80_FR_54955 80 FR 54779 - Texas Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Northern Supply Access Project and Request for Comments on Environmental Issues

80 FR 54779 - Texas Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Northern Supply Access Project and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 176 (September 11, 2015)

Page Range54779-54781
FR Document2015-22916

Federal Register, Volume 80 Issue 176 (Friday, September 11, 2015)
[Federal Register Volume 80, Number 176 (Friday, September 11, 2015)]
[Notices]
[Pages 54779-54781]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-22916]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-513-000]


Texas Gas Transmission, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Northern Supply Access 
Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Northern Supply Access Project 
(Project), which would involve construction and operation of facilities 
by Texas Gas Transmission, LLC (Texas Gas) in Ohio, Indiana, Kentucky, 
Tennessee, Mississippi, and Louisiana. The Commission will use this EA 
in its decision-making process to determine whether the Project is in 
the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the Project. You can make a difference by providing use 
with your specific comments or concerns about the Project. Your 
comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. Your input will help the Commission staff determine what 
issues need to be evaluated in the EA. To ensure that your comments are 
timely and properly recorded, please send your comments so that the 
Commission receives them in Washington, DC on or before October 5, 
2015.
    If you sent comments on this project to the Commission before the 
opening of this docket on June 5, 2015, you will need to file those 
comments in Docket No. CP15-513-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this Project. State and local government 
representatives should notify their constituents of this planned 
Project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the Project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement and the Project is approved, the pipeline company 
could initiate condemnation proceedings where compensation would be 
determined in accordance with state law.
    Texas Gas provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
Project docket number (CP15-513-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or efiling@ferc.gov. 
Please carefully follow these instruction so that your comments are 
properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Summary of the Planned Project

    Texas Gas proposes to construct, install, own, operate, and 
maintain the proposed Northern Supply Access Project, which (as 
described more fully below) would involve modifications at eight 
existing compressor stations along its existing pipeline and one new 
compressor station located in Ohio, Indiana, Kentucky, Tennessee, 
Mississippi, and Louisiana. The project is designed to provide an 
additional 384,000 million standard cubic feet of natural gas per day 
of north to south transportation capacity on Texas Gas's system while 
maintaining bi-directional flow capability on its system.
    Texas Gas proposes to modify seven existing compressor stations 
located in Lawrence and Dearborn Counties, Indiana; Webster, 
Breckinridge, and Jefferson Counties, Kentucky; Tipton County, 
Tennessee; and Coahoma County, Mississippi, by installing yard and 
station pipeline and various auxiliary facilities. Texas Gas also 
proposes to modify the existing Bastrop Compressor Station in Morehouse 
Parish, Louisiana by classifying four existing compressor units as 
back-up units (a total of 7,040 horsepower) and adding one new 9,688 
horsepower turbine compressor unit. The Project also includes the 
construction and operation of the new 23,877 horsepower Harrison 
Compressor Station in Hamilton County, Ohio.

[[Page 54780]]

    The general location of the Project facilities is shown in Appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 146 
acres of land. Following construction, Texas Gas would retain about 13 
acres to operate the new facilities, the remaining acreage would be 
restored and revert to former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This discovery process is referred to as ``scoping''. The 
main goal of the scoping process is to focus the analysis in the EA on 
the important environmental issues. By this notice, the Commission 
requests public comments on the scope of the issues to address in the 
EA. We will consider all filed comments during the preparation of the 
EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation and maintenance of the planned Project 
under these general headings:
     Geology and soils;
     water resources, fisheries, and wetlands;
     vegetation and wildlife, including migratory birds;
     endangered and threatened species;
     land use, including residential, commercial, and prime 
farmland uses;
     cultural resources;
     socioeconomics;
     air quality and noise;
     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
Project or portions of the Project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received durin ghte scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section of this notice, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues 
related to this Project to formally cooperate with us in the 
preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for Section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with applicable State Historic Preservation Offices (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the Project's potential effects on 
historic properties.\4\ We will define the Project-specific Area of 
Potential Effects (APE) in consultation with the SHPOs as the Project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under Section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes: federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for Project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the Project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed Project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (Appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the Project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP15-
513). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription that

[[Page 54781]]

allows you to keep track of all formal issuances and submittals in 
specific dockets. This can reduce the amount of time you spend 
researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

     Dated: September 4, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-22916 Filed 9-10-15; 8:45 pm]
 BILLING CODE 6717-01-P



                                                                           Federal Register / Vol. 80, No. 176 / Friday, September 11, 2015 / Notices                                            54779

                                               Minnesota, and prepared an                              will use to gather input from the public              efiling@ferc.gov. Please carefully follow
                                               environmental assessment (EA).                          and interested agencies on the Project.               these instruction so that your comments
                                                  In the EA, Commission staff analyze                  You can make a difference by providing                are properly recorded.
                                               the potential environmental effects of                  use with your specific comments or                       (1) You can file your comments
                                               licensing the project and conclude that                 concerns about the Project. Your                      electronically using the eComment
                                               licensing the project, with appropriate                 comments should focus on the potential                feature on the Commission’s Web site
                                               measures, would not constitute a major                  environmental effects, reasonable                     (www.ferc.gov) under the link to
                                               federal action significantly affecting the              alternatives, and measures to avoid or                Documents and Filings. This is an easy
                                               quality of the human environment.                       lessen environmental impacts. Your                    method for submitting brief, text-only
                                                  A copy of the EA is available for                    input will help the Commission staff                  comments on a project;
                                               review at the Commission in the Public                  determine what issues need to be
                                                                                                                                                                (2) You can file your comments
                                               Reference Room or may be viewed on                      evaluated in the EA. To ensure that your
                                                                                                       comments are timely and properly                      electronically using the eFiling feature
                                               the Commission’s Web site at                                                                                  on the Commission’s Web site
                                               www.ferc.gov using the ‘‘eLibrary’’ link.               recorded, please send your comments so
                                                                                                       that the Commission receives them in                  (www.ferc.gov) under the link to
                                               Enter the docket number, excluding the                                                                        Documents and Filings. With eFiling,
                                               last three digits, in the docket number                 Washington, DC on or before October 5,
                                                                                                       2015.                                                 you can provide comments in a variety
                                               field to access the document. For                                                                             of formats by attaching them as a file
                                               assistance, contact FERC Online                            If you sent comments on this project
                                                                                                       to the Commission before the opening of               with your submission. New eFiling
                                               Support at FERCOnlineSupport@                                                                                 users must first create an account by
                                               ferc.gov or toll-free number at 1–866–                  this docket on June 5, 2015, you will
                                                                                                       need to file those comments in Docket                 clicking on ‘‘eRegister.’’ If you are filing
                                               208–3676, or for TTY, 202–502–8659.                                                                           a comment on a particular project,
                                                  You may also register online at                      No. CP15–513–000 to ensure they are
                                                                                                       considered as part of this proceeding.                please select ‘‘Comment on a Filing’’ as
                                               www.ferc.gov/docs-filing/                                                                                     the filing type; or
                                               esubscription.asp to be notified via                       This notice is being sent to the
                                               email of new filings and issuances                      Commission’s current environmental                       (3) You can file a paper copy of your
                                               related to this or other pending projects.              mailing list for this Project. State and              comments by mailing them to the
                                               For assistance, contact FERC Online                     local government representatives should               following address: Kimberly D. Bose,
                                               Support.                                                notify their constituents of this planned             Secretary, Federal Energy Regulatory
                                                  For further information, please                      Project and encourage them to comment                 Commission, 888 First Street NE., Room
                                               contact Shana Murray by telephone at                    on their areas of concern.                            1A, Washington, DC 20426.
                                                                                                          If you are a landowner receiving this
                                               (202) 502–8333 or by email at                                                                                 Summary of the Planned Project
                                                                                                       notice, a pipeline company
                                               Shana.Murray@ferc.gov.
                                                                                                       representative may contact you about                     Texas Gas proposes to construct,
                                                 Dated: September 4, 2015.                             the acquisition of an easement to                     install, own, operate, and maintain the
                                               Kimberly D. Bose,                                       construct, operate, and maintain the                  proposed Northern Supply Access
                                               Secretary.                                              proposed facilities. The company would                Project, which (as described more fully
                                               [FR Doc. 2015–22918 Filed 9–10–15; 8:45 am]             seek to negotiate a mutually acceptable               below) would involve modifications at
                                               BILLING CODE 6717–01–P                                  agreement. However, if the Commission                 eight existing compressor stations along
                                                                                                       approves the Project, that approval                   its existing pipeline and one new
                                                                                                       conveys with it the right of eminent                  compressor station located in Ohio,
                                               DEPARTMENT OF ENERGY                                    domain. Therefore, if easement                        Indiana, Kentucky, Tennessee,
                                                                                                       negotiations fail to produce an                       Mississippi, and Louisiana. The project
                                               Federal Energy Regulatory                               agreement and the Project is approved,                is designed to provide an additional
                                               Commission                                              the pipeline company could initiate                   384,000 million standard cubic feet of
                                               [Docket No. CP15–513–000]                               condemnation proceedings where                        natural gas per day of north to south
                                                                                                       compensation would be determined in                   transportation capacity on Texas Gas’s
                                               Texas Gas Transmission, LLC; Notice                     accordance with state law.                            system while maintaining bi-directional
                                               of Intent To Prepare an Environmental                      Texas Gas provided landowners with                 flow capability on its system.
                                               Assessment for the Proposed Northern                    a fact sheet prepared by the FERC
                                                                                                       entitled ‘‘An Interstate Natural Gas                     Texas Gas proposes to modify seven
                                               Supply Access Project and Request for                                                                         existing compressor stations located in
                                               Comments on Environmental Issues                        Facility On My Land? What Do I Need
                                                                                                       To Know?’’ This fact sheet addresses a                Lawrence and Dearborn Counties,
                                                 The staff of the Federal Energy                       number of typically asked questions,                  Indiana; Webster, Breckinridge, and
                                               Regulatory Commission (FERC or                          including the use of eminent domain                   Jefferson Counties, Kentucky; Tipton
                                               Commission) will prepare an                             and how to participate in the                         County, Tennessee; and Coahoma
                                               environmental assessment (EA) that will                 Commission’s proceedings. It is also                  County, Mississippi, by installing yard
                                               discuss the environmental impacts of                    available for viewing on the FERC Web                 and station pipeline and various
                                               the Northern Supply Access Project                      site (www.ferc.gov).                                  auxiliary facilities. Texas Gas also
                                               (Project), which would involve                                                                                proposes to modify the existing Bastrop
                                               construction and operation of facilities                Public Participation                                  Compressor Station in Morehouse
                                               by Texas Gas Transmission, LLC (Texas                     For your convenience, there are three               Parish, Louisiana by classifying four
                                               Gas) in Ohio, Indiana, Kentucky,                        methods you can use to submit your                    existing compressor units as back-up
rmajette on DSK7SPTVN1PROD with NOTICES




                                               Tennessee, Mississippi, and Louisiana.                  comments to the Commission. In all                    units (a total of 7,040 horsepower) and
                                               The Commission will use this EA in its                  instances, please reference the Project               adding one new 9,688 horsepower
                                               decision-making process to determine                    docket number (CP15–513–000) with                     turbine compressor unit. The Project
                                               whether the Project is in the public                    your submission. The Commission                       also includes the construction and
                                               convenience and necessity.                              encourages electronic filing of                       operation of the new 23,877 horsepower
                                                 This notice announces the opening of                  comments and has expert staff available               Harrison Compressor Station in
                                               the scoping process the Commission                      to assist you at (202) 502–8258 or                    Hamilton County, Ohio.


                                          VerDate Sep<11>2014   15:14 Sep 10, 2015   Jkt 235001   PO 00000   Frm 00018   Fmt 4703   Sfmt 4703   E:\FR\FM\11SEN1.SGM   11SEN1


                                               54780                       Federal Register / Vol. 80, No. 176 / Friday, September 11, 2015 / Notices

                                                 The general location of the Project                   eLibrary. Depending on the comments                       interested parties; and local libraries
                                               facilities is shown in Appendix 1.1                     received durin ghte scoping process, we                   and newspapers. This list also includes
                                                                                                       may also publish and distribute the EA                    all affected landowners (as defined in
                                               Land Requirements for Construction
                                                                                                       to the public for an allotted comment                     the Commission’s regulations) who are
                                                 Construction of the proposed facilities               period. We will consider all comments                     potential right-of-way grantors, whose
                                               would disturb about 146 acres of land.                  on the EA before making our                               property may be used temporarily for
                                               Following construction, Texas Gas                       recommendations to the Commission.                        Project purposes, or who own homes
                                               would retain about 13 acres to operate                  To ensure we have the opportunity to                      within certain distances of aboveground
                                               the new facilities, the remaining acreage               consider and address your comments,                       facilities, and anyone who submits
                                               would be restored and revert to former                  please carefully follow the instructions                  comments on the Project. We will
                                               uses.                                                   in the Public Participation section of                    update the environmental mailing list as
                                                                                                       this notice, beginning on page 2.                         the analysis proceeds to ensure that we
                                               The EA Process                                            With this notice, we are asking                         send the information related to this
                                                  The National Environmental Policy                    agencies with jurisdiction by law and/                    environmental review to all individuals,
                                               Act (NEPA) requires the Commission to                   or special expertise with respect to the                  organizations, and government entities
                                               take into account the environmental                     environmental issues related to this                      interested in and/or potentially affected
                                               impacts that could result from an action                Project to formally cooperate with us in                  by the proposed Project.
                                               whenever it considers the issuance of a                 the preparation of the EA.3 Agencies                         If we publish and distribute the EA,
                                               Certificate of Public Convenience and                   that would like to request cooperating                    copies will be sent to the environmental
                                               Necessity. NEPA also requires us 2 to                   agency status should follow the                           mailing list for public review and
                                               discover and address concerns the                       instructions for filing comments                          comment. If you would prefer to receive
                                               public may have about proposals. This                   provided under the Public Participation                   a paper copy of the document instead of
                                               discovery process is referred to as                     section of this notice.                                   the CD version or would like to remove
                                               ‘‘scoping’’. The main goal of the scoping                                                                         your name from the mailing list, please
                                                                                                       Consultations Under Section 106 of the
                                               process is to focus the analysis in the                                                                           return the attached Information Request
                                                                                                       National Historic Preservation Act
                                               EA on the important environmental                                                                                 (Appendix 2).
                                               issues. By this notice, the Commission                     In accordance with the Advisory
                                                                                                       Council on Historic Preservation’s                        Becoming an Intervenor
                                               requests public comments on the scope
                                               of the issues to address in the EA. We                  implementing regulations for Section                         In addition to involvement in the EA
                                               will consider all filed comments during                 106 of the National Historic                              scoping process, you may want to
                                               the preparation of the EA.                              Preservation Act, we are using this                       become an ‘‘intervenor’’ which is an
                                                  In the EA we will discuss impacts that               notice to initiate consultation with                      official party to the Commission’s
                                               could occur as a result of the                          applicable State Historic Preservation                    proceeding. Intervenors play a more
                                               construction and operation and                          Offices (SHPO), and to solicit their                      formal role in the process and are able
                                               maintenance of the planned Project                      views and those of other government                       to file briefs, appear at hearings, and be
                                               under these general headings:                           agencies, interested Indian tribes, and                   heard by the courts if they choose to
                                                  • Geology and soils;                                 the public on the Project’s potential                     appeal the Commission’s final ruling.
                                                  • water resources, fisheries, and                    effects on historic properties.4 We will                  An intervenor formally participates in
                                               wetlands;                                               define the Project-specific Area of                       the proceeding by filing a request to
                                                  • vegetation and wildlife, including                 Potential Effects (APE) in consultation                   intervene. Instructions for becoming an
                                               migratory birds;                                        with the SHPOs as the Project develops.                   intervenor are in the ‘‘Document-less
                                                  • endangered and threatened species;                 On natural gas facility projects, the APE                 Intervention Guide’’ under the ‘‘e-filing’’
                                                  • land use, including residential,                   at a minimum encompasses all areas                        link on the Commission’s Web site.
                                               commercial, and prime farmland uses;                    subject to ground disturbance (examples                   Motions to intervene are more fully
                                                  • cultural resources;                                include construction right-of-way,                        described at http://www.ferc.gov/
                                                  • socioeconomics;                                    contractor/pipe storage yards,                            resources/guides/how-to/intervene.asp.
                                                  • air quality and noise;                             compressor stations, and access roads).
                                                                                                                                                                 Additional Information
                                                  • public safety; and                                 Our EA for this project will document
                                                  • cumulative impacts.                                our findings on the impacts on historic                      Additional information about the
                                                  We will also evaluate reasonable                     properties and summarize the status of                    Project is available from the
                                               alternatives to the proposed Project or                 consultations under Section 106.                          Commission’s Office of External Affairs,
                                               portions of the Project, and make                                                                                 at (866) 208–FERC, or on the FERC Web
                                                                                                       Environmental Mailing List                                site (www.ferc.gov) using the eLibrary
                                               recommendations on how to lessen or
                                               avoid impacts on the various resource                     The environmental mailing list                          link. Click on the eLibrary link, click on
                                               areas.                                                  includes: federal, state, and local                       ‘‘General Search’’ and enter the docket
                                                  The EA will present our independent                  government representatives and                            number, excluding the last three digits
                                               analysis of the issues. The EA will be                  agencies; elected officials;                              in the Docket Number field (i.e., CP15–
                                               available in the public record through                  environmental and public interest                         513). Be sure you have selected an
                                                                                                       groups; Native American Tribes; other                     appropriate date range. For assistance,
                                                 1 The appendices referenced in this notice will                                                                 please contact FERC Online Support at
                                               not appear in the Federal Register. Copies of             3 The Council on Environmental Quality
                                                                                                                                                                 FercOnlineSupport@ferc.gov or toll free
                                               appendices were sent to all those receiving this        regulations addressing cooperating agency
                                                                                                                                                                 at (866) 208–3676, or for TTY, contact
rmajette on DSK7SPTVN1PROD with NOTICES




                                               notice in the mail and are available at www.ferc.gov    responsibilities are at Title 40, Code of Federal
                                               using the link called ‘‘eLibrary’’ or from the          Regulations, Part 1501.6.                                 (202) 502–8659. The eLibrary link also
                                               Commission’s Public Reference Room, 888 First             4 The Advisory Council on Historic Preservation         provides access to the texts of formal
                                               Street NE., Washington, DC 20426, or call (202)         regulations are at Title 36, Code of Federal              documents issued by the Commission,
                                               502–8371. For instructions on connecting to             Regulations, Part 800. Those regulations define
                                               eLibrary, refer to the last page of this notice.
                                                                                                                                                                 such as orders, notices, and
                                                                                                       historic properties as any prehistoric or historic
                                                 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the            district, site, building, structure, or object included   rulemakings.
                                               environmental staff of the Commission’s Office of       in or eligible for inclusion in the National Register        In addition, the Commission offers a
                                               Energy Projects.                                        of Historic Places.                                       free service called eSubscription that


                                          VerDate Sep<11>2014   15:14 Sep 10, 2015   Jkt 235001   PO 00000   Frm 00019   Fmt 4703    Sfmt 4703   E:\FR\FM\11SEN1.SGM   11SEN1


                                                                           Federal Register / Vol. 80, No. 176 / Friday, September 11, 2015 / Notices                                                    54781

                                               allows you to keep track of all formal                     If you sent comments on this project               a comment on a particular project,
                                               issuances and submittals in specific                    to the Commission before the opening of               please select ‘‘Comment on a Filing’’ as
                                               dockets. This can reduce the amount of                  this docket on May 22, 2015, you will                 the filing type; or
                                               time you spend researching proceedings                  need to file those comments in Docket                   (3) You can file a paper copy of your
                                               by automatically providing you with                     No. CP15–498–000 to ensure they are                   comments by mailing them to the
                                               notification of these filings, document                 considered as part of this proceeding.                following address. Be sure to reference
                                               summaries, and direct links to the                         This notice is being sent to the                   the project docket number (CP15–498–
                                               documents. Go to www.ferc.gov/                          Commission’s current environmental                    000) with your submission:
                                               esubscribenow.htm.                                      mailing list for this project. State and              Kimberly D. Bose, Secretary, Federal
                                                  Finally, public meetings or site visits              local government representatives should                 Energy Regulatory Commission, 888
                                               will be posted on the Commission’s                      notify their constituents of this                       First Street NE., Room 1A,
                                               calendar located at www.ferc.gov/                       proposed project and encourage them to                  Washington, DC 20426.
                                               EventCalendar/EventsList.aspx along                     comment on their areas of concern.
                                                                                                          If you are a landowner receiving this              Summary of the Proposed Project
                                               with other related information.
                                                                                                       notice, a pipeline company                               Eastern Shore proposes to construct
                                                 Dated: September 4, 2015.                             representative may contact you about                  and operate 10.1 miles of new natural
                                               Kimberly D. Bose,                                       the acquisition of an easement to                     gas pipeline loops 1 in New Castle and
                                               Secretary.                                              construct, operate, and maintain the                  Kent County, Delaware, and modify its
                                               [FR Doc. 2015–22916 Filed 9–10–15; 8:45 pm]             proposed facilities. The company would                existing Bridgeville Compressor Station
                                               BILLING CODE 6717–01–P                                  seek to negotiate a mutually acceptable               in Sussex County, Delaware. According
                                                                                                       agreement. However, if the Commission                 to Eastern Shore, its project would
                                                                                                       approves the project, that approval                   increase the reliability of natural gas to
                                               DEPARTMENT OF ENERGY                                    conveys with it the right of eminent                  Eastern Shore’s existing customers
                                                                                                       domain. Therefore, if easement                        during high demand winter months; this
                                               Federal Energy Regulatory                               negotiations fail to produce an                       need was not fully met in 2014 and
                                               Commission                                              agreement, the pipeline company could                 2015 and resulted in gas service ‘‘brown
                                                                                                       initiate condemnation proceedings                     outs.’’
                                               [Docket No. CP15–498–000]                               where compensation would be                              The Eastern Shore System Reliability
                                                                                                       determined in accordance with state                   Project would consist of the following
                                               Eastern Shore Natural Gas Company;                      law.                                                  facilities:
                                               Notice of Intent To Prepare an                             Eastern Shore provided landowners                     • 2.5 miles of 16-inch-diameter
                                               Environmental Assessment For the                        with a fact sheet prepared by the FERC                looping pipeline in New Castle County;
                                               Proposed System Reliability Project                     entitled ‘‘An Interstate Natural Gas                     • pigging facilities 2 at the existing
                                               and Request for Comments on                             Facility on My Land? What Do I Need                   Glasgow Control Station in New Castle
                                               Environmental Issues                                    to Know?’’ This fact sheet addresses a                County;
                                                                                                       number of typically asked questions,                     • about 7.6 miles of 16-inch diameter
                                                  The staff of the Federal Energy                      including the use of eminent domain                   looping pipeline, one mainline valve
                                               Regulatory Commission (FERC or                          and how to participate in the                         assembly, pigging facilities, and one
                                               Commission) will prepare an                             Commission’s proceedings. It is also                  permanent access road in Kent County;
                                               environmental assessment (EA) that will                 available for viewing on the FERC Web                 and
                                               discuss the environmental impacts of                    site (www.ferc.gov).                                     • an additional 1,775 horsepower of
                                               the System Reliability Project involving                                                                      compression, a new operations control
                                               construction and operation of facilities                Public Participation
                                                                                                                                                             station, and one permanent access road
                                               by Eastern Shore Natural Gas Company                       For your convenience, there are three              at the existing Bridgeville Compressor
                                               (Eastern Shore) in Kent, New Castle, and                methods you can use to submit your                    Station in Sussex County.
                                               Sussex Counties, Delaware. The                          comments to the Commission. The                          The general location of the project
                                               Commission will use this EA in its                      Commission encourages electronic filing               facilities is shown in appendix 1.3
                                               decision-making process to determine                    of comments and has expert staff
                                               whether the project is in the public                    available to assist you at (202) 502–8258             Land Requirements for Construction
                                               convenience and necessity.                              or efiling@ferc.gov. Please carefully                   Construction of the proposed facilities
                                                  This notice announces the opening of                 follow these instructions so that your                would disturb about 156.7 acres of land
                                               the scoping process the Commission                      comments are properly recorded.                       for the aboveground facilities and the
                                               will use to gather input from the public                   (1) You can file your comments                     pipeline. Following construction,
                                               and interested agencies on the project.                 electronically using the eComment                     Eastern Shore would maintain about
                                               You can make a difference by providing                  feature on the Commission’s Web site
                                               us with your specific comments or                       (www.ferc.gov) under the link to                         1 A pipeline loop is a segment of pipe constructed

                                               concerns about the project. Your                        Documents and Filings. This is an easy                parallel to an existing pipeline to increase capacity.
                                                                                                                                                                2 A ‘‘pig’’ is a tool that the pipeline company
                                               comments should focus on the potential                  method for submitting brief, text-only                inserts into and pushes through the pipeline for
                                               environmental effects, reasonable                       comments on a project;                                cleaning the pipeline, conducting internal
                                               alternatives, and measures to avoid or                     (2) You can file your comments                     inspections, or other purposes. A pipeline loop is
                                               lessen environmental impacts. Your                      electronically by using the eFiling                   a segment of pipe constructed parallel to an existing
                                               input will help the Commission staff                    feature on the Commission’s Web site                  pipeline to increase capacity.
rmajette on DSK7SPTVN1PROD with NOTICES




                                                                                                                                                                3 The appendices referenced in this notice will
                                               determine what issues they need to                      (www.ferc.gov) under the link to                      not appear in the Federal Register. Copies of
                                               evaluate in the EA. To ensure that your                 Documents and Filings. With eFiling,                  appendices were sent to all those receiving this
                                               comments are timely and properly                        you can provide comments in a variety                 notice in the mail and are available at www.ferc.gov
                                               recorded, please send your comments so                  of formats by attaching them as a file                using the link called ‘‘eLibrary’’ or from the
                                                                                                                                                             Commission’s Public Reference Room, 888 First
                                               that the Commission receives them in                    with your submission. New eFiling                     Street NE., Washington, DC 20426, or call (202)
                                               Washington, DC on or before October 5,                  users must first create an account by                 502–8371. For instructions on connecting to
                                               2015.                                                   clicking on ‘‘eRegister.’’ If you are filing          eLibrary, refer to the last page of this notice.



                                          VerDate Sep<11>2014   15:14 Sep 10, 2015   Jkt 235001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\11SEN1.SGM   11SEN1



Document Created: 2015-12-15 10:00:13
Document Modified: 2015-12-15 10:00:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 54779 