80 FR 42099 - Clark Canyon Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 136 (July 16, 2015)

Page Range42099-42099
FR Document2015-17439

Federal Register, Volume 80 Issue 136 (Thursday, July 16, 2015)
[Federal Register Volume 80, Number 136 (Thursday, July 16, 2015)]
[Notices]
[Page 42099]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-17439]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14677-000]


Clark Canyon Hydro, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On April 21, 2015, Clark Canyon Hydro, LLC, filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of the Clark Canyon Dam 
Hydroelectric Project (Clark Canyon Dam Project or project) to be 
located at the U.S. Bureau of Reclamation's Clark Canyon Dam on the 
Beaverhead River, near Dillon, Beaverhead County, Montana. The sole 
purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed project would utilize the existing Clark Canyon Dam 
and would consist of the following: (1) A new 360-foot-long, 8-foot-
diameter steel penstock within the existing concrete conduit, ending in 
a trifurcation; (2) two new 35-foot-long, 8-foot-diameter penstocks 
extending from the trifurcation to the powerhouse, transitioning to 6-
foot-diameter before entering the powerhouse; (3) a new 10-foot-long, 
8-foot-diameter steel penstock leaving the trifurcation and ending in a 
7-foot-diameter cone value and reducer to control discharge into the 
existing outlet stilling basin; (4) a new 62.5-foot-long, 41-foot-wide 
reinforced concrete powerhouse containing two vertical Francis-type 
turbine/generator units rated for 2.35 megawatts each; (5) two new 17-
foot-long, 15-foot-diameter tailrace channels connecting the pump/
turbine draft tubes with the existing spillway stilling basin; (6) a 
new 1,100-foot-long, 4.16-kilovolt (kV) buried transmission line from 
the power house to the substation; (7) a new substation containing 
step-up transformers and switchgear; (8) a new 7.9-mile-long, 69-kV 
transmission line extending from the project substation to the Peterson 
Flat substation (the point of interconnection); and (9) appurtenant 
facilities. The estimated annual generation of the Clark Canyon Dam 
Project would be 15.4 gigawatt-hours.
    Applicant Contact: Mr. David Boyter, NW Engineering Services, P.C., 
1680 Woodruff Park, Idaho Falls, Idaho 83401; phone: (208) 932-2720.
    FERC Contact: Kelly Wolcott; phone: (202) 502-6480.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14677-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14677) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: July 10, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-17439 Filed 7-15-15; 8:45 am]
BILLING CODE 6717-01-P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 42099 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR