80_FR_27246 80 FR 27155 - Northern Indiana Public Service Company v. Midcontinent Independent System Operator, Inc. PJM Interconnection, L.L.C.; Notice of Technical Conference

80 FR 27155 - Northern Indiana Public Service Company v. Midcontinent Independent System Operator, Inc. PJM Interconnection, L.L.C.; Notice of Technical Conference

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 91 (May 12, 2015)

Page Range27155-27157
FR Document2015-11405

Federal Register, Volume 80 Issue 91 (Tuesday, May 12, 2015)
[Federal Register Volume 80, Number 91 (Tuesday, May 12, 2015)]
[Notices]
[Pages 27155-27157]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-11405]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL13-88-000]


Northern Indiana Public Service Company v. Midcontinent 
Independent System Operator, Inc. PJM Interconnection, L.L.C.; Notice 
of Technical Conference

    On September 11, 2013, Northern Indiana Public Service Company 
(NIPSCO) filed a complaint against Midcontinent Independent System 
Operator, Inc. (MISO) and PJM Interconnection, L.L.C. (PJM). NIPSCO 
requested that the Commission order MISO and PJM to reform the 
interregional transmission planning process of the Joint Operating 
Agreement between MISO and PJM (MISO-PJM JOA).\1\ On December 18, 2014, 
the Commission issued an order directing Commission staff to convene a 
technical conference to explore issues raised in the NIPSCO Complaint 
related to the MISO-PJM JOA and the MISO-PJM seam.\2\ Take notice that 
such conference will be held on June 15, 2015, at the Commission's 
headquarters at 888 First Street NE., Washington, DC 20426, between 
9:00 a.m. and 4:00 p.m. (Eastern Time) in the Commission Meeting Room. 
The technical conference will be led by Commission staff and may be 
attended by one or more Commissioners.
---------------------------------------------------------------------------

    \1\ NIPSCO Complaint, Docket No. EL13-88-000 (filed Sept. 11, 
2013).
    \2\ Northern Indiana Public Service Co. v. Midcontinent Indep. 
Sys. Operator, Inc. and PJM Interconnection, L.L.C., 149 FERC ] 
61,248, at P 35 (2014).
---------------------------------------------------------------------------

    The technical conference will not be transcribed. However, there 
will be a free webcast of the conference. The webcast will allow 
persons to listen to the technical conference, but not participate. 
Anyone with Internet access who wants to listen to the conference can 
do so by navigating to the Calendar of Events at www.ferc.gov and 
locating the technical conference in the Calendar. The technical 
conference will contain a link to its webcast. The Capitol Connection 
provides technical support for the webcast and offers the option of 
listening to the meeting via phone-bridge for a fee. If you have any 
questions, visit www.CapitolConnection.org or call 703-993-3100.\3\
---------------------------------------------------------------------------

    \3\ The webcast will continue to be available on the Calendar of 
Events on the Commission's Web site www.ferc.gov for three months 
after the conference.
---------------------------------------------------------------------------

    Advance registration is required for all attendees. Attendees may 
register in advance at the following Web page: https://www.ferc.gov/whats-new/registration/06-15-15-form.asp. Attendees should allow time 
to pass

[[Page 27156]]

through building security procedures before the 9:00 a.m. (Eastern 
Time) start time of the technical conference. In addition, information 
on this event will be posted on the Calendar of Events on the 
Commission's Web site, www.ferc.gov, prior to the event.
    Those wishing to be panelists in the program for this event should 
nominate themselves through the on-line registration form no later than 
close of business May 18, 2015 at the following Web page, https://www.ferc.gov/whats-new/registration/06-15-15-speaker-form.asp. At this 
Web page, please identify the name(s) of the person(s) wishing to be a 
panelist and which issue(s) below you wish to discuss. Panelists will 
be selected to ensure relevant topics and to accommodate time 
constraints. Other attendees may ask questions or make comments as time 
permits.
    Commission conferences are accessible under section 508 of the 
Rehabilitation Act of 1973. For accessibility accommodations please 
send an email to [email protected] or call toll free 1-866-208-
3372 (voice) or 202-502 -8659 (TTY); or send a fax to 202-208-2106 with 
the required accommodations.
    The technical conference will consist of five sessions and focus on 
the issues raised by NIPSCO in the Complaint, as detailed below. The 
times given below are approximate and may change, as needed. As time 
permits, at the end of each session staff will open the floor for 
questions and comments from attendees.

Conference Introduction: Commission Staff (9:00 a.m.-9:15 a.m.)
Session 1: Transmission Planning Cycles (9:15 a.m.-10:15 a.m.)

    Panelists should be prepared to discuss the issue of whether the 
Commission should require the MISO-PJM cross-border transmission 
planning process to run concurrently with the MISO and PJM regional 
transmission planning cycles, rather than after those regional 
transmission planning cycles, and to answer questions including, but 
not limited to, the following: How could MISO and PJM modify their 
regional transmission planning cycles to better align with the MISO-PJM 
cross-border transmission planning process? What impact would this have 
on other regional and interregional transmission planning cycles (i.e., 
neighboring regions)? Should MISO and PJM use the same planning 
deadlines to achieve regional benefits from coordination of the cross-
border transmission planning process? Discussion of these issues should 
focus on the MISO-PJM seam in general, and NIPSCO's location on the 
seam in particular.

Session 2: Modeling and Criteria (10:15 a.m.-11:15 a.m.)

    Panelists should be prepared to describe the existing joint 
interregional transmission planning model used to evaluate cross-border 
transmission projects and to answer questions including, but not 
limited to, the following: Are changes needed to this existing model or 
the assumptions used to enable coordinated study of proposed cross-
border transmission projects? Should the Commission require MISO and 
PJM to use a single common set of criteria to evaluate cross-border 
transmission projects as proposed by NIPSCO in the Complaint? In 
addition to the benefit metric, what other metrics do PJM and MISO 
consider in the evaluation of cross-border transmission projects? 
Should the Commission require that there be consistency between PJM's 
and MISO's regional transmission planning analyses such that both 
entities are consistent in their application of reliability criteria 
and modeling assumptions as proposed by NIPSCO in the Complaint? 
Discussion of these issues should focus on the MISO-PJM seam in 
general, and NIPSCO's location on the seam in particular.

Lunch Break: (11:15 a.m.-12:15 p.m.)
Session 3: Market-to-Market Payments (12:15 p.m.-1:30 p.m.)

    Panelists should be prepared to answer questions including, but not 
limited to, the following: Should the Commission require MISO and PJM 
to amend the criteria to evaluate cross-border market efficiency 
transmission projects to address all known benefits, including 
avoidance of future market-to-market payments made to reallocate short-
term transmission capacity in the real-time operation of the system as 
proposed by NIPSCO in the Complaint? Have MISO, PJM, and the market 
monitors identified trends in market-to-market payments that may be 
relevant to NIPSCO's position along the PJM-MISO seam? Is there a 
relationship between the cross-border transmission planning process 
(and evaluation of potential interregional transmission projects) and 
persistent market-to-market payments being made between the RTOs? Are 
persistent market-to-market payments an indicator of the need for new 
transmission? Please provide examples of transmission projects that 
have been considered under the existing cross-border transmission 
planning process for the purpose of mitigating congestion and/or 
constraints that lead to persistent market-to-market payments but that 
have not been developed, and the reasons the transmission project was 
not developed.

Break: (1:30 p.m.-1:45 p.m.)
Session 4: Lower Voltage Transmission Projects (1:45 p.m.-2:45 p.m.)

    Panelists should be prepared to discuss the issue of whether the 
Commission should require MISO and PJM to have a process for joint 
transmission planning and cost allocation of lower voltage and lower 
cost cross-border upgrades, as proposed by NIPSCO in the Complaint, and 
to answer questions including, but not limited to, the following: How 
would a lower voltage criteria align with current regional cost 
allocation methods? Are lower voltage transmission projects expected to 
provide region-wide or local benefits? Discussion of these issues 
should focus on the MISO-PJM seam in general, and NIPSCO's location on 
the seam in particular.

Session 5: Generator Interconnections and Retirements (2:45 p.m.-3:45 
p.m.)

    Panelists should be prepared to discuss the issue of whether the 
Commission should require MISO and PJM to improve the processes within 
the MISO-PJM JOA with respect to new generator interconnections and 
generation retirements, as proposed by NIPSCO in the Complaint, and to 
answer questions including, but not limited to, the following: What 
impact does the interconnection or retirement of external generation 
have on a neighboring region? How do MISO and PJM model new generation, 
or the retirement of existing generation, on a neighboring system? At 
what stage of the interconnection process do MISO and PJM share 
information or coordinate studies? How does the current process of 
studying external generation impact congestion? How do MISO and PJM 
share information about generator interconnections and retirements? 
What are the differences in timing between the two RTOs for sharing 
information about generator interconnections and retirements? 
Discussion of these issues should focus on the MISO-PJM seam in 
general, and NIPSCO's location on the seam in particular.

Conference Conclusion: Next Steps (3:45 p.m.--4:00 p.m.)

    Following the technical conference, the Commission will consider 
post-technical conference comments submitted on or before July 15, 
2015. Reply comments are due on or before August 5, 2015. The written 
comments will be included in the formal record of

[[Page 27157]]

the proceeding, which, together with the record developed to date, will 
form the basis for further Commission action.
    For more information about this technical conference, please 
contact Lina Naik, 202-502-8882, [email protected], regarding legal 
issues; or Jason Strong, 202-502-6124, [email protected], and Ben 
Foster, 202-502-6149, [email protected], regarding technical issues; 
or Sarah McKinley, 202-502-8368, [email protected], regarding 
logistical issues.

    Dated: May 5, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-11405 Filed 5-11-15; 8:45 a.m.]
 BILLING CODE 6717-01-P



                                                                                        Federal Register / Vol. 80, No. 91 / Tuesday, May 12, 2015 / Notices                                                         27155

                                                                                                                          1016TH—MEETING—Continued
                                                   Item No.                             Docket No.                                                                        Company

                                                  E–10   ......    ES15–14–000 ..............................................    NorthWestern Corporation.
                                                  E–11   ......    OMITTED.
                                                  E–12   ......    ER07–956–008 ............................................     Entergy Services, Inc.
                                                  E–13   ......    ER10–3357–000, ER10–3357–001 ............                     Entergy Services, Inc.
                                                  E–14   ......    EL15–19–000 ..............................................    Avista Corporation.
                                                  E–15   ......    ER15–990–000 ............................................     Southwest Power Pool, Inc.

                                                                                                                                            Gas

                                                  G–1 ........     RP13–436–001 ............................................     CAlifornians for Renewable Energy, Inc.
                                                                                                                                 Michael E. Boyd.
                                                                                                                                 Robert M. Sarvey v. Pacific Gas and Electric Company.

                                                                                                                                           Hydro

                                                  H–1   ........   OMITTED.
                                                  H–2   ........   P–2169–109 ................................................   Brookfield Smoky Mountain Hydropower, LLC.
                                                  H–3   ........   RM15–18–000 .............................................     Commencement of Assessment of Annual Charges.
                                                  H–4   ........   P–1892–027, P–1855–046, P–1904–074 ...                        TransCanada Hydro Northeast Inc.

                                                                                                                                        Certificates

                                                  C–1   ........   CP14–513–000 ............................................     Impulsora Pipeline, LLC.
                                                  C–2   ........   CP14–509–000 ............................................     Paiute Pipeline Company.
                                                  C–3   ........   CP14–522–000 ............................................     Algonquin Gas Transmission, LLC.
                                                  C–4   ........   OMITTED.
                                                  C–5   ........   CP15–161–000 ............................................     Roadrunner Gas Transmission, LLC.
                                                  C–6   ........   CP15–32–000 ..............................................    Black Hills Shoshone Pipeline, LLC.
                                                                   CP15–33–000 ..............................................    Energy West Development, Inc.



                                                    Issued: May 7, 2015.                                            DEPARTMENT OF ENERGY                                   2015, at the Commission’s headquarters
                                                  Nathaniel J. Davis, Sr.,                                                                                                 at 888 First Street NE., Washington, DC
                                                  Deputy Secretary.                                                 Federal Energy Regulatory                              20426, between 9:00 a.m. and 4:00 p.m.
                                                                                                                    Commission                                             (Eastern Time) in the Commission
                                                     A free webcast of this event is                                [Docket No. EL13–88–000]                               Meeting Room. The technical
                                                  available through www.ferc.gov. Anyone                                                                                   conference will be led by Commission
                                                  with Internet access who desires to view                          Northern Indiana Public Service                        staff and may be attended by one or
                                                  this event can do so by navigating to                             Company v. Midcontinent Independent                    more Commissioners.
                                                  www.ferc.gov’s Calendar of Events and                             System Operator, Inc. PJM                                 The technical conference will not be
                                                  locating this event in the Calendar. The                          Interconnection, L.L.C.; Notice of                     transcribed. However, there will be a
                                                  event will contain a link to its webcast.                         Technical Conference                                   free webcast of the conference. The
                                                  The Capitol Connection provides                                                                                          webcast will allow persons to listen to
                                                                                                                      On September 11, 2013, Northern                      the technical conference, but not
                                                  technical support for the free webcasts.                          Indiana Public Service Company
                                                  It also offers access to this event via                                                                                  participate. Anyone with Internet access
                                                                                                                    (NIPSCO) filed a complaint against                     who wants to listen to the conference
                                                  television in the DC area and via phone                           Midcontinent Independent System                        can do so by navigating to the Calendar
                                                  bridge for a fee. If you have any                                 Operator, Inc. (MISO) and PJM                          of Events at www.ferc.gov and locating
                                                  questions, visit                                                  Interconnection, L.L.C. (PJM). NIPSCO                  the technical conference in the
                                                  www.CapitolConnection.org or contact                              requested that the Commission order                    Calendar. The technical conference will
                                                  Danelle Springer or David Reininger at                            MISO and PJM to reform the                             contain a link to its webcast. The
                                                  703–993–3100.                                                     interregional transmission planning                    Capitol Connection provides technical
                                                     Immediately following the conclusion                           process of the Joint Operating                         support for the webcast and offers the
                                                  of the Commission Meeting, a press                                Agreement between MISO and PJM                         option of listening to the meeting via
                                                  briefing will be held in the Commission                           (MISO–PJM JOA).1 On December 18,                       phone-bridge for a fee. If you have any
                                                                                                                    2014, the Commission issued an order                   questions, visit
                                                  Meeting Room. Members of the public
                                                                                                                    directing Commission staff to convene a                www.CapitolConnection.org or call 703–
                                                  may view this briefing in the designated
                                                                                                                    technical conference to explore issues                 993–3100.3
                                                  overflow room. This statement is                                  raised in the NIPSCO Complaint related
                                                  intended to notify the public that the                                                                                      Advance registration is required for
                                                                                                                    to the MISO–PJM JOA and the MISO–                      all attendees. Attendees may register in
                                                  press briefings that follow Commission
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                    PJM seam.2 Take notice that such                       advance at the following Web page:
                                                  meetings may now be viewed remotely                               conference will be held on June 15,
                                                  at Commission headquarters, but will                                                                                     https://www.ferc.gov/whats-new/
                                                                                                                                                                           registration/06-15-15-form.asp.
                                                  not be telecast through the Capitol                                  1 NIPSCO Complaint, Docket No. EL13–88–000

                                                                                                                    (filed Sept. 11, 2013).                                Attendees should allow time to pass
                                                  Connection service.
                                                                                                                       2 Northern Indiana Public Service Co. v.
                                                  [FR Doc. 2015–11509 Filed 5–8–15; 11:15 am]                       Midcontinent Indep. Sys. Operator, Inc. and PJM          3 The webcast will continue to be available on the

                                                  BILLING CODE 6717–01–P                                            Interconnection, L.L.C., 149 FERC ¶ 61,248, at P 35    Calendar of Events on the Commission’s Web site
                                                                                                                    (2014).                                                www.ferc.gov for three months after the conference.



                                             VerDate Sep<11>2014      17:31 May 11, 2015       Jkt 235001    PO 00000      Frm 00014   Fmt 4703   Sfmt 4703   E:\FR\FM\12MYN1.SGM   12MYN1


                                                  27156                          Federal Register / Vol. 80, No. 91 / Tuesday, May 12, 2015 / Notices

                                                  through building security procedures                    general, and NIPSCO’s location on the                 have not been developed, and the
                                                  before the 9:00 a.m. (Eastern Time) start               seam in particular.                                   reasons the transmission project was not
                                                  time of the technical conference. In                    Session 2: Modeling and Criteria                      developed.
                                                  addition, information on this event will                   (10:15 a.m.–11:15 a.m.)                            Break: (1:30 p.m.–1:45 p.m.)
                                                  be posted on the Calendar of Events on                     Panelists should be prepared to                    Session 4: Lower Voltage Transmission
                                                  the Commission’s Web site,                              describe the existing joint interregional                Projects (1:45 p.m.–2:45 p.m.)
                                                  www.ferc.gov, prior to the event.                       transmission planning model used to                      Panelists should be prepared to
                                                     Those wishing to be panelists in the                 evaluate cross-border transmission                    discuss the issue of whether the
                                                  program for this event should nominate                  projects and to answer questions                      Commission should require MISO and
                                                  themselves through the on-line                          including, but not limited to, the                    PJM to have a process for joint
                                                  registration form no later than close of                following: Are changes needed to this                 transmission planning and cost
                                                  business May 18, 2015 at the following                  existing model or the assumptions used                allocation of lower voltage and lower
                                                  Web page, https://www.ferc.gov/whats-                   to enable coordinated study of proposed               cost cross-border upgrades, as proposed
                                                  new/registration/06-15-15-speaker-                      cross-border transmission projects?                   by NIPSCO in the Complaint, and to
                                                  form.asp. At this Web page, please                      Should the Commission require MISO                    answer questions including, but not
                                                  identify the name(s) of the person(s)                   and PJM to use a single common set of                 limited to, the following: How would a
                                                  wishing to be a panelist and which                      criteria to evaluate cross-border                     lower voltage criteria align with current
                                                  issue(s) below you wish to discuss.                     transmission projects as proposed by                  regional cost allocation methods? Are
                                                  Panelists will be selected to ensure                    NIPSCO in the Complaint? In addition                  lower voltage transmission projects
                                                  relevant topics and to accommodate                      to the benefit metric, what other metrics             expected to provide region-wide or local
                                                  time constraints. Other attendees may                   do PJM and MISO consider in the                       benefits? Discussion of these issues
                                                  ask questions or make comments as time                  evaluation of cross-border transmission               should focus on the MISO–PJM seam in
                                                  permits.                                                projects? Should the Commission                       general, and NIPSCO’s location on the
                                                     Commission conferences are                           require that there be consistency                     seam in particular.
                                                  accessible under section 508 of the                     between PJM’s and MISO’s regional
                                                  Rehabilitation Act of 1973. For                         transmission planning analyses such                   Session 5: Generator Interconnections
                                                  accessibility accommodations please                     that both entities are consistent in their               and Retirements (2:45 p.m.–3:45
                                                  send an email to accessibility@ferc.gov                 application of reliability criteria and                  p.m.)
                                                  or call toll free 1–866–208–3372 (voice)                modeling assumptions as proposed by                      Panelists should be prepared to
                                                  or 202–502 -8659 (TTY); or send a fax                   NIPSCO in the Complaint? Discussion                   discuss the issue of whether the
                                                  to 202–208–2106 with the required                       of these issues should focus on the                   Commission should require MISO and
                                                  accommodations.                                         MISO–PJM seam in general, and                         PJM to improve the processes within the
                                                     The technical conference will consist                NIPSCO’s location on the seam in                      MISO–PJM JOA with respect to new
                                                  of five sessions and focus on the issues                particular.                                           generator interconnections and
                                                  raised by NIPSCO in the Complaint, as                   Lunch Break: (11:15 a.m.–12:15 p.m.)                  generation retirements, as proposed by
                                                  detailed below. The times given below                   Session 3: Market-to-Market Payments                  NIPSCO in the Complaint, and to
                                                  are approximate and may change, as                         (12:15 p.m.–1:30 p.m.)                             answer questions including, but not
                                                  needed. As time permits, at the end of                     Panelists should be prepared to                    limited to, the following: What impact
                                                  each session staff will open the floor for              answer questions including, but not                   does the interconnection or retirement
                                                  questions and comments from                             limited to, the following: Should the                 of external generation have on a
                                                  attendees.                                              Commission require MISO and PJM to                    neighboring region? How do MISO and
                                                  Conference Introduction: Commission                     amend the criteria to evaluate cross-                 PJM model new generation, or the
                                                     Staff (9:00 a.m.–9:15 a.m.)                          border market efficiency transmission                 retirement of existing generation, on a
                                                  Session 1: Transmission Planning                        projects to address all known benefits,               neighboring system? At what stage of
                                                     Cycles (9:15 a.m.–10:15 a.m.)                        including avoidance of future market-to-              the interconnection process do MISO
                                                     Panelists should be prepared to                      market payments made to reallocate                    and PJM share information or
                                                  discuss the issue of whether the                        short-term transmission capacity in the               coordinate studies? How does the
                                                  Commission should require the MISO–                     real-time operation of the system as                  current process of studying external
                                                  PJM cross-border transmission planning                  proposed by NIPSCO in the Complaint?                  generation impact congestion? How do
                                                  process to run concurrently with the                    Have MISO, PJM, and the market                        MISO and PJM share information about
                                                  MISO and PJM regional transmission                      monitors identified trends in market-to-              generator interconnections and
                                                  planning cycles, rather than after those                market payments that may be relevant to               retirements? What are the differences in
                                                  regional transmission planning cycles,                  NIPSCO’s position along the PJM–MISO                  timing between the two RTOs for
                                                  and to answer questions including, but                  seam? Is there a relationship between                 sharing information about generator
                                                  not limited to, the following: How could                the cross-border transmission planning                interconnections and retirements?
                                                  MISO and PJM modify their regional                      process (and evaluation of potential                  Discussion of these issues should focus
                                                  transmission planning cycles to better                  interregional transmission projects) and              on the MISO–PJM seam in general, and
                                                  align with the MISO–PJM cross-border                    persistent market-to-market payments                  NIPSCO’s location on the seam in
                                                  transmission planning process? What                     being made between the RTOs? Are                      particular.
                                                  impact would this have on other                         persistent market-to-market payments                  Conference Conclusion: Next Steps
                                                                                                                                                                   (3:45 p.m.—4:00 p.m.)
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  regional and interregional transmission                 an indicator of the need for new
                                                  planning cycles (i.e., neighboring                      transmission? Please provide examples                    Following the technical conference,
                                                  regions)? Should MISO and PJM use the                   of transmission projects that have been               the Commission will consider post-
                                                  same planning deadlines to achieve                      considered under the existing cross-                  technical conference comments
                                                  regional benefits from coordination of                  border transmission planning process                  submitted on or before July 15, 2015.
                                                  the cross-border transmission planning                  for the purpose of mitigating congestion              Reply comments are due on or before
                                                  process? Discussion of these issues                     and/or constraints that lead to persistent            August 5, 2015. The written comments
                                                  should focus on the MISO–PJM seam in                    market-to-market payments but that                    will be included in the formal record of


                                             VerDate Sep<11>2014   17:31 May 11, 2015   Jkt 235001   PO 00000   Frm 00015   Fmt 4703   Sfmt 4703   E:\FR\FM\12MYN1.SGM   12MYN1


                                                                                 Federal Register / Vol. 80, No. 91 / Tuesday, May 12, 2015 / Notices                                                   27157

                                                  the proceeding, which, together with the                Public Reference Room in Washington,                    Dated: May 5, 2015.
                                                  record developed to date, will form the                 DC. There is an ‘‘eSubscription’’ link on             Kimberly D. Bose,
                                                  basis for further Commission action.                    the Web site that enables subscribers to              Secretary.
                                                     For more information about this                      receive email notification when a                     [FR Doc. 2015–11406 Filed 5–11–15; 8:45 am]
                                                  technical conference, please contact                    document is added to a subscribed                     BILLING CODE 6717–01–P
                                                  Lina Naik, 202–502–8882, lina.naik@                     docket(s). For assistance with any FERC
                                                  ferc.gov, regarding legal issues; or Jason              Online service, please email
                                                  Strong, 202–502–6124, jason.strong@                     FERCOnlineSupport@ferc.gov, or call                   DEPARTMENT OF ENERGY
                                                  ferc.gov, and Ben Foster, 202–502–6149,                 (866) 208–3676 (toll free). For TTY, call
                                                  ben.foster@ferc.gov, regarding technical                (202) 502–8659.                                       Federal Energy Regulatory
                                                  issues; or Sarah McKinley, 202–502–                       Comment Date: 5:00 p.m. Eastern                     Commission
                                                  8368, sarah.mckinley@ferc.gov,                          Time on May 8, 2015.                                  [Docket No. CP15–105–000]
                                                  regarding logistical issues.                              Dated: April 28, 2015.
                                                    Dated: May 5, 2015.                                   Kimberly D. Bose,                                     Texas Gas Transmission, LLC; Notice
                                                  Kimberly D. Bose,                                       Secretary.                                            of Intent To Prepare an Environmental
                                                                                                                                                                Assessment for the Proposed Western
                                                  Secretary.                                              [FR Doc. 2015–11410 Filed 5–11–15; 8:45 am]
                                                                                                                                                                Kentucky Lateral Project and Request
                                                  [FR Doc. 2015–11405 Filed 5–11–15; 8:45 a.m.]           BILLING CODE 6717–01–P
                                                                                                                                                                for Comments on Environmental
                                                  BILLING CODE 6717–01–P                                                                                        Issues
                                                                                                          DEPARTMENT OF ENERGY                                     The staff of the Federal Energy
                                                  DEPARTMENT OF ENERGY                                                                                          Regulatory Commission (FERC or
                                                                                                          Federal Energy Regulatory                             Commission) will prepare an
                                                  Federal Energy Regulatory                               Commission                                            environmental assessment (EA) that will
                                                  Commission                                                                                                    discuss the environmental impacts of
                                                                                                          Notice of Commission Staff
                                                  [Docket No. EL15–58–000]                                                                                      the Western Kentucky Lateral Project
                                                                                                          Attendance
                                                                                                                                                                involving construction and operation of
                                                  Louisiana Generating, LLC; Notice of                       The Federal Energy Regulatory                      facilities by Texas Gas Transmission,
                                                  Filing                                                  Commission (Commission) hereby gives                  LLC (Texas Gas) in Muhlenberg County,
                                                                                                          notice that members of the                            Kentucky. The Commission will use this
                                                     Take notice that on April 28, 2015,                  Commission’s staff may attend the                     EA in its decision-making process to
                                                  Louisiana Generating LLC submitted an                   following meeting related to the                      determine whether the project is in the
                                                  amendment to its April 7, 2015 filed                    transmission planning activities of the               public convenience and necessity.
                                                  request to recover costs under                          Florida Reliability Coordinating                         This notice announces the opening of
                                                  Midcontinent Independent System                         Council, Inc.                                         the scoping process the Commission
                                                  Operator, Inc.’s FERC Electric Tariff                   The Florida Reliability Coordinating                  will use to gather input from the public
                                                  Schedule 24 and Schedule 24–A.                             Council, Inc. (FRCC) Process First                 and interested agencies on the project.
                                                     Any person desiring to intervene or to                  Quarter Meeting.                                   You can make a difference by providing
                                                  protest this filing must file in                        May 6, 2015, 10:00 a.m.–12:00 p.m.                    us with your specific comments or
                                                  accordance with Rules 211 and 214 of                       (Eastern Standard Time)                            concerns about the project. Your
                                                  the Commission’s Rules of Practice and                                                                        comments should focus on the potential
                                                                                                             The above-referenced meeting will be
                                                  Procedure (18 CFR 385.211, 385.214).                                                                          environmental effects, reasonable
                                                                                                          via web conference.
                                                  Protests will be considered by the                         The above-referenced meeting is open               alternatives, and measures to avoid or
                                                  Commission in determining the                           to stakeholders.                                      lessen environmental impacts. Your
                                                  appropriate action to be taken, but will                   Further information may be found at:               input will help the Commission staff
                                                  not serve to make protestants parties to                https://www.frcc.com/Default.aspx.                    determine what issues they need to
                                                  the proceeding. Any person wishing to                      The discussions at the meeting                     evaluate in the EA. To ensure that your
                                                  become a party must file a notice of                    described above may address matters at                comments are timely and properly
                                                  intervention or motion to intervene, as                 issue in the following proceedings:                   recorded, please send your comments so
                                                  appropriate. Such notices, motions, or                  Docket No. ER13–1932, Tampa Electric                  that the Commission receives them in
                                                  protests must be filed on or before the                    Company                                            Washington, DC on or before June 4,
                                                  comment date. On or before the                          Docket No. ER13–1922, Duke Energy                     2015.
                                                  comment date, it is not necessary to                       Florida (Progress Energy Florida)                     If you sent comments on this project
                                                  serve motions to intervene or protests                  Docket No. ER13–1929, Florida Power &                 to the Commission before the opening of
                                                  on persons other than the Applicant.                       Light Company                                      this docket on March 4, 2015, you will
                                                     The Commission encourages                            Docket No. ER13–1928, Duke Energy                     need to file those comments in Docket
                                                  electronic submission of protests and                      Carolinas/Carolina Power & Light                   No. CP15–105–000 to ensure they are
                                                  interventions in lieu of paper using the                Docket Nos. ER13–107, ER13–1935,                      considered as part of this proceeding.
                                                  ‘‘eFiling’’ link at http://www.ferc.gov.                   South Carolina Electric & Gas                         This notice is being sent to the
                                                  Persons unable to file electronically                      Company                                            Commission’s current environmental
                                                  should submit an original and 5 copies                  Docket No. ER13–1941, Alabama Power                   mailing list for this project. State and
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  of the protest or intervention to the                      Company et al.                                     local government representatives should
                                                  Federal Energy Regulatory Commission,                   Docket No. ER13–1940, Ohio Valley                     notify their constituents of this
                                                  888 First Street NE., Washington, DC                       Electric Corporation                               proposed project and encourage them to
                                                  20426.                                                     For more information, contact Rhonda               comment on their areas of concern.
                                                     This filing is accessible on-line at                 Jones, Office of Energy Market                           If you are a landowner receiving this
                                                  http://www.ferc.gov, using the                          Regulation, Federal Energy Regulatory                 notice, a pipeline company
                                                  ‘‘eLibrary’’ link and is available for                  Commission at (202) 502–6154 or                       representative may contact you about
                                                  electronic review in the Commission’s                   Rhonda.Jones@ferc.gov.                                the acquisition of an easement to


                                             VerDate Sep<11>2014   17:31 May 11, 2015   Jkt 235001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\12MYN1.SGM   12MYN1



Document Created: 2015-12-16 07:55:07
Document Modified: 2015-12-16 07:55:07
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 27155 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR