DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 193 (October 6, 2015)

Page Range60377-60379
FR Document2015-25387

Federal Register, Volume 80 Issue 193 (Tuesday, October 6, 2015)
[Federal Register Volume 80, Number 193 (Tuesday, October 6, 2015)]
[Notices]
[Pages 60377-60379]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-25387]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF14-17-000]


Louisiana LNG Energy, LLC; Supplemental Notice of Intent To 
Prepare an Environmental Impact Statement for the Planned Mississippi 
River LNG Project, and Request for Comments on Environmental Issues 
Related to Project Changes

    On October 3, 2014, the Federal Energy Regulatory Commission (FERC 
or Commission) issued in Docket No. PF14-17-000 a Notice of Intent to 
Prepare an Environmental Impact Statement for the Planned Mississippi 
River LNG Project and Request for Comments on Environmental Issues 
(NOI). Since the NOI was issued Louisiana LNG Energy, LLC (Louisiana 
LNG) has made project changes. This Supplemental Notice is being issued 
to seek comments on the project changes and opens a new scoping period 
for interested parties to file comments on environmental issues 
specific to these facilities.
    The October 3, 2014 NOI announced that the FERC is the lead federal 
agency responsible for conducting the environmental review of the 
Mississippi River LNG Project (Project) and that the Commission staff 
will prepare an environmental impact statement (EIS) that discusses the 
environmental impacts of the Project. Please refer to the NOI for more 
information about the overall facilities proposed by Louisiana LNG and 
FERC staff's EIS process. This EIS will be used in part by the 
Commission to determine whether the Mississippi River LNG Project is in 
the public convenience and necessity. On November 17, 2015, Louisiana 
LNG is planning on having another open house to give the new landowners 
the opportunity to attend and learn about the Project and the FERC 
process.
    This Supplemental Notice is being sent to the Commission's current 
environmental mailing list for this Project, including new landowners 
that would be affected by the project changes. We encourage elected 
officials and government representatives to notify their constituents 
about the Project and inform them on how they can comment on their 
areas of concern. Please note that comments on this Notice should be 
filed with the Commission by October 30, 2015.
    If your property would be affected by the Project, you should have 
already been contacted by a Louisiana LNG representative. A Louisiana 
LNG

[[Page 60378]]

representative may have also contacted you or may contact you in the 
near future about the acquisition of an easement to construct, operate, 
and maintain the planned pipeline facilities or request permission to 
perform environmental surveys on your property. If the Commission 
approves the Project, that approval conveys with it the right of 
eminent domain for easement acquisition for the pipeline. Therefore, if 
easement negotiations fail to produce an agreement, the company could 
initiate condemnation proceedings where compensation would be 
determined in accordance with state law.
    To help potentially affected landowners better understand the 
Commission and its environmental review process, the ``For Citizens'' 
section of the FERC Web site (www.ferc.gov) provides information about 
getting involved in FERC jurisdictional projects, and a citizens' guide 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need to Know?'' This guide addresses a number of frequently asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings.

Summary of the Planned Project Changes

    Louisiana LNG is planning the following changes in response to new 
ownership and additional environmental and engineering analysis:
     Increase the production capacity to 6.0 million tons per 
annum (MTPA) from 2.0 MTPA;
     increase the storage capacity of the LNG storage tanks to 
140,000 cubic meters (net) from 100,000 cubic meters;
     increase the pipeline from the 1.9-mile 24-inch-diameter 
to 1.9-mile 36-inch-diameter (northern pipeline) with an associated 
meter station that would deliver gas from the Tennessee Gas interstate 
pipeline system;
     increase the pipeline from the 1.6-mile 12-inch-diameter 
to 3.5-mile 36-inch-diameter (southern pipeline) that would deliver gas 
from the Tennessee Gas Pipeline system to the facility;
     eliminate the truck loading facility from the Project 
design; and
     eliminate the compressor station from the Project design.
    A map depicting the general location of the Project facilities is 
included in Appendix 1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice are not being 
printed in the Federal Register. Copies of appendices were sent to 
all those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' of fromthe 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    The planned construction would impact a 190-acre site on the east 
bank of the Mississippi River in Plaquemines Parish, Louisiana, which 
would include the liquefaction trains, LNG storage tanks, marine 
loading facilities, the electrical power station, and ancillary 
facilities. The full 190-acre site would be fenced and retained for 
operations of the planned Project. Construction of the two pipelines 
and associated meter stations would require approximately 65 acres of 
land, 33 of which would be permanently impacted during operations. 
Louisiana LNG is still in the planning phase for the Project and 
requirements for construction workspaces, access roads, and pipe 
storage/contractor yards would be determined during engineering and 
design.

The EIS Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the authorization of LNG 
facilities. NEPA also requires us \2\ to discover and address concerns 
the public may have about proposals. This process is referred to as 
``scoping.'' The main goal of the scoping process is to focus the 
analysis in the EIS on the important environmental issues. By this 
notice, the Commission requests public comments on the scope of the 
issues to address in the EIS. We will consider all filed comments 
during the preparation of the EIS.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EIS we will discuss impacts that could occur as a result of 
the construction and operation of the proposed Project. We will also 
evaluate reasonable alternatives to the planned Project or portions of 
the Project, and make recommendations on how to lessen or avoid impacts 
on the various resource areas.
    The EIS will present our independent analysis of the issues. We 
will publish and distribute the draft EIS for public comment. After the 
comment period, we will consider all timely comments and revise the 
document, as necessary, before issuing a final EIS. To ensure we have 
the opportunity to consider and address your comments, please carefully 
follow the instructions in the Public Participation section below.

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the Louisiana Office of Historic Preservation (State Historic 
Preservation Office [SHPO]), and to solicit their views and those of 
other government agencies, interested Indian tribes, and the public on 
the Project's potential effects on historic properties.\3\ We will 
define the Project-specific Area of Potential Effects (APE) in 
consultation with the SHPO as the Project develops. On natural gas 
facility projects, the APE at a minimum encompasses all areas subject 
to ground disturbance (examples include the terminal plot, construction 
right-of-way, contractor/pipe storage yards, compressor stations, and 
access roads). Our EIS for this Project will document our findings on 
the impacts on historic properties and summarize the status of 
consultations with the Louisiana Office of Historic Preservation under 
section 106.
---------------------------------------------------------------------------

    \3\ The Advisory Council on Historic Preservation's regulations 
are at title 36, Code of Federal Regulations, part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the Project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before 
October 30, 2015.
    For your convenience, there are three methods which you can use to 
submit your comments to the Commission. In all instances please 
reference the Project docket number (PF14-17-000) with your submission. 
The Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy

[[Page 60379]]

method for interested persons to submit brief, text-only comments on a 
project;
    (2) You can file your comments electronically using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for Project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the Project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed Project.
    When we publish and distribute the EIS, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (Appendix 2).

Becoming an Intervenor

    Once Louisiana LNG files its application with the Commission, you 
may want to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site. Please note that the Commission will not accept requests for 
intervenor status at this time. You must wait until the Commission 
receives a formal application for the project.

Additional Information

    Additional information about the Project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., PF14-
17). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: September 30, 2015.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-25387 Filed 10-5-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                           Federal Register / Vol. 80, No. 193 / Tuesday, October 6, 2015 / Notices                                            60377

                                              potentially affected landowners and                     Procedures (18 CFR 385.214).1 Only                    DEPARTMENT OF ENERGY
                                              other interested individuals and groups;                intervenors have the right to seek
                                              newspapers and libraries in the project                 rehearing of the Commission’s decision.               Federal Energy Regulatory
                                              area; and parties to this proceeding.                   The Commission grants affected                        Commission
                                                 In addition, the EA is available for                 landowners and others with                            [Docket No. PF14–17–000]
                                              public viewing on the FERC’s Web site                   environmental concerns intervenor
                                              (www.ferc.gov) using the eLibrary link.                 status upon showing good cause by                     Louisiana LNG Energy, LLC;
                                              A limited number of copies of the EA                    stating that they have a clear and direct             Supplemental Notice of Intent To
                                              are available for distribution and public               interest in this proceeding which no                  Prepare an Environmental Impact
                                              inspection at: Federal Energy Regulatory                other party can adequately represent.                 Statement for the Planned Mississippi
                                              Commission, Public Reference Room,                      Simply filing environmental comments                  River LNG Project, and Request for
                                              888 First Street NE., Room 2A,                          will not give you intervenor status, but              Comments on Environmental Issues
                                              Washington, DC 20426, (202) 502–8371.                                                                         Related to Project Changes
                                                                                                      you do not need intervenor status to
                                                 Any person wishing to comment on
                                                                                                      have your comments considered.                          On October 3, 2014, the Federal
                                              the EA may do so. Your comments
                                              should focus on the potential                              Additional information about the                   Energy Regulatory Commission (FERC
                                              environmental effects, reasonable                       project is available from the                         or Commission) issued in Docket No.
                                              alternatives, and measures to avoid or                  Commission’s Office of External Affairs,              PF14–17–000 a Notice of Intent to
                                              lessen environmental impacts. The more                  at (866) 208–FERC, or on the FERC Web                 Prepare an Environmental Impact
                                              specific your comments, the more useful                 site (www.ferc.gov) using the eLibrary                Statement for the Planned Mississippi
                                              they will be. To ensure that the                        link. Click on the eLibrary link, click on            River LNG Project and Request for
                                              Commission has the opportunity to                       ‘‘General Search,’’ and enter the docket              Comments on Environmental Issues
                                              consider your comments prior to                                                                               (NOI). Since the NOI was issued
                                                                                                      number excluding the last three digits in
                                              making its decision on this project, it is                                                                    Louisiana LNG Energy, LLC (Louisiana
                                                                                                      the Docket Number field (i.e., CP15–
                                              important that we receive your                                                                                LNG) has made project changes. This
                                                                                                      132). Be sure you have selected an                    Supplemental Notice is being issued to
                                              comments in Washington, DC on or                        appropriate date range. For assistance,
                                              before October 30, 2015.                                                                                      seek comments on the project changes
                                                                                                      please contact FERC Online Support at                 and opens a new scoping period for
                                                 For your convenience, there are three                FercOnlineSupport@ferc.gov or toll free
                                              methods you can use to file your                                                                              interested parties to file comments on
                                                                                                      at (866) 208–3676, or for TTY, contact                environmental issues specific to these
                                              comments to the Commission. In all                      (202) 502–8659. The eLibrary link also
                                              instances, please reference the project                                                                       facilities.
                                                                                                      provides access to the texts of formal                  The October 3, 2014 NOI announced
                                              docket number (CP15–132–000) with
                                                                                                      documents issued by the Commission,                   that the FERC is the lead federal agency
                                              your submission. The Commission
                                                                                                      such as orders, notices, and                          responsible for conducting the
                                              encourages electronic filing of
                                                                                                      rulemakings.                                          environmental review of the Mississippi
                                              comments and has expert staff available
                                                                                                         In addition, the Commission offers a               River LNG Project (Project) and that the
                                              to assist you at (202) 502–8258 or
                                                                                                                                                            Commission staff will prepare an
                                              efiling@ferc.gov.                                       free service called eSubscription which
                                                                                                                                                            environmental impact statement (EIS)
                                                 (1) You can file your comments                       allows you to keep track of all formal
                                                                                                                                                            that discusses the environmental
                                              electronically using the eComment                       issuances and submittals in specific                  impacts of the Project. Please refer to the
                                              feature on the Commission’s Web site                    dockets. This can reduce the amount of                NOI for more information about the
                                              (www.ferc.gov) under the link to                        time you spend researching proceedings                overall facilities proposed by Louisiana
                                              Documents and Filings. This is an easy                  by automatically providing you with                   LNG and FERC staff’s EIS process. This
                                              method for submitting brief, text-only                  notification of these filings, document               EIS will be used in part by the
                                              comments on a project;                                  summaries, and direct links to the                    Commission to determine whether the
                                                 (2) You can also file your comments                  documents. Go to www.ferc.gov/docs-                   Mississippi River LNG Project is in the
                                              electronically using the eFiling feature                filing/esubscription.asp.                             public convenience and necessity. On
                                              on the Commission’s Web site                                                                                  November 17, 2015, Louisiana LNG is
                                              (www.ferc.gov) under the link to                          Dated: September 30, 2015.
                                                                                                                                                            planning on having another open house
                                              Documents and Filings. With eFiling,                    Kimberly D. Bose,
                                                                                                                                                            to give the new landowners the
                                              you can provide comments in a variety                   Secretary.                                            opportunity to attend and learn about
                                              of formats by attaching them as a file                  [FR Doc. 2015–25388 Filed 10–5–15; 8:45 am]           the Project and the FERC process.
                                              with your submission. New eFiling                       BILLING CODE 6717–01–P                                  This Supplemental Notice is being
                                              users must first create an account by                                                                         sent to the Commission’s current
                                              clicking on ‘‘eRegister.’’ You must select                                                                    environmental mailing list for this
                                              the type of filing you are making. If you                                                                     Project, including new landowners that
                                              are filing a comment on a particular                                                                          would be affected by the project
                                              project, please select ‘‘Comment on a                                                                         changes. We encourage elected officials
                                              Filing’’; or                                                                                                  and government representatives to
                                                 (3) You can file a paper copy of your                                                                      notify their constituents about the
                                              comments by mailing them to the                                                                               Project and inform them on how they
                                              following address: Kimberly D. Bose,                                                                          can comment on their areas of concern.
                                              Secretary, Federal Energy Regulatory
tkelley on DSK3SPTVN1PROD with NOTICES




                                                                                                                                                            Please note that comments on this
                                              Commission, 888 First Street NE., Room                                                                        Notice should be filed with the
                                              1A, Washington, DC 20426.                                                                                     Commission by October 30, 2015.
                                                 Any person seeking to become a party                                                                         If your property would be affected by
                                              to the proceeding must file a motion to                                                                       the Project, you should have already
                                              intervene pursuant to Rule 214 of the                      1 See the previous discussion on the methods for   been contacted by a Louisiana LNG
                                              Commission’s Rules of Practice and                      filing comments.                                      representative. A Louisiana LNG


                                         VerDate Sep<11>2014   18:31 Oct 05, 2015   Jkt 238001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\06OCN1.SGM   06OCN1


                                              60378                        Federal Register / Vol. 80, No. 193 / Tuesday, October 6, 2015 / Notices

                                              representative may have also contacted                  Land Requirements for Construction                    Consultations Under Section 106 of the
                                              you or may contact you in the near                                                                            National Historic Preservation Act
                                              future about the acquisition of an                        The planned construction would
                                                                                                      impact a 190-acre site on the east bank                 In accordance with the Advisory
                                              easement to construct, operate, and                                                                           Council on Historic Preservation’s
                                              maintain the planned pipeline facilities                of the Mississippi River in Plaquemines
                                                                                                      Parish, Louisiana, which would include                implementing regulations for section
                                              or request permission to perform                                                                              106 of the National Historic
                                              environmental surveys on your                           the liquefaction trains, LNG storage
                                                                                                      tanks, marine loading facilities, the                 Preservation Act, we are using this
                                              property. If the Commission approves                                                                          notice to initiate consultation with the
                                              the Project, that approval conveys with                 electrical power station, and ancillary
                                                                                                      facilities. The full 190-acre site would              Louisiana Office of Historic Preservation
                                              it the right of eminent domain for                                                                            (State Historic Preservation Office
                                              easement acquisition for the pipeline.                  be fenced and retained for operations of
                                                                                                      the planned Project. Construction of the              [SHPO]), and to solicit their views and
                                              Therefore, if easement negotiations fail                                                                      those of other government agencies,
                                              to produce an agreement, the company                    two pipelines and associated meter
                                                                                                      stations would require approximately 65               interested Indian tribes, and the public
                                              could initiate condemnation                                                                                   on the Project’s potential effects on
                                              proceedings where compensation would                    acres of land, 33 of which would be
                                                                                                      permanently impacted during                           historic properties.3 We will define the
                                              be determined in accordance with state                                                                        Project-specific Area of Potential Effects
                                              law.                                                    operations. Louisiana LNG is still in the
                                                                                                      planning phase for the Project and                    (APE) in consultation with the SHPO as
                                                 To help potentially affected
                                                                                                      requirements for construction                         the Project develops. On natural gas
                                              landowners better understand the
                                                                                                      workspaces, access roads, and pipe                    facility projects, the APE at a minimum
                                              Commission and its environmental
                                                                                                      storage/contractor yards would be                     encompasses all areas subject to ground
                                              review process, the ‘‘For Citizens’’
                                                                                                      determined during engineering and                     disturbance (examples include the
                                              section of the FERC Web site
                                                                                                      design.                                               terminal plot, construction right-of-way,
                                              (www.ferc.gov) provides information
                                                                                                                                                            contractor/pipe storage yards,
                                              about getting involved in FERC                          The EIS Process                                       compressor stations, and access roads).
                                              jurisdictional projects, and a citizens’
                                                                                                         The National Environmental Policy                  Our EIS for this Project will document
                                              guide entitled ‘‘An Interstate Natural
                                                                                                      Act (NEPA) requires the Commission to                 our findings on the impacts on historic
                                              Gas Facility On My Land? What Do I
                                                                                                      take into account the environmental                   properties and summarize the status of
                                              Need to Know?’’ This guide addresses a
                                                                                                      impacts that could result from an action              consultations with the Louisiana Office
                                              number of frequently asked questions,
                                                                                                      whenever it considers the authorization               of Historic Preservation under section
                                              including the use of eminent domain
                                                                                                      of LNG facilities. NEPA also requires                 106.
                                              and how to participate in the
                                              Commission’s proceedings.                               us 2 to discover and address concerns                 Public Participation
                                                                                                      the public may have about proposals.
                                              Summary of the Planned Project                          This process is referred to as ‘‘scoping.’’              You can make a difference by
                                              Changes                                                 The main goal of the scoping process is               providing us with your specific
                                                                                                      to focus the analysis in the EIS on the               comments or concerns about the Project.
                                                 Louisiana LNG is planning the
                                                                                                      important environmental issues. By this               Your comments should focus on the
                                              following changes in response to new
                                                                                                      notice, the Commission requests public                potential environmental effects,
                                              ownership and additional
                                                                                                      comments on the scope of the issues to                reasonable alternatives, and measures to
                                              environmental and engineering analysis:
                                                 • Increase the production capacity to                address in the EIS. We will consider all              avoid or lessen environmental impacts.
                                              6.0 million tons per annum (MTPA)                       filed comments during the preparation                 The more specific your comments, the
                                              from 2.0 MTPA;                                          of the EIS.                                           more useful they will be. To ensure that
                                                 • increase the storage capacity of the                                                                     your comments are timely and properly
                                                                                                         In the EIS we will discuss impacts
                                              LNG storage tanks to 140,000 cubic                                                                            recorded, please send your comments so
                                                                                                      that could occur as a result of the
                                              meters (net) from 100,000 cubic meters;                                                                       that the Commission receives them in
                                                                                                      construction and operation of the
                                                 • increase the pipeline from the 1.9-                                                                      Washington, DC on or before October
                                                                                                      proposed Project. We will also evaluate
                                              mile 24-inch-diameter to 1.9-mile 36-                                                                         30, 2015.
                                                                                                      reasonable alternatives to the planned
                                              inch-diameter (northern pipeline) with                                                                           For your convenience, there are three
                                                                                                      Project or portions of the Project, and
                                              an associated meter station that would                                                                        methods which you can use to submit
                                                                                                      make recommendations on how to
                                              deliver gas from the Tennessee Gas                                                                            your comments to the Commission. In
                                                                                                      lessen or avoid impacts on the various
                                              interstate pipeline system;                                                                                   all instances please reference the Project
                                                                                                      resource areas.
                                                 • increase the pipeline from the 1.6-                                                                      docket number (PF14–17–000) with
                                                                                                         The EIS will present our independent               your submission. The Commission
                                              mile 12-inch-diameter to 3.5-mile 36-
                                                                                                      analysis of the issues. We will publish               encourages electronic filing of
                                              inch-diameter (southern pipeline) that
                                                                                                      and distribute the draft EIS for public               comments and has expert staff available
                                              would deliver gas from the Tennessee
                                                                                                      comment. After the comment period, we                 to assist you at (202) 502–8258 or
                                              Gas Pipeline system to the facility;
                                                 • eliminate the truck loading facility               will consider all timely comments and                 efiling@ferc.gov.
                                              from the Project design; and                            revise the document, as necessary,                       (1) You can file your comments
                                                 • eliminate the compressor station                   before issuing a final EIS. To ensure we              electronically using the eComment
                                              from the Project design.                                have the opportunity to consider and                  feature on the Commission’s Web site
                                                 A map depicting the general location                 address your comments, please carefully               (www.ferc.gov) under the link to
                                              of the Project facilities is included in                follow the instructions in the Public                 Documents and Filings. This is an easy
                                                                                                      Participation section below.
tkelley on DSK3SPTVN1PROD with NOTICES




                                              Appendix 1.1
                                                                                                                                                              3 The Advisory Council on Historic Preservation’s
                                                1 The appendices referenced in this notice are not    Street NE., Washington, DC 20426, or call (202)       regulations are at title 36, Code of Federal
                                              being printed in the Federal Register. Copies of        502–8371. For instructions on connecting to           Regulations, part 800. Those regulations define
                                              appendices were sent to all those receiving this        eLibrary, refer to the last page of this notice.      historic properties as any prehistoric or historic
                                              notice in the mail and are available at www.ferc.gov      2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the          district, site, building, structure, or object included
                                              using the link called ‘‘eLibrary’’ of fromthe           environmental staff of the Commission’s Office of     in or eligible for inclusion in the National Register
                                              Commission’s Public Reference Room, 888 First           Energy Projects.                                      of Historic Places.



                                         VerDate Sep<11>2014   18:31 Oct 05, 2015   Jkt 238001   PO 00000   Frm 00030   Fmt 4703   Sfmt 4703   E:\FR\FM\06OCN1.SGM   06OCN1


                                                                           Federal Register / Vol. 80, No. 193 / Tuesday, October 6, 2015 / Notices                                         60379

                                              method for interested persons to submit                 participates in the proceeding by filing              PJM Planning Committee
                                              brief, text-only comments on a project;                 a request to intervene. Instructions for                October 8, 2015, 9:30 a.m.–12:00 p.m.
                                                 (2) You can file your comments                       becoming an intervenor are in the User’s              (EST)
                                              electronically using the eFiling feature                Guide under the ‘‘e-filing’’ link on the
                                              on the Commission’s Web site                            Commission’s Web site. Please note that               PJM Transmission Expansion Advisory
                                              (www.ferc.gov) under the link to                        the Commission will not accept requests               Committee
                                              Documents and Filings. With eFiling,                    for intervenor status at this time. You                  October 8, 2015, 11:00 a.m.–3:00 p.m.
                                              you can provide comments in a variety                   must wait until the Commission                        (EST)
                                              of formats by attaching them as a file                  receives a formal application for the                    The above-referenced meetings will
                                              with your submission. New eFiling                       project.                                              be held at: PJM Conference and Training
                                              users must first create an account by                                                                         Center, PJM Interconnection, 2750
                                              clicking on ‘‘eRegister.’’ You must select              Additional Information
                                                                                                                                                            Monroe Boulevard, Audubon, PA
                                              the type of filing you are making. If you                  Additional information about the                   19403.
                                              are filing a comment on a particular                    Project is available from the                            The above-referenced meetings are
                                              project, please select ‘‘Comment on a                   Commission’s Office of External Affairs,              open to stakeholders.
                                              Filing’’; or                                            at (866) 208–FERC, or on the FERC Web                    Further information may be found at
                                                 (3) You can file a paper copy of your                site at www.ferc.gov using the                        www.pjm.com.
                                              comments by mailing them to the                         ‘‘eLibrary’’ link. Click on the eLibrary                 The discussions at the meetings
                                              following address: Kimberly D. Bose,                    link, click on ‘‘General Search’’ and                 described above may address matters at
                                              Secretary, Federal Energy Regulatory                    enter the docket number, excluding the                issue in the following proceedings:
                                              Commission, 888 First Street NE., Room                  last three digits in the Docket Number
                                              1A, Washington, DC 20426.                               field (i.e., PF14–17). Be sure you have               Docket Nos. ER15–33, et al., The Dayton
                                                                                                      selected an appropriate date range. For                    Power and Light Company
                                              Environmental Mailing List                                                                                    Docket No. ER15–994, PJM
                                                                                                      assistance, please contact FERC Online
                                                 The environmental mailing list                                                                                  Interconnection, L.L.C.
                                                                                                      Support at FercOnlineSupport@ferc.gov
                                              includes federal, state, and local                                                                            Docket No. ER14–2867, Baltimore Gas &
                                                                                                      or toll free at (866) 208–3676, or for
                                              government representatives and                                                                                     Electric Company, et al., and PJM
                                                                                                      TTY, contact (202) 502–8659. The
                                              agencies; elected officials;                                                                                       Interconnection, L.L.C.
                                                                                                      eLibrary link also provides access to the
                                              environmental and public interest                                                                             Docket Nos. ER14–972 and ER14–1485,
                                                                                                      texts of formal documents issued by the
                                              groups; Native American Tribes; other                                                                              PJM Interconnection, L.L.C.
                                                                                                      Commission, such as orders, notices,
                                              interested parties; and local libraries                                                                       Docket No. ER14–1485, PJM
                                                                                                      and rulemakings.
                                              and newspapers. This list also includes                    In addition, the Commission now                         Interconnection, L.L.C.
                                              all affected landowners (as defined in                                                                        Docket Nos. ER13–1957, et al., ISO New
                                                                                                      offers a free service called eSubscription
                                              the Commission’s regulations) who are                                                                              England, Inc. et al.
                                                                                                      which allows you to keep track of all
                                              potential right-of-way grantors, whose                                                                        Docket Nos. ER13–1944, et al., PJM
                                                                                                      formal issuances and submittals in
                                              property may be used temporarily for                                                                               Interconnection, L.L.C.
                                                                                                      specific dockets. This can reduce the
                                              Project purposes, or who own homes                                                                            Docket No. ER15–1344, PJM
                                                                                                      amount of time you spend researching
                                              within certain distances of aboveground                                                                            Interconnection, L.L.C.
                                                                                                      proceedings by automatically providing
                                              facilities, and anyone who submits                                                                            Docket No. ER15–1387, PJM
                                                                                                      you with notification of these filings,
                                              comments on the Project. We will                                                                                   Transmission Owners
                                                                                                      document summaries, and direct links
                                              update the environmental mailing list as                                                                      Docket No. ER15–2648, PJM
                                                                                                      to the documents. Go to www.ferc.gov/
                                              the analysis proceeds to ensure that we                                                                            Interconnection, L.L.C.
                                                                                                      docs-filing/esubscription.asp.                        Docket No. ER15–2562, PJM
                                              send the information related to this                       Finally, public meetings or site visits
                                              environmental review to all individuals,                                                                           Interconnection, L.L.C.
                                                                                                      will be posted on the Commission’s
                                              organizations, and government entities                                                                        Docket No. ER15–2563, PJM
                                                                                                      calendar located at www.ferc.gov/
                                              interested in and/or potentially affected                                                                          Interconnection, L.L.C.
                                                                                                      EventCalendar/EventsList.aspx along
                                              by the proposed Project.                                                                                      Docket No. EL15–18, Consolidated
                                                                                                      with other related information.
                                                 When we publish and distribute the                                                                              Edison Company of New York, Inc.
                                                                                                        Dated: September 30, 2015.                               v. PJM Interconnection, L.L.C.
                                              EIS, copies will be sent to the
                                              environmental mailing list for public                   Kimberly D. Bose,                                     Docket No. EL15–41, Essential Power
                                              review and comment. If you would                        Secretary.                                                 Rock Springs, LLC et al. v. PJM
                                              prefer to receive a paper copy of the                   [FR Doc. 2015–25387 Filed 10–5–15; 8:45 am]                Interconnection, L.L.C.
                                              document instead of the CD version or                   BILLING CODE 6717–01–P                                Docket No. ER13–1927, et al., PJM
                                              would like to remove your name from                                                                                Interconnection—SERTP
                                              the mailing list, please return the                                                                           Docket No. ER15–2114, PJM
                                              attached Information Request                            DEPARTMENT OF ENERGY                                       Interconnection, L.L.C. and
                                              (Appendix 2).                                                                                                      Transource West Virginia, LLC
                                                                                                      Federal Energy Regulatory                             Docket No. EL15–79, TransSource, LLC
                                              Becoming an Intervenor                                  Commission                                                 v. PJM Interconnection, L.L.C.
                                                 Once Louisiana LNG files its                                                                               Docket No. EL15–95, Delaware Public
                                                                                                      Notice of Commission Staff                                 Service Commission et al., v. PJM
                                              application with the Commission, you
                                                                                                      Attendance                                                 Interconnection, L.L.C. et al.
                                              may want to become an ‘‘intervenor’’
                                                                                                                                                            Docket No. EL15–67, Linden VFT, LLC
tkelley on DSK3SPTVN1PROD with NOTICES




                                              which is an official party to the                          The Federal Energy Regulatory
                                              Commission’s proceeding. Intervenors                    Commission (Commission) hereby gives                       v. PJM Interconnection, L.L.C.
                                              play a more formal role in the process                  notice that members of the                            Docket No. EL05–121, PJM
                                              and are able to file briefs, appear at                  Commission’s staff may attend the                          Interconnection, L.L.C.
                                              hearings, and be heard by the courts if                 following meetings related to the                        For more information, contact the
                                              they choose to appeal the Commission’s                  transmission planning activities of the               following: Jonathan Fernandez, Office of
                                              final ruling. An intervenor formally                    PJM Interconnection, L.L.C. (PJM):                    Energy Market Regulation, Federal


                                         VerDate Sep<11>2014   18:31 Oct 05, 2015   Jkt 238001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\06OCN1.SGM   06OCN1



Document Created: 2015-12-15 08:51:04
Document Modified: 2015-12-15 08:51:04
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 60377 