80_FR_52207 80 FR 52041 - West Valley Water District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

80 FR 52041 - West Valley Water District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 166 (August 27, 2015)

Page Range52041-52042
FR Document2015-21264

Federal Register, Volume 80 Issue 166 (Thursday, August 27, 2015)
[Federal Register Volume 80, Number 166 (Thursday, August 27, 2015)]
[Notices]
[Pages 52041-52042]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-21264]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD15-32-000]


West Valley Water District; Notice of Preliminary Determination 
of a Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On August 13, 2015, West Valley Water District filed a notice of 
intent to construct a qualifying conduit hydropower facility, pursuant 
to section 30 of the Federal Power Act (FPA), as amended by section 4 
of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The 
proposed Roemer Water Filtration Facility Hydroelectric Project would 
have an installed capacity of 484 kilowatts (kW) and would be located 
on the existing West Valley Water District's raw water 30-inch-diameter 
Lytle Creek Turnout pipe into the Roemer Water Filtration Facility. The 
project would be located near the City of Rialto in San Bernardino 
County, California.
    Applicant Contact: Thomas J. Crowley, West Valley Water District, 
855 W. Base Line Rd., Rialto, CA 92376, Phone No. (909) 820-3702.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A proposed 141-foot-long by 24-inch-
diameter supply pipe off the 30-inch diameter main pipeline; (2) a 
proposed 1,300 square foot prefabricated steel powerhouse containing 
two generating units with a total installed capacity of 484 kW; (3) a 
28-foot-long 24-inch-diameter exit pipe returning flow back into the 
Roemer Water Filtration Facility and the Cactus Groundwater Recharge 
Pipeline; and (4) appurtenant facilities. The proposed project would 
have an estimated annual generating capacity of 2,200 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
                                                                                                    Satisfies (Y/
              Statutory provision                                   Description                          N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA............  The conduit the facility uses a tunnel, canal,               Y
                                                  pipeline, aqueduct, flume, ditch, or similar
                                                  manmade water conveyance that is operated for
                                                  the distribution of water for agricultural,
                                                  municipal, or industrial consumption and not
                                                  primarily for the generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA.........  The facility is constructed, operated, or                    Y
                                                  maintained for the generation of electric power
                                                  and uses for such generation only the
                                                  hydroelectric potential of a non-federally owned
                                                  conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA........  The facility has an installed capacity that does             Y
                                                  not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA.......  On or before August 9, 2013, the facility is not             Y
                                                  licensed, or exempted from the licensing
                                                  requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2014).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference

[[Page 52042]]

to this application must be accompanied by proof of service on all 
persons listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD15-32-000) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email [email protected]. For TTY, 
call (202) 502-8659.

    Dated: August 21, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-21264 Filed 8-26-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                           Federal Register / Vol. 80, No. 166 / Thursday, August 27, 2015 / Notices                                               52041

                                                  The filings are accessible in the                    DEPARTMENT OF ENERGY                                       Applicant Contact: Thomas J.
                                               Commission’s eLibrary system by                                                                                  Crowley, West Valley Water District,
                                               clicking on the links or querying the                   Federal Energy Regulatory                                855 W. Base Line Rd., Rialto, CA 92376,
                                               docket number.                                          Commission                                               Phone No. (909) 820–3702.
                                                  Any person desiring to intervene or                  [Docket No. CD15–32–000]                                   FERC Contact: Robert Bell, Phone No.
                                               protest in any of the above proceedings                                                                          (202) 502–6062, email:
                                               must file in accordance with Rules 211                  West Valley Water District; Notice of                    robert.bell@ferc.gov.
                                                                                                       Preliminary Determination of a
                                               and 214 of the Commission’s                                                                                        Qualifying Conduit Hydropower
                                                                                                       Qualifying Conduit Hydropower
                                               Regulations (18 CFR 385.211 and                                                                                  Facility Description: The proposed
                                                                                                       Facility and Soliciting Comments and
                                               385.214) on or before 5:00 p.m. Eastern                 Motions To Intervene                                     project would consist of: (1) A proposed
                                               time on the specified comment date.                                                                              141-foot-long by 24-inch-diameter
                                               Protests may be considered, but                           On August 13, 2015, West Valley                        supply pipe off the 30-inch diameter
                                               intervention is necessary to become a                   Water District filed a notice of intent to               main pipeline; (2) a proposed 1,300
                                               party to the proceeding.                                construct a qualifying conduit                           square foot prefabricated steel
                                                                                                       hydropower facility, pursuant to section                 powerhouse containing two generating
                                                  eFiling is encouraged. More detailed                 30 of the Federal Power Act (FPA), as
                                               information relating to filing                                                                                   units with a total installed capacity of
                                                                                                       amended by section 4 of the                              484 kW; (3) a 28-foot-long 24-inch-
                                               requirements, interventions, protests,                  Hydropower Regulatory Efficiency Act
                                               service, and qualifying facilities filings                                                                       diameter exit pipe returning flow back
                                                                                                       of 2013 (HREA). The proposed Roemer
                                               can be found at: http://www.ferc.gov/                                                                            into the Roemer Water Filtration
                                                                                                       Water Filtration Facility Hydroelectric
                                               docs-filing/efiling/filing-req.pdf. For                                                                          Facility and the Cactus Groundwater
                                                                                                       Project would have an installed capacity
                                               other information, call (866) 208–3676                                                                           Recharge Pipeline; and (4) appurtenant
                                                                                                       of 484 kilowatts (kW) and would be
                                               (toll free). For TTY, call (202) 502–8659.              located on the existing West Valley                      facilities. The proposed project would
                                                                                                       Water District’s raw water 30-inch-                      have an estimated annual generating
                                                 Dated: August 21, 2015.                                                                                        capacity of 2,200 megawatt-hours.
                                                                                                       diameter Lytle Creek Turnout pipe into
                                               Nathaniel J. Davis, Sr.,
                                                                                                       the Roemer Water Filtration Facility.                      A qualifying conduit hydropower
                                               Deputy Secretary.                                       The project would be located near the                    facility is one that is determined or
                                               [FR Doc. 2015–21229 Filed 8–26–15; 8:45 am]             City of Rialto in San Bernardino County,                 deemed to meet all of the criteria shown
                                               BILLING CODE 6717–01–P                                  California.                                              in the table below.

                                                                                 TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                 Satisfies
                                                                 Statutory provision                                                              Description                                     (Y/N)

                                               FPA 30(a)(3)(A), as amended by HREA ..................        The conduit the facility uses a tunnel, canal, pipeline, aqueduct, flume,              Y
                                                                                                               ditch, or similar manmade water conveyance that is operated for the dis-
                                                                                                               tribution of water for agricultural, municipal, or industrial consumption and
                                                                                                               not primarily for the generation of electricity.
                                               FPA 30(a)(3)(C)(i), as amended by HREA ...............        The facility is constructed, operated, or maintained for the generation of             Y
                                                                                                               electric power and uses for such generation only the hydroelectric poten-
                                                                                                               tial of a non-federally owned conduit.
                                               FPA 30(a)(3)(C)(ii), as amended by HREA ..............        The facility has an installed capacity that does not exceed 5 megawatts ......         Y
                                               FPA 30(a)(3)(C)(iii), as amended by HREA .............        On or before August 9, 2013, the facility is not licensed, or exempted from            Y
                                                                                                               the licensing requirements of Part I of the FPA.



                                                 Preliminary Determination: Based                      deadline date for the particular                         facility meets the qualifying criteria
                                               upon the above criteria, Commission                     proceeding.                                              must set forth their evidentiary basis.
                                               staff preliminarily determines that the                    Filing and Service of Responsive                         The Commission strongly encourages
                                               proposal satisfies the requirements for a               Documents: All filings must (1) bear in                  electronic filing. Please file motions to
                                               qualifying conduit hydropower facility,                 all capital letters the ‘‘COMMENTS                       intervene and comments using the
                                               which is not required to be licensed or                 CONTESTING QUALIFICATION FOR A                           Commission’s eFiling system at http://
                                               exempted from licensing.                                                                                         www.ferc.gov/docs-filing/efiling.asp.
                                                                                                       CONDUIT HYDROPOWER FACILITY’’
                                                 Comments and Motions to Intervene:                    or ‘‘MOTION TO INTERVENE,’’ as                           Commenters can submit brief comments
                                               Deadline for filing comments contesting                                                                          up to 6,000 characters, without prior
                                                                                                       applicable; (2) state in the heading the
                                               whether the facility meets the qualifying                                                                        registration, using the eComment system
                                                                                                       name of the applicant and the project
                                               criteria is 45 days from the issuance                                                                            at http://www.ferc.gov/docs-filing/
                                                                                                       number of the application to which the
                                               date of this notice.                                                                                             ecomment.asp. You must include your
                                                                                                       filing responds; (3) state the name,                     name and contact information at the end
                                                 Deadline for filing motions to                        address, and telephone number of the                     of your comments. For assistance,
                                               intervene is 30 days from the issuance                  person filing; and (4) otherwise comply                  please contact FERC Online Support at
rmajette on DSK2VPTVN1PROD with NOTICES




                                               date of this notice.                                    with the requirements of sections                        FERCOnlineSupport@ferc.gov, (866)
                                                 Anyone may submit comments or a                       385.2001 through 385.2005 of the                         208–3676 (toll free), or (202) 502–8659
                                               motion to intervene in accordance with                  Commission’s regulations.1 All                           (TTY). In lieu of electronic filing, please
                                               the requirements of Rules of Practice                   comments contesting Commission staff’s                   send a paper copy to: Secretary, Federal
                                               and Procedure, 18 CFR 385.210 and                       preliminary determination that the                       Energy Regulatory Commission, 888
                                               385.214. Any motions to intervene must                                                                           First Street NE., Washington, DC 20426.
                                               be received on or before the specified                    1 18   CFR 385.2001–2005 (2014).                       A copy of all other filings in reference


                                          VerDate Sep<11>2014   15:08 Aug 26, 2015   Jkt 235001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\27AUN1.SGM    27AUN1


                                               52042                       Federal Register / Vol. 80, No. 166 / Thursday, August 27, 2015 / Notices

                                               to this application must be accompanied                 CFR 385.2001(a)(1)(iii) and the                       (202) 502–8371. This filing may also be
                                               by proof of service on all persons listed               instructions on the Commission’s Web                  viewed on the Commission’s Web site at
                                               in the service list prepared by the                     site at http://www.ferc.gov/docs-filing/              http://www.ferc.gov using the
                                               Commission in this proceeding, in                       efiling.asp. Commenters can submit                    ‘‘eLibrary’’ link. Enter the docket
                                               accordance with 18 CFR 4.34(b) and                      brief comments up to 6,000 characters,                number excluding the last three digits in
                                               385.2010.                                               without prior registration, using the                 the docket number field (P–10489–014)
                                                 Locations of Notice of Intent: Copies                 eComment system at http://                            to access the document. You may also
                                               of the notice of intent can be obtained                 www.ferc.gov/docs-filing/                             register online at http://www.ferc.gov/
                                               directly from the applicant or such                     ecomment.asp. You must include your                   docs-filing/esubscription.asp to be
                                               copies can be viewed and reproduced at                  name and contact information at the end               notified via email of new filings and
                                               the Commission in its Public Reference                  of your comments. For assistance,
                                                                                                                                                             issuances related to this or other
                                               Room, Room 2A, 888 First Street NE.,                    please contact FERC Online Support at
                                                                                                       FERCOnlineSupport@ferc.gov, or toll                   pending projects. A copy is also
                                               Washington, DC 20426. The filing may
                                                                                                       free at 1–866–208–3676, or for TTY,                   available for inspection and
                                               also be viewed on the web at http://
                                                                                                       (202) 502–8659. Although the                          reproduction at the address in item (h)
                                               www.ferc.gov/docs-filing/elibrary.asp
                                               using the ‘‘eLibrary’’ link. Enter the                  Commission strongly encourages                        above.
                                               docket number (e.g., CD15–32–000) in                    electronic filing, documents may be                      m. Individuals desiring to be included
                                               the docket number field to access the                   paper-filed. To paper-file, mail an                   on the Commission’s mailing list should
                                               document. For assistance, call toll-free                original and seven copies to: Secretary,              so indicate by writing to the Secretary
                                               1–866–208–3676 or email                                 Federal Energy Regulatory Commission,                 of the Commission.
                                               FERCOnlineSupport@ferc.gov. For TTY,                    888 First Street NE., Washington, DC
                                                                                                                                                                n. Comments, Protests, or Motions to
                                               call (202) 502–8659.                                    20426. Please include the project
                                                                                                       number (P–10489–014) on any                           Intervene: Anyone may submit
                                                 Dated: August 21, 2015.                                                                                     comments, a protest, or a motion to
                                                                                                       comments or motions filed.
                                               Kimberly D. Bose,                                          The Commission’s Rules of Practice                 intervene in accordance with the
                                               Secretary.                                              and Procedure require all intervenors                 requirements of Rules of Practice and
                                               [FR Doc. 2015–21264 Filed 8–26–15; 8:45 am]             filing documents with the Commission                  Procedure, 18 CFR 385.210, .211, and
                                               BILLING CODE 6717–01–P                                  to serve a copy of that document on                   .214, respectively. In determining the
                                                                                                       each person whose name appears on the                 appropriate action to take, the
                                                                                                       official service list for the project.                Commission will consider all protests or
                                               DEPARTMENT OF ENERGY                                    Further, if an intervenor files comments              other comments filed, but only those
                                                                                                       or documents with the Commission                      who file a motion to intervene in
                                               Federal Energy Regulatory                               relating to the merits of an issue that               accordance with the Commission’s
                                               Commission                                              may affect the responsibilities of a                  Rules may become a party to the
                                               [Project No. 10489–014]                                 particular resource agency, they must                 proceeding. Any comments, protests, or
                                                                                                       also serve a copy of the document on                  motions to intervene must be received
                                               City of River Falls, Wisconsin; Notice                  that resource agency.                                 on or before the specified comment date
                                               of Application Accepted for Filing,                        k. Description of Application: On
                                                                                                                                                             for the particular application.
                                               Soliciting Comments, Motions To                         September 27, 1988, the River Falls
                                               Intervene, and Protests                                 Project was issued a 30-year license that                o. Filing and Service of Documents:
                                                                                                       expires August 31, 2018. The licensee                 Any filing must (1) bear in all capital
                                                  Take notice that the following                       requests the Commission extend the                    letters the title ‘‘COMMENTS’’,
                                               hydroelectric application has been filed                term of the license for an additional 5               ‘‘PROTEST’’, or ‘‘MOTION TO
                                               with the Commission and is available                    years from August 31, 2018, to August                 INTERVENE’’ as applicable; (2) set forth
                                               for public inspection:                                  31, 2023. The City submitted its notice               in the heading the name of the applicant
                                                  a. Application Type: Extension of                    of intent to relicense the project and                and the project number of the
                                               license term.                                           pre-application document on November                  application to which the filing
                                                  b. Project No.: 10489–014.                           27, 2013 and a request to use the                     responds; (3) furnish the name, address,
                                                  c. Date Filed: July 6, 2015.                         traditional licensing process also on that            and telephone number of the person
                                                  d. Applicant: City of River Falls,                   date, which was granted by the                        commenting, protesting or intervening;
                                               Wisconsin.                                              Commission on January 27, 2014. Since                 and (4) otherwise comply with the
                                                  e. Name of Project: River Falls                      that time, the River Falls City Council
                                               Hydroelectric Project.                                                                                        requirements of 18 CFR 385.2001
                                                                                                       adopted resolutions that require a
                                                  f. Location: Kinnickinnic River in                                                                         through 385.2005. All comments,
                                                                                                       comprehensive river corridor planning
                                               Pierce County, Wisconsin.                                                                                     motions to intervene, or protests must
                                                                                                       process to determine whether to
                                                  g. Filed Pursuant to: Federal Power                  continue with the re-license or possibly              set forth their evidentiary basis. Any
                                               Act, 16 U.S.C. 791a–825r.                               surrender the project. The licensee                   filing made by an intervenor must be
                                                  h. Applicant Contact: Kevin                          states that it will be conducting                     accompanied by a proof of service on all
                                               Westhuis, City of River Falls, 222 Lewis                additional studies to evaluate the                    persons listed in the service list
                                               Street, River Falls, WI 54022, (715) 425–               potential for dam removal. The                        prepared by the Commission in this
                                               0906.                                                   development of further study plans is                 proceeding, in accordance with 18 CFR
                                                  i. FERC Contact: Rebecca Martin,                     expected to continue with stakeholders                385.2010.
rmajette on DSK2VPTVN1PROD with NOTICES




                                               (202) 502–6012, Rebecca.Martin@                         through 2017.                                           Dated: August 21, 2015.
                                               ferc.gov.                                                  l. Locations of the Application: A
                                                                                                                                                             Kimberly D. Bose,
                                                  j. Deadline for filing comments,                     copy of the application is available for
                                               motions to intervene, and protests:                     inspection and reproduction at the                    Secretary.
                                               September 21, 2015.                                     Commission’s Public Reference Room,                   [FR Doc. 2015–21265 Filed 8–26–15; 8:45 am]
                                                  All documents may be filed                           located at 888 First Street NE., Room                 BILLING CODE 6717–01–P
                                               electronically via the Internet. See, 18                2A, Washington, DC 20426, or by calling


                                          VerDate Sep<11>2014   15:08 Aug 26, 2015   Jkt 235001   PO 00000   Frm 00017   Fmt 4703   Sfmt 9990   E:\FR\FM\27AUN1.SGM   27AUN1



Document Created: 2015-12-15 10:53:21
Document Modified: 2015-12-15 10:53:21
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 52041 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR