80_FR_37107 80 FR 36983 - Columbia Gas Transmission, LLC; Notice of Application

80 FR 36983 - Columbia Gas Transmission, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 124 (June 29, 2015)

Page Range36983-36983
FR Document2015-15870

Federal Register, Volume 80 Issue 124 (Monday, June 29, 2015)
[Federal Register Volume 80, Number 124 (Monday, June 29, 2015)]
[Notices]
[Page 36983]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-15870]



[[Page 36983]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. Cp15-514-000; Pf14-23-000]


Columbia Gas Transmission, LLC; Notice of Application

    Take notice that on June 8, 2015, Columbia Gas Transmission, LLC 
(Columbia), 5151 San Felipe, Suite 2500, Houston, Texas 77056, filed an 
application under sections 7(c) and 7(b) of the Natural Gas Act and 
Part 157 of the Commission's regulations requesting authorization to 
install construct, operate and abandon certain natural gas pipeline 
facilities for its Leach Xpress project consisting of: (1) Two natural 
gas greenfield pipelines; (ii) two natural gas pipeline loops; (iii) 
the abandonment in place of a segment of one existing natural gas 
pipeline; (iv) the construction of three greenfield compressor 
stations; (v) the construction of three compressor units and the 
abandonment of one compressor unit at an existing compressor station; 
and (vi) various appurtenant and auxiliary facilities. The proposed 
Leach Xpress project's pipeline facilities would total approximately 
160.5 miles of pipe and add approximately 143,000 horsepower of 
compression to transport up to 1.5 Billion cubic feet per day of 
natural gas. Facilities to be constructed are located in Marshall and 
Wayne Counties, West Virginia, Greene County, Pennsylvania, and Monroe, 
Noble, Muskingum, Morgan, Perry Fairfield, Hocking, Jackson, Lawrence 
and Vinton Counties, Ohio, all as more fully described in the 
application.
    The filing may also be viewed on the web at http://www.ferc.gov 
using the ``eLibrary'' link. Enter the docket number excluding the last 
three digits in the docket number field to access the document. For 
assistance, please contact FERC at FERCOnlineSupport@ferc.gov or toll 
free at (866) 208-3676, or TTY, (202) 502-8659.
    Any questions regarding the proposed project should be directed to 
Tyler R. Brown, Senior Counsel, Columbia Gas Transmission, LLC, 5151 
San Felipe, Suite 2500, Houston, Texas 77056; telephone: 713-386-3797.
    On October 9, 2014, the Commission staff granted Columbia's request 
to utilize the National Environmental Policy Act (NEPA) Pre-Filing 
Process and assigned Docket No. PF14-23-000 to staff activities 
involving the project. Now, as of the filing of this application on 
June 8, 2015, the NEPA Pre-Filing Process for this project has ended. 
From this time forward, this proceeding will be conducted in Docket No. 
CP15-514-000, as noted in the caption of this Notice.
    It appears that an expansion project which Columbia indicates may 
be proposed by its affiliate, Columbia Gulf Transmission, LLC, in the 
fall of 2015, the Rayne Xpress Certificated Capacity Increase Project 
(Rayne Express) may have some connection to Columbia's Leach Xpress 
Project. Until the details of the Rayne Xpress project are filed and 
more fully understood, the Commission cannot begin preparation of the 
Environmental Impact Statement (EIS) to comply with the NEPA of 1969. 
Within 90 days after the Commission issues a Notice of Application for 
the Rayne Xpress project, the Commission staff will issue a Notice of 
Schedule for Environmental Review that will indicate the anticipated 
date for the Commission's staff issuance of the final EIS analyzing 
both the Leach Xpress and Rayne XPress proposals. The issuance of a 
Notice of Schedule for Environmental Review will also serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's final EIS.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 7 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: July 13, 2015.

    Dated: June 22, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-15870 Filed 6-26-15; 8:45 am]
 BILLING CODE P



                                                                                 Federal Register / Vol. 80, No. 124 / Monday, June 29, 2015 / Notices                                                   36983

                                                  DEPARTMENT OF ENERGY                                    be conducted in Docket No. CP15–514–                   determining the appropriate action to be
                                                                                                          000, as noted in the caption of this                   taken, but the filing of a comment alone
                                                  Federal Energy Regulatory                               Notice.                                                will not serve to make the filer a party
                                                  Commission                                                 It appears that an expansion project                to the proceeding. The Commission’s
                                                  [Docket No. Cp15–514–000; Pf14–23–000]
                                                                                                          which Columbia indicates may be                        rules require that persons filing
                                                                                                          proposed by its affiliate, Columbia Gulf               comments in opposition to the project
                                                  Columbia Gas Transmission, LLC;                         Transmission, LLC, in the fall of 2015,                provide copies of their protests only to
                                                  Notice of Application                                   the Rayne Xpress Certificated Capacity                 the party or parties directly involved in
                                                                                                          Increase Project (Rayne Express) may                   the protest.
                                                     Take notice that on June 8, 2015,                    have some connection to Columbia’s                        Persons who wish to comment only
                                                  Columbia Gas Transmission, LLC                          Leach Xpress Project. Until the details                on the environmental review of this
                                                  (Columbia), 5151 San Felipe, Suite                      of the Rayne Xpress project are filed and
                                                  2500, Houston, Texas 77056, filed an                                                                           project should submit an original and
                                                                                                          more fully understood, the Commission                  two copies of their comments to the
                                                  application under sections 7(c) and 7(b)                cannot begin preparation of the
                                                  of the Natural Gas Act and Part 157 of                                                                         Secretary of the Commission.
                                                                                                          Environmental Impact Statement (EIS)                   Environmental commenters will be
                                                  the Commission’s regulations requesting                 to comply with the NEPA of 1969.
                                                  authorization to install construct,                                                                            placed on the Commission’s
                                                                                                          Within 90 days after the Commission                    environmental mailing list, will receive
                                                  operate and abandon certain natural gas                 issues a Notice of Application for the
                                                  pipeline facilities for its Leach Xpress                                                                       copies of the environmental documents,
                                                                                                          Rayne Xpress project, the Commission                   and will be notified of meetings
                                                  project consisting of: (1) Two natural gas              staff will issue a Notice of Schedule for
                                                  greenfield pipelines; (ii) two natural gas                                                                     associated with the Commission’s
                                                                                                          Environmental Review that will indicate                environmental review process.
                                                  pipeline loops; (iii) the abandonment in                the anticipated date for the
                                                  place of a segment of one existing                                                                             Environmental commenters will not be
                                                                                                          Commission’s staff issuance of the final               required to serve copies of filed
                                                  natural gas pipeline; (iv) the                          EIS analyzing both the Leach Xpress
                                                  construction of three greenfield                                                                               documents on all other parties.
                                                                                                          and Rayne XPress proposals. The                        However, the non-party commenters
                                                  compressor stations; (v) the construction               issuance of a Notice of Schedule for
                                                  of three compressor units and the                                                                              will not receive copies of all documents
                                                                                                          Environmental Review will also serve to
                                                  abandonment of one compressor unit at                                                                          filed by other parties or issued by the
                                                                                                          notify federal and state agencies of the
                                                  an existing compressor station; and (vi)                                                                       Commission (except for the mailing of
                                                                                                          timing for the completion of all
                                                  various appurtenant and auxiliary                                                                              environmental documents issued by the
                                                                                                          necessary reviews, and the subsequent
                                                  facilities. The proposed Leach Xpress                                                                          Commission) and will not have the right
                                                                                                          need to complete all federal
                                                  project’s pipeline facilities would total                                                                      to seek court review of the
                                                                                                          authorizations within 90 days of the
                                                  approximately 160.5 miles of pipe and                                                                          Commission’s final order.
                                                                                                          date of issuance of the Commission
                                                  add approximately 143,000 horsepower                    staff’s final EIS.                                        The Commission strongly encourages
                                                  of compression to transport up to 1.5                      There are two ways to become                        electronic filings of comments, protests
                                                  Billion cubic feet per day of natural gas.              involved in the Commission’s review of                 and interventions in lieu of paper using
                                                  Facilities to be constructed are located                this project. First, any person wishing to             the ‘‘eFiling’’ link at http://
                                                  in Marshall and Wayne Counties, West                    obtain legal status by becoming a party                www.ferc.gov. Persons unable to file
                                                  Virginia, Greene County, Pennsylvania,                  to the proceedings for this project                    electronically should submit an original
                                                  and Monroe, Noble, Muskingum,                           should, on or before the comment date                  and 5 copies of the protest or
                                                  Morgan, Perry Fairfield, Hocking,                       stated below, file with the Federal                    intervention to the Federal Energy
                                                  Jackson, Lawrence and Vinton Counties,                  Energy Regulatory Commission, 888                      regulatory Commission, 888 First Street
                                                  Ohio, all as more fully described in the                First Street NE., Washington, DC 20426,                NE., Washington, DC 20426.
                                                  application.                                            a motion to intervene in accordance                       Comment Date: July 13, 2015.
                                                     The filing may also be viewed on the                 with the requirements of the                             Dated: June 22, 2015.
                                                  web at http://www.ferc.gov using the                    Commission’s Rules of Practice and                     Kimberly D. Bose,
                                                  ‘‘eLibrary’’ link. Enter the docket                     Procedure (18 CFR 385.214 or 385.211)
                                                                                                                                                                 Secretary.
                                                  number excluding the last three digits in               and the Regulations under the NGA (18
                                                                                                                                                                 [FR Doc. 2015–15870 Filed 6–26–15; 8:45 am]
                                                  the docket number field to access the                   CFR 157.10). A person obtaining party
                                                  document. For assistance, please contact                status will be placed on the service list              BILLING CODE P

                                                  FERC at FERCOnlineSupport@ferc.gov                      maintained by the Secretary of the
                                                  or toll free at (866) 208–3676, or TTY,                 Commission and will receive copies of
                                                  (202) 502–8659.                                         all documents filed by the applicant and               DEPARTMENT OF ENERGY
                                                     Any questions regarding the proposed                 by all other parties. A party must submit              Federal Energy Regulatory
                                                  project should be directed to Tyler R.                  7 copies of filings made with the                      Commission
                                                  Brown, Senior Counsel, Columbia Gas                     Commission and must mail a copy to
                                                  Transmission, LLC, 5151 San Felipe,                     the applicant and to every other party in              Combined Notice of Filings #1
                                                  Suite 2500, Houston, Texas 77056;                       the proceeding. Only parties to the
                                                  telephone: 713–386–3797.                                proceeding can ask for court review of                   Take notice that the Commission
                                                     On October 9, 2014, the Commission                   Commission orders in the proceeding.                   received the following exempt
                                                  staff granted Columbia’s request to                        However, a person does not have to                  wholesale generator filings:
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  utilize the National Environmental                      intervene in order to have comments                      Docket Numbers: EG15–98–000.
                                                  Policy Act (NEPA) Pre-Filing Process                    considered. The second way to
                                                                                                                                                                   Applicants: North Star Solar, LLC.
                                                  and assigned Docket No. PF14–23–000                     participate is by filing with the
                                                  to staff activities involving the project.              Secretary of the Commission, as soon as                  Description: Self-Certification of EG or
                                                  Now, as of the filing of this application               possible, an original and two copies of                FC of North Star Solar, LLC.
                                                  on June 8, 2015, the NEPA Pre-Filing                    comments in support of or in opposition                  Filed Date: 6/23/15.
                                                  Process for this project has ended. From                to this project. The Commission will                     Accession Number: 20150623–5076.
                                                  this time forward, this proceeding will                 consider these comments in                               Comments Due: 5 p.m. ET 7/14/15.


                                             VerDate Sep<11>2014   17:13 Jun 26, 2015   Jkt 235001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\29JNN1.SGM   29JNN1



Document Created: 2015-12-15 14:25:24
Document Modified: 2015-12-15 14:25:24
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesJuly 13, 2015.
FR Citation80 FR 36983 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR