The U.S. Nuclear Regulatory Commission (NRC) is issuing an Order to Duke Energy Progress, Inc. (Duke Energy) and North Carolina Eastern Municipal Power Agency (NCEMPA) approving the direct transfer of control of the Renewed Facility Operating License No. NPF-63, and ownership interest for the Shearon Harris Nuclear Power Plant (Harris), Unit 1, to the extent currently held by NCEMPA. As a result of the transaction, Duke Energy will become the sole owner of the Harris facility and hold 100 percent ownership of the facility. The conforming license amendment will remove references to NCEMPA. No physical changes to the facility or operational changes were proposed in the application and Duke Energy will remain as the licensed operator of the facility. This Order is effective upon issuance.

Federal Register, Volume 80 Issue 134 (Tuesday, July 14, 2015)
[Federal Register Volume 80, Number 134 (Tuesday, July 14, 2015)]
[Notices]
[Pages 41097-41099]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-17278]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-400; License No. NPF-63; NRC-2015-0101]


In the Matter of Duke Energy Progress, Inc., and North Carolina 
Eastern Municipal Power Agency; Shearon Harris Nuclear Power Plant, 
Unit 1

AGENCY: Nuclear Regulatory Commission.

ACTION: Direct transfer of license, order; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an 
Order to Duke Energy Progress, Inc. (Duke Energy) and North Carolina 
Eastern Municipal Power Agency (NCEMPA)

[[Page 41098]]

approving the direct transfer of control of the Renewed Facility 
Operating License No. NPF-63, and ownership interest for the Shearon 
Harris Nuclear Power Plant (Harris), Unit 1, to the extent currently 
held by NCEMPA. As a result of the transaction, Duke Energy will become 
the sole owner of the Harris facility and hold 100 percent ownership of 
the facility. The conforming license amendment will remove references 
to NCEMPA. No physical changes to the facility or operational changes 
were proposed in the application and Duke Energy will remain as the 
licensed operator of the facility. This Order is effective upon 
issuance.

DATES: The Order was issued on July 6, 2015, and is effective for 1 
year.

ADDRESSES: Please refer to Docket ID NRC-2015-0101 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2015-0101. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The 
ADAMS accession number for each document referenced (if that document 
is available in ADAMS) is provided the first time that a document is 
referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Martha Barillas, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-2760, email: Martha.Barillas@nrc.gov.

SUPPLEMENTARY INFORMATION: The text of the Order is attached.

    Dated at Rockville, Maryland, this 6th day of July 2015.

    For the Nuclear Regulatory Commission.
Martha Barillas,
Project Manager, Plant Licensing Branch II-2, Division of Operator 
Reactor Licensing, Office of Nuclear Reactor Regulation.

UNITED STATES OF AMERICA

NUCLEAR REGULATORY COMMISSION

    In the Matter of DUKE ENERGY PROGRESS, INC., NORTH CAROLINA EASTERN 
MUNICIPAL POWER AGENCY, Shearon Harris Nuclear Power Plant Unit 1
Docket No. 50-400
License No. NPF-63

ORDER APPROVING DIRECT TRANSFER OF LICENSE AND APPROVING CONFORMING 
AMENDMENT

I

    Duke Energy Progress, Inc. (Duke Energy), and North Carolina 
Eastern Municipal Power Agency (NCEMPA), are the owners of Shearon 
Harris Nuclear Power Plant, Unit 1 (Harris). With respect to their 
ownership, they are co-holders of Renewed Facility Operating License 
No. NPF-63. The Harris facility consists of a Westinghouse three-loop 
pressurized-water reactor located in Wake and Chatham Counties, North 
Carolina. The facility operating license authorizes Duke Energy to 
possess, use, and operate the Harris facility.

II

    By application dated December 22, 2014 (Agencywide Documents Access 
and Management System (ADAMS) Accession No. ML14358A253), as 
supplemented by letters dated March 4, 2015 (ADAMS Accession No. 
ML15075A102); June 1, 2015 (ADAMS Accession No. ML15152A205); June 10, 
2015 (ADAMS Accession No. ML15161A289); and June 24, 2015 (ADAMS 
Accession No. ML15175A036), Duke Energy and NCEMPA requested, pursuant 
to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.80 
(10 CFR 50.80), that the U.S. Nuclear Regulatory Commission (NRC) 
consent to the direct transfer of Operating License No. NPF-63 for the 
Harris facility, to the extent currently held by NCEMPA, to co-owner 
Duke Energy.
    The interest in Harris held by Duke Energy is 83.83 percent 
undivided ownership interest and that held by NCEMPA is 16.17 percent 
undivided ownership interest. Duke Energy is the licensed operator for 
the facility. Following approval of the proposed direct transfer of 
control of the licenses, Duke Energy would acquire NCEMPA's ownership 
interest in the facility and would hold 100 percent of the facility.
    The applicant also requested approval of the conforming license 
amendment that would remove references to NCEMPA in the license. The 
proposed direct transfer of control of the Harris operating license 
will not result in any change in the role of Duke Energy as the 
licensed operator and owner of the licensed facility and will not 
result in any changes to its financial qualifications, decommissioning 
funding assurance, or technical qualifications.
    Approval of the direct transfer of the facility operating license 
and conforming license amendment was requested by Duke Energy and 
NCEMPA pursuant to 10 CFR 50.80 and 50.90. A notice entitled, ``Notice 
of Consideration of Approval of Transfer of Licenses and Conforming 
Amendment,'' was published in the Federal Register on April 21, 2015 
(80 FR 22224). No comments or hearing requests were received.
    Under 10 CFR 50.80, no license, or any right thereunder, shall be 
transferred, directly or indirectly, through transfer of control of the 
license, unless the Commission gives its consent in writing. Upon 
review of the information in the licensee's application, and other 
information before the Commission, the NRC staff has determined that 
Duke Energy is qualified to hold 100 percent of the license as proposed 
by the transfer of NCEMPA's 16.17 percent ownership interests, and that 
the transfer of the license is otherwise consistent with the applicable 
provisions of law, regulations, and orders issued by the NRC and 
subject to the conditions set forth below. The NRC staff has further 
found that the application for the proposed license amendment complies 
with the standards and requirements of the Atomic Energy Act of 1954, 
as amended (the Act), and the Commission's rules and regulations set 
forth in 10 CFR Chapter I; the facility will operate in conformity with 
the application, the provisions of the Act and the rules and 
regulations of the Commission; there is reasonable assurance that the 
activities authorized by the proposed license amendment can be 
conducted without endangering the health and safety of the public and 
that such activities will be conducted in compliance with the 
Commission's regulations; the issuance of the proposed license 
amendment will not

[[Page 41099]]

be inimical to the common defense and security or to the health and 
safety of the public; and the issuance of the proposed amendment will 
be in accordance with 10 CFR part 51 of the Commission's regulations 
and all applicable requirements have been satisfied. The findings set 
forth above are supported by a safety evaluation dated July 6, 2015.

III

    Accordingly, pursuant to Sections 161b, 161i, 161.o, and 184 of the 
Atomic Energy Act of 1954, as amended (the Act), 42 U.S.C. Sections 
2201(b), 2201(i), 2201(o), and 2234; and 10 CFR 50.80, IT IS HEREBY 
ORDERED that the application regarding the proposed direct license 
transfer is approved, subject to the following condition:
    1. Duke Energy shall provide satisfactory documentary evidence to 
the Director of the Office of Nuclear Reactor Regulation that it has 
obtained the appropriate amount of insurance required of a licensee 
under 10 CFR part 140 within 30 days of the transfer.
    IT IS FURTHER ORDERED that consistent with 10 CFR 2.1315(b), the 
license amendment that make changes, as indicated in Enclosure 5 to the 
cover letter forwarding this order, to reflect the subject direct 
transfer, is approved. The amendment shall be issued and made effective 
at the time the proposed direct transfer action is completed.
    IT IS FURTHER ORDERED that after receipt of all required regulatory 
approvals of the proposed direct transfer action, Duke Energy shall 
inform the Director of the Office of Nuclear Reactor Regulation in 
writing of such receipt no later than 2 business days prior to the date 
of the closing of the direct transfer. Should the proposed direct 
transfer not be completed within 1 year of this order's date of issue, 
this order shall become null and void. However, upon written 
application and good cause shown, such date may be extended by order.
    This order is effective upon issuance.
    For further details with respect to this order, see the initial 
application dated December 22, 2014 (ADAMS Accession No. ML14358A253), 
as supplemented by letters dated March 4, 2015 (ADAMS Accession No. 
ML15075A102); June 1, 2015 (ADAMS Accession No. ML15152A205); June 10. 
2015 (ADAMS Accession No. ML15161A289); and June 24, 2015 
(ML15175A036), and the safety evaluation dated July 6, 2015 (ADAMS 
Accession No. ML15159A632), which are available for public inspection 
at the NRC's Public Document Room (PDR), located at One White Flint 
North, Room O1-F21, 11555 Rockville Pike, Rockville, Maryland 20852. 
You may obtain publicly-available documents online in the ADAMS Public 
Documents collection at http://www.nrc.gov/reading-rm/adams.html. 
Persons who do not have access to ADAMS or who encounter problems in 
accessing the documents located in ADAMS, should contact the NRC's PDR 
reference staff at 1-800-397-4209 or 301-415-4737 or by email to 
pdr.resource@nrc.gov.

    Dated at Rockville, Maryland, this 6th day of July 2015.

    For the Nuclear Regulatory Commission.
William M. Dean,
Director, Office of Nuclear Reactor Regulation.
[FR Doc. 2015-17278 Filed 7-13-15; 8:45 am]
 BILLING CODE 7590-01-P



                                                                                    Federal Register / Vol. 80, No. 134 / Tuesday, July 14, 2015 / Notices                                                 41097

                                                    order’s date of issue, this order shall                  (DOT) that defines a cooperative                      between the agencies for radioactive
                                                    become null and void. However, upon                      working relationship between the                      material transportation security.
                                                    written application and good cause                       agencies for radioactive material
                                                                                                                                                                   II. Summary
                                                    shown, such date may be extended by                      transportation security. The goal of the
                                                    order.                                                   MOU is to ensure that the transportation                 The Energy Policy Act of 2005 (Pub.
                                                      This order is effective upon issuance.                 of radioactive material in the U.S. and               L. 109–58, August 8, 2005) established
                                                      For further details with respect to this               across U.S. borders is carried out in a               the Task Force on Radiation Source
                                                    order, see the initial application dated                 secure manner that protects public                    Protection and Security. Subsequently,
                                                    December 22, 2014 (ADAMS Accession                       health and safety, and in a manner that               the Task Force recommended that the
                                                    No. ML14358A253), as supplemented                        is not inimical to the common defense                 participating departments and agencies
                                                    by letters dated March 4, 2015 (ADAMS                    and security of the U.S.                              develop an interagency MOU for
                                                    Accession No. ML15075A102); June 1,                      DATES: The Memorandum of
                                                                                                                                                                   radioactive material transportation
                                                    2015 (ADAMS Accession No.                                Understanding is available July 14,                   security. The MOU establishes a
                                                    ML15152A205); June 10, 2015 (ADAMS                       2015.                                                 framework for departments and agencies
                                                    Accession No. ML15161A289); and June                                                                           to coordinate, to the maximum extent
                                                    24, 2015 (ADAMS Accession No.                            ADDRESSES:   Please refer to Docket ID                practicable, their respective
                                                    ML15175A036), and the safety                             NRC–2015–0164 when contacting the                     responsibilities and activities on
                                                    evaluation dated July 6, 2015 (ADAMS                     NRC about the availability of                         security of radioactive material
                                                    Accession No. ML15159A632), which                        information regarding this document.                  transportation within the U.S. or across
                                                    are available for public inspection at the               You may obtain publicly-available                     U.S. borders. The intent of the MOU is
                                                    NRC’s Public Document Room (PDR),                        information related to this document                  to enhance collaborative exchanges,
                                                    located at One White Flint North, Public                 using any of the following methods:                   facilitate the sharing of expertise and
                                                    File Area O1–F21, 11555 Rockville Pike,                     • Federal Rulemaking Web site: Go to               information, promote leveraging of
                                                    Rockville, Maryland 20852. You may                       http://www.regulations.gov and search                 mutual interests, and reduce
                                                    obtain publicly-available documents                      for Docket ID NRC–2015–0164. Address                  duplication in shared areas of
                                                    online in the ADAMS Public Documents                     questions about NRC dockets to Carol                  responsibility.
                                                    collection at http://www.nrc.gov/                        Gallagher; telephone: 301–415–3463;
                                                                                                             email: Carol.Gallagher@nrc.gov. For                   III. Further Information
                                                    reading-rm/adams.html. Persons who
                                                    do not have access to ADAMS, or who                      technical questions, contact the                         The Task Force on Radiation Source
                                                    encounter problems in accessing the                      individual listed in the FOR FURTHER                  Protection and Security has produced
                                                    documents located in ADAMS, should                       INFORMATION CONTACT section of this                   three reports. The reports were
                                                    contact the NRC’s PDR reference staff at                 document.                                             published in 2006, 2010 and 2014.
                                                    1–800–397–4209 or 301–415–4737 or by                        • NRC’s Agencywide Documents                       Those reports may be found in the NRC
                                                    email to pdr.resource@nrc.gov.                           Access and Management System                          ADAMS public document collection at
                                                                                                             (ADAMS): You may obtain publicly-                     accession numbers ML062190349,
                                                      Dated at Rockville, Maryland, this 6th day             available documents online in the                     ML102230141 and ML14219A642, for
                                                    of July 2015.                                                                                                  the 2006, 2010 and 2014 reports,
                                                                                                             ADAMS Public Documents collection at
                                                      For the Nuclear Regulatory Commission.                 http://www.nrc.gov/reading-rm/                        respectively.
                                                    William M. Dean,                                         adams.html. To begin the search, select                 Dated at Rockville, Maryland, this 7th day
                                                    Director, Office of Nuclear Reactor                      ‘‘ADAMS Public Documents’’ and then                   of July 2015.
                                                    Regulation.                                              select ‘‘Begin Web-based ADAMS                          For the Nuclear Regulatory Commission.
                                                    [FR Doc. 2015–17279 Filed 7–13–15; 8:45 am]              Search.’’ For problems with ADAMS,                    Mark Thaggard,
                                                    BILLING CODE 7590–01–P                                   please contact the NRC’s Public                       Deputy Director, Division of Security Policy,
                                                                                                             Document Room (PDR) reference staff at                Office of Nuclear Security and Incident
                                                                                                             1–800–397–4209, 301–415–4737, or by                   Response.
                                                    NUCLEAR REGULATORY                                       email to pdr.resource@nrc.gov. The                    [FR Doc. 2015–17274 Filed 7–13–15; 8:45 am]
                                                    COMMISSION                                               three sections of the MOU are available               BILLING CODE 7590–01–P
                                                    [NRC–2015–0164]                                          in ADAMS under Accession Nos.:
                                                                                                             ML15057A336, ML13240A347, and
                                                    Memorandum of Understanding                              ML13240A350, respectively.                            NUCLEAR REGULATORY
                                                    Among the Department of Homeland                            • NRC’s PDR: You may examine and                   COMMISSION
                                                    Security, the Department of                              purchase copies of public documents at
                                                                                                                                                                   [Docket No. 50–400; License No. NPF–63;
                                                    Transportation, and the Nuclear                          the NRC’s PDR, Room O1–F21, One
                                                                                                                                                                   NRC–2015–0101]
                                                    Regulatory Commission Concerning                         White Flint North, 11555 Rockville
                                                    Cooperation on Radioactive Materials                     Pike, Rockville, Maryland 20852.                      In the Matter of Duke Energy Progress,
                                                    Transportation Security                                  FOR FURTHER INFORMATION CONTACT:                      Inc., and North Carolina Eastern
                                                    AGENCY: Nuclear Regulatory                               Albert Tardiff, Office of Nuclear                     Municipal Power Agency; Shearon
                                                    Commission.                                              Security and Incident Response, U.S.                  Harris Nuclear Power Plant, Unit 1
                                                                                                             Nuclear Regulatory Commission,
                                                    ACTION: Memorandum of
                                                                                                             Washington, DC 20555–0001; telephone:                 AGENCY: Nuclear Regulatory
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    Understanding; issuance.                                 301–287–3613, email: Al.Tardiff@                      Commission.
                                                                                                             nrc.gov.                                              ACTION: Direct transfer of license, order;
                                                    SUMMARY:   The United States (U.S.)                                                                            issuance.
                                                    Nuclear Regulatory Commission (NRC)                      SUPPLEMENTARY INFORMATION:
                                                    is issuing a notice regarding a finalized                                                                      SUMMARY:  The U.S. Nuclear Regulatory
                                                    Memorandum of Understanding (MOU)                        I. Introduction                                       Commission (NRC) is issuing an Order
                                                    between the NRC, the U.S. Department                        The NRC, DHS, and DOT have                         to Duke Energy Progress, Inc. (Duke
                                                    of Homeland Security (DHS) and the                       finalized an MOU to define the                        Energy) and North Carolina Eastern
                                                    U.S. Department of Transportation                        cooperative working relationship                      Municipal Power Agency (NCEMPA)


                                               VerDate Sep<11>2014   19:09 Jul 13, 2015   Jkt 235001   PO 00000   Frm 00107   Fmt 4703   Sfmt 4703   E:\FR\FM\14JYN1.SGM   14JYN1


                                                    41098                           Federal Register / Vol. 80, No. 134 / Tuesday, July 14, 2015 / Notices

                                                    approving the direct transfer of control                    Dated at Rockville, Maryland, this 6th day         licensed operator for the facility.
                                                    of the Renewed Facility Operating                        of July 2015.                                         Following approval of the proposed
                                                    License No. NPF–63, and ownership                           For the Nuclear Regulatory Commission.             direct transfer of control of the licenses,
                                                    interest for the Shearon Harris Nuclear                  Martha Barillas,                                      Duke Energy would acquire NCEMPA’s
                                                    Power Plant (Harris), Unit 1, to the                     Project Manager, Plant Licensing Branch II–           ownership interest in the facility and
                                                    extent currently held by NCEMPA. As a                    2, Division of Operator Reactor Licensing,            would hold 100 percent of the facility.
                                                    result of the transaction, Duke Energy                   Office of Nuclear Reactor Regulation.                    The applicant also requested approval
                                                    will become the sole owner of the Harris                                                                       of the conforming license amendment
                                                                                                             UNITED STATES OF AMERICA                              that would remove references to
                                                    facility and hold 100 percent ownership
                                                    of the facility. The conforming license                  NUCLEAR REGULATORY                                    NCEMPA in the license. The proposed
                                                    amendment will remove references to                      COMMISSION                                            direct transfer of control of the Harris
                                                    NCEMPA. No physical changes to the                         In the Matter of DUKE ENERGY                        operating license will not result in any
                                                    facility or operational changes were                     PROGRESS, INC., NORTH CAROLINA                        change in the role of Duke Energy as the
                                                    proposed in the application and Duke                     EASTERN MUNICIPAL POWER                               licensed operator and owner of the
                                                    Energy will remain as the licensed                       AGENCY, Shearon Harris Nuclear                        licensed facility and will not result in
                                                    operator of the facility. This Order is                  Power Plant Unit 1                                    any changes to its financial
                                                    effective upon issuance.                                                                                       qualifications, decommissioning
                                                                                                             Docket No. 50–400                                     funding assurance, or technical
                                                    DATES: The Order was issued on July 6,
                                                                                                             License No. NPF–63                                    qualifications.
                                                    2015, and is effective for 1 year.                                                                                Approval of the direct transfer of the
                                                    ADDRESSES: Please refer to Docket ID                     ORDER APPROVING DIRECT                                facility operating license and
                                                    NRC–2015–0101 when contacting the                        TRANSFER OF LICENSE AND                               conforming license amendment was
                                                    NRC about the availability of                            APPROVING CONFORMING                                  requested by Duke Energy and NCEMPA
                                                    information regarding this document.                     AMENDMENT                                             pursuant to 10 CFR 50.80 and 50.90. A
                                                    You may obtain publicly-available                                                                              notice entitled, ‘‘Notice of Consideration
                                                                                                             I
                                                    information related to this document                                                                           of Approval of Transfer of Licenses and
                                                    using any of the following methods:                        Duke Energy Progress, Inc. (Duke                    Conforming Amendment,’’ was
                                                       • Federal Rulemaking Web site: Go to                  Energy), and North Carolina Eastern                   published in the Federal Register on
                                                    http://www.regulations.gov and search                    Municipal Power Agency (NCEMPA),                      April 21, 2015 (80 FR 22224). No
                                                    for Docket ID NRC–2015–0101. Address                     are the owners of Shearon Harris                      comments or hearing requests were
                                                    questions about NRC dockets to Carol                     Nuclear Power Plant, Unit 1 (Harris).                 received.
                                                    Gallagher; telephone: 301–415–3463;                      With respect to their ownership, they                    Under 10 CFR 50.80, no license, or
                                                    email: Carol.Gallagher@nrc.gov. For                      are co-holders of Renewed Facility                    any right thereunder, shall be
                                                    technical questions, contact the                         Operating License No. NPF–63. The                     transferred, directly or indirectly,
                                                    individual listed in the FOR FURTHER                     Harris facility consists of a                         through transfer of control of the
                                                    INFORMATION CONTACT section of this                      Westinghouse three-loop pressurized-                  license, unless the Commission gives its
                                                    document.                                                water reactor located in Wake and                     consent in writing. Upon review of the
                                                       • NRC’s Agencywide Documents                          Chatham Counties, North Carolina. The                 information in the licensee’s
                                                    Access and Management System                             facility operating license authorizes                 application, and other information
                                                    (ADAMS): You may obtain publicly                         Duke Energy to possess, use, and                      before the Commission, the NRC staff
                                                    available documents online in the                        operate the Harris facility.                          has determined that Duke Energy is
                                                    ADAMS Public Documents collection at                                                                           qualified to hold 100 percent of the
                                                                                                             II
                                                    http://www.nrc.gov/reading-rm/                                                                                 license as proposed by the transfer of
                                                    adams.html. To begin the search, select                    By application dated December 22,                   NCEMPA’s 16.17 percent ownership
                                                    ‘‘ADAMS Public Documents’’ and then                      2014 (Agencywide Documents Access                     interests, and that the transfer of the
                                                    select ‘‘Begin Web-based ADAMS                           and Management System (ADAMS)                         license is otherwise consistent with the
                                                    Search.’’ For problems with ADAMS,                       Accession No. ML14358A253), as                        applicable provisions of law,
                                                    please contact the NRC’s Public                          supplemented by letters dated March 4,                regulations, and orders issued by the
                                                    Document Room (PDR) reference staff at                   2015 (ADAMS Accession No.                             NRC and subject to the conditions set
                                                    1–800–397–4209, 301–415–4737, or by                      ML15075A102); June 1, 2015 (ADAMS                     forth below. The NRC staff has further
                                                    email to pdr.resource@nrc.gov. The                       Accession No. ML15152A205); June 10,                  found that the application for the
                                                    ADAMS accession number for each                          2015 (ADAMS Accession No.                             proposed license amendment complies
                                                    document referenced (if that document                    ML15161A289); and June 24, 2015                       with the standards and requirements of
                                                    is available in ADAMS) is provided the                   (ADAMS Accession No. ML15175A036),                    the Atomic Energy Act of 1954, as
                                                    first time that a document is referenced.                Duke Energy and NCEMPA requested,                     amended (the Act), and the
                                                                                                             pursuant to Title 10 of the Code of                   Commission’s rules and regulations set
                                                       • NRC’s PDR: You may examine and
                                                                                                             Federal Regulations (10 CFR), Section                 forth in 10 CFR Chapter I; the facility
                                                    purchase copies of public documents at
                                                                                                             50.80 (10 CFR 50.80), that the U.S.                   will operate in conformity with the
                                                    the NRC’s PDR, Room O1–F21, One
                                                                                                             Nuclear Regulatory Commission (NRC)                   application, the provisions of the Act
                                                    White Flint North, 11555 Rockville
                                                                                                             consent to the direct transfer of                     and the rules and regulations of the
                                                    Pike, Rockville, Maryland 20852.
                                                                                                             Operating License No. NPF–63 for the                  Commission; there is reasonable
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    FOR FURTHER INFORMATION CONTACT:                         Harris facility, to the extent currently              assurance that the activities authorized
                                                    Martha Barillas, Office of Nuclear                       held by NCEMPA, to co-owner Duke                      by the proposed license amendment can
                                                    Reactor Regulation, U.S. Nuclear                         Energy.                                               be conducted without endangering the
                                                    Regulatory Commission, Washington,                         The interest in Harris held by Duke                 health and safety of the public and that
                                                    DC 20555–0001; telephone: 301–415–                       Energy is 83.83 percent undivided                     such activities will be conducted in
                                                    2760, email: Martha.Barillas@nrc.gov.                    ownership interest and that held by                   compliance with the Commission’s
                                                    SUPPLEMENTARY INFORMATION: The text of                   NCEMPA is 16.17 percent undivided                     regulations; the issuance of the
                                                    the Order is attached.                                   ownership interest. Duke Energy is the                proposed license amendment will not


                                               VerDate Sep<11>2014   19:09 Jul 13, 2015   Jkt 235001   PO 00000   Frm 00108   Fmt 4703   Sfmt 4703   E:\FR\FM\14JYN1.SGM   14JYN1


                                                                                               Federal Register / Vol. 80, No. 134 / Tuesday, July 14, 2015 / Notices                                                                               41099

                                                    be inimical to the common defense and                                         For further details with respect to this                               the functions of the agency, including
                                                    security or to the health and safety of                                     order, see the initial application dated                                 whether the information has practical
                                                    the public; and the issuance of the                                         December 22, 2014 (ADAMS Accession                                       utility; (b) the accuracy of the RRB’s
                                                    proposed amendment will be in                                               No. ML14358A253), as supplemented                                        estimate of the burden of the collection
                                                    accordance with 10 CFR part 51 of the                                       by letters dated March 4, 2015 (ADAMS                                    of the information; (c) ways to enhance
                                                    Commission’s regulations and all                                            Accession No. ML15075A102); June 1,                                      the quality, utility, and clarity of the
                                                    applicable requirements have been                                           2015 (ADAMS Accession No.                                                information to be collected; and (d)
                                                    satisfied. The findings set forth above                                     ML15152A205); June 10. 2015 (ADAMS                                       ways to minimize the burden related to
                                                    are supported by a safety evaluation                                        Accession No. ML15161A289); and June                                     the collection of information on
                                                    dated July 6, 2015.                                                         24, 2015 (ML15175A036), and the safety                                   respondents, including the use of
                                                                                                                                evaluation dated July 6, 2015 (ADAMS                                     automated collection techniques or
                                                    III
                                                                                                                                Accession No. ML15159A632), which                                        other forms of information technology.
                                                       Accordingly, pursuant to Sections                                        are available for public inspection at the                                 Title and purpose of information
                                                    161b, 161i, 161.o, and 184 of the Atomic                                    NRC’s Public Document Room (PDR),                                        collection: Employer’s Quarterly Report
                                                    Energy Act of 1954, as amended (the                                         located at One White Flint North, Room                                   of Contributions under the Railroad
                                                    Act), 42 U.S.C. Sections 2201(b),                                           O1–F21, 11555 Rockville Pike,                                            Unemployment Insurance Act; OMB
                                                    2201(i), 2201(o), and 2234; and 10 CFR                                      Rockville, Maryland 20852. You may                                       3220–0012.
                                                    50.80, IT IS HEREBY ORDERED that the                                        obtain publicly-available documents                                        Under Section 8 of the Railroad
                                                    application regarding the proposed                                          online in the ADAMS Public Documents                                     Unemployment Insurance Act (RUIA),
                                                    direct license transfer is approved,                                        collection at http://www.nrc.gov/                                        as amended by the Railroad
                                                    subject to the following condition:                                         reading-rm/adams.html. Persons who                                       Unemployment Improvement Act of
                                                       1. Duke Energy shall provide                                             do not have access to ADAMS or who                                       1988 (Pub. L. 100–647), the RRB
                                                    satisfactory documentary evidence to                                        encounter problems in accessing the                                      determines the amount of an employer’s
                                                    the Director of the Office of Nuclear                                       documents located in ADAMS, should                                       contribution, primarily on the basis of
                                                    Reactor Regulation that it has obtained                                     contact the NRC’s PDR reference staff at                                 the RUIA benefits paid, both
                                                    the appropriate amount of insurance                                         1–800–397–4209 or 301–415–4737 or by                                     unemployment and sickness, to the
                                                    required of a licensee under 10 CFR part                                    email to pdr.resource@nrc.gov.                                           employees of the railroad employer.
                                                    140 within 30 days of the transfer.                                           Dated at Rockville, Maryland, this 6th day                             These experienced-based contributions
                                                       IT IS FURTHER ORDERED that                                               of July 2015.                                                            take into account the frequency,
                                                    consistent with 10 CFR 2.1315(b), the                                         For the Nuclear Regulatory Commission.                                 volume, and duration of the employees’
                                                    license amendment that make changes,                                        William M. Dean,                                                         unemployment and sickness benefits.
                                                    as indicated in Enclosure 5 to the cover                                                                                                             Each employer’s contribution rate
                                                                                                                                Director, Office of Nuclear Reactor
                                                    letter forwarding this order, to reflect                                    Regulation.                                                              includes a component for administrative
                                                    the subject direct transfer, is approved.                                                                                                            expenses as well as a component to
                                                                                                                                [FR Doc. 2015–17278 Filed 7–13–15; 8:45 am]
                                                    The amendment shall be issued and                                                                                                                    cover costs shared by all employers. The
                                                                                                                                BILLING CODE 7590–01–P
                                                    made effective at the time the proposed                                                                                                              regulations prescribing the manner and
                                                    direct transfer action is completed.                                                                                                                 conditions for remitting the
                                                       IT IS FURTHER ORDERED that after                                                                                                                  contributions and for adjusting
                                                    receipt of all required regulatory                                          RAILROAD RETIREMENT BOARD                                                overpayments or underpayments of
                                                    approvals of the proposed direct transfer                                                                                                            contributions are contained in 20 CFR
                                                                                                                                Proposed Collection; Comment
                                                    action, Duke Energy shall inform the                                                                                                                 345.
                                                                                                                                Request
                                                    Director of the Office of Nuclear Reactor                                                                                                              RRB Form DC–1, Employer’s
                                                    Regulation in writing of such receipt no                                      Summary: In accordance with the                                        Quarterly Report of Contributions under
                                                    later than 2 business days prior to the                                     requirement of Section 3506 (c)(2)(A) of                                 the Railroad Unemployment Insurance
                                                    date of the closing of the direct transfer.                                 the Paperwork Reduction Act of 1995                                      Act, is used by railroad employers to
                                                    Should the proposed direct transfer not                                     which provides opportunity for public                                    report and remit their quarterly
                                                    be completed within 1 year of this                                          comment on new or revised data                                           contributions to the RRB. Employers can
                                                    order’s date of issue, this order shall                                     collections, the Railroad Retirement                                     use either the manual version of the
                                                    become null and void. However, upon                                         Board (RRB) will publish periodic                                        form or its Internet equivalent. One
                                                    written application and good cause                                          summaries of proposed data collections.                                  response is requested quarterly of each
                                                    shown, such date may be extended by                                           Comments are invited on: (a) Whether                                   respondent and completion is
                                                    order.                                                                      the proposed information collection is                                   mandatory. The RRB proposes no
                                                       This order is effective upon issuance.                                   necessary for the proper performance of                                  changes to Form DC–1.

                                                                                                                           ESTIMATE OF ANNUAL RESPONDENT BURDEN
                                                                                                                                                                                                           Annual            Time                 Burden
                                                                                                                     Form No.                                                                            responses         (minutes)              (hours)

                                                    DC–1 (Manual) ............................................................................................................................                 1,235                      25                515
                                                    DC–1 (Internet) ............................................................................................................................               1,365                      25                569
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                          Total ......................................................................................................................................         2,600   ........................        1,084



                                                      Additional Information or Comments:                                       supporting material, contact Dana                                        should be addressed to Charles
                                                    To request more information or to                                           Hickman at (312) 751–4981 or                                             Mierzwa, Railroad Retirement Board,
                                                    obtain a copy of the information                                            Dana.Hickman@RRB.GOV. Comments                                           844 North Rush Street, Chicago, Illinois
                                                    collection justification, forms, and/or                                     regarding the information collection                                     60611–2092 or emailed to


                                               VerDate Sep<11>2014         19:09 Jul 13, 2015        Jkt 235001       PO 00000        Frm 00109        Fmt 4703       Sfmt 4703       E:\FR\FM\14JYN1.SGM     14JYN1



Document Created: 2018-02-23 09:19:54
Document Modified: 2018-02-23 09:19:54
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDirect transfer of license, order; issuance.
DatesThe Order was issued on July 6, 2015, and is effective for 1 year.
ContactMartha Barillas, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-2760, email: [email protected]
FR Citation80 FR 41097 