80_FR_26390 80 FR 26302 - DTE Electric Company; Fermi 3

80 FR 26302 - DTE Electric Company; Fermi 3

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 80, Issue 88 (May 7, 2015)

Page Range26302-26303
FR Document2015-11038

The U.S. Nuclear Regulatory Commission (NRC) is providing notice of the issuance of Combined License (COL), NPF-95 to DTE Electric Company (DTE, formerly Detroit Edison Company) and Record of Decision.

Federal Register, Volume 80 Issue 88 (Thursday, May 7, 2015)
[Federal Register Volume 80, Number 88 (Thursday, May 7, 2015)]
[Notices]
[Pages 26302-26303]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-11038]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 52-033; NRC-2008-0566]


DTE Electric Company; Fermi 3

AGENCY: Nuclear Regulatory Commission.

ACTION: Combined license and record of decision; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is providing 
notice of the issuance of Combined License (COL), NPF-95 to DTE 
Electric Company (DTE, formerly Detroit Edison Company) and Record of 
Decision.

ADDRESSES: Please refer to Docket ID NRC-2008-0566 when contacting the 
NRC about the availability of information regarding this document. You 
may access publicly-available information related to this document 
using any of the following methods:
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Douments'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The 
ADAMS accession number for each document referenced in this document 
(if that document is available in ADAMS) is provided at the end of this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Adrian Mu[ntilde]iz, Office of New 
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-4093, email: Adrian.Muniz@nrc.gov regarding 
safety matters; or Mallecia Sutton, at 301-415-0673, email: 
Mallecia.Sutton@nrc.gov regarding environmental matters.

SUPPLEMENTARY INFORMATION:

I. Introduction

    Under section 2.106 of Title 10 of the Code of Federal Regulations 
(10 CFR), the NRC is providing notice of the issuance of COL NPF-95 to 
DTE and, under 10 CFR 51.102(c), the Record of Decision (ROD). With 
respect to the application for the COL filed by DTE, the NRC finds that 
the applicable standards and requirements of the Atomic Energy Act of 
1954, as amended, and the Commission's regulations have been met. The 
NRC finds that any required notifications to other agencies or bodies 
have been duly made and that there is reasonable assurance that the 
facility will be constructed and will operate in conformity with the 
license, as amended, the provisions of the Act, and the Commission's 
regulations. Furthermore, the NRC finds that the licensee is 
technically and financially qualified to engage in the activities 
authorized, and that issuance of the license will not be inimical to 
the common defense and security or to the health and safety of the 
public. Finally, the NRC finds that the findings required by subpart A 
of 10 CFR part 51 have been made.
    Accordingly, the COL was issued on May 1, 2015, and is effective 
immediately.

II. Further Information

    The NRC has prepared a Final Safety Evaluation Report (FSER) and 
Final Environmental Impact Statement (FEIS) that document the 
information reviewed and NRC's conclusion. The Commission has also 
issued its Memorandum and Order documenting its final decision on the 
uncontested hearing held on February 4, 2015, which serves as the 
Record of Decision ROD in this proceeding. The NRC also prepared a 
document summarizing the ROD to accompany its action on the COL 
application that incorporates by reference materials contained in the 
FEIS. In accordance with 10 CFR 2.390 of the NRC's ``Rules of 
Practice,'' details with respect to this action, including the FSER 
FEIS, Summary ROD, and accompanying documentation included in the 
combined license package, as well as the Commission's hearing decision 
and ROD, are available online in the ADAMS Public Documents collection 
at http://www.nrc.gov/reading-rm/adams.html. From this site, persons 
can access the NRC's ADAMS, which provides text and image files of 
NRC's public documents.
    The ADAMS accession numbers for the documents related to this 
notice are:

------------------------------------------------------------------------
 
------------------------------------------------------------------------
ML14296A540..........................  ``Final Safety Evaluation Report
                                        for Combined Licenses for Enrico
                                        Fermi Unit 3''.
ML12307A172, ML12307A176,              NUREG-2105, ``Final Environmental
 ML12307A177, and ML12347A202.          Impact Statement for the
                                        Combined License for Enrico
                                        Fermi Unit 3''.
ML14308A337..........................  DTE COL Application--Revision 8
                                        of the application.
ML15120A040..........................  Commission's Memorandum and Order
                                        on the uncontested hearing
                                        (Record of Decision).
ML15120A221..........................  Summary of the Record of
                                        Decision.
ML15084A160..........................  Combined License No. NPF-95.
------------------------------------------------------------------------



[[Page 26303]]

    Dated at Rockville, Maryland, this 1st day of May 2014.

    For the Nuclear Regulatory Commission.
Mark Delligatti,
Deputy Director, Division of New Reactor Licensing, Office of New 
Reactors.
[FR Doc. 2015-11038 Filed 5-6-15; 8:45 am]
 BILLING CODE 7590-01-P



                                                  26302                                  Federal Register / Vol. 80, No. 88 / Thursday, May 7, 2015 / Notices

                                                  ENTERGY NUCLEAR VERMONT                                            of the issuance of Combined License                       and the Commission’s regulations have
                                                  YANKEE, LLC AND ENTERGY                                            (COL), NPF–95 to DTE Electric                             been met. The NRC finds that any
                                                  NUCLEAR OPERATIONS, INC.                                           Company (DTE, formerly Detroit Edison                     required notifications to other agencies
                                                  (Vermont Yankee Nuclear Power                                      Company) and Record of Decision.                          or bodies have been duly made and that
                                                  Station)                                                           ADDRESSES: Please refer to Docket ID                      there is reasonable assurance that the
                                                    This proceeding involves an                                      NRC–2008–0566 when contacting the                         facility will be constructed and will
                                                  application by Entergy Nuclear Vermont                             NRC about the availability of                             operate in conformity with the license,
                                                  Yankee, LLC and Entergy Nuclear                                    information regarding this document.                      as amended, the provisions of the Act,
                                                  Operations, Inc. for a license                                     You may access publicly-available                         and the Commission’s regulations.
                                                  amendment for the Vermont Yankee                                   information related to this document                      Furthermore, the NRC finds that the
                                                  Nuclear Power Station, which is located                            using any of the following methods:                       licensee is technically and financially
                                                  in Vernon, Vermont. In response to a                                  • NRC’s Agencywide Documents                           qualified to engage in the activities
                                                  notice filed in the Federal Register, see                          Access and Management System                              authorized, and that issuance of the
                                                  80 FR 8,355, 8,359 (Feb. 17, 2015), a                              (ADAMS): You may obtain publicly-                         license will not be inimical to the
                                                  hearing request was filed on April 20,                             available documents online in the                         common defense and security or to the
                                                  2015 by the State of Vermont.                                      ADAMS Public Documents collection at                      health and safety of the public. Finally,
                                                    The Board is comprised of the                                    http://www.nrc.gov/reading-rm/                            the NRC finds that the findings required
                                                  following administrative judges:                                   adams.html. To begin the search, select                   by subpart A of 10 CFR part 51 have
                                                    William J. Froehlich, Chairman,                                  ‘‘ADAMS Public Douments’’ and then                        been made.
                                                  Atomic Safety and Licensing Board                                  select ‘‘Begin Web-based ADAMS
                                                                                                                     Search.’’ For problems with ADAMS,                           Accordingly, the COL was issued on
                                                  Panel, U.S. Nuclear Regulatory
                                                                                                                     please contact the NRC’s Public                           May 1, 2015, and is effective
                                                  Commission, Washington, DC 20555–
                                                                                                                     Document Room (PDR) reference staff at                    immediately.
                                                  0001.
                                                    Dr. Michael F. Kennedy, Atomic                                   1–800–397–4209, 301–415–4737, or by                       II. Further Information
                                                  Safety and Licensing Board Panel, U.S.                             email to pdr.resource@nrc.gov. The
                                                  Nuclear Regulatory Commission,                                     ADAMS accession number for each                             The NRC has prepared a Final Safety
                                                  Washington, DC 20555–0001.                                         document referenced in this document                      Evaluation Report (FSER) and Final
                                                    Dr. Richard E. Wardwell, Atomic                                  (if that document is available in                         Environmental Impact Statement (FEIS)
                                                  Safety and Licensing Board Panel, U.S.                             ADAMS) is provided at the end of this                     that document the information reviewed
                                                  Nuclear Regulatory Commission,                                     document.                                                 and NRC’s conclusion. The Commission
                                                  Washington, DC 20555–0001.                                            • NRC’s PDR: You may examine and                       has also issued its Memorandum and
                                                    All correspondence, documents, and                               purchase copies of public documents at                    Order documenting its final decision on
                                                  other materials shall be filed in                                  the NRC’s PDR, Room O1–F21, One                           the uncontested hearing held on
                                                  accordance with the NRC E-Filing rule.                             White Flint North, 11555 Rockville                        February 4, 2015, which serves as the
                                                  See 10 CFR 2.302.                                                  Pike, Rockville, Maryland 20852.                          Record of Decision ROD in this
                                                  Rockville, Maryland,                                               FOR FURTHER INFORMATION CONTACT:                          proceeding. The NRC also prepared a
                                                    Dated: May 1, 2015.                                              Adrian Muñiz, Office of New Reactors,                    document summarizing the ROD to
                                                  E. Roy Hawkens,                                                    U.S. Nuclear Regulatory Commission,                       accompany its action on the COL
                                                  Chief Administrative Judge, Atomic Safety                          Washington, DC 20555–0001; telephone:                     application that incorporates by
                                                  and Licensing Board Panel.                                         301–415–4093, email: Adrian.Muniz@                        reference materials contained in the
                                                  [FR Doc. 2015–11039 Filed 5–6–15; 8:45 am]
                                                                                                                     nrc.gov regarding safety matters; or                      FEIS. In accordance with 10 CFR 2.390
                                                                                                                     Mallecia Sutton, at 301–415–0673,                         of the NRC’s ‘‘Rules of Practice,’’ details
                                                  BILLING CODE 7590–01–P
                                                                                                                     email: Mallecia.Sutton@nrc.gov                            with respect to this action, including the
                                                                                                                     regarding environmental matters.                          FSER FEIS, Summary ROD, and
                                                  NUCLEAR REGULATORY                                                 SUPPLEMENTARY INFORMATION:                                accompanying documentation included
                                                  COMMISSION                                                         I. Introduction                                           in the combined license package, as
                                                  [Docket No. 52–033; NRC–2008–0566]                                                                                           well as the Commission’s hearing
                                                                                                                        Under section 2.106 of Title 10 of the
                                                                                                                                                                               decision and ROD, are available online
                                                                                                                     Code of Federal Regulations (10 CFR),
                                                  DTE Electric Company; Fermi 3                                                                                                in the ADAMS Public Documents
                                                                                                                     the NRC is providing notice of the
                                                                                                                     issuance of COL NPF–95 to DTE and,                        collection at http://www.nrc.gov/
                                                  AGENCY:  Nuclear Regulatory                                                                                                  reading-rm/adams.html. From this site,
                                                  Commission.                                                        under 10 CFR 51.102(c), the Record of
                                                                                                                     Decision (ROD). With respect to the                       persons can access the NRC’s ADAMS,
                                                  ACTION: Combined license and record of                                                                                       which provides text and image files of
                                                  decision; issuance.                                                application for the COL filed by DTE,
                                                                                                                     the NRC finds that the applicable                         NRC’s public documents.
                                                  SUMMARY:The U.S. Nuclear Regulatory                                standards and requirements of the                           The ADAMS accession numbers for
                                                  Commission (NRC) is providing notice                               Atomic Energy Act of 1954, as amended,                    the documents related to this notice are:

                                                  ML14296A540 ..............................................................    ‘‘Final Safety Evaluation Report for Combined Licenses for Enrico Fermi Unit 3’’.
                                                  ML12307A172, ML12307A176, ML12307A177, and                                    NUREG–2105, ‘‘Final Environmental Impact Statement for the Combined License for
                                                   ML12347A202.                                                                    Enrico Fermi Unit 3’’.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  ML14308A337 ..............................................................    DTE COL Application—Revision 8 of the application.
                                                  ML15120A040 ..............................................................    Commission’s Memorandum and Order on the uncontested hearing (Record of Decision).
                                                  ML15120A221 ..............................................................    Summary of the Record of Decision.
                                                  ML15084A160 ..............................................................    Combined License No. NPF–95.




                                             VerDate Sep<11>2014       18:57 May 06, 2015      Jkt 235001     PO 00000         Frm 00087   Fmt 4703   Sfmt 4703   E:\FR\FM\07MYN1.SGM   07MYN1


                                                                                  Federal Register / Vol. 80, No. 88 / Thursday, May 7, 2015 / Notices                                             26303

                                                    Dated at Rockville, Maryland, this 1st day            ADAMS Public Documents collection at                  containments. While developing the
                                                  of May 2014.                                            http://www.nrc.gov/reading-rm/                        requirements for Order EA–12–050, the
                                                    For the Nuclear Regulatory Commission.                adams.html. To begin the search, select               NRC acknowledged that questions
                                                  Mark Delligatti,                                        ‘‘ADAMS Public Documents’’ and then                   remained about maintaining
                                                  Deputy Director, Division of New Reactor                select ‘‘Begin Web-based ADAMS                        containment integrity and limiting the
                                                  Licensing, Office of New Reactors.                      Search.’’ For problems with ADAMS,                    release of radioactive materials if
                                                  [FR Doc. 2015–11038 Filed 5–6–15; 8:45 am]              please contact the NRC’s Public                       licensees used the venting systems
                                                  BILLING CODE 7590–01–P                                  Document Room (PDR) reference staff at                during severe accident conditions.
                                                                                                          1–800–397–4209, 301–415–4737, or by                      The NRC staff on November 26, 2012,
                                                                                                          email to pdr.resource@nrc.gov. The                    presented the Commission with options
                                                  NUCLEAR REGULATORY                                      ADAMS accession number for each                       to address these issues in SECY–12–
                                                  COMMISSION                                              document referenced (if it available in               0157, ‘‘Consideration of Additional
                                                                                                          ADAMS) is provided the first time that                Requirements for Containment Venting
                                                  [NRC–2015–0048]
                                                                                                          a document is referenced. The JLD–ISG–                Systems for Boiling Water Reactors with
                                                  Compliance With Phase 2 of Order EA–                    2015–01 is available in ADAMS under                   Mark I and Mark II Containments’’
                                                  13–109                                                  Accession No. ML15104A118. The ISG                    (ADAMS Accession No. ML12325A704).
                                                                                                          for complying with Phase 1                            In the staff requirements memorandum
                                                  AGENCY:  Nuclear Regulatory                             requirements of the order (JLD–ISG–                   (SRM) for SECY–12–0157, dated March
                                                  Commission.                                             2013–02) was issued on November 14,                   19, 2013 (ADAMS Accession No.
                                                  ACTION: Interim staff guidance; issuance.               2013 (ADAMS Accession No.                             ML13078A017), the Commission
                                                                                                          ML13304B836). The NEI 13–02,                          directed the staff to: (1) Issue a
                                                  SUMMARY:   The U.S. Nuclear Regulatory                                                                        modification to Order EA–12–050
                                                  Commission (NRC) is issuing its Japan                   Revision 1 is available in ADAMS under
                                                                                                          Accession No. ML15113B318.                            requiring BWR licensees with Mark I
                                                  Lessons-Learned Division Interim Staff
                                                  Guidance (JLD–ISG), JLD–ISG–2015–01,                       • NRC’s PDR: You may examine and                   and Mark II containments to upgrade or
                                                                                                          purchase copies of public documents at                replace the reliable hardened vents
                                                  ‘‘Compliance with Phase 2 of Order EA–                                                                        required by Order EA–12–050 with a
                                                  13–109, Order Modifying Licenses with                   the NRC’s PDR, Room O1–F21, One
                                                                                                          White Flint North, 11555 Rockville                    containment venting system designed
                                                  Regard to Reliable Hardened                                                                                   and installed to remain functional
                                                  Containment Vents Capable of                            Pike, Rockville, Maryland 20852.
                                                  Operation under Severe Accident                            • NRC’s Interim Staff Guidance Web                 during severe accident conditions, and
                                                                                                          site: JLD–ISG documents are also                      (2) develop a technical basis and
                                                  Conditions.’’ This ISG provides                                                                               rulemaking for filtering strategies with
                                                  guidance and clarifies the Phase 2                      available online under the ‘‘Japan
                                                                                                          Lessons Learned’’ heading at http://                  drywell filtration and severe accident
                                                  requirements in the order to assist the                                                                       management of BWR Mark I and II
                                                  licensees that have Boiling Water                       www.nrc.gov/reading-rm/doc-
                                                                                                          collections/isg/japan-lessons-                        containments. The NRC subsequently
                                                  Reactors (BWRs) with Mark I and Mark                                                                          issued Order EA–13–109 to define
                                                  II Containments in the design and                       learned.html.
                                                                                                                                                                requirements and schedules for
                                                  implementation of either a vent path                    FOR FURTHER INFORMATION CONTACT:
                                                                                                                                                                licensees for BWRs with Mark I and
                                                  from the containment drywell or a                       Rajender Auluck, Office of Nuclear                    Mark II containments to install severe
                                                  strategy that makes it unlikely that                    Reactor Regulation, U.S. Nuclear                      accident capable containment venting
                                                  venting would be needed from the                        Regulatory Commission, Washington,                    systems.
                                                  drywell before alternate reliable                       DC 20555–0001; telephone: 301–415–                       In recognition of the relative
                                                  containment heat removal and pressure                   1025; email: Rajender.Auluck@nrc.gov.                 importance of venting capabilities from
                                                  control is reestablished. This ISG also                 SUPPLEMENTARY INFORMATION: The NRC                    the wetwell and drywell, a phased
                                                  endorses, with clarifications, the                      developed JLD–ISG–2015–01 to provide                  approach to implementation is being
                                                  industry guidance contained in Nuclear                  guidance and clarification to assist                  used to minimize delays in
                                                  Energy Institute (NEI) 13–02, ‘‘Industry                nuclear power reactor licensees with the              implementing the requirements
                                                  Guidance for Compliance with Order                      identification of methods needed to                   originally imposed by Order EA–12–
                                                  EA–13–109,’’ Revision 1.                                comply with Phase 2 requirements in                   050. Phase 1 involves upgrading the
                                                  ADDRESSES: Please refer to Docket ID                    Order EA–13–109 (ADAMS Accession                      venting capabilities from the
                                                  NRC–2015–0048 when contacting the                       No. ML13130A067), ‘‘Order Modifying                   containment wetwell to provide
                                                  NRC about the availability of                           Licenses with Regard to Reliable                      reliable, severe accident capable
                                                  information regarding this document.                    Hardened Containment Vents Capable                    hardened vents to assist in preventing
                                                  You may obtain publicly-available                       of Operation under Severe Accident                    core damage and, if necessary, to
                                                  information related to this document by                 Conditions.’’ This ISG is not a substitute            provide venting capability during severe
                                                  using any of the following methods:                     for the requirements in Order EA–13–                  accident conditions. Phase 2 involves
                                                     • Federal Rulemaking Web site: Go to                 109, and compliance with the ISG                      providing additional protection during
                                                  http://www.regulations.gov and search                   would not be a requirement.                           severe accident conditions through
                                                  for Docket ID NRC–2015–0048. Address                       The accident at the Fukushima Dai-                 installation of a reliable, severe accident
                                                  questions about NRC dockets to Carol                    ichi nuclear power station reinforced                 capable drywell vent system or the
                                                  Gallagher; telephone: 301–415–3463;                     the importance of reliable operation of               development of a reliable containment
                                                  email: Carol.Gallagher@nrc.gov. For                     containment vents for BWR plants with                 venting strategy that makes it unlikely
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  technical questions, contact the                        Mark I and Mark II containments. As                   that a licensee would need to vent from
                                                  individual listed in the FOR FURTHER                    part of its response to the lessons                   the containment drywell during severe
                                                  INFORMATION CONTACT section of this                     learned from the accident, on March 12,               accident conditions. For
                                                  document.                                               2012, the NRC issued Order EA–12–050                  implementation of Phase 1 order
                                                     • NRC’s Agencywide Documents                         (ADAMS Accession No. ML12056A043)                     requirements, the NRC issued JLD–ISG–
                                                  Access and Management System                            requiring licensees to upgrade or install             2013–02 on November 14, 2013 (78 FR
                                                  (ADAMS): You may obtain publicly-                       a reliable hardened containment venting               70356), which endorsed, with
                                                  available documents online in the                       system (HCVS) for Mark I and Mark II                  exceptions and clarifications, the


                                             VerDate Sep<11>2014   18:07 May 06, 2015   Jkt 235001   PO 00000   Frm 00088   Fmt 4703   Sfmt 4703   E:\FR\FM\07MYN1.SGM   07MYN1



Document Created: 2015-12-16 07:50:48
Document Modified: 2015-12-16 07:50:48
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionCombined license and record of decision; issuance.
ContactAdrian Mu[ntilde]iz, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555- 0001; telephone: 301-415-4093, email: [email protected] regarding safety matters; or Mallecia Sutton, at 301-415-0673, email: [email protected] regarding environmental matters.
FR Citation80 FR 26302 