80_FR_47639 80 FR 47487 - Comanche Trail Pipeline, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed San Elizario Crossing Project; Request for Comments on Environmental Issues

80 FR 47487 - Comanche Trail Pipeline, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed San Elizario Crossing Project; Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 152 (August 7, 2015)

Page Range47487-47489
FR Document2015-19420

Federal Register, Volume 80 Issue 152 (Friday, August 7, 2015)
[Federal Register Volume 80, Number 152 (Friday, August 7, 2015)]
[Notices]
[Pages 47487-47489]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-19420]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-503-000]


Comanche Trail Pipeline, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed San Elizario Crossing 
Project; Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the San Elizario Crossing Project 
involving construction and operation of specific border crossing 
facilities for the export of natural gas by Comanche Trail Pipeline, 
LLC (Comanche Trail) in El Paso County, Texas. The Commission will use 
this EA in its decision-making process to determine whether the project 
is in the public interest.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before September 2, 2015.
    If you sent comments on this project to the Commission before the 
opening of this docket on May 29, 2015, you will need to file those 
comments in Docket No. CP15-503-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    Comanche Trail provided landowners with a fact sheet prepared by 
the FERC entitled ``An Interstate Natural Gas Facility On My Land? What 
Do I Need To Know?''. This fact sheet addresses a number of typically-
asked questions, including the use of eminent domain and how to 
participate in the Commission's proceedings. It is also available for 
viewing on the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP15-503-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Comanche Trail proposes to construct and operate a new border 
crossing at the international boundary between the United States and 
Mexico in El Paso County, Texas. The San Elizario Crossing Project 
would consist of the construction of approximately 1,086 feet of FERC-
jurisdictional 42-inch-diameter pipeline, installed using a horizontal 
directional drill (HDD) beneath the Rio Grande River near the City of 
San Elizario in El Paso, Texas. The new pipeline would have a maximum 
design export capacity of approximately 1.1 billion cubic feet per day, 
in order to transport natural gas to a new delivery interconnect in the 
vicinity of the City of San Isidro, in the State of Chihuahua, Mexico.
    The general location of the project facilities is shown in appendix 
1.\1\

Non-Jurisdictional Facilities

    The San Elizario Crossing Project has associated facilities that 
would be constructed in support of the project, but do not fall under 
the jurisdiction of the FERC. The proposed Comanche Trail intrastate 
pipeline facilities, consist of 196 miles of new 42-inch-diameter 
pipeline, multiple receipt and delivery metering stations, and other 
auxiliary facilities extending from Pecos County, Texas and terminating 
at the proposed FERC-jurisdictional project facilities in El Paso 
County. The intrastate facilities would be subject to the jurisdiction 
of the Texas Railroad Commission and would be non-jurisdictional to the 
FERC. In the EA, we will provide available descriptions of the non-
jurisdictional facilities and include available environmental impact 
information under our analysis of cumulative impacts.

Land Requirements for Construction

    Construction of the San Elizario Crossing Project pipeline would 
affect a total of 4.2 acres of land in the United States, which 
includes temporary workspace for HDD construction, hydrostatic testing 
of the pipeline, and project access. Following construction, Comanche 
Trail would retain 1.3 acres as a 50-foot-wide permanent easement for 
operation of the FERC-jurisdictional pipeline, and the remaining 
acreage would be restored and revert to former uses.

[[Page 47488]]

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of an 
Authorization. NEPA also requires us \2\ to discover and address 
concerns the public may have about proposals. This process is referred 
to as ``scoping.'' The main goal of the scoping process is to focus the 
analysis in the EA on the important environmental issues. By this 
notice, the Commission requests public comments on the scope of the 
issues to address in the EA. We note that many comments were filed 
prior to this notice. We want to assure those commentors that their 
concerns will be considered in the scope of our environmental review; 
you do not need to resubmit comments. We will consider all filed 
comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. We will also 
publish and distribute the EA to the public for an allotted comment 
period. We will consider all comments on the EA before making our 
recommendations to the Commission. To ensure we have the opportunity to 
consider and address your comments, please carefully follow the 
instructions in the Public Participation section beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes: Federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    When we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are 
available on the Commission's Web site at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP15-
503). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.


[[Page 47489]]


    Dated: August 3, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-19420 Filed 8-6-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                             Federal Register / Vol. 80, No. 152 / Friday, August 7, 2015 / Notices                                          47487

                                              protests must set forth their evidentiary               alternatives, and measures to avoid or                000) with your submission: Kimberly D.
                                              basis and otherwise comply with the                     lessen environmental impacts. Your                    Bose, Secretary, Federal Energy
                                              requirements of 18 CFR 4.34(b). All                     input will help the Commission staff                  Regulatory Commission, 888 First Street
                                              comments, motions to intervene, or                      determine what issues they need to                    NE., Room 1A, Washington, DC 20426.
                                              protests should relate to project works                 evaluate in the EA. To ensure that your
                                              which are the subject of the amendment                  comments are timely and properly                      Summary of the Proposed Project
                                              application. Agencies may obtain copies                 recorded, please send your comments so                   Comanche Trail proposes to construct
                                              of the application directly from the                    that the Commission receives them in                  and operate a new border crossing at the
                                              applicant. A copy of any protest or                     Washington, DC on or before September
                                                                                                                                                            international boundary between the
                                              motion to intervene must be served                      2, 2015.
                                                                                                         If you sent comments on this project               United States and Mexico in El Paso
                                              upon each representative of the                                                                               County, Texas. The San Elizario
                                              applicant specified in the particular                   to the Commission before the opening of
                                                                                                      this docket on May 29, 2015, you will                 Crossing Project would consist of the
                                              application. If an intervener files
                                                                                                      need to file those comments in Docket                 construction of approximately 1,086 feet
                                              comments or documents with the
                                                                                                      No. CP15–503–000 to ensure they are                   of FERC-jurisdictional 42-inch-diameter
                                              Commission relating to the merits of an
                                                                                                      considered as part of this proceeding.                pipeline, installed using a horizontal
                                              issue that may affect the responsibilities
                                                                                                         This notice is being sent to the                   directional drill (HDD) beneath the Rio
                                              of a particular resource agency, they
                                                                                                      Commission’s current environmental                    Grande River near the City of San
                                              must also serve a copy of the document
                                              on that resource agency. A copy of all                  mailing list for this project. State and              Elizario in El Paso, Texas. The new
                                              other filings in reference to this                      local government representatives should               pipeline would have a maximum design
                                              application must be accompanied by                      notify their constituents of this                     export capacity of approximately 1.1
                                              proof of service on all persons listed in               proposed project and encourage them to                billion cubic feet per day, in order to
                                              the service list prepared by the                        comment on their areas of concern.                    transport natural gas to a new delivery
                                              Commission in this proceeding, in                          Comanche Trail provided landowners                 interconnect in the vicinity of the City
                                              accordance with 18 CFR 4.34(b) and                      with a fact sheet prepared by the FERC                of San Isidro, in the State of Chihuahua,
                                              385.2010.                                               entitled ‘‘An Interstate Natural Gas                  Mexico.
                                                                                                      Facility On My Land? What Do I Need                      The general location of the project
                                                Dated: August 3, 2015.                                To Know?’’. This fact sheet addresses a
                                              Nathaniel J. Davis, Sr.,                                                                                      facilities is shown in appendix 1.1
                                                                                                      number of typically-asked questions,
                                              Deputy Secretary.                                       including the use of eminent domain                   Non-Jurisdictional Facilities
                                              [FR Doc. 2015–19423 Filed 8–6–15; 8:45 am]              and how to participate in the
                                              BILLING CODE 6717–01–P                                  Commission’s proceedings. It is also                    The San Elizario Crossing Project has
                                                                                                      available for viewing on the FERC Web                 associated facilities that would be
                                                                                                      site (www.ferc.gov).                                  constructed in support of the project,
                                              DEPARTMENT OF ENERGY                                                                                          but do not fall under the jurisdiction of
                                                                                                      Public Participation                                  the FERC. The proposed Comanche
                                              Federal Energy Regulatory                                 For your convenience, there are three               Trail intrastate pipeline facilities,
                                              Commission                                              methods you can use to submit your                    consist of 196 miles of new 42-inch-
                                              [Docket No. CP15–503–000]                               comments to the Commission. The                       diameter pipeline, multiple receipt and
                                                                                                      Commission encourages electronic filing               delivery metering stations, and other
                                              Comanche Trail Pipeline, LLC; Notice                    of comments and has expert staff                      auxiliary facilities extending from Pecos
                                              of Intent To Prepare an Environmental                   available to assist you at (202) 502–8258             County, Texas and terminating at the
                                              Assessment for the Proposed San                         or efiling@ferc.gov. Please carefully                 proposed FERC-jurisdictional project
                                              Elizario Crossing Project; Request for                  follow these instructions so that your                facilities in El Paso County. The
                                              Comments on Environmental Issues                        comments are properly recorded.                       intrastate facilities would be subject to
                                                                                                         (1) You can file your comments                     the jurisdiction of the Texas Railroad
                                                The staff of the Federal Energy                       electronically using the eComment                     Commission and would be non-
                                              Regulatory Commission (FERC or                          feature on the Commission’s Web site                  jurisdictional to the FERC. In the EA, we
                                              Commission) will prepare an                             (www.ferc.gov) under the link to                      will provide available descriptions of
                                              environmental assessment (EA) that will                 Documents and Filings. This is an easy                the non-jurisdictional facilities and
                                              discuss the environmental impacts of                    method for submitting brief, text-only                include available environmental impact
                                              the San Elizario Crossing Project                       comments on a project;                                information under our analysis of
                                              involving construction and operation of                    (2) You can file your comments
                                                                                                                                                            cumulative impacts.
                                              specific border crossing facilities for the             electronically by using the eFiling
                                              export of natural gas by Comanche Trail                 feature on the Commission’s Web site                  Land Requirements for Construction
                                              Pipeline, LLC (Comanche Trail) in El                    (www.ferc.gov) under the link to
                                              Paso County, Texas. The Commission                      Documents and Filings. With eFiling,                    Construction of the San Elizario
                                              will use this EA in its decision-making                 you can provide comments in a variety                 Crossing Project pipeline would affect a
                                              process to determine whether the                        of formats by attaching them as a file                total of 4.2 acres of land in the United
                                              project is in the public interest.                      with your submission. New eFiling                     States, which includes temporary
                                                This notice announces the opening of                  users must first create an account by                 workspace for HDD construction,
                                              the scoping process the Commission                      clicking on ‘‘eRegister.’’ If you are filing          hydrostatic testing of the pipeline, and
tkelley on DSK3SPTVN1PROD with NOTICES




                                              will use to gather input from the public                a comment on a particular project,                    project access. Following construction,
                                              and interested agencies on the project.                 please select ‘‘Comment on a Filing’’ as              Comanche Trail would retain 1.3 acres
                                              You can make a difference by providing                  the filing type; or                                   as a 50-foot-wide permanent easement
                                              us with your specific comments or                          (3) You can file a paper copy of your              for operation of the FERC-jurisdictional
                                              concerns about the project. Your                        comments by mailing them to the                       pipeline, and the remaining acreage
                                              comments should focus on the potential                  following address. Be sure to reference               would be restored and revert to former
                                              environmental effects, reasonable                       the project docket number (CP15–503–                  uses.


                                         VerDate Sep<11>2014   18:24 Aug 06, 2015   Jkt 235001   PO 00000   Frm 00038   Fmt 4703   Sfmt 4703   E:\FR\FM\07AUN1.SGM   07AUN1


                                              47488                          Federal Register / Vol. 80, No. 152 / Friday, August 7, 2015 / Notices

                                              The EA Process                                          preparation of the EA.3 Agencies that                        When we publish and distribute the
                                                 The National Environmental Policy                    would like to request cooperating                         EA, copies will be sent to the
                                              Act (NEPA) requires the Commission to                   agency status should follow the                           environmental mailing list for public
                                              take into account the environmental                     instructions for filing comments                          review and comment. If you would
                                                                                                      provided under the Public Participation                   prefer to receive a paper copy of the
                                              impacts that could result from an action
                                                                                                      section of this notice.                                   document instead of the CD version or
                                              whenever it considers the issuance of an
                                              Authorization. NEPA also requires us 2                  Consultations Under Section 106 of the                    would like to remove your name from
                                              to discover and address concerns the                    National Historic Preservation Act                        the mailing list, please return the
                                              public may have about proposals. This                     In accordance with the Advisory                         attached Information Request (appendix
                                              process is referred to as ‘‘scoping.’’ The              Council on Historic Preservation’s                        2).
                                              main goal of the scoping process is to                  implementing regulations for section                      Becoming an Intervenor
                                              focus the analysis in the EA on the                     106 of the National Historic
                                              important environmental issues. By this                 Preservation Act, we are using this                         In addition to involvement in the EA
                                              notice, the Commission requests public                  notice to initiate consultation with the                  scoping process, you may want to
                                              comments on the scope of the issues to                  applicable State Historic Preservation                    become an ‘‘intervenor’’ which is an
                                              address in the EA. We note that many                    Office (SHPO), and to solicit their views                 official party to the Commission’s
                                              comments were filed prior to this                       and those of other government agencies,                   proceeding. Intervenors play a more
                                              notice. We want to assure those                         interested Indian tribes, and the public                  formal role in the process and are able
                                              commentors that their concerns will be                  on the project’s potential effects on                     to file briefs, appear at hearings, and be
                                              considered in the scope of our                          historic properties.4 We will define the                  heard by the courts if they choose to
                                              environmental review; you do not need                   project-specific Area of Potential Effects
                                              to resubmit comments. We will consider                                                                            appeal the Commission’s final ruling.
                                                                                                      (APE) in consultation with the SHPO as                    An intervenor formally participates in
                                              all filed comments during the                           the project develops. On natural gas
                                              preparation of the EA.                                                                                            the proceeding by filing a request to
                                                                                                      facility projects, the APE at a minimum
                                                 In the EA we will discuss impacts that                                                                         intervene. Instructions for becoming an
                                                                                                      encompasses all areas subject to ground
                                              could occur as a result of the                          disturbance (examples include                             intervenor are available on the
                                              construction and operation of the                       construction right-of-way, contractor/                    Commission’s Web site at http://
                                              proposed project under these general                    pipe storage yards, compressor stations,                  www.ferc.gov/resources/guides/how-to/
                                              headings:                                               and access roads). Our EA for this                        intervene.asp.
                                                 • Geology and soils;                                 project will document our findings on                     Additional Information
                                                 • land use;                                          the impacts on historic properties and
                                                 • water resources, fisheries, and                    summarize the status of consultations                        Additional information about the
                                              wetlands;                                               under section 106.                                        project is available from the
                                                 • cultural resources;                                                                                          Commission’s Office of External Affairs,
                                                                                                      Environmental Mailing List
                                                 • vegetation and wildlife;                                                                                     at (866) 208–FERC, or on the FERC Web
                                                 • air quality and noise;                                The environmental mailing list                         site at www.ferc.gov using the
                                                 • endangered and threatened species;                 includes: Federal, state, and local
                                                                                                                                                                ‘‘eLibrary’’ link. Click on the eLibrary
                                                 • public safety; and                                 government representatives and
                                                                                                                                                                link, click on ‘‘General Search’’ and
                                                 • cumulative impacts.                                agencies; elected officials;
                                                                                                                                                                enter the docket number, excluding the
                                                 We will also evaluate reasonable                     environmental and public interest
                                                                                                      groups; Native American Tribes; other                     last three digits in the Docket Number
                                              alternatives to the proposed project or                                                                           field (i.e., CP15–503). Be sure you have
                                              portions of the project, and make                       interested parties; and local libraries
                                                                                                      and newspapers. This list also includes                   selected an appropriate date range. For
                                              recommendations on how to lessen or                                                                               assistance, please contact FERC Online
                                              avoid impacts on the various resource                   all affected landowners (as defined in
                                                                                                      the Commission’s regulations) who are                     Support at FercOnlineSupport@ferc.gov
                                              areas.
                                                                                                      potential right-of-way grantors, whose                    or toll free at (866) 208–3676, or for
                                                 The EA will present our independent
                                                                                                      property may be used temporarily for                      TTY, contact (202) 502–8659. The
                                              analysis of the issues. The EA will be
                                              available in the public record through                  project purposes, or who own homes                        eLibrary link also provides access to the
                                              eLibrary. We will also publish and                      within certain distances of aboveground                   texts of formal documents issued by the
                                              distribute the EA to the public for an                  facilities, and anyone who submits                        Commission, such as orders, notices,
                                              allotted comment period. We will                        comments on the project. We will                          and rulemakings.
                                              consider all comments on the EA before                  update the environmental mailing list as                     In addition, the Commission now
                                              making our recommendations to the                       the analysis proceeds to ensure that we                   offers a free service called eSubscription
                                              Commission. To ensure we have the                       send the information related to this                      which allows you to keep track of all
                                              opportunity to consider and address                     environmental review to all individuals,                  formal issuances and submittals in
                                              your comments, please carefully follow                  organizations, and government entities                    specific dockets. This can reduce the
                                              the instructions in the Public                          interested in and/or potentially affected
                                                                                                                                                                amount of time you spend researching
                                              Participation section beginning on page                 by the proposed project.
                                                                                                                                                                proceedings by automatically providing
                                              2.                                                        3 The Council on Environmental Quality
                                                                                                                                                                you with notification of these filings,
                                                 With this notice, we are asking                      regulations addressing cooperating agency                 document summaries, and direct links
                                              agencies with jurisdiction by law and/                  responsibilities are at Title 40, Code of Federal         to the documents. Go to www.ferc.gov/
tkelley on DSK3SPTVN1PROD with NOTICES




                                              or special expertise with respect to the                Regulations, Part 1501.6.                                 docs-filing/esubscription.asp.
                                              environmental issues of this project to                   4 The Advisory Council on Historic Preservation’s

                                              formally cooperate with us in the                       regulations are at Title 36, Code of Federal                 Finally, public meetings or site visits
                                                                                                      Regulations, Part 800. Those regulations define           will be posted on the Commission’s
                                                                                                      historic properties as any prehistoric or historic
                                                2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the            district, site, building, structure, or object included
                                                                                                                                                                calendar located at www.ferc.gov/
                                              environmental staff of the Commission’s Office of       in or eligible for inclusion in the National Register     EventCalendar/EventsList.aspx along
                                              Energy Projects.                                        of Historic Places.                                       with other related information.


                                         VerDate Sep<11>2014   18:24 Aug 06, 2015   Jkt 235001   PO 00000   Frm 00039   Fmt 4703   Sfmt 4703   E:\FR\FM\07AUN1.SGM     07AUN1


                                                                             Federal Register / Vol. 80, No. 152 / Friday, August 7, 2015 / Notices                                                47489

                                                Dated: August 3, 2015.                                  Dated: August 4, 2015.                                * Session Closed-Exempt pursuant to 5
                                              Nathaniel J. Davis, Sr.,                                Karin Leff,                                           U.S.C. Section 552b(c)(8) and (9).
                                              Deputy Secretary.                                       Acting Director, NEPA Compliance Division,              Dated: August 4, 2015.
                                              [FR Doc. 2015–19420 Filed 8–6–15; 8:45 am]              Office of Federal Activities.                         Dale L. Aultman,
                                              BILLING CODE 6717–01–P                                  [FR Doc. 2015–19441 Filed 8–6–15; 8:45 am]            Secretary, Farm Credit Administration Board.
                                                                                                      BILLING CODE 6560–50–P                                [FR Doc. 2015–19578 Filed 8–5–15; 4:15 pm]
                                                                                                                                                            BILLING CODE 6705–01–P

                                              ENVIRONMENTAL PROTECTION                                FARM CREDIT ADMINISTRATION
                                              AGENCY                                                                                                        FEDERAL COMMUNICATIONS
                                                                                                      Farm Credit Administration Board;
                                                                                                      Sunshine Act; Regular Meeting                         COMMISSION
                                              [ER–FRL–9022–3]
                                                                                                      AGENCY:  Farm Credit Administration.                  Federal Advisory Committee Act;
                                              Environmental Impact Statements;                        SUMMARY:   Notice is hereby given,                    Downloadable Security Technology
                                              Notice of Availability                                  pursuant to the Government in the                     Advisory Committee
                                                Responsible Agency: Office of Federal                 Sunshine Act, of the regular meeting of               AGENCY: Federal Communications
                                              Activities, General Information (202)                   the Farm Credit Administration Board                  Commission.
                                              564–7146 or http://www2.epa.gov/nepa.                   (Board).                                              ACTION: Notice.
                                              Weekly receipt of Environmental Impact                  DATES: The regular meeting of the Board
                                                Statements (EISs)                                     will be held at the offices of the Farm               SUMMARY:   In accordance with the
                                              Filed 07/27/2015 Through 07/31/2015                     Credit Administration in McLean,                      Federal Advisory Committee Act, this
                                              Pursuant to 40 CFR 1506.9.                              Virginia, on August 13, 2015, from 9:00               notice advises interested persons that
                                                                                                      a.m. until such time as the Board                     the Federal Communications
                                              Notice                                                  concludes its business.                               Commission’s (‘‘FCC’’ or
                                                Section 309(a) of the Clean Air Act                   FOR FURTHER INFORMATION CONTACT: Dale                 ‘‘Commission’’) Downloadable Security
                                              requires that EPA make public its                       L. Aultman, Secretary to the Farm                     Technology Advisory Committee
                                              comments on EISs issued by other                        Credit Administration Board, (703) 883–               (‘‘DSTAC’’) will hold a meeting on
                                              Federal agencies. EPA’s comment letters                 4009, TTY (703) 883–4056.                             August 28, 2015. At the meeting, the
                                              on EISs are available at: https://                                                                            committee will consider and debate a
                                                                                                      ADDRESSES: Farm Credit
                                              cdxnodengn.epa.gov/cdx-enepa-public/                                                                          final DSTAC report and discuss any
                                                                                                      Administration, 1501 Farm Credit Drive,
                                              action/eis/search.                                                                                            other DSTAC issues that may arise.
                                                                                                      McLean, Virginia 22102–5090. Submit
                                              EIS No. 20150208, Final, DOE, AL,                       attendance requests via email to                      DATES: August 28, 2015.
                                                PROGRAMMATIC—Engineered High                          VisitorRequest@FCA.gov. See                           ADDRESSES: Federal Communications
                                                Energy Crop (EHEC) Programs,                          SUPPLEMENTARY INFORMATION for further                 Commission, Room TW–C305
                                                Review Period Ends: 09/08/2015,                       information about attendance requests.                (Commission Meeting Room), 445 12th
                                                Contact: Dr. Jonathan Burbaum 202–                    SUPPLEMENTARY INFORMATION: Parts of                   Street SW., Washington, DC 20554.
                                                287–6413.                                             this meeting of the Board will be open                FOR FURTHER INFORMATION CONTACT: For
                                              EIS No. 20150209, Final, USFS, AZ,                      to the public (limited space available),              additional information on this
                                                Prescott National Forest Revision of                  and parts will be closed to the public.               proceeding, contact Brendan Murray,
                                                Land and Resource Management Plan,                    Please send an email to VisitorRequest@               Brendan.Murry@fcc.gov, of the Media
                                                Review Period Ends: 11/05/2015,                       FCA.gov at least 24 hours before the                  Bureau, Policy Division, (202) 418–1573
                                                Contact: Gabrielle Kenton 928–443–                    meeting. In your email include: Name,                 or Nancy Murphy, Nancy.Murphy@
                                                8221.                                                 postal address, entity you are                        fcc.gov, of the Media Bureau, (202) 418–
                                              EIS No. 20150210, Draft, USFS, WY,                      representing (if applicable), and                     1043.
                                                Teton to Snake Fuels Management,                      telephone number. You will receive an                 SUPPLEMENTARY INFORMATION: This
                                                Comment Period Ends: 09/21/2015,                      email confirmation from us. Please be                 meeting will be held on August 28,
                                                Contact: Steve Markason 307–739–                      prepared to show a photo identification               2015, from 9:30 a.m. to 4:00 p.m. in the
                                                5431.                                                 when you arrive. If you need assistance               Commission Meeting Room of the
                                              EIS No. 20150211, Draft, FHWA, LA,                      for accessibility reasons, or if you have             Federal Communications Commission,
                                                Houma-Thibodaux to LA 3127                            any questions, contact Dale L. Aultman,               Room TW–C305, 445 12th Street SW.,
                                                Connection, Comment Period Ends:                      Secretary to the Farm Credit                          Washington, DC 20554.
                                                09/21/2015, Contact: Carl Highsmith                   Administration Board, at (703) 883–                      The DSTAC is a Federal Advisory
                                                225–757–7615.                                         4009. The matters to be considered at                 Committee that will ‘‘identify, report,
                                              EIS No. 20150212, Draft, BLM, CA, West                  the meeting are:                                      and recommend performance objectives,
                                                Of Devers Upgrade Project, Comment                                                                          technical capabilities, and technical
                                                Period Ends: 09/21/2015, Contact:                     Open Session
                                                                                                                                                            standards of a not unduly burdensome,
                                                Frank McMenimen 760–833–7150.                         A. Approval of Minutes                                uniform, and technology- and platform-
                                              EIS No. 20150213, Final, USFS, CA,                        • July 8, 2015                                      neutral software-based downloadable
                                                Westside Fire Recovery Project,                                                                             security system.’’
                                                Review Period Ends: 09/08/2015,                       B. New Business                                          The meeting on August 28, 2015, will
tkelley on DSK3SPTVN1PROD with NOTICES




                                                Contact: Wendy Coats 530–841–4470.                      • Mergers, Consolidations and                       be the seventh meeting of the DSTAC.
                                              EIS No. 20150214, Draft, BR, CA,                        Charter Amendments of Banks and                       The FCC will attempt to accommodate
                                                Coordinated Long-Term Operation of                    Associations—Final Rule                               as many attendees as possible; however,
                                                the Central Valley Project and State                                                                        admittance will be limited to seating
                                                Water Project, Comment Period Ends:                   Closed Session *                                      availability. The Commission will
                                                09/29/2015, Contact: Janice Piñero                     • Office of Secondary Market                        provide audio and/or video coverage of
                                                916–414–2428.                                         Oversight Quarterly Report                            the meeting over the Internet from the


                                         VerDate Sep<11>2014   18:24 Aug 06, 2015   Jkt 235001   PO 00000   Frm 00040   Fmt 4703   Sfmt 4703   E:\FR\FM\07AUN1.SGM   07AUN1



Document Created: 2015-12-15 10:56:25
Document Modified: 2015-12-15 10:56:25
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 47487 