The U.S. Nuclear Regulatory Commission (NRC) has issued renewed facility operating licenses Nos. DPR-77 and DPR-79 to Tennessee Valley Authority, the operator of the Sequoyah Nuclear Plant, Units 1 and 2 (SQN). Renewed facility operating licenses Nos. DPR-77 and DPR-79 authorize operation of SQN by the licensee at reactor core power levels not in excess of 3455 megawatts thermal, in accordance with the provisions of the SQN renewed licenses and technical specifications. In addition, the NRC has prepared a record of decision (ROD) that supports the NRC's decision to renew facility operating licenses Nos. DPR-77 and DPR-79.

Federal Register, Volume 80 Issue 191 (Friday, October 2, 2015)
[Federal Register Volume 80, Number 191 (Friday, October 2, 2015)]
[Notices]
[Pages 59831-59832]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-25128]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-327 and 50-328; NRC-2013-0037]


License Renewal for Sequoyah Nuclear Plant, Units 1 and 2

AGENCY: Nuclear Regulatory Commission.

ACTION: License renewal and record of decision; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued 
renewed facility operating licenses Nos. DPR-77 and DPR-79 to Tennessee 
Valley Authority, the operator of the Sequoyah Nuclear Plant, Units 1 
and 2 (SQN). Renewed facility operating licenses Nos. DPR-77 and DPR-79 
authorize operation of SQN by the licensee at reactor core power levels 
not in excess of 3455 megawatts thermal, in accordance with the 
provisions of the SQN renewed licenses and technical specifications. In 
addition, the NRC has prepared a record of decision (ROD) that supports 
the NRC's decision to renew facility operating licenses Nos. DPR-77 and 
DPR-79.

DATES: The license renewal of facility operating licenses Nos. DPR-77 
and DPR-79 were effective on September 28, 2015.

ADDRESSES: Please refer to Docket ID NRC-2013-0037 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2013-0037. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if that document 
is available in ADAMS) is provided the first time that a document is 
referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Emmanuel Sayoc, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555; telephone: 301-415-4084; email: [email protected].

SUPPLEMENTARY INFORMATION: Notice is hereby given that the NRC has 
issued renewed facility operating licenses Nos. DPR-77 and DPR-79 to 
Tennessee Valley Authority, the operator of SQN. Renewed facility 
operating licenses Nos. DPR-77 and DPR-79 authorize operation of SQN by 
the licensee at reactor core power levels not in excess of 3455 
megawatts thermal, in accordance with the provisions of the SQN renewed 
licenses and technical specifications. The NRC's ROD that supports the 
NRC's decision to renew facility operating licenses Nos. DPR-77 and 
DPR-79 is available in ADAMS under Accession No. ML15104A689. As 
discussed in the ROD and the final supplemental environmental impact 
statement (FSEIS) for SQN, Supplement

[[Page 59832]]

53 to NUREG-1437, ``Generic Environmental Impact Statement for License 
Renewal of Nuclear Plants Regarding Sequoyah Nuclear Plant, Units 1 and 
2,'' dated March 2015 (ADAMS Accession No. ML15075A438), the NRC has 
considered a range of reasonable alternatives that included natural gas 
combined-cycle, supercritical pulverized coal, new nuclear, wind and 
solar power, and the no action alternative. The ROD and FSEIS document 
the NRC's determination in its environmental review that the adverse 
environmental impacts of license renewal for SQN are not so great that 
preserving the option of license renewal for energy planning decision 
makers would be unreasonable.
    SQN is a dual pressurized water reactor nuclear steam supply 
system, with four coolant loops for each unit, and located 
approximately 9.5 miles northeast of Chattanooga, Tennessee. The 
application for the renewed license, ``Sequoyah Nuclear Plant, Units 1 
and 2, License Renewal Application,'' dated January 7, 2013 (ADAMS 
Accession No. ML130240007), as supplemented by letters dated through 
August 17, 2015, complied with the standards and requirements of the 
Atomic Energy Act of 1954, as amended (the Act), and the NRC's 
regulations. As required by the Act and the NRC's regulations in 
Chapter 1 of Title 10 of the Code of Federal Regulations, the NRC has 
made appropriate findings, which are set forth in the license. A public 
notice of acceptance for docketing of the application and an 
opportunity for a hearing was published in the Federal Register on 
March 5, 2013 (78 FR 14362).
    For further details with respect to this action, see: (1) Tennessee 
Valley Authority license renewal application for Sequoyah Nuclear 
Plant, Units 1 and 2, dated January 7, 2013, as supplemented by letters 
dated through August 17, 2017; (2) the NRC's safety evaluation report 
published in January 2015 (ADAMS Accession No. ML15021A356); (3) the 
NRC's final environmental impact statement (NUREG-1437, Supplement 53) 
for Sequoyah Nuclear Plant, Units 1 and 2, published in March 2015; and 
(4) the NRC's ROD.

    Dated at Rockville, Maryland, this 28th day of September, 2015.

    For the Nuclear Regulatory Commission.
Christopher G. Miller,
Director, Division of License Renewal, Office of Nuclear Reactor 
Regulation.
[FR Doc. 2015-25128 Filed 10-1-15; 8:45 am]
 BILLING CODE 7590-01-P



                                                                                 Federal Register / Vol. 80, No. 191 / Friday, October 2, 2015 / Notices                                         59831

                                                  If you would like to be added to the                    published in the Federal Register on                  DPR–79 were effective on September 28,
                                                  distribution, please contact the Nuclear                October 1, 2014, (79 FR 59307).                       2015.
                                                  Regulatory Commission, Office of the                       Detailed meeting agendas and meeting               ADDRESSES: Please refer to Docket ID
                                                  Secretary, Washington, DC 20555 (301–                   transcripts are available on the NRC                  NRC–2013–0037 when contacting the
                                                  415–1969), or email                                     Web site at http://www.nrc.gov/reading-               NRC about the availability of
                                                  Brenda.Akstulewicz@nrc.gov or                           rm/doc-collections/acrs. Information                  information regarding this document.
                                                  Patricia.Jimenez@nrc.gov.                               regarding topics to be discussed,                     You may obtain publicly-available
                                                    Dated: September 30, 2015.                            changes to the agenda, whether the                    information related to this document
                                                                                                          meeting has been canceled or                          using any of the following methods:
                                                  Glenn Ellmers,
                                                  Policy Coordinator, Office of the Secretary.
                                                                                                          rescheduled, and the time allotted to                    • Federal Rulemaking Web site: Go to
                                                                                                          present oral statements can be obtained               http://www.regulations.gov and search
                                                  [FR Doc. 2015–25312 Filed 9–30–15; 4:15 pm]             from the Web site cited above or by                   for Docket ID NRC–2013–0037. Address
                                                  BILLING CODE 7590–01–P                                  contacting the identified DFO.                        questions about NRC dockets to Carol
                                                                                                          Moreover, in view of the possibility that             Gallagher; telephone: 301–415–3463;
                                                                                                          the schedule for ACRS meetings may be                 email: Carol.Gallagher@nrc.gov. For
                                                  NUCLEAR REGULATORY                                      adjusted by the Chairman as necessary
                                                  COMMISSION                                                                                                    technical questions, contact the
                                                                                                          to facilitate the conduct of the meeting,             individual listed in the FOR FURTHER
                                                  Advisory Committee on Reactor                           persons planning to attend should check               INFORMATION CONTACT section of this
                                                  Safeguards; Meeting of the ACRS                         with these references if such                         document.
                                                  Subcommittee on Future Plant                            rescheduling would result in a major                     • NRC’s Agencywide Documents
                                                  Designs; Notice of Meeting                              inconvenience.                                        Access and Management System
                                                                                                             If attending this meeting, please enter            (ADAMS): You may obtain publicly-
                                                     The ACRS Subcommittee on Future                      through the One White Flint North                     available documents online in the
                                                  Plant Designs will hold a meeting on                    building, 11555 Rockville Pike,                       ADAMS Public Documents collection at
                                                  October 7, 2015, Room T–2B1, 11545                      Rockville, MD. After registering with                 http://www.nrc.gov/reading-rm/
                                                  Rockville Pike, Rockville, Maryland.                    security, please contact Mr. Theron                   adams.html. To begin the search, select
                                                     The meeting will be open to public                   Brown (Telephone 240–888–9835) to be                  ‘‘ADAMS Public Documents’’ and then
                                                  attendance.                                             escorted to the meeting room.                         select ‘‘Begin Web-based ADAMS
                                                     The agenda for the subject meeting                     Dated: September 24, 2015.                          Search.’’ For problems with ADAMS,
                                                  shall be as follows:
                                                                                                          Mark L. Banks,                                        please contact the NRC’s Public
                                                  Wednesday, October 7, 2015–8:30 a.m.                    Chief, Technical Support Branch, Advisory             Document Room (PDR) reference staff at
                                                  Until 1:00 p.m.                                         Committee on Reactor Safeguards.                      1–800–397–4209, 301–415–4737, or by
                                                    The Subcommittee will discuss                         [FR Doc. 2015–25118 Filed 10–1–15; 8:45 am]           email to pdr.resource@nrc.gov. The
                                                  sections of the NuScale Design-Specific                 BILLING CODE 7590–01–P                                ADAMS accession number for each
                                                  Review Standard. The Subcommittee                                                                             document referenced (if that document
                                                  will hear presentations by and hold                                                                           is available in ADAMS) is provided the
                                                  discussions with the NRC staff and                      NUCLEAR REGULATORY                                    first time that a document is referenced.
                                                  other interested persons regarding this                 COMMISSION                                               • NRC’s PDR: You may examine and
                                                  matter. The Subcommittee will gather                    [Docket No. 50–327 and 50–328; NRC–2013–
                                                                                                                                                                purchase copies of public documents at
                                                  information, analyze relevant issues and                0037]                                                 the NRC’s PDR, Room O1–F21, One
                                                  facts, and formulate proposed positions                                                                       White Flint North, 11555 Rockville
                                                  and actions, as appropriate, for                        License Renewal for Sequoyah Nuclear                  Pike, Rockville, Maryland 20852.
                                                  deliberation by the Full Committee.                     Plant, Units 1 and 2                                  FOR FURTHER INFORMATION CONTACT:
                                                    Members of the public desiring to                                                                           Emmanuel Sayoc, Office of Nuclear
                                                                                                          AGENCY:  Nuclear Regulatory
                                                  provide oral statements and/or written                  Commission.                                           Reactor Regulation, U.S. Nuclear
                                                  comments should notify the Designated                                                                         Regulatory Commission, Washington,
                                                                                                          ACTION: License renewal and record of
                                                  Federal Official (DFO), Maitri Banerjee                                                                       DC 20555; telephone: 301–415–4084;
                                                                                                          decision; issuance.                                   email: Emmanuel.Sayoc@nrc.gov.
                                                  (Telephone 301–415–6973 or Email:
                                                  Maitri.Banerjee@nrc.gov) five days prior                SUMMARY:   The U.S. Nuclear Regulatory                SUPPLEMENTARY INFORMATION: Notice is
                                                  to the meeting, if possible, so that                    Commission (NRC) has issued renewed                   hereby given that the NRC has issued
                                                  appropriate arrangements can be made.                   facility operating licenses Nos. DPR–77               renewed facility operating licenses Nos.
                                                  Thirty-five hard copies of each                         and DPR–79 to Tennessee Valley                        DPR–77 and DPR–79 to Tennessee
                                                  presentation or handout should be                       Authority, the operator of the Sequoyah               Valley Authority, the operator of SQN.
                                                  provided to the DFO thirty minutes                      Nuclear Plant, Units 1 and 2 (SQN).                   Renewed facility operating licenses Nos.
                                                  before the meeting. In addition, one                    Renewed facility operating licenses Nos.              DPR–77 and DPR–79 authorize
                                                  electronic copy of each presentation                    DPR–77 and DPR–79 authorize                           operation of SQN by the licensee at
                                                  should be emailed to the DFO one day                    operation of SQN by the licensee at                   reactor core power levels not in excess
                                                  before the meeting. If an electronic copy               reactor core power levels not in excess               of 3455 megawatts thermal, in
                                                  cannot be provided within this                          of 3455 megawatts thermal, in                         accordance with the provisions of the
                                                  timeframe, presenters should provide                    accordance with the provisions of the                 SQN renewed licenses and technical
                                                                                                          SQN renewed licenses and technical
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  the DFO with a CD containing each                                                                             specifications. The NRC’s ROD that
                                                  presentation at least thirty minutes                    specifications. In addition, the NRC has              supports the NRC’s decision to renew
                                                  before the meeting. Electronic                          prepared a record of decision (ROD) that              facility operating licenses Nos. DPR–77
                                                  recordings will be permitted only                       supports the NRC’s decision to renew                  and DPR–79 is available in ADAMS
                                                  during those portions of the meeting                    facility operating licenses Nos. DPR–77               under Accession No. ML15104A689. As
                                                  that are open to the public. Detailed                   and DPR–79.                                           discussed in the ROD and the final
                                                  procedures for the conduct of and                       DATES: The license renewal of facility                supplemental environmental impact
                                                  participation in ACRS meetings were                     operating licenses Nos. DPR–77 and                    statement (FSEIS) for SQN, Supplement


                                             VerDate Sep<11>2014   20:43 Oct 01, 2015   Jkt 238001   PO 00000   Frm 00112   Fmt 4703   Sfmt 4703   E:\FR\FM\02OCN1.SGM   02OCN1


                                                  59832                          Federal Register / Vol. 80, No. 191 / Friday, October 2, 2015 / Notices

                                                  53 to NUREG–1437, ‘‘Generic                             NUCLEAR REGULATORY                                    Saporito (the petitioner) on July 18,
                                                  Environmental Impact Statement for                      COMMISSION                                            2014, as supplemented on September 3,
                                                  License Renewal of Nuclear Plants                                                                             2014 (ADAMS Package Accession No.
                                                                                                          [Docket Nos. 50–250, and 50–251; NRC–                 ML14202A521).
                                                  Regarding Sequoyah Nuclear Plant,
                                                                                                          2015–0011]
                                                  Units 1 and 2,’’ dated March 2015                                                                                The petitioner requested that the NRC
                                                  (ADAMS Accession No. ML15075A438),                      Florida Power & Light Company                         take enforcement action against Florida
                                                  the NRC has considered a range of                       Turkey Point Nuclear Generating, Units                Power & Light Company (the licensee)
                                                  reasonable alternatives that included                   3 and 4                                               regarding the Turkey Point Nuclear
                                                  natural gas combined-cycle,                                                                                   Generating, Units 3 and 4. Specifically,
                                                  supercritical pulverized coal, new                      AGENCY: Nuclear Regulatory                            the petitioner requested that the NRC
                                                  nuclear, wind and solar power, and the                  Commission.                                           suspend or revoke the licenses for
                                                  no action alternative. The ROD and                      ACTION: Director’s decision; issuance.                Turkey Point, issue a violation with a
                                                  FSEIS document the NRC’s                                                                                      civil penalty of $1 million, and issue a
                                                  determination in its environmental                      SUMMARY:    The U.S. Nuclear Regulatory               confirmatory order that the plant stays
                                                  review that the adverse environmental                   Commission (NRC) has issued a                         in a cold shutdown mode until the
                                                  impacts of license renewal for SQN are                  director’s decision with regard to a                  licensee completes (1) an independent
                                                  not so great that preserving the option                 petition dated July 18, 2014, as                      assessment (through a contractor) to
                                                  of license renewal for energy planning                  supplemented on September 3, 2014,                    assess, fully understand, and correct the
                                                  decision makers would be unreasonable.                  filed by Mr. Thomas Saporito (the                     root cause of the rise in ultimate heat
                                                                                                          petitioner), requesting that the NRC take             sink (UHS) temperature; (2) a
                                                     SQN is a dual pressurized water                                                                            comprehensive evaluation of all nuclear
                                                                                                          action with regard to Turkey Point
                                                  reactor nuclear steam supply system,                                                                          safety-related equipment and
                                                                                                          Nuclear Generating, Units 3 and 4. The
                                                  with four coolant loops for each unit,                                                                        components that may have been
                                                                                                          petitioner’s requests and the director’s
                                                  and located approximately 9.5 miles                                                                           affected; and (3) an independent
                                                                                                          decision are included in the
                                                  northeast of Chattanooga, Tennessee.                                                                          evaluation of all nuclear safety-related
                                                                                                          SUPPLEMENTARY INFORMATION section of
                                                  The application for the renewed license,                                                                      equipment and components that may
                                                                                                          this document.
                                                  ‘‘Sequoyah Nuclear Plant, Units 1 and 2,                                                                      have been affected.
                                                  License Renewal Application,’’ dated                    ADDRESSES: Please refer to Docket ID
                                                                                                          NRC–2015–0011 when contacting the                        On September 3, 2015, the petitioner
                                                  January 7, 2013 (ADAMS Accession No.                                                                          addressed the NRC’s Petition Review
                                                  ML130240007), as supplemented by                        NRC about the availability of
                                                                                                          information regarding this document.                  Board by teleconference. The meeting
                                                  letters dated through August 17, 2015,                                                                        provided the petitioner an opportunity
                                                  complied with the standards and                         You may obtain publicly-available
                                                                                                                                                                to provide additional information and to
                                                  requirements of the Atomic Energy Act                   information related to this document
                                                                                                                                                                clarify issues cited in the petition. The
                                                  of 1954, as amended (the Act), and the                  using any of the following methods:
                                                                                                                                                                transcript for that meeting is available in
                                                  NRC’s regulations. As required by the                      • Federal Rulemaking Web site: Go to
                                                                                                                                                                ADAMS under Accession No.
                                                  Act and the NRC’s regulations in                        http://www.regulations.gov and search
                                                                                                                                                                ML14266A123.
                                                  Chapter 1 of Title 10 of the Code of                    for Docket ID NRC–2015–0011. Address                     The NRC reviewed the petition, its
                                                  Federal Regulations, the NRC has made                   questions about NRC dockets to Carol                  supplements, and the transcripts from
                                                  appropriate findings, which are set forth               Gallagher; telephone: 301–415–3463;                   the meeting on September 3, 2014, and
                                                  in the license. A public notice of                      email: Carol.Gallagher@nrc.gov.                       referred the request to the Director of
                                                  acceptance for docketing of the                            • NRC’s Agencywide Documents                       the Office of Nuclear Reactor
                                                  application and an opportunity for a                    Access and Management System                          Regulation. By letter dated January 30,
                                                  hearing was published in the Federal                    (ADAMS): You may obtain publicly                      2015 (ADAMS Accession No.
                                                  Register on March 5, 2013 (78 FR                        available documents online in the                     ML14349A597), the Deputy Director
                                                  14362).                                                 ADAMS Public Documents collection at                  determined that the petitioner’s request
                                                                                                          http://www.nrc.gov/reading-rm/                        that the NRC take enforcement action
                                                     For further details with respect to this             adams.html. To begin the search, select
                                                  action, see: (1) Tennessee Valley                                                                             until the licensee completes an
                                                                                                          ‘‘ADAMS Public Documents’’ and then                   independent root cause assessment for
                                                  Authority license renewal application                   select ‘‘Begin Web-based ADAMS
                                                  for Sequoyah Nuclear Plant, Units 1 and                                                                       the rise in UHS temperature met the
                                                                                                          Search.’’ For problems with ADAMS,                    criteria for review under the petition
                                                  2, dated January 7, 2013, as                            please contact the NRC’s Public
                                                  supplemented by letters dated through                                                                         process. The Deputy Director
                                                                                                          Document Room (PDR) reference staff at                determined that the other requests in
                                                  August 17, 2017; (2) the NRC’s safety                   1–800–397–4209, 301–415–4737, or by
                                                  evaluation report published in January                                                                        the petition did not meet the criteria for
                                                                                                          email to pdr.resource@nrc.gov. The                    review under the petition process.
                                                  2015 (ADAMS Accession No.                               ADAMS accession number for each
                                                  ML15021A356); (3) the NRC’s final                                                                                By letters to the petitioner and
                                                                                                          document referenced (if that document                 licensee dated July 27, 2015 (ADAMS
                                                  environmental impact statement                          is available in ADAMS) is provided the
                                                  (NUREG–1437, Supplement 53) for                                                                               Accession Nos. ML15162B048 and
                                                                                                          first time that a document is referenced.             ML15162B050, respectively), the NRC
                                                  Sequoyah Nuclear Plant, Units 1 and 2,                     • NRC’s PDR: You may examine and
                                                  published in March 2015; and (4) the                                                                          issued the proposed director’s decision
                                                                                                          purchase copies of public documents at                (ADAMS Accession No. ML15162B053)
                                                  NRC’s ROD.                                              the NRC’s PDR, Room O1–F21, One                       for comment. The petitioner and the
                                                     Dated at Rockville, Maryland, this 28th day          White Flint North, 11555 Rockville
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                                                                licensee were asked to provide
                                                  of September, 2015.                                     Pike, Rockville, Maryland 20852.                      comments within 15 days on any part of
                                                     For the Nuclear Regulatory Commission.               SUPPLEMENTARY INFORMATION: Notice is                  the proposed director’s decision that
                                                  Christopher G. Miller,                                  hereby given that the Director, Office of             was considered to be erroneous or any
                                                  Director, Division of License Renewal, Office           Nuclear Reactor Regulation, NRC has                   issues in the petition that were not
                                                  of Nuclear Reactor Regulation.                          issued Director’s Decision DD–15–10                   addressed. Comments were received
                                                  [FR Doc. 2015–25128 Filed 10–1–15; 8:45 am]             (ADAMS Accession No. ML15237A181)                     from the petitioner by electronic mail
                                                  BILLING CODE 7590–01–P                                  for a petition filed by Mr. Thomas                    dated August 5, 2015, and August 12,


                                             VerDate Sep<11>2014   20:43 Oct 01, 2015   Jkt 238001   PO 00000   Frm 00113   Fmt 4703   Sfmt 4703   E:\FR\FM\02OCN1.SGM   02OCN1



Document Created: 2015-12-15 08:45:30
Document Modified: 2015-12-15 08:45:30
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionLicense renewal and record of decision; issuance.
DatesThe license renewal of facility operating licenses Nos. DPR-77 and DPR-79 were effective on September 28, 2015.
ContactEmmanuel Sayoc, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555; telephone: 301-415-4084; email: [email protected]
FR Citation80 FR 59831 