80_FR_38320 80 FR 38193 - Freeport LNG Development, L.P., FLNG Liquefaction, LLC., FLNG Liquefaction 2, LLC. and FLNG Liquefaction 3, LLC.; Notice of Application To Amend Aurhtorization Under Section 3 of the Natural Gas Act

80 FR 38193 - Freeport LNG Development, L.P., FLNG Liquefaction, LLC., FLNG Liquefaction 2, LLC. and FLNG Liquefaction 3, LLC.; Notice of Application To Amend Aurhtorization Under Section 3 of the Natural Gas Act

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 127 (July 2, 2015)

Page Range38193-38194
FR Document2015-16309

Federal Register, Volume 80 Issue 127 (Thursday, July 2, 2015)
[Federal Register Volume 80, Number 127 (Thursday, July 2, 2015)]
[Notices]
[Pages 38193-38194]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-16309]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulation Commission

[Docket No. CP15-518-000]


Freeport LNG Development, L.P., FLNG Liquefaction, LLC., FLNG 
Liquefaction 2, LLC. and FLNG Liquefaction 3, LLC.; Notice of 
Application To Amend Aurhtorization Under Section 3 of the Natural Gas 
Act

    Take notice that on June 15, 2015 Freeport LNG Development, L.P., 
FLNG Liquefaction, LLC, FLNG Liquefaction 2, LLC, and FLNG Liquefaction 
3, LLC (collectively Freeport LNG), 333 Clay Street, Suite 5050, 
Houston, TX 77002, filed in Docket No. CP15-518-000, an application 
pursuant to section 3(a) of the Natural Gas Act (NGA), and Part 153 of 
the Commission's Regulations, to amend the authorizations granted on 
July 30, 2014 in Docket Nos. CP12-509-000 and CP12-29-000. Freeport LNG 
seeks authorization from the Commission to increase the total liquefied 
natural gas production capacity of its Liquefaction Project from the 
currently authorized 1.8 billion cubic feet (Bcf) per day (657 Bcf per 
year) to 2.14 Bcf per day (782 Bcf per year). No new facilities are 
proposed, all as more full set forth in the application which is on 
file with the Commission and open to public inspection.
    This filing is accessible on-line at http://www.ferc.gov, using the 
``eLibrary'' link. Enter the docket number, excluding the last three 
digits, in the docket number filed to access the document. It is also 
available for review in the Commission's Public Reference Room in 
Washington, DC. For assistance, please contact FERC Online Support at 
[email protected]

[[Page 38194]]

ferc.gov, or call toll-free at (866) 208-3676, or for TTY, contact 
(202) 502-8659.
    Any questions regarding the application should be directed to John 
B. Tobola, Freeport LNG Development, L.P., 333 Clay Street, Suite 5050, 
Houston, TX 77002, (713) 980-2888; or Lisa M. Tonery, Norton Rose 
Fulbright US LLP, 666 Fifth Avenue, New York, NY 10103, (212) 318-3009, 
[email protected].
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this Project. First, any person wishing to obtain legal status by 
becoming a party to the proceeding for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirement of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) A person obtaining party status will be placed on the service 
list maintained by the Secretary of the Commission, and will receive 
copies of all documents filed by the applicant and by all other 
parties. A party must submit filing made it the Commission by mail, 
hand delivery, or internet, in accordance with Rule 2001 of the 
Commission's Rules of Practice and Procedure (18 CFR 385.2001). A copy 
must be served on every other party in the proceeding. Only parties to 
the proceeding may ask for court review of Commission orders in the 
proceeding.
    However, a person does not have to intervene to have comments 
considered. The second way to participate is by filing with the 
Secretary of the Commission, as soon as possible, an original and two 
copies of comments in support of or in opposition to this project and/
or associated pipeline. The Commission will consider these comments in 
determining the appropriate action to be taken, but the filing of a 
comment alone will not serve to make the filer a party to the 
proceeding. The Commission's rules require that person filing comments 
in opposition to the project provide copies of their protests only to 
the party or parties directly involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 7 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    If the Commission decides to set the application for a formal 
hearing before an Administrative Law Judge, the Commission will issue 
another notice describing that process. At the end of the Commission's 
review process, a final Commission order approving or denying the 
requested authorization will be issued.
    Comment Date: 5:00 p.m. Eastern Daylight Savings Time July 15, 
2015.

    Dated: June 24, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-16309 Filed 7-1-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                    Federal Register / Vol. 80, No. 127 / Thursday, July 2, 2015 / Notices                                                 38193

                                                    the new 83,597 horsepower (HP) Wilson                    the subsequent need to complete all                   to seek court review of the
                                                    Compressor Station (CS) in Wharton                       federal authorizations within 90 days of              Commission’s final order.
                                                    County, Texas; (iii) the new 26,400 HP                   the date of issuance of the Commission                  The Commission strongly encourages
                                                    Brazos CS in Fort Bend County, Texas;                    staff’s FEIS or EA.                                   electronic filings of comments, protests
                                                    (iv) the new 10,700 HP North Houston                        There are two ways to become                       and interventions in lieu of paper using
                                                    CS in Harris County, Texas; (v) piping                   involved in the Commission’s review of                the ‘‘eFiling’’ link at http://
                                                    modifications at Goodrich CS in Polk                     this project. First, any person wishing to            www.ferc.gov. Persons unable to file
                                                    County, Texas to allow for bi-directional                obtain legal status by becoming a party               electronically should submit an original
                                                    flow; and (vi) additional 15,748 HP and                  to the proceedings for this project                   and five copies of the protest or
                                                    modifications to allow for bi-directional                should, on or before the comment date                 intervention to the Federal Energy
                                                    flow at Magasco CS site in Sabine                        stated below file with the Federal                    Regulatory Commission, 888 First Street
                                                    County, Texas. Gulf South estimates the                  Energy Regulatory Commission, 888                     NE., Washington, DC 20426.
                                                    cost of the Coastal Bend Header Project                  First Street NE., Washington, DC 20426,                 Comment Date: 5:00 p.m. Eastern
                                                    to be $690,357,089, all as more fully set                a motion to intervene in accordance                   Time on July 16, 2015.
                                                    forth in the application which is on file                with the requirements of the
                                                                                                                                                                     Dated: June 25, 2015.
                                                    with the Commission and open to                          Commission’s Rules of Practice and
                                                                                                             Procedure (18 CFR 385.214 or 385.211)                 Kimberly D. Bose,
                                                    public inspection. The filing is available
                                                    for review at the Commission in the                      and the Regulations under the NGA (18                 Secretary.
                                                    Public Reference Room or may be                          CFR 157.10). A person obtaining party                 [FR Doc. 2015–16300 Filed 7–1–15; 8:45 am]
                                                    viewed on the Commission’s Web site                      status will be placed on the service list             BILLING CODE 6717–01–P
                                                    web at http://www.ferc.gov using the                     maintained by the Secretary of the
                                                    ‘‘eLibrary’’ link. Enter the docket                      Commission and will receive copies of
                                                    number excluding the last three digits in                all documents filed by the applicant and              DEPARTMENT OF ENERGY
                                                    the docket number field to access the                    by all other parties. A party must submit
                                                    document. For assistance, contact FERC                   five copies of filings made in the                    Federal Energy Regulation
                                                    at FERCOnlineSupport@ferc.gov or call                    proceeding with the Commission and                    Commission
                                                    toll-free, (886) 208–3676 or TYY, (202)                  must mail a copy to the applicant and                 [Docket No. CP15–518–000]
                                                    502–8659.                                                to every other party. Only parties to the
                                                       Any questions regarding this                          proceeding can ask for court review of                Freeport LNG Development, L.P., FLNG
                                                    application may be directed to J. Kyle                   Commission orders in the proceeding.                  Liquefaction, LLC., FLNG Liquefaction
                                                    Stephens, Vice President of Regulatory                      However, a person does not have to                 2, LLC. and FLNG Liquefaction 3, LLC.;
                                                    Affairs, Gulf South Pipeline Company,                    intervene in order to have comments                   Notice of Application To Amend
                                                    LP, 9 Greenway Plaza, Suite 2800,                        considered. The second way to                         Aurhtorization Under Section 3 of the
                                                    Houston, Texas 77046, by telephone at                    participate is by filing with the                     Natural Gas Act
                                                    (713) 479–8252, or by email to                           Secretary of the Commission, as soon as
                                                    kyle.stephens@bwpmlp.com.                                possible, an original and two copies of                  Take notice that on June 15, 2015
                                                       On November 5, 2014, the                              comments in support of or in opposition               Freeport LNG Development, L.P., FLNG
                                                    Commission staff granted Gulf South’s                    to this project. The Commission will                  Liquefaction, LLC, FLNG Liquefaction 2,
                                                    request to utilize the Pre-Filing Process                consider these comments in                            LLC, and FLNG Liquefaction 3, LLC
                                                    and assigned Docket No. PF15–4–000 to                    determining the appropriate action to be              (collectively Freeport LNG), 333 Clay
                                                    staff activities involved in the Coastal                 taken, but the filing of a comment alone              Street, Suite 5050, Houston, TX 77002,
                                                    Bend Header Project. Now, as of the                      will not serve to make the filer a party              filed in Docket No. CP15–518–000, an
                                                    filing of the June 12, 2015 application,                 to the proceeding. The Commission’s                   application pursuant to section 3(a) of
                                                    the Pre-Filing Process for this project                  rules require that persons filing                     the Natural Gas Act (NGA), and Part 153
                                                    has ended. From this time forward, this                  comments in opposition to the project                 of the Commission’s Regulations, to
                                                    proceeding will be conducted in Docket                   provide copies of their protests only to              amend the authorizations granted on
                                                    No. CP15–517–000, as noted in the                        the party or parties directly involved in             July 30, 2014 in Docket Nos. CP12–509–
                                                    caption of this Notice.                                  the protest.                                          000 and CP12–29–000. Freeport LNG
                                                       Pursuant to section 157.9 of the                         Persons who wish to comment only                   seeks authorization from the
                                                    Commission’s rules, 18 CFR 157.9,                        on the environmental review of this                   Commission to increase the total
                                                    within 90 days of this Notice, the                       project should submit an original and                 liquefied natural gas production
                                                    Commission staff will either: Complete                   two copies of their comments to the                   capacity of its Liquefaction Project from
                                                    its environmental assessment (EA) and                    Secretary of the Commission.                          the currently authorized 1.8 billion
                                                    place it into the Commission’s public                    Environmental commenters will be                      cubic feet (Bcf) per day (657 Bcf per
                                                    record (eLibrary) for this proceeding; or                placed on the Commission’s                            year) to 2.14 Bcf per day (782 Bcf per
                                                    issue a Notice of Schedule for                           environmental mailing list, will receive              year). No new facilities are proposed, all
                                                    Environmental Review. If a Notice of                     copies of the environmental documents,                as more full set forth in the application
                                                    Schedule for Environmental Review is                     and will be notified of meetings                      which is on file with the Commission
                                                    issued, it will indicate, among other                    associated with the Commission’s                      and open to public inspection.
                                                    milestones, the anticipated date for the                 environmental review process.                            This filing is accessible on-line at
                                                    Commission staff’s issuance of the final                 Environmental commenters will not be                  http://www.ferc.gov, using the
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    environmental impact statement (FEIS)                    required to serve copies of filed                     ‘‘eLibrary’’ link. Enter the docket
                                                    or EA for this proposal. The filing of the               documents on all other parties.                       number, excluding the last three digits,
                                                    EA in the Commission’s public record                     However, the non-party commenters                     in the docket number filed to access the
                                                    for this proceeding or the issuance of a                 will not receive copies of all documents              document. It is also available for review
                                                    Notice of Schedule for Environmental                     filed by other parties or issued by the               in the Commission’s Public Reference
                                                    Review will serve to notify federal and                  Commission (except for the mailing of                 Room in Washington, DC. For
                                                    state agencies of the timing for the                     environmental documents issued by the                 assistance, please contact FERC Online
                                                    completion of all necessary reviews, and                 Commission) and will not have the right               Support at FERCOnlineSupport@


                                               VerDate Sep<11>2014   21:16 Jul 01, 2015   Jkt 235001   PO 00000   Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\02JYN1.SGM   02JYN1


                                                    38194                           Federal Register / Vol. 80, No. 127 / Thursday, July 2, 2015 / Notices

                                                    ferc.gov, or call toll-free at (866) 208–                Commission, as soon as possible, an                   DEPARTMENT OF ENERGY
                                                    3676, or for TTY, contact (202) 502–                     original and two copies of comments in
                                                    8659.                                                    support of or in opposition to this                   Federal Energy Regulatory
                                                       Any questions regarding the                           project and/or associated pipeline. The               Commission
                                                    application should be directed to John                   Commission will consider these
                                                    B. Tobola, Freeport LNG Development,                                                                           Combined Notice of Filings #1
                                                                                                             comments in determining the
                                                    L.P., 333 Clay Street, Suite 5050,                       appropriate action to be taken, but the                  Take notice that the Commission
                                                    Houston, TX 77002, (713) 980–2888; or                    filing of a comment alone will not serve              received the following electric rate
                                                    Lisa M. Tonery, Norton Rose Fulbright                                                                          filings:
                                                                                                             to make the filer a party to the
                                                    US LLP, 666 Fifth Avenue, New York,                                                                               Docket Numbers: ER10–1945–005;
                                                                                                             proceeding. The Commission’s rules
                                                    NY 10103, (212) 318–3009, lisa.tonery@                                                                         ER10–2042–017; ER10–2039–005;
                                                    nortonrosefulbright.com.                                 require that person filing comments in
                                                                                                             opposition to the project provide copies              ER10–1938–012; ER10–1934–011;
                                                       Pursuant to section 157.9 of the
                                                                                                             of their protests only to the party or                ER10–1893–011; ER10–1871–005;
                                                    Commission’s rules (18 CFR 157.9),
                                                                                                             parties directly involved in the protest.             ER13–1406–003; ER10–1862–011.
                                                    within 90 days of this Notice the
                                                                                                                                                                      Applicants: Auburndale Peaker
                                                    Commission staff will either: complete                      Persons who wish to comment only                   Energy Center, LLC, Calpine Energy
                                                    its environmental assessment (EA) and                    on the environmental review of this                   Services, L.P., Calpine Newark, LLC,
                                                    place it into the Commission’s public                    project should submit an original and                 Calpine Power America—CA, LLC, CES
                                                    record (eLibrary) for this proceeding, or                two copies of their comments to the                   Marketing IX, LLC, CES Marketing X,
                                                    issue a Notice of Schedule for                           Secretary of the Commission.                          LLC, Morgan Energy Center, LLC,
                                                    Environmental Review. If a Notice of                     Environmental commenters will be
                                                    Schedule for Environmental Review is                                                                           Osprey Energy Center, LLC, Power
                                                                                                             placed on the Commission’s                            Contract Financing, L.L.C.
                                                    issued, it will indicate, among other
                                                                                                             environmental mailing list, will receive                 Description: Supplement to December
                                                    milestones, the anticipated date for the
                                                                                                             copies of the environmental documents,                31, 2014 Updated Market Power
                                                    Commission staff’s issuance of the final
                                                    environmental impact statement (FEIS)                    and will be notified of meetings                      Analysis of the Calpine Southeast MBR
                                                    or EA for this proposal. The filing of the               associated with the Commission’s                      Sellers.
                                                    EA in the Commission’s public record                     environmental review process.                            Filed Date: 6/25/15.
                                                                                                             Environmental commenters will not be                     Accession Number: 20150625–5130.
                                                    for this proceeding or the issuance of a
                                                                                                             required to serve copies of filed                        Comments Due: 5 p.m. ET 7/16/15.
                                                    Notice of Schedule for Environmental
                                                    Review will serve to notify federal and                  documents on all other parties.                          Docket Numbers: ER10–2407–003;
                                                    state agencies of the timing for the                     However, the non-party commenters                     ER10–2425–004; ER10–2424–003;
                                                    completion of all necessary reviews, and                 will not receive copies of all documents              ER13–1816–002.
                                                    the subsequent need to complete all                      filed by other parties or issued by the                  Applicants: Lost Lakes Wind Farm
                                                    federal authorizations within 90 days of                 Commission (except for the mailing of                 LLC, Pioneer Prairie Wind Farm I, LLC,
                                                    the date of issuance of the Commission                   environmental documents issued by the                 Rail Splitter Wind Farm, LLC,
                                                    staff’s FEIS or EA.                                      Commission) and will not have the right               Sustaining Power Solutions LLC
                                                       There are two ways to become                                                                                   Description: Updated Market Power
                                                                                                             to seek court review of the
                                                    involved in the Commission’s review of                                                                         Analysis for Central Region of Lost
                                                                                                             Commission’s final order.
                                                    this Project. First, any person wishing to                                                                     Lakes Wind Farm LLC, et al.
                                                    obtain legal status by becoming a party                     The Commission strongly encourages                    Filed Date: 6/26/15.
                                                    to the proceeding for this project                       electronic filings of comments, protests                 Accession Number: 20150626–5087.
                                                    should, on or before the comment date                    and interventions in lieu of paper using                 Comments Due: 5 p.m. ET 8/25/15.
                                                    stated below, file with the Federal                      the ‘‘eFiling’’ link at http://                          Docket Numbers: ER11–47–006;
                                                    Energy Regulatory Commission, 888                        www.ferc.gov. Persons unable to file                  ER12–1540–004; ER12–1541–004;
                                                    First Street NE., Washington, DC 20426,                  electronically should submit an original              ER12–1542–004; ER12–1544–004;
                                                    a motion to intervene in accordance                      and 7 copies of the protest or                        ER10–2981–006; ER14–2475–003;
                                                    with the requirement of the                              intervention to the Federal Energy                    ER14–2476–003; ER14–2477–003;
                                                    Commission’s Rules of Practice and                       regulatory Commission, 888 First Street               ER14–594–006; ER11–46–009; ER10–
                                                    Procedure (18 CFR 385.214 or 385.211)                    NE., Washington, DC 20426.                            2975–009; ER11–41–006; ER12–2343–
                                                    A person obtaining party status will be                                                                        004; ER13–1896–009.
                                                                                                                If the Commission decides to set the
                                                    placed on the service list maintained by                                                                          Applicants: Appalachian Power
                                                                                                             application for a formal hearing before
                                                    the Secretary of the Commission, and                                                                           Company, Indiana Michigan Power
                                                                                                             an Administrative Law Judge, the                      Company, Kentucky Power Company,
                                                    will receive copies of all documents
                                                    filed by the applicant and by all other                  Commission will issue another notice                  Kingsport Power Company, Wheeling
                                                    parties. A party must submit filing made                 describing that process. At the end of                Power Company, AEP Texas Central
                                                    it the Commission by mail, hand                          the Commission’s review process, a                    Company, AEP Texas North Company,
                                                    delivery, or internet, in accordance with                final Commission order approving or                   Public Service Company of Oklahoma,
                                                    Rule 2001 of the Commission’s Rules of                   denying the requested authorization                   Southwestern Electric Power Company,
                                                    Practice and Procedure (18 CFR                           will be issued.                                       Ohio Power Company, AEP Energy
                                                    385.2001). A copy must be served on                                                                            Partners, Inc., CSW Energy Services,
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                Comment Date: 5:00 p.m. Eastern
                                                    every other party in the proceeding.                     Daylight Savings Time July 15, 2015.                  Inc., AEP Retail Energy Partners LLC,
                                                    Only parties to the proceeding may ask                                                                         AEP Energy, Inc., AEP Generation
                                                                                                               Dated: June 24, 2015.
                                                    for court review of Commission orders                                                                          Resources Inc.
                                                    in the proceeding.                                       Kimberly D. Bose,                                        Description: Updated Market Power
                                                       However, a person does not have to                    Secretary.                                            Analysis in the Southwest Power Pool
                                                    intervene to have comments considered.                   [FR Doc. 2015–16309 Filed 7–1–15; 8:45 am]            balancing area authority of the AEP
                                                    The second way to participate is by                      BILLING CODE 6717–01–P                                MBR affiliates.
                                                    filing with the Secretary of the                                                                                  Filed Date: 6/26/15.


                                               VerDate Sep<11>2014   21:16 Jul 01, 2015   Jkt 235001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\02JYN1.SGM   02JYN1



Document Created: 2015-12-15 13:15:31
Document Modified: 2015-12-15 13:15:31
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Daylight Savings Time July 15, 2015.
FR Citation80 FR 38193 

2024 Federal Register | Disclaimer | Privacy Policy