS
                                              DATES: The COL application is available                                 telephone: 301–415–6145, email:                                         Public Documents collection. A copy of
                                              on May 6, 2015.                                                         Luis.Betancourt@nrc.gov. Both are staff                                 the COL application is also available for
                                              ADDRESSES: Please refer to Docket ID                                    of the Office of New Reactors, U.S.                                     public inspection at the NRC’s PDR and
                                              NRC–2008–0091 when contacting the                                       Nuclear Regulatory Commission,                                          at http://www.nrc.gov/reactors/new-
                                              NRC about the availability of                                           Washington, DC 20555–0001.                                              reactors/col.html.

                                                                                                                                                                                                                                       Adams Accession
                                                                                                                                 Document                                                                                                   No.

                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 0, September 20, 2007 .....................................                                                      ML072830407
                                              South Texas Project, Units 3 and 4, Supplement to Combined License Application ‘‘Safeguards Information,’’ Part 8, Revi-
                                                sion 0, September 26, 2007 ......................................................................................................................................................         ML072740461
                                              South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, October 15, 2007 ..................                                                              ML072960352
                                              South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, October 18, 2007 ..................                                                              ML072960489
                                              South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, November 13, 2007 ..............                                                                 ML073200992
                                              South Texas Project, Units 3 and 4, Supplement to Combined License Application Revision 0, November 21, 2007 ..............                                                                 ML073310616
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 1, January 31, 2008 ..........................................                                                   ML080700399
                                              South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’
tkelley on DSK3SPTVN1PROD with NOTICES




                                                Part 8, Revision 1, January 31, 2008 ........................................................................................................................................             ML080420090
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 2, September 24, 2008 .....................................                                                      ML082830938
                                              South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’
                                                Part 8, Revision 2, September 24, 2008 ...................................................................................................................................                ML082730700
                                              South Texas Project, Units 3 and 4, Submittal of Combined License Application, ‘‘Proprietary Information,’’ Part 10, Revision
                                                2, December 11, 2008 ...............................................................................................................................................................      ML083530131
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 3, September 16, 2009 .....................................                                                      ML092930393



                                         VerDate Sep<11>2014        18:43 May 05, 2015        Jkt 235001      PO 00000       Frm 00110       Fmt 4703      Sfmt 4703      E:\FR\FM\06MYN1.SGM             06MYN1


                                                                                     Federal Register / Vol. 80, No. 87 / Wednesday, May 6, 2015 / Notices                                                                                 26105

                                                                                                                                                                                                                                   Adams Accession
                                                                                                                               Document                                                                                                 No.

                                              South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’
                                                Part 8, Revision 3, July 15, 2010 ..............................................................................................................................................      ML102010268
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 4, October 5, 2010 ............................................                                              ML102861292
                                              South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’
                                                Part 8, Revision 4, February 3, 2011 ........................................................................................................................................         ML110400425
                                              South Texas Project, Units 3 and 4, Update to Change in Lead Applicant, January 19, 2011 ...................................................                                            ML110250369
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 5, January 26, 2011 ..........................................                                               ML110340451
                                              South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’
                                                Part 8, Revision 5, August 30, 2011 ..........................................................................................................................................        ML11243A171
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 6, August 30, 2011 ...........................................                                               ML11252A505
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 7, February 1, 2012 ..........................................                                               ML12048A714
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 8, September 17, 2012 .....................................                                                  ML12291A415
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 9, April 17, 2013 ...............................................                                            ML13115A094
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 10, October 29, 2013 ........................................                                                ML13310A599
                                              South Texas Project, Units 3 and 4, Combined License Application, Revision 11, October 21, 2014 ........................................                                                ML14307A876



                                                Dated at Rockville, Maryland, this 29th day                         reporting the burden, including                                        of the Foreign Assistance Act of 1961,
                                              of April 2015.                                                        automated collected techniques and                                     as amended.
                                                For the Nuclear Regulatory Commission.                              uses of other forms of technology.                                        Abstract (Needs and Uses): The
                                              Samuel Lee,                                                           DATES: Comments must be received                                       information provided in the OPIC–129
                                              Chief, Licensing Branch 2, Division of New                            within thirty (30) calendar days of                                    is used by OPIC as a part of the
                                              Reactor Licensing, Office of New Reactors.                            publication of this Notice.                                            Character Risk Due Diligence/
                                              [FR Doc. 2015–10492 Filed 5–5–15; 8:45 am]                                                                                                   background check procedure (similar to
                                                                                                                    ADDRESSES: Mail all comments and
                                                                                                                                                                                           a commercial bank’s Know Your
                                              BILLING CODE 7590–01–P                                                requests for copies of the subject form
                                                                                                                                                                                           Customer procedure) that it performs on
                                                                                                                    to OPIC’s Agency Submitting Officer:
                                                                                                                                                                                           each party that has a significant
                                                                                                                    James Bobbitt, Overseas Private
                                              OVERSEAS PRIVATE INVESTMENT                                                                                                                  relationship (10% or more beneficial
                                                                                                                    Investment Corporation, 1100 New York
                                              CORPORATION                                                                                                                                  ownership, provision of significant
                                                                                                                    Avenue NW., Washington, DC 20527.
                                                                                                                                                                                           credit support, significant managerial
                                                                                                                    See SUPPLEMENTARY INFORMATION for
                                              Submission for OMB Review;                                                                                                                   relationship) to the projects that OPIC
                                                                                                                    other information about filing.
                                              Comments Request                                                                                                                             finances. The threshold has been
                                                                                                                    FOR FURTHER INFORMATION CONTACT:                                       changed from 5% to 10% in order to
                                              AGENCY: Overseas Private Investment                                   OPIC Agency Submitting Officer: James                                  make OPIC’s due diligence process more
                                              Corporation (OPIC).                                                   Bobbitt, (202) 336–8558.                                               efficient and less resource intensive
                                              ACTION: Notice and request for                                        SUPPLEMENTARY INFORMATION: All mailed                                  without significantly increasing the
                                              comments; correction.                                                 comments and requests for copies of the                                reputational and project risks associated
                                                                                                                    subject form should include form                                       with OPIC transactions.
                                              SUMMARY:   OPIC published a duplicate                                 number OPIC–129 on both the envelope                                     Dated: May 1, 2015.
                                              sixty day notice in the Federal Register                              and in the subject line of the letter.
                                              on May 1, 2015 at 80 FR 24985. This                                                                                                          Nichole Cadiente,
                                                                                                                    Electronic comments and requests for
                                              notice replaces the May 1st publication                                                                                                      Administrative Counsel, Department of Legal
                                                                                                                    copies of the subject form may be sent                                 Affairs.
                                              with the correct thirty day notice as                                 to James.Bobbitt@opic.gov, subject line
                                              required by the Paperwork Reduction                                                                                                          [FR Doc. 2015–10547 Filed 5–5–15; 8:45 am]
                                                                                                                    OPIC–129.
                                              Action (44 U.S.C. Chapter 35).                                                                                                               BILLING CODE 3210–01–P
                                                Under the provisions of the                                         Summary Form Under Review
                                              Paperwork Reduction Act, agencies are                                   Type of Request: Revision of currently
                                              required to publish a Notice in the                                   approved information collection.                                       OFFICE OF SCIENCE AND
                                              Federal Register notifying the public                                   Title: Sponsor Disclosure Report.                                    TECHNOLOGY POLICY
                                              that the agency is modifying and                                        Form Number: OPIC–129.
                                              renewing an existing previously                                         Frequency of Use: One per investor                                   Request for Information: Public Input
                                              approved information collection for                                   per project.                                                           on the Sustained Assessment Process
                                              OMB review and approval and requests                                    Type of Respondents: Business or                                     of the U.S. National Climate
                                              public review and comment on the                                      other institution (except farms);                                      Assessment
                                              submission. OPIC received no                                          individuals.                                                           ACTION:Notice of Request for
                                              comments in response to the sixty (60)                                  Standard Industrial Classification                                   Information.
                                              day notice published in Federal                                       Codes: All.
                                              Register volume 80 page 10522 on                                        Description of Affected Public: U.S.                                 SUMMARY:  The U.S. Global Change
                                              February 26, 2015. The purpose of this                                companies or citizens investing                                        Research Program (USGCRP) has a legal
                                              notice is to allow an additional thirty                               overseas.                                                              mandate to conduct a National Climate
tkelley on DSK3SPTVN1PROD with NOTICES




                                              (30) days for public comments to be                                     Reporting Hours: 1,890 (3 hours per                                  Assessment (NCA) not less frequently
                                              submitted. Comments are being                                         form).                                                                 than every four years. Under its current
                                              solicited on the need for the                                           Number of Responses: 630 per year.                                   decadal strategic plan (http://
                                              information; the accuracy of OPIC’s                                     Federal Cost: $64,801.80 ($51.43 ×                                   go.usa.gov/3qGU4), USGCRP is building
                                              burden estimate; the quality, practical                               630 × 2).                                                              sustained assessment capacity to
                                              utility, and clarity of the information to                              Authority for Information Collection:                                support the Nation’s ability to
                                              be collected; and ways to minimize                                    Sections 231, 234(a), 239(d), and 240A                                 understand, anticipate, and respond to


                                         VerDate Sep<11>2014       18:43 May 05, 2015        Jkt 235001      PO 00000      Frm 00111      Fmt 4703      Sfmt 4703      E:\FR\FM\06MYN1.SGM            06MYN1



Document Created: 2015-12-16 07:41:53
Document Modified: 2015-12-16 07:41:53
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionCombined license application; availability.
DatesThe COL application is available on May 6, 2015.
ContactTom Tai, telephone: 301-415-8484, email: [email protected]; or Luis Betancourt, telephone: 301-415-6145, email: [email protected] Both are staff of the Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555- 0001.
FR Citation80 FR 26104 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR