80_FR_57990 80 FR 57804 - City of Cheyenne, Wyoming; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

80 FR 57804 - City of Cheyenne, Wyoming; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 186 (September 25, 2015)

Page Range57804-57805
FR Document2015-24375

Federal Register, Volume 80 Issue 186 (Friday, September 25, 2015)
[Federal Register Volume 80, Number 186 (Friday, September 25, 2015)]
[Notices]
[Pages 57804-57805]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-24375]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD15-33-000]


City of Cheyenne, Wyoming; Notice of Preliminary Determination of 
a Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On August 26, 2015, the City of Cheyenne, Wyoming, by and through 
its Board of Public Utilities, filed a notice of intent to construct a 
qualifying conduit hydropower facility, pursuant to section 30 of the 
Federal Power Act (FPA), as amended by section 4 of the Hydropower 
Regulatory Efficiency Act of 2013 (HREA). The proposed Sherard 
Hydroelectric Generation Facility would have an installed capacity of 
950 kilowatts (kW), and would be located along an existing 48-inch-
diameter raw water pipeline within the city's water treatment plant. 
The project would be located near the City of Cheyenne, Wyoming.
    Applicant Contact: Tim Wilson, Director, 2416 Snyder Ave., 
Cheyenne, WY 82001, Phone No. (307) 637-6460.
    FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A proposed two-level powerhouse 
approximately 36 feet by 36 feet adjacent to the existing water 
treatment plant building; (2) an approximately 800-foot-long, up to 48-
inch-diameter penstock teeing off the existing 48-inch-diameter raw 
water pipeline; (3) one impulse turbine/generator unit with an 
installed capacity of 950 kilowatt (kW); (4) a short discharge 
returning water to the existing 48-inch-diameter raw water pipeline; 
and (5) appurtenant facilities.
    The proposed project would have a total installed capacity of 950 
kW.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

[[Page 57805]]



      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
                                                              Satisfies
     Statutory provision                Description             (Y/N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended    The conduit the facility      Y
 by HREA.                       uses is a tunnel, canal,
                                pipeline, aqueduct, flume,
                                ditch, or similar manmade
                                water conveyance that is
                                operated for the
                                distribution of water for
                                agricultural, municipal, or
                                industrial consumption and
                                not primarily for the
                                generation of electricity.
FPA 30(a)(3)(C)(i), as         The facility is constructed,  Y
 amended by HREA.               operated, or maintained for
                                the generation of electric
                                power and uses for such
                                generation only the
                                hydroelectric potential of
                                a non-federally owned
                                conduit.
FPA 30(a)(3)(C)(ii), as        The facility has an           Y
 amended by HREA.               installed capacity that
                                does not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as       On or before August 9, 2013,  Y
 amended by HREA.               the facility is not
                                licensed, or exempted from
                                the licensing requirements
                                of Part I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2015).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the Web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (i.e., CD15-33) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email [email protected]. For TTY, call 
(202) 502-8659.

    Dated: September 3, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-24375 Filed 9-24-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                  57804                       Federal Register / Vol. 80, No. 186 / Friday, September 25, 2015 / Notices

                                                  also register online at http://                         DEPARTMENT OF ENERGY                                    Dated: September 21, 2015.
                                                  www.ferc.gov/docs-filing/                                                                                     Nathaniel J. Davis, Sr.,
                                                  esubscription.asp to be notified via                    Federal Energy Regulatory                             Deputy Secretary.
                                                  email of new filings and issuances                      Commission                                            [FR Doc. 2015–24371 Filed 9–24–15; 8:45 am]
                                                  related to this or other pending projects.                                                                    BILLING CODE 6717–01–P
                                                                                                          Combined Notice of Filings #2
                                                  For assistance, call 1–866–208–3676 or
                                                  email FERCOnlineSupport@ferc.gov, for                   September 21, 2015.
                                                  TTY, call (202) 502–8659. A copy is also                   Take notice that the Commission                    DEPARTMENT OF ENERGY
                                                  available for inspection and                            received the following electric rate
                                                  reproduction at the address in item (h)                                                                       Federal Energy Regulatory
                                                                                                          filings:                                              Commission
                                                  above.
                                                                                                             Docket Numbers: ER15–2678–000.
                                                     m. Individuals desiring to be included                                                                     [Docket No. CD15–33–000]
                                                                                                             Applicants: NorthWestern
                                                  on the Commission’s mailing list should                 Corporation.                                          City of Cheyenne, Wyoming; Notice of
                                                  so indicate by writing to the Secretary                    Description: Initial rate filing: Rate             Preliminary Determination of a
                                                  of the Commission.                                      Schedule FERC No. 38–SD—                              Qualifying Conduit Hydropower
                                                     n. Comments, Protests, or Motions to                 Agreements with Western Area Power                    Facility and Soliciting Comments and
                                                  Intervene: Anyone may submit                            Administration to be effective                        Motions To Intervene
                                                  comments, a protest, or a motion to                     9/22/2015.
                                                  intervene in accordance with the                           Filed Date: 9/21/15.                                  On August 26, 2015, the City of
                                                  requirements of Rules of Practice and                                                                         Cheyenne, Wyoming, by and through its
                                                                                                             Accession Number: 20150921–5097.
                                                  Procedure, 18 CFR 385.210, .211, .214.                                                                        Board of Public Utilities, filed a notice
                                                                                                             Comments Due: 5 p.m. ET 10/13/15.                  of intent to construct a qualifying
                                                  In determining the appropriate action to
                                                                                                             Docket Numbers: ER15–2679–000.                     conduit hydropower facility, pursuant
                                                  take, the Commission will consider all
                                                                                                             Applicants: Latigo Wind Park, LLC.                 to section 30 of the Federal Power Act
                                                  protests or other comments filed, but
                                                                                                             Description: Baseline eTariff Filing:              (FPA), as amended by section 4 of the
                                                  only those who file a motion to
                                                                                                          Latigo Wind Park, LLC MBR Tariff to be                Hydropower Regulatory Efficiency Act
                                                  intervene in accordance with the                                                                              of 2013 (HREA). The proposed Sherard
                                                  Commission’s Rules may become a                         effective 11/15/2015.
                                                                                                             Filed Date: 9/21/15.                               Hydroelectric Generation Facility would
                                                  party to the proceeding. Any comments,                                                                        have an installed capacity of 950
                                                  protests, or motions to intervene must                     Accession Number: 20150921–5133.
                                                                                                                                                                kilowatts (kW), and would be located
                                                  be received on or before the specified                     Comments Due: 5 p.m. ET 10/13/15.
                                                                                                                                                                along an existing 48-inch-diameter raw
                                                  comment date for the particular                            Docket Numbers: ER15–2680–000.                     water pipeline within the city’s water
                                                  application.                                               Applicants: Sandstone Solar LLC.                   treatment plant. The project would be
                                                     o. Filing and Service of Responsive                     Description: Baseline eTariff Filing:              located near the City of Cheyenne,
                                                  Documents: All filings must bear in all                 Sandstone Solar LLC MBR Tariff to be                  Wyoming.
                                                  capital letters the title ‘‘COMMENTS’’,                 effective 11/1/2015.                                     Applicant Contact: Tim Wilson,
                                                  ‘‘PROTESTS’’, AND ‘‘MOTIONS TO                             Filed Date: 9/21/15.                               Director, 2416 Snyder Ave., Cheyenne,
                                                  INTERVENE’’, as applicable, and the                        Accession Number: 20150921–5161.                   WY 82001, Phone No. (307) 637–6460.
                                                  Docket Number of the particular                            Comments Due: 5 p.m. ET 10/13/15.                     FERC Contact: Christopher Chaney,
                                                  application to which the filing refers. A                                                                     Phone No. (202) 502–6778, email:
                                                                                                             The filings are accessible in the                  christopher.chaney@ferc.gov.
                                                  copy of any Motion to Intervene must
                                                                                                          Commission’s eLibrary system by                          Qualifying Conduit Hydropower
                                                  also be served upon each representative
                                                                                                          clicking on the links or querying the                 Facility Description: The proposed
                                                  of the Applicant specified in the                       docket number.
                                                  particular application.                                                                                       project would consist of: (1) A proposed
                                                                                                             Any person desiring to intervene or                two-level powerhouse approximately 36
                                                     p. Agency Comments: Federal, state,                  protest in any of the above proceedings               feet by 36 feet adjacent to the existing
                                                  and local agencies are invited to file                  must file in accordance with Rules 211                water treatment plant building; (2) an
                                                  comments on the described application.                  and 214 of the Commission’s                           approximately 800-foot-long, up to 48-
                                                  A copy of the application may be                        Regulations (18 CFR 385.211 and                       inch-diameter penstock teeing off the
                                                  obtained by agencies directly from the                  385.214) on or before 5:00 p.m. Eastern               existing 48-inch-diameter raw water
                                                  Applicant. If an agency does not file                   time on the specified comment date.                   pipeline; (3) one impulse turbine/
                                                  comments within the time specified for                  Protests may be considered, but                       generator unit with an installed capacity
                                                  filing comments, it will be presumed to                 intervention is necessary to become a                 of 950 kilowatt (kW); (4) a short
                                                  have no comments. One copy of an                        party to the proceeding.                              discharge returning water to the existing
                                                  agency’s comments must also be sent to                     eFiling is encouraged. More detailed               48-inch-diameter raw water pipeline;
                                                  the Applicant’s representatives.                        information relating to filing                        and (5) appurtenant facilities.
                                                    Dated: September 3, 2015.                             requirements, interventions, protests,                   The proposed project would have a
                                                                                                          service, and qualifying facilities filings            total installed capacity of 950 kW.
                                                  Nathaniel J. Davis, Sr.,
                                                                                                          can be found at: http://www.ferc.gov/                    A qualifying conduit hydropower
                                                  Deputy Secretary.                                       docs-filing/efiling/filing-req.pdf. For               facility is one that is determined or
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  [FR Doc. 2015–24376 Filed 9–24–15; 8:45 am]             other information, call (866) 208–3676                deemed to meet all of the criteria shown
                                                  BILLING CODE 6717–01–P                                  (toll free). For TTY, call (202) 502–8659.            in the table below.




                                             VerDate Sep<11>2014   19:58 Sep 24, 2015   Jkt 235001   PO 00000   Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\25SEN1.SGM   25SEN1


                                                                               Federal Register / Vol. 80, No. 186 / Friday, September 25, 2015 / Notices                                                   57805

                                                                                       TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                           Satisfies
                                                                  Statutory provision                                                               Description                                             (Y/N)

                                                  FPA 30(a)(3)(A), as amended by HREA .....             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or            Y
                                                                                                          similar manmade water conveyance that is operated for the distribution of water for
                                                                                                          agricultural, municipal, or industrial consumption and not primarily for the generation
                                                                                                          of electricity.
                                                  FPA 30(a)(3)(C)(i), as amended by HREA ..             The facility is constructed, operated, or maintained for the generation of electric power         Y
                                                                                                          and uses for such generation only the hydroelectric potential of a non-federally
                                                                                                          owned conduit.
                                                  FPA 30(a)(3)(C)(ii), as amended by HREA               The facility has an installed capacity that does not exceed 5 megawatts .......................   Y
                                                  FPA 30(a)(3)(C)(iii), as amended by HREA              On or before August 9, 2013, the facility is not licensed, or exempted from the licens-           Y
                                                                                                          ing requirements of Part I of the FPA.



                                                     Preliminary Determination: Based                      ecomment.asp. You must include your                    Products (KEP) informed the
                                                  upon the above criteria, Commission                      name and contact information at the end                Commission that the exemption from
                                                  staff preliminarily determines that the                  of your comments. For assistance,                      licensing for the Sygitowicz Creek
                                                  proposal satisfies the requirements for a                please contact FERC Online Support at                  Power Project, FERC No. 5069,
                                                  qualifying conduit hydropower facility,                  FERCOnlineSupport@ferc.gov, (866)                      originally issued July 14, 1982,1 has
                                                  which is not required to be licensed or                  208–3676 (toll free), or (202) 502–8659                been transferred to Kingdom Energy
                                                  exempted from licensing.                                 (TTY). In lieu of electronic filing, please            Products. The project is located on the
                                                     Comments and Motions to Intervene:                    send a paper copy to: Secretary, Federal               Sygitowicz Creek, Whatcom County,
                                                  Deadline for filing comments contesting                  Energy Regulatory Commission, 888                      Washington. The transfer of an
                                                  whether the facility meets the qualifying                First Street NE., Washington, DC 20426.                exemption does not require Commission
                                                  criteria is 45 days from the issuance                    A copy of all other filings in reference               approval.
                                                  date of this notice.                                     to this application must be accompanied                   2. Kingdom Energy Products is now
                                                     Deadline for filing motions to                        by proof of service on all persons listed              the exemptee of the Sygitowicz Creek
                                                  intervene is 30 days from the issuance                   in the service list prepared by the                    Power Project, FERC No. 5069. All
                                                  date of this notice.                                     Commission in this proceeding, in                      correspondence should be forwarded to:
                                                     Anyone may submit comments or a                       accordance with 18 CFR 4.34(b) and                     Mr. Alan Van Hook, Kingdom Energy
                                                  motion to intervene in accordance with                   385.2010.                                              Products, Box 557, Klawock, AK 99925.
                                                  the requirements of Rules of Practice                      Locations of Notice of Intent: Copies                  Dated: September 3, 2015.
                                                  and Procedure, 18 CFR 385.210 and                        of the notice of intent can be obtained
                                                  385.214. Any motions to intervene must                                                                          Nathaniel J. Davis, Sr.,
                                                                                                           directly from the applicant or such                    Deputy Secretary.
                                                  be received on or before the specified                   copies can be viewed and reproduced at
                                                  deadline date for the particular                                                                                [FR Doc. 2015–24383 Filed 9–24–15; 8:45 am]
                                                                                                           the Commission in its Public Reference
                                                  proceeding.                                              Room, Room 2A, 888 First Street NE.,
                                                                                                                                                                  BILLING CODE 6717–01–P
                                                     Filing and Service of Responsive
                                                                                                           Washington, DC 20426. The filing may
                                                  Documents: All filings must (1) bear in
                                                                                                           also be viewed on the Web at http://                   DEPARTMENT OF ENERGY
                                                  all capital letters the ‘‘COMMENTS
                                                                                                           www.ferc.gov/docs-filing/elibrary.asp
                                                  CONTESTING QUALIFICATION FOR A
                                                                                                           using the ‘‘eLibrary’’ link. Enter the                 Federal Energy Regulatory
                                                  CONDUIT HYDROPOWER FACILITY’’
                                                                                                           docket number (i.e., CD15–33) in the                   Commission
                                                  or ‘‘MOTION TO INTERVENE,’’ as
                                                                                                           docket number field to access the
                                                  applicable; (2) state in the heading the                                                                        [Docket No. RM98–1–000]
                                                                                                           document. For assistance, call toll-free
                                                  name of the applicant and the project
                                                                                                           1–866–208–3676 or email                                Records Governing Off-the-Record
                                                  number of the application to which the
                                                                                                           FERCOnlineSupport@ferc.gov. For TTY,                   Communications; Public Notice
                                                  filing responds; (3) state the name,
                                                                                                           call (202) 502–8659.
                                                  address, and telephone number of the                                                                              This constitutes notice, in accordance
                                                  person filing; and (4) otherwise comply                    Dated: September 3, 2015.
                                                                                                                                                                  with 18 CFR 385.2201(b), of the receipt
                                                  with the requirements of sections                        Nathaniel J. Davis, Sr.,
                                                                                                                                                                  of prohibited and exempt off-the-record
                                                  385.2001 through 385.2005 of the                         Deputy Secretary.                                      communications. Order No. 607 (64 FR
                                                  Commission’s regulations.1 All                           [FR Doc. 2015–24375 Filed 9–24–15; 8:45 am]            51222, September 22, 1999) requires
                                                  comments contesting Commission staff’s                   BILLING CODE 6717–01–P                                 Commission decisional employees, who
                                                  preliminary determination that the                                                                              make or receive a prohibited or exempt
                                                  facility meets the qualifying criteria                                                                          off-the-record communication relevant
                                                  must set forth their evidentiary basis.                  DEPARTMENT OF ENERGY                                   to the merits of a contested proceeding,
                                                     The Commission strongly encourages
                                                                                                                                                                  to deliver to the Secretary of the
                                                  electronic filing. Please file motions to                Federal Energy Regulatory
                                                                                                                                                                  Commission, a copy of the
                                                  intervene and comments using the                         Commission
                                                                                                                                                                  communication, if written, or a
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Commission’s eFiling system at http://                   [Project No. 5069–011]                                 summary of the substance of any oral
                                                  www.ferc.gov/docs-filing/efiling.asp.
                                                                                                                                                                  communication.
                                                  Commenters can submit brief comments                     Cascade Clean Energy, Inc.; Kingdom                      Prohibited communications are
                                                  up to 6,000 characters, without prior                    Energy Products; Notice of Transfer of                 included in a public, non-decisional file
                                                  registration, using the eComment system                  Exemption
                                                  at http://www.ferc.gov/docs-filing/                                                                               1 20 FERC ¶ 62,051, Order Granting Exemption
                                                                                                            1. By letter filed August 19, 2015,                   From Licensing of a Small Hydroelectric Project of
                                                    1 18   CFR 385.2001–2005 (2015).                       Neva Van Hook, d/b/a Kingdom Energy                    5 Megawatts or Less (1982).



                                             VerDate Sep<11>2014    19:58 Sep 24, 2015   Jkt 235001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\25SEN1.SGM   25SEN1



Document Created: 2018-02-26 10:19:26
Document Modified: 2018-02-26 10:19:26
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 57804 

2025 Federal Register | Disclaimer | Privacy Policy