80_FR_33623 80 FR 33510 - Notice of Availability (NOA) for the Draft Environmental Impact Statement (EIS) and Announcement of Public Hearings for the Proposed New England Clean Power Link (NECPL) Transmission Line

80 FR 33510 - Notice of Availability (NOA) for the Draft Environmental Impact Statement (EIS) and Announcement of Public Hearings for the Proposed New England Clean Power Link (NECPL) Transmission Line

DEPARTMENT OF ENERGY

Federal Register Volume 80, Issue 113 (June 12, 2015)

Page Range33510-33511
FR Document2015-14335

The U.S. Department of Energy (DOE) announces the availability of the ``Draft Environmental Impact Statement for the New England Clean Power Link Transmission Line Project'' (DOE/EIS-0503) for public review and comment. DOE is also announcing two public hearings to receive comments on the Draft EIS. The Draft EIS evaluates the environmental impacts of DOE's proposed Federal action of issuing a Presidential permit to the Applicant: Champlain VT, LLC, doing business as TDI New England (``TDI-NE''), to construct, operate, maintain, and connect a new electric transmission line across the U.S./Canada border in northern Vermont.

Federal Register, Volume 80 Issue 113 (Friday, June 12, 2015)
[Federal Register Volume 80, Number 113 (Friday, June 12, 2015)]
[Notices]
[Pages 33510-33511]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-14335]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

[OE Docket No. PP-400]


Notice of Availability (NOA) for the Draft Environmental Impact 
Statement (EIS) and Announcement of Public Hearings for the Proposed 
New England Clean Power Link (NECPL) Transmission Line

AGENCY: U.S. Department of Energy.

ACTION: Notice of availability and public hearings.

-----------------------------------------------------------------------

SUMMARY: The U.S. Department of Energy (DOE) announces the availability 
of the ``Draft Environmental Impact Statement for the New England Clean 
Power Link Transmission Line Project'' (DOE/EIS-0503) for public review 
and comment. DOE is also announcing two public hearings to receive 
comments on the Draft EIS. The Draft EIS evaluates the environmental 
impacts of DOE's proposed Federal action of issuing a Presidential 
permit to the Applicant: Champlain VT, LLC, doing business as TDI New 
England (``TDI-NE''), to construct, operate, maintain, and connect a 
new electric transmission line across the U.S./Canada border in 
northern Vermont.

DATES: DOE invites interested Members of Congress, state and local 
governments, other Federal agencies, American Indian tribal 
governments, organizations, and members of the public to provide 
comments on the Draft EIS during the 60-day public comment period. The 
public comment period starts on June 12, 2015, with the publication in 
the Federal Register by the U.S. Environmental Protection Agency of its 
Notice of Availability of the Draft EIS, and will continue until August 
11, 2015. Written and oral comments will be given equal weight and all 
comments received or postmarked by that date will be considered by DOE 
in preparing the Final EIS. Comments received or postmarked after that 
date will be considered to the extent practicable.
    Locations, dates, and start time for the public hearings are listed 
in the SUPPLEMENTARY INFORMATION section of this NOA.

ADDRESSES: Requests to provide oral comments at the public hearings may 
be made at the time of the hearing(s).
    Written comments on the Draft EIS may be provided on the NECPL EIS 
Web site at http://necplinkeis.com/ (preferred) or addressed to Mr. 
Brian Mills, Office of Electricity Delivery and Energy Reliability (OE-
20), U.S. Department of Energy, 1000 Independence Avenue SW.,

[[Page 33511]]

Washington, DC 20585; by electronic mail to [email protected]; or 
by facsimile to 202-318-7761.

FOR FURTHER INFORMATION CONTACT: Mr. Brian Mills at the addresses 
above, or at 202-586-8267.

SUPPLEMENTARY INFORMATION: The public hearings will consist of the 
formal taking of comments with transcription by a court stenographer. 
The hearings will provide interested parties the opportunity to make 
comments for consideration in the preparation of the Final EIS.
    The locations, dates, and starting times of the public hearings are 
listed in the table below:

------------------------------------------------------------------------
            Location                 Date and time          Address
------------------------------------------------------------------------
Sheraton, Burlington, Vermont...  July 15, 2015,      870 Williston
                                   6:00 p.m.           Road, South
                                                       Burlington,
                                                       Vermont 05403.
Holiday Inn, Rutland, Vermont...  July 16, 2015,      476 Holiday Drive,
                                   6:00 p.m.           Rutland, Vermont
                                                       05701.
------------------------------------------------------------------------

Availability of the Draft EIS

    Copies of the Draft EIS have been distributed to appropriate 
members of Congress, state and local government officials, American 
Indian tribal governments, and other Federal agencies, groups, and 
interested parties. Printed copies of the document may be obtained by 
contacting Mr. Mills at the above address. Copies of the Draft EIS and 
supporting documents are also available for inspection at the following 
locations:
 South Hero Free Library--76 South Street, South Hero, Vermont
 Fletcher Free Library--235 College Street, Burlington, Vermont
 Winooski Public Library--32 Malletts Bay Avenue, Winooski, 
Vermont
 Middlebury Library--75 Main Street, Middlebury, Vermont
 Rutland Free Library--10 Court Street, Rutland, Vermont
 West Rutland Library--595 Main Street, West Rutland, Vermont
 Shrewsbury Library--98 Town Hill Road, Cuttingsville, Vermont
 Gilbert Hart Library--14 S. Main Street, Wallingford, Vermont
 Fair Haven Public Library--107 North Main Street, Fair Haven, 
Vermont
 Mount Holly Town Library--26 Maple Hill Road, Belmont, Vermont
 Bailey Memorial Library--111 Moulton Avenue, North Clarendon, 
Vermont

    The Draft EIS is also available on the EIS Web site at http://necplinkeis.com/ and on the DOE NEPA Web site at http://nepa.energy.gov/.

    Issued in Washington, DC, on June 4, 2015.
Patricia A. Hoffman,
Assistant Secretary, Office of Electricity Delivery and Energy 
Reliability.
[FR Doc. 2015-14335 Filed 6-11-15; 8:45 am]
 BILLING CODE 6450-01-P



                                                  33510                           Federal Register / Vol. 80, No. 113 / Friday, June 12, 2015 / Notices

                                                  measure and when, during the project                    grantee is operating in compliance with                DEPARTMENT OF ENERGY
                                                  period, the applicant would meet the                    the assurances in its approved
                                                                                                                                                                 [OE Docket No. PP–400]
                                                  performance target(s).                                  application, including those applicable
                                                    Note: The Secretary encourages applicants             to Federal civil rights laws that prohibit             Notice of Availability (NOA) for the
                                                  to consider measures and targets tied to their          discrimination in programs or activities               Draft Environmental Impact Statement
                                                  grant activities (for instance, if grant funds          receiving Federal financial assistance                 (EIS) and Announcement of Public
                                                  will support professional development for               from the Department (34 CFR 100.4,                     Hearings for the Proposed New
                                                  teachers and other staff, applicants should
                                                                                                          104.5, 106.4, 108.8, and 110.23).                      England Clean Power Link (NECPL)
                                                  include measures related to the outcomes for
                                                  the professional development), as well as to                                                                   Transmission Line
                                                                                                          VII. Agency Contact
                                                  student academic achievement during the
                                                                                                                                                                 AGENCY:  U.S. Department of Energy.
                                                  grant period. The measures should be                      For Further Information Contact:
                                                  sufficient to gauge the progress throughout                                                                    ACTION: Notice of availability and public
                                                                                                          Brian Martin, U.S. Department of
                                                  the grant period, and show results by the end                                                                  hearings.
                                                  of the grant period.
                                                                                                          Education, 400 Maryland Avenue SW.,
                                                                                                          room 4W224, Washington, DC 20202–                      SUMMARY:    The U.S. Department of
                                                     For technical assistance in developing               5970. Telephone: (202) 205–9085 or by                  Energy (DOE) announces the availability
                                                  effective performance measures,                         email: brian.martin@ed.gov.                            of the ‘‘Draft Environmental Impact
                                                  applicants are encouraged to review                                                                            Statement for the New England Clean
                                                  information provided by the                               If you use a TDD or a TTY, call the
                                                                                                          FRS, toll free, at 1–800–877–8339.                     Power Link Transmission Line Project’’
                                                  Department’s Regional Educational                                                                              (DOE/EIS–0503) for public review and
                                                  Laboratories (RELs). The RELs seek to                   VIII. Other Information                                comment. DOE is also announcing two
                                                  build the capacity of States and school                                                                        public hearings to receive comments on
                                                  districts to incorporate data and                          Accessible Format: Individuals with                 the Draft EIS. The Draft EIS evaluates
                                                  research into education decision-                       disabilities can obtain this document                  the environmental impacts of DOE’s
                                                  making. Each REL provides research                      and a copy of the application package in               proposed Federal action of issuing a
                                                  support and technical assistance to its                 an accessible format (e.g., braille, large             Presidential permit to the Applicant:
                                                  region but makes learning opportunities                 print, audiotape, or compact disc) on                  Champlain VT, LLC, doing business as
                                                  available to educators everywhere. For                  request to the program contact person                  TDI New England (‘‘TDI–NE’’), to
                                                  example, the REL Northeast and Islands                  listed under For Further Information                   construct, operate, maintain, and
                                                  has created the following resource on                   Contact in section VII of this notice.                 connect a new electric transmission line
                                                  logic models: relpacific.mcrel.org/                                                                            across the U.S./Canada border in
                                                  resources/elm-app.                                         Electronic Access to This Document:
                                                                                                          The official version of this document is               northern Vermont.
                                                     (4) The applicant must also describe
                                                  in the application: (i) the data collection             the document published in the Federal                  DATES: DOE invites interested Members
                                                  and reporting methods the applicant                     Register. Free Internet access to the                  of Congress, state and local
                                                  would use and why those methods are                     official edition of the Federal Register               governments, other Federal agencies,
                                                  likely to yield reliable, valid, and                    and the Code of Federal Regulations is                 American Indian tribal governments,
                                                  meaningful performance data, and (ii)                   available via the Federal Digital System               organizations, and members of the
                                                  the applicant’s capacity to collect and                 at: www.gpo.gov/fdsys. At this site you                public to provide comments on the Draft
                                                  report reliable, valid, and meaningful                  can view this document, as well as all                 EIS during the 60-day public comment
                                                  performance data, as evidenced by high-                 other documents of this Department                     period. The public comment period
                                                  quality data collection, analysis, and                  published in the Federal Register, in                  starts on June 12, 2015, with the
                                                  reporting in other projects or research.                                                                       publication in the Federal Register by
                                                                                                          text or Adobe Portable Document
                                                                                                                                                                 the U.S. Environmental Protection
                                                    Note: If the applicant does not have                  Format (PDF). To use PDF you must
                                                                                                                                                                 Agency of its Notice of Availability of
                                                  experience with collection and reporting of             have Adobe Acrobat Reader, which is
                                                  performance data through other projects or                                                                     the Draft EIS, and will continue until
                                                                                                          available free at the site.                            August 11, 2015. Written and oral
                                                  research, the applicant should provide other
                                                  evidence of capacity to successfully carry out             You may also access documents of the                comments will be given equal weight
                                                  data collection and reporting for their                 Department published in the Federal                    and all comments received or
                                                  proposed project.                                       Register by using the article search                   postmarked by that date will be
                                                     All grantees must submit an annual                   feature at: www.federalregister.gov.                   considered by DOE in preparing the
                                                  performance report with information                     Specifically, through the advanced                     Final EIS. Comments received or
                                                  that is responsive to these performance                 search feature at this site, you can limit             postmarked after that date will be
                                                  measures.                                               your search to documents published by                  considered to the extent practicable.
                                                     5. Continuation Awards: In making a                  the Department.                                           Locations, dates, and start time for the
                                                  continuation award under 34 CFR                                                                                public hearings are listed in the
                                                                                                            Dated: June 8, 2015.
                                                  75.253, the Secretary considers, among                                                                         SUPPLEMENTARY INFORMATION section of
                                                                                                          Nadya Chinoy Dabby,                                    this NOA.
                                                  other things: whether a grantee has
                                                  made substantial progress in achieving                  Assistant Deputy Secretary for Innovation and          ADDRESSES: Requests to provide oral
                                                  the goals and objectives of the project;                Improvement.                                           comments at the public hearings may be
                                                  whether the grantee has expended funds                  [FR Doc. 2015–14386 Filed 6–11–15; 8:45 am]            made at the time of the hearing(s).
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  in a manner that is consistent with its                 BILLING CODE 4000–01–P                                    Written comments on the Draft EIS
                                                  approved application and budget; and,                                                                          may be provided on the NECPL EIS Web
                                                  if the Secretary has established                                                                               site at http://necplinkeis.com/
                                                  performance measurement                                                                                        (preferred) or addressed to Mr. Brian
                                                  requirements, the performance targets in                                                                       Mills, Office of Electricity Delivery and
                                                  the grantee’s approved application. In                                                                         Energy Reliability (OE–20), U.S.
                                                  making a continuation grant, the                                                                               Department of Energy, 1000
                                                  Secretary also considers whether the                                                                           Independence Avenue SW.,


                                             VerDate Sep<11>2014   19:05 Jun 11, 2015   Jkt 235001   PO 00000   Frm 00036   Fmt 4703   Sfmt 4703   E:\FR\FM\12JNN1.SGM   12JNN1


                                                                                  Federal Register / Vol. 80, No. 113 / Friday, June 12, 2015 / Notices                                               33511

                                                  Washington, DC 20585; by electronic                     SUPPLEMENTARY INFORMATION:    The                       comments for consideration in the
                                                  mail to Brian.Mills@hq.doe.gov; or by                   public hearings will consist of the                     preparation of the Final EIS.
                                                  facsimile to 202–318–7761.                              formal taking of comments with                            The locations, dates, and starting
                                                  FOR FURTHER INFORMATION CONTACT: Mr.                    transcription by a court stenographer.                  times of the public hearings are listed in
                                                  Brian Mills at the addresses above, or at               The hearings will provide interested                    the table below:
                                                  202–586–8267.                                           parties the opportunity to make

                                                                   Location                                     Date and time                                               Address

                                                  Sheraton, Burlington, Vermont ...........     July 15, 2015, 6:00 p.m ....................   870 Williston Road, South Burlington, Vermont 05403.
                                                  Holiday Inn, Rutland, Vermont ...........     July 16, 2015, 6:00 p.m ....................   476 Holiday Drive, Rutland, Vermont 05701.



                                                  Availability of the Draft EIS                           DEPARTMENT OF ENERGY                                       Filed Date: 6/5/15.
                                                                                                                                                                     Accession Number: 20150605–5136.
                                                    Copies of the Draft EIS have been                     Federal Energy Regulatory                                  Comments Due: 5 p.m. ET 6/26/15.
                                                  distributed to appropriate members of                   Commission                                                 Take notice that the Commission
                                                  Congress, state and local government                                                                            received the following electric rate
                                                  officials, American Indian tribal                       Combined Notice of Filings #1
                                                                                                                                                                  filings:
                                                  governments, and other Federal                             Take notice that the Commission
                                                  agencies, groups, and interested parties.                                                                          Docket Numbers: ER10–2249–004.
                                                                                                          received the following electric corporate                  Applicants: Portland General Electric
                                                  Printed copies of the document may be                   filings:
                                                  obtained by contacting Mr. Mills at the                                                                         Company.
                                                                                                             Docket Numbers: EC15–96–000.                            Description: Supplement to February
                                                  above address. Copies of the Draft EIS                     Applicants: Osprey Energy Center,                    13, 2015 Notice of Non-Material Change
                                                  and supporting documents are also                       LLC, Duke Energy Florida, Inc.                          in Status of Portland General Electric
                                                  available for inspection at the following                  Description: Osprey Energy Center,                   Company.
                                                  locations:                                              LLC and Duke Energy Florida, Inc                           Filed Date: 6/5/15
                                                  • South Hero Free Library—76 South                      submit additional information                              Accession Number: 20150605–5237
                                                    Street, South Hero, Vermont                           concerning the 3/13/15 application.                        Comments Due: 5 p.m. ET 6/26/15.
                                                                                                             Filed Date: 6/4/15.
                                                  • Fletcher Free Library—235 College                        Accession Number: 20150608–0019.
                                                                                                                                                                     Docket Numbers: ER13–80–006.
                                                    Street, Burlington, Vermont                                                                                      Applicants: Tampa Electric Company.
                                                                                                             Comments Due: 5 p.m. ET 6/18/15.
                                                                                                                                                                     Description: Compliance filing per 35:
                                                  • Winooski Public Library—32 Malletts                      Docket Numbers: EC15–154–000.                        OATT Order No. 1000 Amendment of
                                                    Bay Avenue, Winooski, Vermont                            Applicants: 67RK 8me LLC.                            2014–2015 Compliance Filings to be
                                                  • Middlebury Library—75 Main Street,                       Description: Application for
                                                                                                                                                                  effective 1/1/2015.
                                                    Middlebury, Vermont                                   Authorization Under Section 203 of the
                                                                                                                                                                     Filed Date: 6/8/15.
                                                                                                          Federal Power Act, Request for
                                                  • Rutland Free Library—10 Court                                                                                    Accession Number: 20150608–5080.
                                                                                                          Expedited Consideration and
                                                    Street, Rutland, Vermont                                                                                         Comments Due: 5 p.m. ET 6/29/15.
                                                                                                          Confidential Treatment of 67RK 8me
                                                  • West Rutland Library—595 Main                         LLC.                                                       Docket Numbers: ER13–86–006.
                                                                                                             Filed Date: 6/5/15.                                     Applicants: Duke Energy Florida, Inc.,
                                                    Street, West Rutland, Vermont
                                                                                                             Accession Number: 20150605–5239.                     Duke Energy Carolinas, LLC.
                                                  • Shrewsbury Library—98 Town Hill                          Comments Due: 5 p.m. ET 6/26/15.                        Description: Compliance filing per 35:
                                                    Road, Cuttingsville, Vermont                                                                                  FRCC Fourth Order No. 1000
                                                                                                             Take notice that the Commission
                                                  • Gilbert Hart Library—14 S. Main                       received the following exempt                           Compliance Filing to be effective 1/1/
                                                    Street, Wallingford, Vermont                          wholesale generator filings:                            2015.
                                                                                                                                                                     Filed Date: 6/8/15.
                                                  • Fair Haven Public Library—107 North                      Docket Numbers: EG15–92–000.                            Accession Number: 20150608–5076.
                                                    Main Street, Fair Haven, Vermont                         Applicants: Panda Liberty LLC.
                                                                                                                                                                     Comments Due: 5 p.m. ET 6/29/15.
                                                  • Mount Holly Town Library—26                              Description: Notice of Self-
                                                                                                          Certification of Exempt Wholesale                          Docket Numbers: ER15–1210–001
                                                    Maple Hill Road, Belmont, Vermont                                                                                Applicants: Midcontinent
                                                                                                          Generator Status of Panda Liberty LLC.
                                                  • Bailey Memorial Library—111                              Filed Date: 6/5/15.                                  Independent System Operator, Inc.
                                                    Moulton Avenue, North Clarendon,                         Accession Number: 20150605–5131.                        Description: Compliance filing per 35:
                                                    Vermont                                                  Comments Due: 5 p.m. ET 6/26/15.                     2015–06–08_Hoosier-SIPC RTO Adder
                                                                                                             Docket Numbers: EG15–93–000.                         Compliance to be effective 5/10/2015.
                                                    The Draft EIS is also available on the                   Applicants: Panda Patriot LLC.                          Filed Date: 6/8/15.
                                                  EIS Web site at http://necplinkeis.com/                    Description: Notice of Self-                            Accession Number: 20150608–5152.
                                                  and on the DOE NEPA Web site at                         Certification of Exempt Wholesale                          Comments Due: 5 p.m. ET 6/29/15.
                                                  http://nepa.energy.gov/.                                Generator Status of Panda Patriot LLC.                     Docket Numbers: ER15–1386–000.
                                                    Issued in Washington, DC, on June 4, 2015.               Filed Date: 6/5/15.                                     Applicants: Arizona Public Service
                                                                                                                                                                  Company.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Patricia A. Hoffman,                                       Accession Number: 20150605–5132.
                                                                                                             Comments Due: 5 p.m. ET 6/26/15.                        Description: eTariff filing per
                                                  Assistant Secretary, Office of Electricity                                                                      35.19a(b): Service Agreement No. 343
                                                  Delivery and Energy Reliability.                           Docket Numbers: EG15–94–000.
                                                                                                             Applicants: Panda Stonewall LLC.                     Refund Report to be effective N/A.
                                                  [FR Doc. 2015–14335 Filed 6–11–15; 8:45 am]                                                                        Filed Date: 6/5/15.
                                                                                                             Description: Notice of Self-
                                                  BILLING CODE 6450–01–P                                  Certification of Exempt Wholesale                          Accession Number: 20150605–5121.
                                                                                                          Generator Status of Panda Stonewall                        Comments Due: 5 p.m. ET 6/26/15.
                                                                                                          LLC.                                                       Docket Numbers: ER15–1877–000.


                                             VerDate Sep<11>2014   19:05 Jun 11, 2015   Jkt 235001   PO 00000    Frm 00037   Fmt 4703   Sfmt 4703   E:\FR\FM\12JNN1.SGM   12JNN1



Document Created: 2018-02-22 10:16:03
Document Modified: 2018-02-22 10:16:03
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability and public hearings.
DatesDOE invites interested Members of Congress, state and local governments, other Federal agencies, American Indian tribal governments, organizations, and members of the public to provide comments on the Draft EIS during the 60-day public comment period. The public comment period starts on June 12, 2015, with the publication in the Federal Register by the U.S. Environmental Protection Agency of its Notice of Availability of the Draft EIS, and will continue until August 11, 2015. Written and oral comments will be given equal weight and all comments received or postmarked by that date will be considered by DOE in preparing the Final EIS. Comments received or postmarked after that date will be considered to the extent practicable.
FR Citation80 FR 33510 

2025 Federal Register | Disclaimer | Privacy Policy