80_FR_35458 80 FR 35340 - Mountain Village, CO; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

80 FR 35340 - Mountain Village, CO; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 118 (June 19, 2015)

Page Range35340-35341
FR Document2015-15099

Federal Register, Volume 80 Issue 118 (Friday, June 19, 2015)
[Federal Register Volume 80, Number 118 (Friday, June 19, 2015)]
[Notices]
[Pages 35340-35341]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-15099]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD15-27-000]


Mountain Village, CO; Notice of Preliminary Determination of a 
Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On June 3, 2015, the town of Mountain Village, CO filed a notice of 
intent to construct a qualifying conduit hydropower facility, pursuant 
to section 30 of the Federal Power Act (FPA), as amended by section 4 
of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The 
proposed Double Cabins PRV Hydro Project would have an installed 
capacity of 5 kilowatts (kW) and would be located on the existing water 
supply pipeline for Mountain Village, which transports water for 
municipal consumption. The project would be located near Mountain 
Village in San Miguel County, Colorado.
    Applicant Contact: Finn Kjome, Director of Public Works, 455 
Mountain Village Blvd., Suite A, Mountain Village, CO 81435, Phone No. 
(970) 369-8206.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
robert.bell@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A proposed short, 2-inch-diameter intake 
pipe that connects to a 10-inch-diameter main water supply pipe; (2) a 
proposed powerhouse that contains one turbine-generator unit with an 
installed capacity of 5 kW; (3) a proposed short 2-inch-diameter exit 
pipe returning flow to the main water supply pipe, making the total 
bypass approximately 10-feet; and (5) appurtenant facilities. The 
proposed project would have an estimated annual generating capacity of 
10 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

[[Page 35341]]



                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
                                                                                                    Satisfies (Y/
              Statutory provision                                   Description                          N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA............  The conduit the facility uses is a tunnel, canal,            Y
                                                  pipeline, aqueduct, flume, ditch, or similar
                                                  manmade water conveyance that is operated for
                                                  the distribution of water for agricultural,
                                                  municipal, or industrial consumption and not
                                                  primarily for the generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA.........  The facility is constructed, operated, or                    Y
                                                  maintained for the generation of electric power
                                                  and uses for such generation only the
                                                  hydroelectric potential of a non-federally owned
                                                  conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA........  The facility has an installed capacity that does             Y
                                                  not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA.......  On or before August 9, 2013, the facility is not             Y
                                                  licensed, or exempted from the licensing
                                                  requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2014).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD15-27-000) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, 
call (202) 502-8659.

    Dated: June 15, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-15099 Filed 6-18-15; 8:45 am]
BILLING CODE 6717-01-P



                                                    35340                            Federal Register / Vol. 80, No. 118 / Friday, June 19, 2015 / Notices

                                                                              TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY—Continued
                                                                                                                                                                                                         Satisfies
                                                                   Statutory provision                                                            Description                                             (Y/N)

                                                    FPA 30(a)(3)(C)(ii), as amended by HREA              The facility has an installed capacity that does not exceed 5 megawatts .....................      Y
                                                    FPA 30(a)(3)(C)(iii), as amended by                  On or before August 9, 2013, the facility is not licensed, or exempted from the licens-            Y
                                                      HREA.                                                ing requirements of Part I of the FPA.



                                                       Preliminary Determination: Based                      of your comments. For assistance,                      intent to construct a qualifying conduit
                                                    upon the above criteria, Commission                      please contact FERC Online Support at                  hydropower facility, pursuant to section
                                                    staff preliminarily determines that the                  FERCOnlineSupport@ferc.gov, (866)                      30 of the Federal Power Act (FPA), as
                                                    proposal satisfies the requirements for a                208–3676 (toll free), or (202) 502–8659                amended by section 4 of the
                                                    qualifying conduit hydropower facility,                  (TTY). In lieu of electronic filing, please            Hydropower Regulatory Efficiency Act
                                                    which is not required to be licensed or                  send a paper copy to: Secretary, Federal               of 2013 (HREA). The proposed Double
                                                    exempted from licensing.                                 Energy Regulatory Commission, 888                      Cabins PRV Hydro Project would have
                                                       Comments and Motions to Intervene:                    First Street NE., Washington, DC 20426.                an installed capacity of 5 kilowatts (kW)
                                                    Deadline for filing comments contesting                  A copy of all other filings in reference               and would be located on the existing
                                                    whether the facility meets the qualifying                to this application must be accompanied                water supply pipeline for Mountain
                                                    criteria is 45 days from the issuance                    by proof of service on all persons listed
                                                    date of this notice.                                                                                            Village, which transports water for
                                                                                                             in the service list prepared by the                    municipal consumption. The project
                                                       Deadline for filing motions to                        Commission in this proceeding, in
                                                    intervene is 30 days from the issuance                                                                          would be located near Mountain Village
                                                                                                             accordance with 18 CFR 4.34(b) and
                                                    date of this notice.                                                                                            in San Miguel County, Colorado.
                                                                                                             385.2010.
                                                       Anyone may submit comments or a                         Locations of Notice of Intent: Copies                  Applicant Contact: Finn Kjome,
                                                    motion to intervene in accordance with                   of the notice of intent can be obtained                Director of Public Works, 455 Mountain
                                                    the requirements of Rules of Practice                    directly from the applicant or such                    Village Blvd., Suite A, Mountain
                                                    and Procedure, 18 CFR 385.210 and                        copies can be viewed and reproduced at                 Village, CO 81435, Phone No. (970)
                                                    385.214. Any motions to intervene must                   the Commission in its Public Reference                 369–8206.
                                                    be received on or before the specified                   Room, Room 2A, 888 First Street NE.,
                                                    deadline date for the particular                                                                                  FERC Contact: Robert Bell, Phone No.
                                                                                                             Washington, DC 20426. The filing may                   (202) 502–6062, email: robert.bell@
                                                    proceeding.                                              also be viewed on the web at http://
                                                       Filing and Service of Responsive                                                                             ferc.gov.
                                                                                                             www.ferc.gov/docs-filing/elibrary.asp
                                                    Documents: All filings must (1) bear in                  using the ‘‘eLibrary’’ link. Enter the                   Qualifying Conduit Hydropower
                                                    all capital letters the ‘‘COMMENTS                       docket number (e.g., CD15–26–000) in                   Facility Description: The proposed
                                                    CONTESTING QUALIFICATION FOR A                                                                                  project would consist of: (1) A proposed
                                                                                                             the docket number field to access the
                                                    CONDUIT HYDROPOWER FACILITY’’                                                                                   short, 2-inch-diameter intake pipe that
                                                                                                             document. For assistance, call toll-free
                                                    or ‘‘MOTION TO INTERVENE,’’ as                                                                                  connects to a 10-inch-diameter main
                                                                                                             1–866–208–3676 or email
                                                    applicable; (2) state in the heading the
                                                                                                             FERCOnlineSupport@ferc.gov. For TTY,                   water supply pipe; (2) a proposed
                                                    name of the applicant and the project
                                                                                                             call (202) 502–8659.                                   powerhouse that contains one turbine-
                                                    number of the application to which the
                                                    filing responds; (3) state the name,                       Dated: June 15, 2015.                                generator unit with an installed capacity
                                                    address, and telephone number of the                     Kimberly D. Bose,                                      of 5 kW; (3) a proposed short 2-inch-
                                                    person filing; and (4) otherwise comply                  Secretary.                                             diameter exit pipe returning flow to the
                                                    with the requirements of sections                        [FR Doc. 2015–15098 Filed 6–18–15; 8:45 am]
                                                                                                                                                                    main water supply pipe, making the
                                                    385.2001 through 385.2005 of the                         BILLING CODE 6717–01–P
                                                                                                                                                                    total bypass approximately 10-feet; and
                                                    Commission’s regulations.1 All                                                                                  (5) appurtenant facilities. The proposed
                                                    comments contesting Commission staff’s                                                                          project would have an estimated annual
                                                    preliminary determination that the                       DEPARTMENT OF ENERGY                                   generating capacity of 10 megawatt-
                                                    facility meets the qualifying criteria                                                                          hours.
                                                    must set forth their evidentiary basis.                  Federal Energy Regulatory                                A qualifying conduit hydropower
                                                       The Commission strongly encourages                    Commission
                                                                                                                                                                    facility is one that is determined or
                                                    electronic filing. Please file motions to                [Docket No. CD15–27–000]                               deemed to meet all of the criteria shown
                                                    intervene and comments using the
                                                    Commission’s eFiling system at http://                                                                          in the table below.
                                                                                                             Mountain Village, CO; Notice of
                                                    www.ferc.gov/docs-filing/efiling.asp.                    Preliminary Determination of a
                                                    Commenters can submit brief comments                     Qualifying Conduit Hydropower
                                                    up to 6,000 characters, without prior                    Facility and Soliciting Comments and
                                                    registration, using the eComment system                  Motions To Intervene
                                                    at http://www.ferc.gov/docs-filing/
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    ecomment.asp. You must include your                       On June 3, 2015, the town of
                                                    name and contact information at the end                  Mountain Village, CO filed a notice of




                                                      1 18   CFR 385.2001–2005 (2014).



                                               VerDate Sep<11>2014    19:33 Jun 18, 2015   Jkt 235001   PO 00000   Frm 00042   Fmt 4703   Sfmt 4703   E:\FR\FM\19JNN1.SGM   19JNN1


                                                                                     Federal Register / Vol. 80, No. 118 / Friday, June 19, 2015 / Notices                                                     35341

                                                                                         TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                   Statutory                                                                                                                                 Satisfies
                                                                                                                                             Description
                                                                   provision                                                                                                                                  (Y/N)

                                                    FPA 30(a)(3)(A), as amended              The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar man-                Y
                                                      by HREA.                                 made water conveyance that is operated for the distribution of water for agricultural, munic-
                                                                                               ipal, or industrial consumption and not primarily for the generation of electricity.
                                                    FPA 30(a)(3)(C)(i), as amended           The facility is constructed, operated, or maintained for the generation of electric power and                      Y
                                                      by HREA.                                 uses for such generation only the hydroelectric potential of a non-federally owned conduit.
                                                    FPA 30(a)(3)(C)(ii), as amended          The facility has an installed capacity that does not exceed 5 megawatts .....................................      Y
                                                      by HREA.
                                                    FPA 30(a)(3)(C)(iii), as amend-          On or before August 9, 2013, the facility is not licensed, or exempted from the licensing re-                      Y
                                                      ed by HREA.                             quirements of Part I of the FPA.



                                                       Preliminary Determination: Based                      name and contact information at the end                 New York Independent System
                                                    upon the above criteria, Commission                      of your comments. For assistance,                       Operator, Inc.
                                                    staff preliminarily determines that the                  please contact FERC Online Support at
                                                    proposal satisfies the requirements for a                FERCOnlineSupport@ferc.gov, (866)                       The New York Independent System
                                                    qualifying conduit hydropower facility,                  208–3676 (toll free), or (202) 502–8659                 Operator, Inc. Electric System Planning
                                                    which is not required to be licensed or                  (TTY). In lieu of electronic filing, please             Working Group Meeting
                                                    exempted from licensing.                                 send a paper copy to: Secretary, Federal                June 25, 2015, 10:00 a.m.–4:00 p.m.
                                                       Comments and Motions to Intervene:                    Energy Regulatory Commission, 888                       (EST)
                                                    Deadline for filing comments contesting                  First Street NE., Washington, DC 20426.
                                                    whether the facility meets the qualifying                A copy of all other filings in reference                   The above-referenced meeting will be
                                                    criteria is 45 days from the issuance                    to this application must be accompanied                 via web conference and teleconference.
                                                    date of this notice.                                     by proof of service on all persons listed
                                                       Deadline for filing motions to                                                                                   The above-referenced meeting is open
                                                                                                             in the service list prepared by the                     to stakeholders.
                                                    intervene is 30 days from the issuance                   Commission in this proceeding, in
                                                    date of this notice.                                     accordance with 18 CFR 4.34(b) and                         Further information may be found at:
                                                       Anyone may submit comments or a                       385.2010.                                               http://www.nyiso.com/public/markets_
                                                    motion to intervene in accordance with                                                                           operations/services/planning/index.jsp.
                                                    the requirements of Rules of Practice                      Locations of Notice of Intent: Copies
                                                    and Procedure, 18 CFR 385.210 and                        of the notice of intent can be obtained                    The discussions at the meeting
                                                    385.214. Any motions to intervene must                   directly from the applicant or such                     described above may address matters at
                                                    be received on or before the specified                   copies can be viewed and reproduced at                  issue in the following proceedings:
                                                    deadline date for the particular                         the Commission in its Public Reference
                                                                                                                                                                     Docket Nos. ER13–102, ER13–1942,
                                                    proceeding.                                              Room, Room 2A, 888 First Street NE.,
                                                                                                             Washington, DC 20426. The filing may                      ER13–1946, New York Independent
                                                       Filing and Service of Responsive                                                                                System Operator, Inc. and New York
                                                    Documents: All filings must (1) bear in                  also be viewed on the web at http://
                                                                                                             www.ferc.gov/docs-filing/elibrary.asp                     Transmission Owners
                                                    all capital letters the ‘‘COMMENTS
                                                    CONTESTING QUALIFICATION FOR A                           using the ‘‘eLibrary’’ link. Enter the                  Docket No. ER13–1926, PJM
                                                    CONDUIT HYDROPOWER FACILITY’’                            docket number (e.g., CD15–27–000) in                      Transmission Owners
                                                    or ‘‘MOTION TO INTERVENE,’’ as                           the docket number field to access the                   Docket Nos. ER13–1947, ER13–198, PJM
                                                    applicable; (2) state in the heading the                 document. For assistance, call toll-free                  Interconnection, L.L.C.
                                                    name of the applicant and the project                    1–866–208–3676 or email
                                                                                                             FERCOnlineSupport@ferc.gov. For TTY,                    Docket Nos. ER13–1957, ER13–193,
                                                    number of the application to which the
                                                    filing responds; (3) state the name,                     call (202) 502–8659.                                      ER13–196, ISO New England Inc.
                                                    address, and telephone number of the                       Dated: June 15, 2015.                                 Docket No. ER13–1960, ISO New
                                                    person filing; and (4) otherwise comply                  Kimberly D. Bose,                                         England Inc., Participating
                                                    with the requirements of sections                        Secretary.                                                Transmission Owners Administrative
                                                    385.2001 through 385.2005 of the                                                                                   Committee, and New England Power
                                                                                                             [FR Doc. 2015–15099 Filed 6–18–15; 8:45 am]
                                                    Commission’s regulations.1 All                                                                                     Pool Participants Committee
                                                                                                             BILLING CODE 6717–01–P
                                                    comments contesting Commission staff’s
                                                    preliminary determination that the                                                                                 For more information, contact James
                                                    facility meets the qualifying criteria                                                                           Eason, Office of Energy Market
                                                                                                             DEPARTMENT OF ENERGY                                    Regulation, Federal Energy Regulatory
                                                    must set forth their evidentiary basis.
                                                       The Commission strongly encourages                                                                            Commission at (202) 502–8622 or
                                                                                                             Federal Energy Regulatory
                                                    electronic filing. Please file motions to                Commission                                              James.Eason@ferc.gov.
                                                    intervene and comments using the                                                                                   Dated: June 15, 2015.
                                                    Commission’s eFiling system at http://
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                             Notice of Commission Staff                              Kimberly D. Bose,
                                                    www.ferc.gov/docs-filing/efiling.asp.                    Attendance
                                                    Commenters can submit brief comments                                                                             Secretary.
                                                    up to 6,000 characters, without prior                       The Federal Energy Regulatory                        [FR Doc. 2015–15108 Filed 6–18–15; 8:45 am]
                                                    registration, using the eComment system                  Commission (Commission) hereby gives                    BILLING CODE 6717–01–P
                                                    at http://www.ferc.gov/docs-filing/                      notice that members of the
                                                    ecomment.asp. You must include your                      Commission’s staff may attend the
                                                                                                             following meeting related to the
                                                      1 18   CFR 385.2001–2005 (2014).                       transmission planning activities of the


                                               VerDate Sep<11>2014    19:33 Jun 18, 2015   Jkt 235001   PO 00000   Frm 00043   Fmt 4703   Sfmt 9990   E:\FR\FM\19JNN1.SGM    19JNN1



Document Created: 2018-02-22 11:10:13
Document Modified: 2018-02-22 11:10:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 35340 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR