80_FR_38316 80 FR 38189 - Port Arthur LNG, LLC and Port Arthur Pipeline, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Planned Port Arthur Liquefaction Project and Port Arthur Pipeline Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meetings

80 FR 38189 - Port Arthur LNG, LLC and Port Arthur Pipeline, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Planned Port Arthur Liquefaction Project and Port Arthur Pipeline Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meetings

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 127 (July 2, 2015)

Page Range38189-38191
FR Document2015-16311

Federal Register, Volume 80 Issue 127 (Thursday, July 2, 2015)
[Federal Register Volume 80, Number 127 (Thursday, July 2, 2015)]
[Notices]
[Pages 38189-38191]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-16311]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. PF15-18-000 and PF15-19-000]


Port Arthur LNG, LLC and Port Arthur Pipeline, LLC; Notice of 
Intent To Prepare an Environmental Impact Statement for the Planned 
Port Arthur Liquefaction Project and Port Arthur Pipeline Project, 
Request for Comments on Environmental Issues, and Notice of Public 
Scoping Meetings

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental impact statement (EIS) that 
will discuss the environmental impacts of the Port Arthur Liquefaction 
Project and Port Arthur Pipeline Project (projects) involving 
construction and operation of facilities by Port Arthur LNG, LLC 
(PALNG) and Port Arthur Pipeline, LLC (PAPL), respectively, in 
Jefferson and Orange Counties, Texas, and Cameron Parish, Louisiana. 
The Commission will use this EIS in its decision-making process to 
determine whether the projects are in the public interest and public 
convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the projects. You can make a difference by providing us 
with your specific comments or concerns about the projects. Your 
comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. Your input will help the Commission staff determine what 
issues they need to evaluate in the EIS. To ensure that your comments 
are timely and properly recorded, please send your comments so that the 
Commission receives them in Washington, DC on or before July 24, 2015.
    If you sent comments on these projects to the Commission before the 
opening of these dockets on March 31, 2015, you will need to file those 
comments in Docket Nos. PF15-18-000 and PF15-19-000 to ensure they are 
considered as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for these projects. State and local government 
representatives should notify their constituents of these planned 
projects and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the Port Arthur Pipeline Project, that approval 
conveys with it the right of eminent domain. Therefore, if easement 
negotiations fail to produce an agreement, the pipeline company could 
initiate condemnation proceedings where compensation would be 
determined in accordance with state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses 
a number of typically asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings.

Public Participation

    For your convenience, there are four methods you can use to submit 
your comments to the Commission. The Commission will provide equal 
consideration to all comments received, whether filed in written form 
or provided verbally. The Commission encourages electronic filing of 
comments and has expert staff available to assist you at (202) 502-8258 
or [email protected]. Please carefully follow these instructions so that 
your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the projects' docket 
numbers (PF15-18-000 for the Port Arthur Liquefaction Project; PF15-19-
000 for the Port Arthur Pipeline Project) with your submission: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE., Room 1A, Washington, DC 20426.
    (4) In lieu of sending written or electronic comments, the 
Commission invites you to attend one of the public scoping meetings its 
staff will conduct in the projects' area, scheduled as follows.

FERC Public Scoping Meetings--Port Arthur Liquefaction Project and Port 
Arthur Pipeline Project

Holiday Inn Port Arthur-Park Central, 2929 Jimmy Johnson Blvd., Port 
Arthur, Texas 77642

Monday, July 13, 2015
Midday Meeting--11:00 a.m. to 2:00 p.m.
Evening Meeting--5:00 p.m. to 8:00 p.m.

    You may attend at any time during either session, as the primary 
goal of a scoping meeting is for us to have your environmental concerns 
documented. There will not be a formal presentation, but you will have 
the opportunity to learn, in an open-house setting, about the FERC 
Process in addition to presenting your comments. Representatives of 
PAPL and PALNG will also be present to answer questions about their 
projects.
    A court reporter will be available to take verbal comments. Those 
comments will be transcribed and then placed into the dockets for the 
projects and be available for public viewing on FERC's eLibrary system 
in the respective dockets. We believe it is important to note that 
verbal comments hold the same weight as written or electronically 
submitted comments. If a significant number of people are interested in 
providing verbal comments, a time limit of 3 to 5 minutes may be 
implemented for each commenter to ensure all those wishing to comment 
have the opportunity to do so within the designated meeting times. Time 
limits will be strictly enforced if they are implemented.
    Please note this is not your only public input opportunity; please 
refer to the review process flow chart in appendix 1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.

---------------------------------------------------------------------------

[[Page 38190]]

Summary of the Planned Project

    PALNG, an affiliate of Sempra LNG, and PAPL, a subsidiary of Sempra 
U.S. Gas and Power, LLC, are planning to construct and operate 
interrelated liquefied natural gas (LNG) terminal and natural gas 
infrastructure projects. The Port Arthur Liquefaction Project would 
involve the construction of an LNG export terminal and a marine 
facility to accommodate LNG vessels along the Sabine-Neches ship 
channel in Jefferson County, Texas, with a total production capacity of 
up to 1.38 billion cubic feet per day (bcf/d) of natural gas. The Port 
Arthur Pipeline Project would involve the construction of about 35 
miles of new pipeline and would provide approximately 1.6 bcf/d of feed 
natural gas supply to the LNG facilities. The projects would also 
require the relocation of a portion of State Highway 87 and up to five 
existing third-party pipelines to accommodate a marine terminal berth 
for ship docking and loading.
    The Port Arthur Liquefaction Project and Port Arthur Pipeline 
Project would consist of the following facilities:

 An export liquefaction terminal that includes:
    [cir] Two liquefaction trains;
    [cir] a natural gas liquids (NGL) and refrigerant storage area;
    [cir] a marine facility, including two LNG berths, each with three 
liquid loading arms, one vapor loading arm, and one spare hybrid 
loading arm;
    [cir] an NGL and refrigerant truck loading/unloading facility;
    [cir] a construction dock; and
    [cir] three full containment LNG storage tanks;
 an approximately 28-mile-long, 42-inch-diameter pipeline 
extending northerly from the LNG facility to Orange County, Texas;
 an approximately 7-mile-long, 42-inch-diameter pipeline 
extending southerly to Cameron Parish, Louisiana;
 two compressor stations;
 one delivery point and six receipt point meter stations;
 mainline and block valves;
 pig launchers and receiver facilities; \2\ and
---------------------------------------------------------------------------

    \2\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------

 other pipeline-related facilities (e.g., access roads, 
contractor and pipe yards).

    The general location of the project facilities is shown in appendix 
2.

Land Requirements for Construction

    Construction of the planned Port Arthur Liquefaction Project would 
occur on a portion of a 2,900-acre property owned by an affiliate of 
PALNG. The LNG ship berth would be approximately 1,350 feet in width 
and 1,900 feet in length and dredged to a nominal depth of minus 40 
feet mean lower low water. Construction of the marine facilities would 
require dredging of approximately 4.9 million cubic yards (yd\3\) of 
material and construction of the turning basin would require the 
dredging of approximately 1.4 million yd\3\, for a total of 6.3 million 
yd\3\.
    Construction of the planned Port Arthur Pipeline Project would 
disturb about 580 acres of land for the pipeline and aboveground 
facilities. Following construction, PAPL would maintain about 217 acres 
for permanent operation of the pipeline project; the remaining acreage 
would be restored and revert to former uses.

The EIS Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the authorization of LNG 
facilities under section 3 of the Natural Gas Act and the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EIS on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EIS. We will 
consider all filed comments during the preparation of the EIS.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EIS we will discuss impacts that could occur as a result of 
the construction and operation of the planned projects under these 
general headings:

 Geology and soils;
 land use;
 water resources, fisheries, and wetlands;
 cultural resources;
 vegetation and wildlife;
 air quality and noise;
 endangered and threatened species;
 socioeconomics;
 public safety; and
 cumulative impacts.
    We will also evaluate possible alternatives to the planned projects 
or portions of the projects, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Although no formal applications have been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders and to identify and resolve issues before 
the FERC receives an application. As part of our pre-filing review, we 
have begun to contact some federal and state agencies to discuss their 
involvement in the scoping process and the preparation of the EIS.
    The EIS will present our independent analysis of the issues. We 
will publish and distribute the draft EIS for public comment. After the 
comment period, we will consider all timely comments and revise the 
document, as necessary, before issuing a final EIS. To ensure we have 
the opportunity to consider and address your comments, please carefully 
follow the instructions in the Public Participation section, beginning 
on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues 
related to these projects to formally cooperate with us in the 
preparation of the EIS.\4\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice. Currently, the U.S. Department of Energy and U.S. Department of 
Transportation have expressed their intention to participate as a 
cooperating agency in the preparation of the EIS to satisfy their NEPA 
responsibilities related to these projects.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office(s), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the projects' potential effects on

[[Page 38191]]

historic properties.\5\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPOs as the projects 
develop. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EIS for these projects will document 
our findings on the impacts on historic properties and summarize the 
status of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation regulations 
are at Title 36, Code of Federal Regulations, part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    We have already identified two specific issues that we think 
deserve attention based on a preliminary review of the planned 
facilities and the environmental information provided by PAPL and 
PALNG. This preliminary list of issues may change based on your 
comments and our analysis.

 Impacts on wetlands; and
 Impacts on Texas Parks and Wildlife Department land.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the projects. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
planned projects.
    Copies of the completed draft EIS will be sent to the environmental 
mailing list for public review and comment. If you would prefer to 
receive a paper copy of the document instead of the CD version or would 
like to remove your name from the mailing list, please return the 
attached Information Request (appendix 3).

Becoming an Intervenor

    Once PAPL and PALNG file their applications with the Commission, 
you may want to become an ``intervenor'' which is an official party to 
the Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site. Please note that the Commission will not accept requests for 
intervenor status at this time. You must wait until the Commission 
receives formal applications for the projects.

Additional Information

    Additional information about the projects is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., PF15-
18 for the Port Arthur Liquefaction Project; PF15-19 for the Port 
Arthur Pipeline Project). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: June 24, 2015.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-16311 Filed 7-1-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                    Federal Register / Vol. 80, No. 127 / Thursday, July 2, 2015 / Notices                                                    38189

                                                      Dated: June 24, 2015.                                  mailing list for these projects. State and            following address. Be sure to reference
                                                    Kimberly D. Bose,                                        local government representatives should               the projects’ docket numbers (PF15–18–
                                                    Secretary.                                               notify their constituents of these                    000 for the Port Arthur Liquefaction
                                                    [FR Doc. 2015–16308 Filed 7–1–15; 8:45 am]               planned projects and encourage them to                Project; PF15–19–000 for the Port
                                                    BILLING CODE 6717–01–P                                   comment on their areas of concern.                    Arthur Pipeline Project) with your
                                                                                                                If you are a landowner receiving this              submission: Kimberly D. Bose,
                                                                                                             notice, a pipeline company                            Secretary, Federal Energy Regulatory
                                                    DEPARTMENT OF ENERGY                                     representative may contact you about                  Commission, 888 First Street NE., Room
                                                                                                             the acquisition of an easement to                     1A, Washington, DC 20426.
                                                    Federal Energy Regulatory                                construct, operate, and maintain the                    (4) In lieu of sending written or
                                                    Commission                                               planned facilities. The company would                 electronic comments, the Commission
                                                    [Docket Nos. PF15–18–000 and PF15–19–
                                                                                                             seek to negotiate a mutually acceptable               invites you to attend one of the public
                                                    000]                                                     agreement. However, if the Commission                 scoping meetings its staff will conduct
                                                                                                             approves the Port Arthur Pipeline                     in the projects’ area, scheduled as
                                                    Port Arthur LNG, LLC and Port Arthur                     Project, that approval conveys with it                follows.
                                                    Pipeline, LLC; Notice of Intent To                       the right of eminent domain. Therefore,
                                                    Prepare an Environmental Impact                          if easement negotiations fail to produce              FERC Public Scoping Meetings—Port
                                                    Statement for the Planned Port Arthur                    an agreement, the pipeline company                    Arthur Liquefaction Project and Port
                                                    Liquefaction Project and Port Arthur                     could initiate condemnation                           Arthur Pipeline Project
                                                    Pipeline Project, Request for                            proceedings where compensation would                  Holiday Inn Port Arthur-Park Central,
                                                    Comments on Environmental Issues,                        be determined in accordance with state                2929 Jimmy Johnson Blvd., Port Arthur,
                                                    and Notice of Public Scoping Meetings                    law.                                                  Texas 77642
                                                                                                                A fact sheet prepared by the FERC
                                                       The staff of the Federal Energy                       entitled ‘‘An Interstate Natural Gas                  Monday, July 13, 2015
                                                    Regulatory Commission (FERC or                           Facility On My Land? What Do I Need                   Midday Meeting—11:00 a.m. to 2:00
                                                    Commission) will prepare an                              To Know?’’ is available for viewing on                   p.m.
                                                    environmental impact statement (EIS)                     the FERC Web site (www.ferc.gov). This                Evening Meeting—5:00 p.m. to 8:00
                                                    that will discuss the environmental                      fact sheet addresses a number of                         p.m.
                                                    impacts of the Port Arthur Liquefaction                  typically asked questions, including the
                                                    Project and Port Arthur Pipeline Project                                                                          You may attend at any time during
                                                                                                             use of eminent domain and how to
                                                    (projects) involving construction and                                                                          either session, as the primary goal of a
                                                                                                             participate in the Commission’s
                                                    operation of facilities by Port Arthur                                                                         scoping meeting is for us to have your
                                                                                                             proceedings.
                                                    LNG, LLC (PALNG) and Port Arthur                                                                               environmental concerns documented.
                                                    Pipeline, LLC (PAPL), respectively, in                   Public Participation                                  There will not be a formal presentation,
                                                    Jefferson and Orange Counties, Texas,                       For your convenience, there are four               but you will have the opportunity to
                                                    and Cameron Parish, Louisiana. The                       methods you can use to submit your                    learn, in an open-house setting, about
                                                    Commission will use this EIS in its                      comments to the Commission. The                       the FERC Process in addition to
                                                    decision-making process to determine                     Commission will provide equal                         presenting your comments.
                                                    whether the projects are in the public                   consideration to all comments received,               Representatives of PAPL and PALNG
                                                    interest and public convenience and                      whether filed in written form or                      will also be present to answer questions
                                                    necessity.                                               provided verbally. The Commission                     about their projects.
                                                       This notice announces the opening of                  encourages electronic filing of                          A court reporter will be available to
                                                    the scoping process the Commission                       comments and has expert staff available               take verbal comments. Those comments
                                                    will use to gather input from the public                 to assist you at (202) 502–8258 or                    will be transcribed and then placed into
                                                    and interested agencies on the projects.                 efiling@ferc.gov. Please carefully follow             the dockets for the projects and be
                                                    You can make a difference by providing                   these instructions so that your                       available for public viewing on FERC’s
                                                    us with your specific comments or                        comments are properly recorded.                       eLibrary system in the respective
                                                    concerns about the projects. Your                           (1) You can file your comments                     dockets. We believe it is important to
                                                    comments should focus on the potential                   electronically using the eComment                     note that verbal comments hold the
                                                    environmental effects, reasonable                        feature on the Commission’s Web site                  same weight as written or electronically
                                                    alternatives, and measures to avoid or                   (www.ferc.gov) under the link to                      submitted comments. If a significant
                                                    lessen environmental impacts. Your                       Documents and Filings. This is an easy                number of people are interested in
                                                    input will help the Commission staff                     method for submitting brief, text-only                providing verbal comments, a time limit
                                                    determine what issues they need to                       comments on a project;                                of 3 to 5 minutes may be implemented
                                                    evaluate in the EIS. To ensure that your                    (2) You can file your comments                     for each commenter to ensure all those
                                                    comments are timely and properly                         electronically by using the eFiling                   wishing to comment have the
                                                    recorded, please send your comments so                   feature on the Commission’s Web site                  opportunity to do so within the
                                                    that the Commission receives them in                     (www.ferc.gov) under the link to                      designated meeting times. Time limits
                                                    Washington, DC on or before July 24,                     Documents and Filings. With eFiling,                  will be strictly enforced if they are
                                                    2015.                                                    you can provide comments in a variety                 implemented.
                                                       If you sent comments on these                         of formats by attaching them as a file                   Please note this is not your only
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    projects to the Commission before the                    with your submission. New eFiling                     public input opportunity; please refer to
                                                    opening of these dockets on March 31,                    users must first create an account by                 the review process flow chart in
                                                    2015, you will need to file those                        clicking on ‘‘eRegister.’’ If you are filing          appendix 1.1
                                                    comments in Docket Nos. PF15–18–000                      a comment on a particular project,
                                                                                                                                                                     1 The appendices referenced in this notice will
                                                    and PF15–19–000 to ensure they are                       please select ‘‘Comment on a Filing’’ as
                                                                                                                                                                   not appear in the Federal Register. Copies of the
                                                    considered as part of this proceeding.                   the filing type; or                                   appendices were sent to all those receiving this
                                                       This notice is being sent to the                         (3) You can file a paper copy of your              notice in the mail and are available at www.ferc.gov
                                                    Commission’s current environmental                       comments by mailing them to the                                                                  Continued




                                               VerDate Sep<11>2014   21:16 Jul 01, 2015   Jkt 235001   PO 00000   Frm 00018   Fmt 4703   Sfmt 4703   E:\FR\FM\02JYN1.SGM   02JYN1


                                                    38190                           Federal Register / Vol. 80, No. 127 / Thursday, July 2, 2015 / Notices

                                                    Summary of the Planned Project                              The general location of the project                   • cumulative impacts.
                                                       PALNG, an affiliate of Sempra LNG,                     facilities is shown in appendix 2.                         We will also evaluate possible
                                                    and PAPL, a subsidiary of Sempra U.S.                                                                             alternatives to the planned projects or
                                                                                                              Land Requirements for Construction
                                                    Gas and Power, LLC, are planning to                                                                               portions of the projects, and make
                                                    construct and operate interrelated                          Construction of the planned Port                      recommendations on how to lessen or
                                                    liquefied natural gas (LNG) terminal and                  Arthur Liquefaction Project would occur                 avoid impacts on the various resource
                                                    natural gas infrastructure projects. The                  on a portion of a 2,900-acre property                   areas.
                                                    Port Arthur Liquefaction Project would                    owned by an affiliate of PALNG. The                        Although no formal applications have
                                                    involve the construction of an LNG                        LNG ship berth would be approximately                   been filed, we have already initiated our
                                                    export terminal and a marine facility to                  1,350 feet in width and 1,900 feet in                   NEPA review under the Commission’s
                                                    accommodate LNG vessels along the                         length and dredged to a nominal depth                   pre-filing process. The purpose of the
                                                    Sabine-Neches ship channel in Jefferson                   of minus 40 feet mean lower low water.                  pre-filing process is to encourage early
                                                    County, Texas, with a total production                    Construction of the marine facilities                   involvement of interested stakeholders
                                                    capacity of up to 1.38 billion cubic feet                 would require dredging of                               and to identify and resolve issues before
                                                    per day (bcf/d) of natural gas. The Port                  approximately 4.9 million cubic yards                   the FERC receives an application. As
                                                    Arthur Pipeline Project would involve                     (yd3) of material and construction of the               part of our pre-filing review, we have
                                                    the construction of about 35 miles of                     turning basin would require the                         begun to contact some federal and state
                                                    new pipeline and would provide                            dredging of approximately 1.4 million                   agencies to discuss their involvement in
                                                    approximately 1.6 bcf/d of feed natural                   yd3, for a total of 6.3 million yd3.                    the scoping process and the preparation
                                                    gas supply to the LNG facilities. The                       Construction of the planned Port                      of the EIS.
                                                    projects would also require the                           Arthur Pipeline Project would disturb                      The EIS will present our independent
                                                    relocation of a portion of State Highway                  about 580 acres of land for the pipeline                analysis of the issues. We will publish
                                                    87 and up to five existing third-party                    and aboveground facilities. Following                   and distribute the draft EIS for public
                                                    pipelines to accommodate a marine                         construction, PAPL would maintain                       comment. After the comment period, we
                                                    terminal berth for ship docking and                       about 217 acres for permanent operation                 will consider all timely comments and
                                                    loading.                                                  of the pipeline project; the remaining                  revise the document, as necessary,
                                                       The Port Arthur Liquefaction Project                   acreage would be restored and revert to                 before issuing a final EIS. To ensure we
                                                    and Port Arthur Pipeline Project would                    former uses.                                            have the opportunity to consider and
                                                    consist of the following facilities:                      The EIS Process                                         address your comments, please carefully
                                                    • An export liquefaction terminal that                                                                            follow the instructions in the Public
                                                       includes:                                                 The National Environmental Policy                    Participation section, beginning on page
                                                       Æ Two liquefaction trains;                             Act (NEPA) requires the Commission to                   2.
                                                       Æ a natural gas liquids (NGL) and                      take into account the environmental                        With this notice, we are asking
                                                         refrigerant storage area;                            impacts that could result from an action                agencies with jurisdiction by law and/
                                                       Æ a marine facility, including two                     whenever it considers the authorization                 or special expertise with respect to the
                                                         LNG berths, each with three liquid                   of LNG facilities under section 3 of the                environmental issues related to these
                                                         loading arms, one vapor loading                      Natural Gas Act and the issuance of a                   projects to formally cooperate with us in
                                                         arm, and one spare hybrid loading                    Certificate of Public Convenience and                   the preparation of the EIS.4 Agencies
                                                         arm;                                                 Necessity. NEPA also requires us 3 to                   that would like to request cooperating
                                                       Æ an NGL and refrigerant truck                         discover and address concerns the                       agency status should follow the
                                                         loading/unloading facility;                          public may have about proposals. This                   instructions for filing comments
                                                       Æ a construction dock; and                             process is referred to as scoping. The                  provided under the Public Participation
                                                       Æ three full containment LNG storage                   main goal of the scoping process is to                  section of this notice. Currently, the
                                                         tanks;                                               focus the analysis in the EIS on the                    U.S. Department of Energy and U.S.
                                                    • an approximately 28-mile-long, 42-                      important environmental issues. By this
                                                       inch-diameter pipeline extending                                                                               Department of Transportation have
                                                                                                              notice, the Commission requests public                  expressed their intention to participate
                                                       northerly from the LNG facility to                     comments on the scope of the issues to
                                                       Orange County, Texas;                                                                                          as a cooperating agency in the
                                                                                                              address in the EIS. We will consider all                preparation of the EIS to satisfy their
                                                    • an approximately 7-mile-long, 42-                       filed comments during the preparation
                                                       inch-diameter pipeline extending                                                                               NEPA responsibilities related to these
                                                                                                              of the EIS.                                             projects.
                                                       southerly to Cameron Parish,                              In the EIS we will discuss impacts
                                                       Louisiana;                                             that could occur as a result of the                     Consultations Under Section 106 of the
                                                    • two compressor stations;                                construction and operation of the                       National Historic Preservation Act
                                                    • one delivery point and six receipt
                                                                                                              planned projects under these general                      In accordance with the Advisory
                                                       point meter stations;
                                                    • mainline and block valves;                              headings:                                               Council on Historic Preservation’s
                                                    • pig launchers and receiver facilities; 2                • Geology and soils;                                    implementing regulations for section
                                                       and                                                    • land use;                                             106 of the National Historic
                                                    • other pipeline-related facilities (e.g.,                • water resources, fisheries, and                       Preservation Act, we are using this
                                                       access roads, contractor and pipe                         wetlands;                                            notice to initiate consultation with the
                                                       yards).                                                • cultural resources;                                   applicable State Historic Preservation
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                              • vegetation and wildlife;                              Office(s), and to solicit their views and
                                                    using the link called ‘‘eLibrary’’ or from the            • air quality and noise;                                those of other government agencies,
                                                    Commission’s Public Reference Room, 888 First             • endangered and threatened species;                    interested Indian tribes, and the public
                                                    Street NE., Washington, DC 20426, or call (202)           • socioeconomics;                                       on the projects’ potential effects on
                                                    502–8371. For instructions on connecting to
                                                    eLibrary, refer to the last page of this notice.          • public safety; and
                                                      2 A ‘‘pig’’ is a tool that the pipeline company                                                                   4 The Council on Environmental Quality

                                                    inserts into and pushes through the pipeline for               3 ‘‘We,’’
                                                                                                                        ‘‘us,’’ and ‘‘our’’ refer to the              regulations addressing cooperating agency
                                                    cleaning the pipeline, conducting internal                environmental staff of the Commission’s Office of       responsibilities are at Title 40, Code of Federal
                                                    inspections, or other purposes.                           Energy Projects.                                        Regulations, part 1501.6.



                                               VerDate Sep<11>2014   21:16 Jul 01, 2015   Jkt 235001    PO 00000     Frm 00019   Fmt 4703   Sfmt 4703   E:\FR\FM\02JYN1.SGM   02JYN1


                                                                                     Federal Register / Vol. 80, No. 127 / Thursday, July 2, 2015 / Notices                                          38191

                                                    historic properties.5 We will define the                  Becoming an Intervenor                                DEPARTMENT OF ENERGY
                                                    project-specific Area of Potential Effects
                                                    (APE) in consultation with the SHPOs                         Once PAPL and PALNG file their                     Federal Energy Regulatory
                                                    as the projects develop. On natural gas                   applications with the Commission, you                 Commission
                                                    facility projects, the APE at a minimum                   may want to become an ‘‘intervenor’’
                                                    encompasses all areas subject to ground                   which is an official party to the                     Combined Notice of Filings #1
                                                    disturbance (examples include                             Commission’s proceeding. Intervenors
                                                                                                                                                                       Take notice that the Commission
                                                    construction right-of-way, contractor/                    play a more formal role in the process
                                                                                                                                                                    received the following electric corporate
                                                    pipe storage yards, compressor stations,                  and are able to file briefs, appear at
                                                                                                                                                                    filings:
                                                    and access roads). Our EIS for these                      hearings, and be heard by the courts if
                                                    projects will document our findings on                    they choose to appeal the Commission’s                   Docket Numbers: EC15–96–000.
                                                    the impacts on historic properties and                    final ruling. An intervenor formally                     Applicants: Osprey Energy Center,
                                                    summarize the status of consultations                     participates in the proceeding by filing              LLC, Duke Energy Florida, Inc.
                                                                                                              a request to intervene. Instructions for                 Description: Supplement to May 13,
                                                    under section 106.
                                                                                                              becoming an intervenor are in the User’s              2015 Joint Application for Approval
                                                    Currently Identified Environmental                                                                              Under Section 203 of the Federal Power
                                                                                                              Guide under the ‘‘e-filing’’ link on the
                                                    Issues                                                                                                          Act of Osprey Energy Center, LLC and
                                                                                                              Commission’s Web site. Please note that
                                                       We have already identified two                         the Commission will not accept requests               Duke Energy Florida, Inc.
                                                    specific issues that we think deserve                                                                              Filed Date: 6/23/15.
                                                                                                              for intervenor status at this time. You
                                                    attention based on a preliminary review                                                                            Accession Number: 20150623–5171.
                                                                                                              must wait until the Commission
                                                    of the planned facilities and the                                                                                  Comments Due: 5 p.m. ET 7/2/15.
                                                                                                              receives formal applications for the
                                                    environmental information provided by                     projects.                                                Docket Numbers: EC15–158–000.
                                                    PAPL and PALNG. This preliminary list                                                                              Applicants: DTE Electric Company,
                                                    of issues may change based on your                        Additional Information                                Renaissance Power, L.L.C.
                                                    comments and our analysis.                                                                                         Description: Application for
                                                                                                                 Additional information about the                   Authorization for Disposition of
                                                    • Impacts on wetlands; and                                projects is available from the
                                                    • Impacts on Texas Parks and Wildlife                                                                           Jurisdictional Facilities pursuant to FPA
                                                                                                              Commission’s Office of External Affairs,              Section 203 by DTE Electric Company
                                                       Department land.
                                                                                                              at (866) 208–FERC, or on the FERC Web                 and Renaissance Power. L.L.C.
                                                    Environmental Mailing List                                site (www.ferc.gov) using the eLibrary                   Filed Date: 6/23/15.
                                                       The environmental mailing list                         link. Click on the eLibrary link, click on               Accession Number: 20150623–5170.
                                                    includes federal, state, and local                        ‘‘General Search’’ and enter the docket                  Comments Due: 5 p.m. ET 7/14/15.
                                                    government representatives and                            number, excluding the last three digits                  Take notice that the Commission
                                                    agencies; elected officials;                              in the Docket Number field (i.e., PF15–               received the following exempt
                                                    environmental and public interest                         18 for the Port Arthur Liquefaction                   wholesale generator filings:
                                                    groups; Native American tribes; other                     Project; PF15–19 for the Port Arthur
                                                                                                                                                                       Docket Numbers: EG15–99–000.
                                                    interested parties; and local libraries                   Pipeline Project). Be sure you have
                                                                                                                                                                       Applicants: Indeck Corinth Limited
                                                    and newspapers. This list also includes                   selected an appropriate date range. For
                                                                                                                                                                    Partnership.
                                                    all affected landowners (as defined in                    assistance, please contact FERC Online                   Description: Self-Certification of EWG
                                                    the Commission’s regulations) who are                     Support at FercOnlineSupport@ferc.gov                 Status of Indeck Corinth Limited
                                                    potential right-of-way grantors, whose                    or toll free at (866) 208–3676, or for                Partnership.
                                                    property may be used temporarily for                      TTY, contact (202) 502–8659. The                         Filed Date: 6/23/15.
                                                    project purposes, or who own homes                        eLibrary link also provides access to the                Accession Number: 20150623–5159.
                                                    within certain distances of aboveground                   texts of formal documents issued by the                  Comments Due: 5 p.m. ET 7/14/15.
                                                    facilities, and anyone who submits                        Commission, such as orders, notices,
                                                                                                                                                                       Take notice that the Commission
                                                    comments on the projects. We will                         and rulemakings.
                                                                                                                                                                    received the following electric rate
                                                    update the environmental mailing list as                     In addition, the Commission offers a               filings:
                                                    the analysis proceeds to ensure that we                   free service called eSubscription which
                                                    send the information related to this                                                                               Docket Numbers: ER10–3254–002.
                                                                                                              allows you to keep track of all formal                   Applicants: Cooperative Energy
                                                    environmental review to all individuals,                  issuances and submittals in specific
                                                    organizations, and government entities                                                                          Incorporated (An Electric Membership
                                                                                                              dockets. This can reduce the amount of                Coporation).
                                                    interested in and/or potentially affected                 time you spend researching proceedings
                                                    by the planned projects.                                                                                           Description: Supplement to May 12,
                                                                                                              by automatically providing you with                   2015 Updated Market Power Analysis of
                                                       Copies of the completed draft EIS will                 notification of these filings, document
                                                    be sent to the environmental mailing list                                                                       Cooperative Energy Incorporated (An
                                                                                                              summaries, and direct links to the                    Electric Membership Corporation).
                                                    for public review and comment. If you                     documents. Go to www.ferc.gov/docs-
                                                    would prefer to receive a paper copy of                                                                            Filed Date: 6/19/15.
                                                                                                              filing/esubscription.asp.                                Accession Number: 20150619–5231.
                                                    the document instead of the CD version
                                                    or would like to remove your name from                       Finally, public meetings or site visits               Comments Due: 5 p.m. ET 7/10/15.
                                                    the mailing list, please return the                       will be posted on the Commission’s                       Docket Numbers: ER13–1523–002.
                                                                                                              calendar located at www.ferc.gov/                        Applicants: Blythe Energy Inc.,
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    attached Information Request (appendix
                                                    3).                                                       EventCalendar/EventsList.aspx along                   AltaGas Renewable Energy Colorado
                                                                                                              with other related information.                       LLC.
                                                      5 The Advisory Council on Historic Preservation
                                                                                                                Dated: June 24, 2015.                                  Description: Supplement to February
                                                    regulations are at Title 36, Code of Federal                                                                    9, 2015 Notice of Change in Status of
                                                    Regulations, part 800. Those regulations define           Kimberly D. Bose,
                                                                                                                                                                    Blythe Energy Inc.
                                                    historic properties as any prehistoric or historic        Secretary.
                                                    district, site, building, structure, or object included
                                                                                                                                                                       Filed Date: 5/11/15.
                                                                                                              [FR Doc. 2015–16311 Filed 7–1–15; 8:45 am]               Accession Number: 20150511–5244.
                                                    in or eligible for inclusion in the National Register
                                                    of Historic Places.                                       BILLING CODE 6717–01–P                                   Comments Due: 5 p.m. ET 7/15/15.


                                               VerDate Sep<11>2014    21:16 Jul 01, 2015   Jkt 235001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\02JYN1.SGM   02JYN1



Document Created: 2015-12-15 13:16:02
Document Modified: 2015-12-15 13:16:02
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 38189 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR