80_FR_35457 80 FR 35339 - Mountain Village, CO; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

80 FR 35339 - Mountain Village, CO; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 118 (June 19, 2015)

Page Range35339-35340
FR Document2015-15098

Federal Register, Volume 80 Issue 118 (Friday, June 19, 2015)
[Federal Register Volume 80, Number 118 (Friday, June 19, 2015)]
[Notices]
[Pages 35339-35340]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-15098]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD15-26-000]


Mountain Village, CO; Notice of Preliminary Determination of a 
Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On June 3, 2015, the town of Mountain Village, CO filed a notice of 
intent to construct a qualifying conduit hydropower facility, pursuant 
to section 30 of the Federal Power Act (FPA), as amended by section 4 
of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The 
proposed San Joaquin PRV Hydro Project would have an installed capacity 
of 15 kilowatts (kW) and would be located on the existing water supply 
pipeline for Mountain Village, which transports water for municipal 
consumption. The project would be located near Mountain Village in San 
Miguel County, Colorado.
    Applicant Contact: Finn Kjome, Director of Public Works, 455 
Mountain Village Blvd., Suite A, Mountain Village, CO 81435, Phone No. 
(970) 369-8206.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
robert.bell@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A proposed short, 2-inch-diameter intake 
pipe that connects to a 10-inch-diameter main water supply pipe; (2) a 
proposed powerhouse that contains one turbine-generator unit with an 
installed capacity of 15 kW; (3) a proposed short 2-inch-diamter exit 
pipe returning flow to the main water supply pipe, making the total 
bypass approximately 10-feet; and (5) appurtenant facilities. The 
proposed project would have an estimated annual generating capacity of 
15 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
                                                            Satisfies (Y/
       Statutory provision               Description             N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by    The conduit the facility            Y
 HREA.                             uses is a tunnel,
                                   canal, pipeline,
                                   aqueduct, flume, ditch,
                                   or similar manmade
                                   water conveyance that
                                   is operated for the
                                   distribution of water
                                   for agricultural,
                                   municipal, or
                                   industrial consumption
                                   and not primarily for
                                   the generation of
                                   electricity.
FPA 30(a)(3)(C)(i), as amended    The facility is                     Y
 by HREA.                          constructed, operated,
                                   or maintained for the
                                   generation of electric
                                   power and uses for such
                                   generation only the
                                   hydroelectric potential
                                   of a non-federally
                                   owned conduit.

[[Page 35340]]

 
FPA 30(a)(3)(C)(ii), as amended   The facility has an                 Y
 by HREA.                          installed capacity that
                                   does not exceed 5
                                   megawatts.
FPA 30(a)(3)(C)(iii), as amended  On or before August 9,              Y
 by HREA.                          2013, the facility is
                                   not licensed, or
                                   exempted from the
                                   licensing requirements
                                   of Part I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2014).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD15-26-000) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, 
call (202) 502-8659.

    Dated: June 15, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-15098 Filed 6-18-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                    Federal Register / Vol. 80, No. 118 / Friday, June 19, 2015 / Notices                                           35339

                                                    viewed on the Commission’s Web site at                  upon each representative of the                        DEPARTMENT OF ENERGY
                                                    http://www.ferc.gov using the                           applicant specified in the particular
                                                    ‘‘eLibrary’’ link. Enter the docket                     application. A copy of all other filings               Federal Energy Regulatory
                                                    number excluding the last three digits in               in reference to this application must be               Commission
                                                    the docket number field to access the                   accompanied by proof of service on all                 [Docket No. CD15–26–000]
                                                    document. For assistance, contact FERC                  persons listed in the service list
                                                    Online Support at FERCOnlineSupport.                    prepared by the Commission in this                     Mountain Village, CO; Notice of
                                                    A copy of the application is also                       proceeding, in accordance with 18 CFR                  Preliminary Determination of a
                                                    available for inspection and                            4.34(b) and 385.2010.                                  Qualifying Conduit Hydropower
                                                    reproduction at the address in item h                                                                          Facility and Soliciting Comments and
                                                    above.                                                    o. Procedural Schedule:
                                                                                                                                                                   Motions To Intervene
                                                       Register online at http://                             The application will be processed
                                                    www.ferc.gov/docs-filing/                               according to the following revised                       On June 3, 2015, the town of
                                                    esubscription.asp to be notified via                    Hydro Licensing Schedule. Revisions to                 Mountain Village, CO filed a notice of
                                                    email of new filings and issuances                      the schedule may be made as                            intent to construct a qualifying conduit
                                                    related to this or other pending projects.              appropriate.                                           hydropower facility, pursuant to section
                                                    For assistance, contact FERC Online                                                                            30 of the Federal Power Act (FPA), as
                                                    Support.                                                        Milestone                 Target Date          amended by section 4 of the
                                                       n. Anyone may submit comments, a                                                                            Hydropower Regulatory Efficiency Act
                                                    protest, or a motion to intervene in                    Filing of recommenda-        August 2015.              of 2013 (HREA). The proposed San
                                                    accordance with the requirements of                        tions terms and                                     Joaquin PRV Hydro Project would have
                                                    Rules of Practice and Procedure, 18 CFR                    conditions, and pre-                                an installed capacity of 15 kilowatts
                                                    385.210, .211, and .214. In determining                    scriptions.                                         (kW) and would be located on the
                                                    the appropriate action to take, the                     Commission issues            February 2016.            existing water supply pipeline for
                                                                                                               Environmental As-
                                                    Commission will consider all protests or                                                                       Mountain Village, which transports
                                                                                                               sessment.
                                                    other comments filed, but only those                                                                           water for municipal consumption. The
                                                    who file a motion to intervene in                                                                              project would be located near Mountain
                                                    accordance with the Commission’s                           p. Final amendments to the                          Village in San Miguel County, Colorado.
                                                    Rules may become a party to the                         application must be filed with the                       Applicant Contact: Finn Kjome,
                                                    proceeding. Any comments, protests, or                  Commission no later than 30 days from                  Director of Public Works, 455 Mountain
                                                    motions to intervene must be received                   the issuance date of this notice.                      Village Blvd., Suite A, Mountain
                                                    on or before the specified comment date                    q. A license applicant must file no                 Village, CO 81435, Phone No. (970)
                                                    for the particular application.                         later than 60 days following the date of               369–8206.
                                                       All filings must (1) bear in all capital             issuance of the notice of acceptance and                 FERC Contact: Robert Bell, Phone No.
                                                    letters the title ‘‘PROTEST’’, ‘‘MOTION                 ready for environmental analysis                       (202) 502–6062, email: robert.bell@
                                                    TO INTERVENE’’, ‘‘COMMENTS,’’                           provided for in 5.22: (1) A copy of the                ferc.gov.
                                                    ‘‘REPLY COMMENTS,’’                                     water quality certification; (2) a copy of               Qualifying Conduit Hydropower
                                                    ‘‘RECOMMENDATIONS,’’ ‘‘TERMS                            the request for certification, including               Facility Description: The proposed
                                                    AND CONDITIONS,’’ or                                                                                           project would consist of: (1) A proposed
                                                                                                            proof of the date on which the certifying
                                                    ‘‘PRESCRIPTIONS;’’ (2) set forth in the                                                                        short, 2-inch-diameter intake pipe that
                                                                                                            agency received the request; or (3)
                                                    heading the name of the applicant and                                                                          connects to a 10-inch-diameter main
                                                                                                            evidence of waiver of water quality
                                                    the project number of the application to                                                                       water supply pipe; (2) a proposed
                                                    which the filing responds; (3) furnish                  certification.                                         powerhouse that contains one turbine-
                                                    the name, address, and telephone                          Dated: June 12, 2015.                                generator unit with an installed capacity
                                                    number of the person protesting or                      Kimberly D. Bose,                                      of 15 kW; (3) a proposed short 2-inch-
                                                    intervening; and (4) otherwise comply                   Secretary.                                             diamter exit pipe returning flow to the
                                                    with the requirements of 18 CFR                         [FR Doc. 2015–15097 Filed 6–18–15; 8:45 am]
                                                                                                                                                                   main water supply pipe, making the
                                                    385.2001 through 385.2005. All                                                                                 total bypass approximately 10-feet; and
                                                                                                            BILLING CODE 6717–01–P
                                                    comments, recommendations, terms and                                                                           (5) appurtenant facilities. The proposed
                                                    conditions or prescriptions must set                                                                           project would have an estimated annual
                                                    forth their evidentiary basis and                                                                              generating capacity of 15 megawatt-
                                                    otherwise comply with the requirements                                                                         hours.
                                                    of 18 CFR 4.34(b). Agencies may obtain                                                                           A qualifying conduit hydropower
                                                    copies of the application directly from                                                                        facility is one that is determined or
                                                    the applicant. A copy of any protest or                                                                        deemed to meet all of the criteria shown
                                                    motion to intervene must be served                                                                             in the table below.

                                                                                      TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                  Satisfies
                                                                 Statutory provision                                                             Description
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                                                                                                   (Y/N)

                                                    FPA 30(a)(3)(A), as amended by HREA ...             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or        Y
                                                                                                          similar manmade water conveyance that is operated for the distribution of water for
                                                                                                          agricultural, municipal, or industrial consumption and not primarily for the genera-
                                                                                                          tion of electricity.
                                                    FPA 30(a)(3)(C)(i), as amended by HREA              The facility is constructed, operated, or maintained for the generation of electric           Y
                                                                                                          power and uses for such generation only the hydroelectric potential of a non-feder-
                                                                                                          ally owned conduit.



                                               VerDate Sep<11>2014   19:33 Jun 18, 2015   Jkt 235001   PO 00000   Frm 00041   Fmt 4703   Sfmt 4703   E:\FR\FM\19JNN1.SGM   19JNN1


                                                    35340                            Federal Register / Vol. 80, No. 118 / Friday, June 19, 2015 / Notices

                                                                              TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY—Continued
                                                                                                                                                                                                         Satisfies
                                                                   Statutory provision                                                            Description                                             (Y/N)

                                                    FPA 30(a)(3)(C)(ii), as amended by HREA              The facility has an installed capacity that does not exceed 5 megawatts .....................      Y
                                                    FPA 30(a)(3)(C)(iii), as amended by                  On or before August 9, 2013, the facility is not licensed, or exempted from the licens-            Y
                                                      HREA.                                                ing requirements of Part I of the FPA.



                                                       Preliminary Determination: Based                      of your comments. For assistance,                      intent to construct a qualifying conduit
                                                    upon the above criteria, Commission                      please contact FERC Online Support at                  hydropower facility, pursuant to section
                                                    staff preliminarily determines that the                  FERCOnlineSupport@ferc.gov, (866)                      30 of the Federal Power Act (FPA), as
                                                    proposal satisfies the requirements for a                208–3676 (toll free), or (202) 502–8659                amended by section 4 of the
                                                    qualifying conduit hydropower facility,                  (TTY). In lieu of electronic filing, please            Hydropower Regulatory Efficiency Act
                                                    which is not required to be licensed or                  send a paper copy to: Secretary, Federal               of 2013 (HREA). The proposed Double
                                                    exempted from licensing.                                 Energy Regulatory Commission, 888                      Cabins PRV Hydro Project would have
                                                       Comments and Motions to Intervene:                    First Street NE., Washington, DC 20426.                an installed capacity of 5 kilowatts (kW)
                                                    Deadline for filing comments contesting                  A copy of all other filings in reference               and would be located on the existing
                                                    whether the facility meets the qualifying                to this application must be accompanied                water supply pipeline for Mountain
                                                    criteria is 45 days from the issuance                    by proof of service on all persons listed
                                                    date of this notice.                                                                                            Village, which transports water for
                                                                                                             in the service list prepared by the                    municipal consumption. The project
                                                       Deadline for filing motions to                        Commission in this proceeding, in
                                                    intervene is 30 days from the issuance                                                                          would be located near Mountain Village
                                                                                                             accordance with 18 CFR 4.34(b) and
                                                    date of this notice.                                                                                            in San Miguel County, Colorado.
                                                                                                             385.2010.
                                                       Anyone may submit comments or a                         Locations of Notice of Intent: Copies                  Applicant Contact: Finn Kjome,
                                                    motion to intervene in accordance with                   of the notice of intent can be obtained                Director of Public Works, 455 Mountain
                                                    the requirements of Rules of Practice                    directly from the applicant or such                    Village Blvd., Suite A, Mountain
                                                    and Procedure, 18 CFR 385.210 and                        copies can be viewed and reproduced at                 Village, CO 81435, Phone No. (970)
                                                    385.214. Any motions to intervene must                   the Commission in its Public Reference                 369–8206.
                                                    be received on or before the specified                   Room, Room 2A, 888 First Street NE.,
                                                    deadline date for the particular                                                                                  FERC Contact: Robert Bell, Phone No.
                                                                                                             Washington, DC 20426. The filing may                   (202) 502–6062, email: robert.bell@
                                                    proceeding.                                              also be viewed on the web at http://
                                                       Filing and Service of Responsive                                                                             ferc.gov.
                                                                                                             www.ferc.gov/docs-filing/elibrary.asp
                                                    Documents: All filings must (1) bear in                  using the ‘‘eLibrary’’ link. Enter the                   Qualifying Conduit Hydropower
                                                    all capital letters the ‘‘COMMENTS                       docket number (e.g., CD15–26–000) in                   Facility Description: The proposed
                                                    CONTESTING QUALIFICATION FOR A                                                                                  project would consist of: (1) A proposed
                                                                                                             the docket number field to access the
                                                    CONDUIT HYDROPOWER FACILITY’’                                                                                   short, 2-inch-diameter intake pipe that
                                                                                                             document. For assistance, call toll-free
                                                    or ‘‘MOTION TO INTERVENE,’’ as                                                                                  connects to a 10-inch-diameter main
                                                                                                             1–866–208–3676 or email
                                                    applicable; (2) state in the heading the
                                                                                                             FERCOnlineSupport@ferc.gov. For TTY,                   water supply pipe; (2) a proposed
                                                    name of the applicant and the project
                                                                                                             call (202) 502–8659.                                   powerhouse that contains one turbine-
                                                    number of the application to which the
                                                    filing responds; (3) state the name,                       Dated: June 15, 2015.                                generator unit with an installed capacity
                                                    address, and telephone number of the                     Kimberly D. Bose,                                      of 5 kW; (3) a proposed short 2-inch-
                                                    person filing; and (4) otherwise comply                  Secretary.                                             diameter exit pipe returning flow to the
                                                    with the requirements of sections                        [FR Doc. 2015–15098 Filed 6–18–15; 8:45 am]
                                                                                                                                                                    main water supply pipe, making the
                                                    385.2001 through 385.2005 of the                         BILLING CODE 6717–01–P
                                                                                                                                                                    total bypass approximately 10-feet; and
                                                    Commission’s regulations.1 All                                                                                  (5) appurtenant facilities. The proposed
                                                    comments contesting Commission staff’s                                                                          project would have an estimated annual
                                                    preliminary determination that the                       DEPARTMENT OF ENERGY                                   generating capacity of 10 megawatt-
                                                    facility meets the qualifying criteria                                                                          hours.
                                                    must set forth their evidentiary basis.                  Federal Energy Regulatory                                A qualifying conduit hydropower
                                                       The Commission strongly encourages                    Commission
                                                                                                                                                                    facility is one that is determined or
                                                    electronic filing. Please file motions to                [Docket No. CD15–27–000]                               deemed to meet all of the criteria shown
                                                    intervene and comments using the
                                                    Commission’s eFiling system at http://                                                                          in the table below.
                                                                                                             Mountain Village, CO; Notice of
                                                    www.ferc.gov/docs-filing/efiling.asp.                    Preliminary Determination of a
                                                    Commenters can submit brief comments                     Qualifying Conduit Hydropower
                                                    up to 6,000 characters, without prior                    Facility and Soliciting Comments and
                                                    registration, using the eComment system                  Motions To Intervene
                                                    at http://www.ferc.gov/docs-filing/
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    ecomment.asp. You must include your                       On June 3, 2015, the town of
                                                    name and contact information at the end                  Mountain Village, CO filed a notice of




                                                      1 18   CFR 385.2001–2005 (2014).



                                               VerDate Sep<11>2014    19:33 Jun 18, 2015   Jkt 235001   PO 00000   Frm 00042   Fmt 4703   Sfmt 4703   E:\FR\FM\19JNN1.SGM   19JNN1



Document Created: 2018-02-22 11:10:27
Document Modified: 2018-02-22 11:10:27
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 35339 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR