NUCLEAR REGULATORY COMMISSION

Federal Register Volume 80, Issue 164 (August 25, 2015)

Page Range51614-51615
FR Document2015-21074

The U.S. Nuclear Regulatory Commission (NRC) is soliciting public comment on the following sections in Chapter 3, ``Design of Structures, Components, Equipment, and Systems Reactor Coolant System and Connected Systems,'' and Chapter 5, ``Reactor Coolant System and Connected Systems,'' of NUREG-0800, ``Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition,'' Section 3.2.1, ``Seismic Classification,'' Section 3.2.2, ``System Quality Group Classification,'' Section 3.6.2, ``Determination of Rupture Locations and Dynamic Effects Associated with the Postulated Rupture of Piping,'' Section 3.9.1, ``Special Topics for Mechanical Components,'' Section 3.10, ``Seismic and Dynamic Qualification of Mechanical and Electrical Equipment,'' Section 5.2.1.1, ``Compliance with the Codes and Standards Rule,'' Section 5.2.1.2, ``Applicable Code Cases,'' and Branch Technical Position (BTP) 3-4, ``Applicable Code Cases.''

Federal Register, Volume 80 Issue 164 (Tuesday, August 25, 2015)
[Federal Register Volume 80, Number 164 (Tuesday, August 25, 2015)]
[Notices]
[Pages 51614-51615]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-21074]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2015-0198]


Design of Structures, Components, Equipment, and Systems, and 
Reactor Coolant System and Connected Systems

AGENCY: Nuclear Regulatory Commission.

ACTION: Standard review plan-draft section revision; request for 
comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is soliciting 
public comment on the following sections in Chapter 3, ``Design of 
Structures, Components, Equipment, and Systems Reactor Coolant System 
and Connected Systems,'' and Chapter 5, ``Reactor Coolant System and 
Connected Systems,'' of NUREG-0800, ``Standard Review Plan for the 
Review of Safety Analysis Reports for Nuclear Power Plants: LWR 
Edition,'' Section 3.2.1, ``Seismic Classification,'' Section 3.2.2, 
``System Quality Group Classification,'' Section 3.6.2, ``Determination 
of Rupture Locations and Dynamic Effects Associated with the Postulated 
Rupture of Piping,'' Section 3.9.1, ``Special Topics for Mechanical 
Components,'' Section 3.10, ``Seismic and Dynamic Qualification of 
Mechanical and Electrical Equipment,'' Section 5.2.1.1, ``Compliance 
with the Codes and Standards Rule,'' Section 5.2.1.2, ``Applicable Code 
Cases,'' and Branch Technical Position (BTP) 3-4, ``Applicable Code 
Cases.''

DATES: Comments must be filed no later than October 26, 2015.

ADDRESSES: You may submit comments by any of the following methods 
(unless this document describes a different method for submitting 
comments on a specific subject):
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2015-0198. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual(s) listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     Mail comments to: Cindy Bladey, Office of Administration, 
Mail Stop: O12-H08, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001.
    For additional direction on accessing information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Mark Notich, telephone: 301-415-3053; 
email: [email protected] or Nishka Devaser, telephone: 301-415-5196; 
email: [email protected], both are staff of the Office of New 
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001.

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2015-0198 when contacting the NRC 
about the availability of information regarding this document. You may 
obtain publicly-available information related to this action by the 
following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2015-0198.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it available in 
ADAMS) is provided the first time that a document is referenced. In 
addition, for the convenience of the reader, the ADAMS accession 
numbers are provided in a table in the section of this notice entitled, 
Availability of Documents.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2015-0198 in the subject line of your 
comment submission, in order to ensure that the NRC is able to make 
your comment submission available to the public in this docket.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC posts all comment submissions at http://www.regulations.gov as well as entering the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Further Information

    The NRC seeks public comment on the proposed draft revisions of 
Standard Review Plan (SRP) Sections 3.2.1, 3.2.2, 3.6.2, 3.9.1, 3.10, 
5.2.1.1, 5.2.1.2, and BTP 3-4. These sections have been developed to 
assist NRC staff's review the design of structures, components, 
equipment, and systems, as well as assess compliance with codes, 
standards, and code cases for the reactor coolant system and connected 
systems under parts 50 and 52 of Title 10 of the

[[Page 51615]]

Code of Federal Regulations (10 CFR). The revisions to these SRP 
sections reflect no changes in staff position; rather they clarify the 
original intent of these SRP sections using plain language throughout 
in accordance with the NRC's Plain Writing Action Plan. Additionally, 
these revisions reflect operating experience, lessons learned, and 
updated guidance since the last revision, and address the applicability 
of regulatory treatment of non-safety systems where appropriate.
    Following NRC staff's evaluation of submitted comments, the NRC 
intends to finalize the proposed revisions of SRP Sections 3.2.1, 
3.2.2, 3.6.2, 3.9.1, 3.10, 5.2.1.1, 5.2.1.2, and BTP 3-4 in ADAMS and 
post them on the NRC's public Web site at http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr0800/.

III. Availability of Documents

    The ADAMS accession numbers for the current revisions, proposed 
draft revisions, and redline strikeouts comparing current revisions and 
the proposed revisions of individual sections are available in ADAMS 
under the following accession numbers:

----------------------------------------------------------------------------------------------------------------
                                     Current revision ADAMS     Proposed revision
            SRP Section                   accession No.        ADAMS accession No.   Redline ADAMS accession No.
----------------------------------------------------------------------------------------------------------------
Section 3.2.1, ``Seismic             Revision 2              Revision 3              ML14198A162
 Classification''.                    (ML063190002).          (ML14227A643).
Section 3.2.2, ``System Quality      Revision 2              Revision 3              ML14198A145
 Group Classification''.              (ML063190003).          (ML14227A641).
Section 3.6.2, ``Determination of    Revision 2              Revision 3              ML14198A166
 Rupture Locations and Dynamic        (ML070660494).          (ML14230A035).
 Effects Associated with the
 Postulated Rupture of Piping''.
Section 3.9.1, ``Special Topics for  Revision 3              Revision 4              ML14198A150
 Mechanical Components''.             (ML070430402).          (ML14227A637).
Section 3.10, ``Seismic and Dynamic  Revision 3              Revision 4              ML14198A171
 Qualification of Mechanical and      (ML070720037).          (ML14227A631).
 Electrical Equipment''.
Section 5.2.1.1, ``Compliance with   Revision 3              Revision 4              ML14198A155
 the Codes and Standards Rule, 10     (ML070040003).          (ML14227A623).
 CFR 50.55a''.
Section 5.2.1.2 , ``Applicable Code  Revision 3              Revision 4              ML14198A172
 Cases''.                             (ML070040004).          (ML14227A659).
Branch Technical Position 3-4,       Revision 2              Revision 3              ML14198A126
 ``Applicable Code Cases''.           (ML070800008).          (ML14227A646).
----------------------------------------------------------------------------------------------------------------

IV. Backfitting and Issue Finality

    Issuance of these draft SRP sections does not constitute 
backfitting as defined in 10 CFR 50.109, nor is it inconsistent with 
any of the issue finality provisions in 10 CFR part 52. These draft SRP 
sections do not contain any new requirements for COL applicants or 
holders under 10 CFR part 52, or for licensees of existing operating 
units licensed under 10 CFR part 50. Rather, it contains additional 
draft guidance and clarification on staff review of Preliminary 
Amendment Requests.
    The NRC staff does not intend to impose or apply the positions 
described in the draft SRP to existing licenses and regulatory 
approvals. Hence, the issuance of a final SRP--even if considered 
guidance within the purview of the issue finality provisions in 10 CFR 
part 52--would not need to be evaluated as if it were a backfit or as 
being inconsistent with issue finality provisions. If, in the future, 
the NRC staff seeks to impose a position in the SRP on holders of 
already issued licenses in a manner that does not provide issue 
finality as described in the applicable issue finality provision, then 
the staff must make the showing as set forth in the Backfit Rule or 
address the criteria for avoiding issue finality as described in the 
applicable issue finality provision.
    The NRC staff does not, at this time, intend to impose the 
positions represented in the draft SRP sections in a manner that is 
inconsistent with any issue finality provisions. If, in the future, the 
staff seeks to impose a position in the draft SRP in a manner that does 
not provide issue finality as described in the applicable issue 
finality provision, then the staff must address the criteria for 
avoiding issue finality as described in the applicable issue finality 
provision.

    Dated at Rockville, Maryland, this 14th day of August, 2015.

    For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, New Reactor Rulemaking and Guidance Branch, Division of Advanced 
Reactors and Rulemaking, Office of New Reactors.
[FR Doc. 2015-21074 Filed 8-24-15; 8:45 am]
BILLING CODE 7590-01-P



                                                    51614                        Federal Register / Vol. 80, No. 164 / Tuesday, August 25, 2015 / Notices

                                                    of radioactive source material. The                     Associated with the Postulated Rupture                adams.html. To begin the search, select
                                                    application, reporting, recordkeeping,                  of Piping,’’ Section 3.9.1, ‘‘Special                 ‘‘ADAMS Public Documents’’ and then
                                                    and third party notification                            Topics for Mechanical Components,’’                   select ‘‘Begin Web-based ADAMS
                                                    requirements are necessary to permit the                Section 3.10, ‘‘Seismic and Dynamic                   Search.’’ For problems with ADAMS,
                                                    NRC to make a determination as to                       Qualification of Mechanical and                       please contact the NRC’s Public
                                                    whether the possession, use, and                        Electrical Equipment,’’ Section 5.2.1.1,              Document Room (PDR) reference staff at
                                                    transfer of source and byproduct                        ‘‘Compliance with the Codes and                       1–800–397–4209, 301–415–4737, or by
                                                    material is in conformance with the                     Standards Rule,’’ Section 5.2.1.2,                    email to pdr.resource@nrc.gov. The
                                                    Commission’s regulations for protection                 ‘‘Applicable Code Cases,’’ and Branch                 ADAMS accession number for each
                                                    of public health and safety.                            Technical Position (BTP) 3–4,                         document referenced (if it available in
                                                                                                            ‘‘Applicable Code Cases.’’                            ADAMS) is provided the first time that
                                                    III. Specific Requests for Comments                                                                           a document is referenced. In addition,
                                                                                                            DATES: Comments must be filed no later
                                                      The NRC is seeking comments that                      than October 26, 2015.                                for the convenience of the reader, the
                                                    address the following questions:                                                                              ADAMS accession numbers are
                                                                                                            ADDRESSES: You may submit comments
                                                      1. Is the proposed collection of                                                                            provided in a table in the section of this
                                                                                                            by any of the following methods (unless               notice entitled, Availability of
                                                    information necessary for the NRC to
                                                                                                            this document describes a different                   Documents.
                                                    properly perform its functions? Does the
                                                                                                            method for submitting comments on a                      • NRC’s PDR: You may examine and
                                                    information have practical utility?
                                                                                                            specific subject):                                    purchase copies of public documents at
                                                      2. Is the estimate of the burden of the
                                                                                                               • Federal Rulemaking Web site: Go to               the NRC’s PDR, Room O1–F21, One
                                                    information collection accurate?
                                                                                                            http://www.regulations.gov and search                 White Flint North, 11555 Rockville
                                                      3. Is there a way to enhance the
                                                                                                            for Docket ID NRC–2015–0198. Address                  Pike, Rockville, Maryland 20852.
                                                    quality, utility, and clarity of the
                                                                                                            questions about NRC dockets to Carol
                                                    information to be collected?                                                                                  B. Submitting Comments
                                                                                                            Gallagher; telephone: 301–415–3463;
                                                      4. How can the burden of the
                                                                                                            email: Carol.Gallagher@nrc.gov. For                     Please include Docket ID NRC–2015–
                                                    information collection on respondents
                                                                                                            technical questions, contact the                      0198 in the subject line of your
                                                    be minimized, including the use of
                                                                                                            individual(s) listed in the FOR FURTHER               comment submission, in order to ensure
                                                    automated collection techniques or
                                                                                                            INFORMATION CONTACT section of this                   that the NRC is able to make your
                                                    other forms of information technology?
                                                                                                            document.                                             comment submission available to the
                                                      Dated at Rockville, Maryland, this 20th day              • Mail comments to: Cindy Bladey,                  public in this docket.
                                                    of August 2015.                                         Office of Administration, Mail Stop:                    The NRC cautions you not to include
                                                      For the Nuclear Regulatory Commission.                O12–H08, U.S. Nuclear Regulatory                      identifying or contact information that
                                                    Tremaine Donnell,                                       Commission, Washington, DC 20555–                     you do not want to be publicly
                                                    NRC Clearance Officer, Office of Information            0001.                                                 disclosed in your comment submission.
                                                    Services.                                                  For additional direction on accessing              The NRC posts all comment
                                                    [FR Doc. 2015–20998 Filed 8–24–15; 8:45 am]             information and submitting comments,                  submissions at http://
                                                    BILLING CODE 7590–01–P                                  see ‘‘Obtaining Information and                       www.regulations.gov as well as entering
                                                                                                            Submitting Comments’’ in the                          the comment submissions into ADAMS.
                                                                                                            SUPPLEMENTARY INFORMATION section of                  The NRC does not routinely edit
                                                    NUCLEAR REGULATORY                                      this document.                                        comment submissions to remove
                                                    COMMISSION                                              FOR FURTHER INFORMATION CONTACT:                      identifying or contact information.
                                                                                                            Mark Notich, telephone: 301–415–3053;                   If you are requesting or aggregating
                                                    [NRC–2015–0198]
                                                                                                            email: Mark.Notich@nrc.gov or Nishka                  comments from other persons for
                                                    Design of Structures, Components,                       Devaser, telephone: 301–415–5196;                     submission to the NRC, then you should
                                                    Equipment, and Systems, and Reactor                     email: Nishka.Devaser@nrc.gov, both are               inform those persons not to include
                                                    Coolant System and Connected                            staff of the Office of New Reactors, U.S.             identifying or contact information that
                                                    Systems                                                 Nuclear Regulatory Commission,                        they do not want to be publicly
                                                                                                            Washington, DC 20555–0001.                            disclosed in their comment submission.
                                                    AGENCY:  Nuclear Regulatory                                                                                   Your request should state that the NRC
                                                                                                            SUPPLEMENTARY INFORMATION:
                                                    Commission.                                                                                                   does not routinely edit comment
                                                    ACTION: Standard review plan-draft                      I. Obtaining Information and                          submissions to remove such information
                                                    section revision; request for comment.                  Submitting Comments                                   before making the comment
                                                                                                            A. Obtaining Information                              submissions available to the public or
                                                    SUMMARY:  The U.S. Nuclear Regulatory                                                                         entering the comment submissions into
                                                    Commission (NRC) is soliciting public                     Please refer to Docket ID NRC–2015–                 ADAMS.
                                                    comment on the following sections in                    0198 when contacting the NRC about
                                                    Chapter 3, ‘‘Design of Structures,                      the availability of information regarding             II. Further Information
                                                    Components, Equipment, and Systems                      this document. You may obtain                            The NRC seeks public comment on
                                                    Reactor Coolant System and Connected                    publicly-available information related to             the proposed draft revisions of Standard
                                                    Systems,’’ and Chapter 5, ‘‘Reactor                     this action by the following methods:                 Review Plan (SRP) Sections 3.2.1, 3.2.2,
                                                    Coolant System and Connected                              • Federal Rulemaking Web site: Go to                3.6.2, 3.9.1, 3.10, 5.2.1.1, 5.2.1.2, and
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    Systems,’’ of NUREG–0800, ‘‘Standard                    http://www.regulations.gov and search                 BTP 3–4. These sections have been
                                                    Review Plan for the Review of Safety                    for Docket ID NRC–2015–0198.                          developed to assist NRC staff’s review
                                                    Analysis Reports for Nuclear Power                        • NRC’s Agencywide Documents                        the design of structures, components,
                                                    Plants: LWR Edition,’’ Section 3.2.1,                   Access and Management System                          equipment, and systems, as well as
                                                    ‘‘Seismic Classification,’’ Section 3.2.2,              (ADAMS): You may obtain publicly-                     assess compliance with codes,
                                                    ‘‘System Quality Group Classification,’’                available documents online in the                     standards, and code cases for the reactor
                                                    Section 3.6.2, ‘‘Determination of                       ADAMS Public Documents collection at                  coolant system and connected systems
                                                    Rupture Locations and Dynamic Effects                   http://www.nrc.gov/reading-rm/                        under parts 50 and 52 of Title 10 of the


                                               VerDate Sep<11>2014   17:10 Aug 24, 2015   Jkt 235001   PO 00000   Frm 00084   Fmt 4703   Sfmt 4703   E:\FR\FM\25AUN1.SGM   25AUN1


                                                                                    Federal Register / Vol. 80, No. 164 / Tuesday, August 25, 2015 / Notices                                                         51615

                                                    Code of Federal Regulations (10 CFR).                         revision, and address the applicability                 III. Availability of Documents
                                                    The revisions to these SRP sections                           of regulatory treatment of non-safety
                                                    reflect no changes in staff position;                         systems where appropriate.                                The ADAMS accession numbers for
                                                    rather they clarify the original intent of                       Following NRC staff’s evaluation of                  the current revisions, proposed draft
                                                    these SRP sections using plain language                       submitted comments, the NRC intends                     revisions, and redline strikeouts
                                                    throughout in accordance with the                             to finalize the proposed revisions of SRP               comparing current revisions and the
                                                    NRC’s Plain Writing Action Plan.                              Sections 3.2.1, 3.2.2, 3.6.2, 3.9.1, 3.10,              proposed revisions of individual
                                                    Additionally, these revisions reflect                         5.2.1.1, 5.2.1.2, and BTP 3–4 in ADAMS                  sections are available in ADAMS under
                                                                                                                  and post them on the NRC’s public Web                   the following accession numbers:
                                                    operating experience, lessons learned,
                                                                                                                  site at http://www.nrc.gov/reading-rm/
                                                    and updated guidance since the last
                                                                                                                  doc-collections/nuregs/staff/sr0800/.

                                                                                                                                        Current revision ADAMS           Proposed revision ADAMS            Redline ADAMS
                                                                                  SRP Section                                                accession No.                    accession No.                  accession No.

                                                    Section 3.2.1, ‘‘Seismic Classification’’ ...................................   Revision 2 (ML063190002) ...        Revision 3 (ML14227A643) ...        ML14198A162
                                                    Section 3.2.2, ‘‘System Quality Group Classification’’ ............             Revision 2 (ML063190003) ...        Revision 3 (ML14227A641) ...        ML14198A145
                                                    Section 3.6.2, ‘‘Determination of Rupture Locations and Dy-                     Revision 2 (ML070660494) ...        Revision 3 (ML14230A035) ...        ML14198A166
                                                      namic Effects Associated with the Postulated Rupture of
                                                      Piping’’.
                                                    Section 3.9.1, ‘‘Special Topics for Mechanical Components’’                     Revision 3 (ML070430402) ...        Revision 4 (ML14227A637) ...        ML14198A150
                                                    Section 3.10, ‘‘Seismic and Dynamic Qualification of Me-                        Revision 3 (ML070720037) ...        Revision 4 (ML14227A631) ...        ML14198A171
                                                      chanical and Electrical Equipment’’.
                                                    Section 5.2.1.1, ‘‘Compliance with the Codes and Standards                      Revision 3 (ML070040003) ...        Revision 4 (ML14227A623) ...        ML14198A155
                                                      Rule, 10 CFR 50.55a’’.
                                                    Section 5.2.1.2 , ‘‘Applicable Code Cases’’ ............................        Revision 3 (ML070040004) ...        Revision 4 (ML14227A659) ...        ML14198A172
                                                    Branch Technical Position 3–4, ‘‘Applicable Code Cases’’ .....                  Revision 2 (ML070800008) ...        Revision 3 (ML14227A646) ...        ML14198A126



                                                    IV. Backfitting and Issue Finality                            issue finality provisions. If, in the                   notice is hereby given that, on August
                                                                                                                  future, the staff seeks to impose a                     13, 2015, The NASDAQ Stock Market
                                                       Issuance of these draft SRP sections
                                                                                                                  position in the draft SRP in a manner                   LLC (‘‘NASDAQ’’ or ‘‘Exchange’’) filed
                                                    does not constitute backfitting as                            that does not provide issue finality as                 with the Securities and Exchange
                                                    defined in 10 CFR 50.109, nor is it                           described in the applicable issue finality              Commission (‘‘Commission’’) the
                                                    inconsistent with any of the issue                            provision, then the staff must address                  proposed rule change as described in
                                                    finality provisions in 10 CFR part 52.                        the criteria for avoiding issue finality as             Items I, II, and III, below, which Items
                                                    These draft SRP sections do not contain                       described in the applicable issue finality              have been prepared by the Exchange.
                                                    any new requirements for COL                                  provision.
                                                    applicants or holders under 10 CFR part                                                                               The Commission is publishing this
                                                    52, or for licensees of existing operating                      Dated at Rockville, Maryland, this 14th day           notice to solicit comments on the
                                                    units licensed under 10 CFR part 50.                          of August, 2015.                                        proposed rule change from interested
                                                    Rather, it contains additional draft                            For the Nuclear Regulatory Commission.                persons.
                                                    guidance and clarification on staff                           Joseph Colaccino,
                                                                                                                                                                          I. Self-Regulatory Organization’s
                                                    review of Preliminary Amendment                               Chief, New Reactor Rulemaking and                       Statement of the Terms of Substance of
                                                    Requests.                                                     Guidance Branch, Division of Advanced
                                                                                                                  Reactors and Rulemaking, Office of New                  the Proposed Rule Change
                                                       The NRC staff does not intend to                           Reactors.
                                                    impose or apply the positions described                                                                                  The Exchange proposes to waive SQF
                                                                                                                  [FR Doc. 2015–21074 Filed 8–24–15; 8:45 am]             Port 3 Fees under certain circumstances
                                                    in the draft SRP to existing licenses and
                                                                                                                  BILLING CODE 7590–01–P                                  for NASDAQ members using the
                                                    regulatory approvals. Hence, the
                                                    issuance of a final SRP—even if                                                                                       NASDAQ Options Market (‘‘NOM’’),
                                                    considered guidance within the purview                                                                                NASDAQ’s facility for executing and
                                                    of the issue finality provisions in 10                        SECURITIES AND EXCHANGE                                 routing standardized equity and index
                                                    CFR part 52—would not need to be                              COMMISSION                                              options.
                                                    evaluated as if it were a backfit or as                       [Release No. 34–75739; File No. SR–                        The text of the proposed rule change
                                                    being inconsistent with issue finality                        NASDAQ–2015–101]                                        is available on the Exchange’s Web site
                                                    provisions. If, in the future, the NRC                                                                                at http://nasdaq.cchwallstreet.com, at
                                                    staff seeks to impose a position in the                       Self-Regulatory Organizations; The
                                                                                                                                                                          the principal office of the Exchange, and
                                                    SRP on holders of already issued                              NASDAQ Stock Market LLC; Notice of
                                                                                                                                                                          at the Commission’s Public Reference
                                                    licenses in a manner that does not                            Filing and Immediate Effectiveness of
                                                                                                                                                                          Room.
                                                    provide issue finality as described in the                    Proposed Rule Change To Amend
                                                    applicable issue finality provision, then                     Chapter XV, Section 3 Entitled
                                                                                                                                                                             3 SQF ports are ports that receive inbound quotes
                                                    the staff must make the showing as set                        ‘‘NASDAQ Options Market—Access
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                                                                          at any time within that month. The SQF Port allows
                                                    forth in the Backfit Rule or address the                      Services’’                                              a NOM Participant to access information such as
                                                    criteria for avoiding issue finality as                                                                               execution reports and other relevant data through
                                                                                                                  August 19, 2015.                                        a single feed. For example, this data would show
                                                    described in the applicable issue finality                       Pursuant to section 19(b)(1) of the                  which symbols are trading on NOM and the current
                                                    provision.                                                    Securities Exchange Act of 1934                         state of an options symbol (i.e., open for trading,
                                                       The NRC staff does not, at this time,                                                                              trading, halted or closed). Auction notifications and
                                                                                                                  (‘‘Act’’) 1 and Rule 19b–4 thereunder,2                 execution reports are also available. NOM Market
                                                    intend to impose the positions                                                                                        Makers rely on data available through the SQF Port
                                                    represented in the draft SRP sections in                        1 15   U.S.C. 78s(b)(1).                              to provide them the necessary information to
                                                    a manner that is inconsistent with any                          2 17   CFR 240.19b–4.                                 perform market making activities.



                                               VerDate Sep<11>2014     17:10 Aug 24, 2015    Jkt 235001    PO 00000     Frm 00085     Fmt 4703   Sfmt 4703   E:\FR\FM\25AUN1.SGM   25AUN1



Document Created: 2018-02-23 11:03:15
Document Modified: 2018-02-23 11:03:15
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionStandard review plan-draft section revision; request for comment.
DatesComments must be filed no later than October 26, 2015.
ContactMark Notich, telephone: 301-415-3053; email: [email protected] or Nishka Devaser, telephone: 301-415-5196; email: [email protected], both are staff of the Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555- 0001.
FR Citation80 FR 51614 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR