80_FR_63751 80 FR 63549 - Crescent Point Energy U.S. Corp., Eagle Rock Exploration Ltd.; Notice of Application

80 FR 63549 - Crescent Point Energy U.S. Corp., Eagle Rock Exploration Ltd.; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 202 (October 20, 2015)

Page Range63549-63550
FR Document2015-26540

Federal Register, Volume 80 Issue 202 (Tuesday, October 20, 2015)
[Federal Register Volume 80, Number 202 (Tuesday, October 20, 2015)]
[Notices]
[Pages 63549-63550]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-26540]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-561-000]


Crescent Point Energy U.S. Corp., Eagle Rock Exploration Ltd.; 
Notice of Application

    Take notice that on September 29, 2015, Crescent Point Energy U.S. 
Corp. (Crescent Point), 555 17th Street, Suite 1800, Denver, Colorado 
80202 and Eagle Rock Exploration Ltd. (Eagle Rock), 300, 340-12th 
Avenue SW., Calgary, Alberta T2R IL5, filed a joint application in the 
above-referenced docket seeking authorization under section 3 of the 
Natural Gas Act (NGA) and Part 153 of the Commission's regulations to: 
(i) Transfer to Crescent Point the NGA section 3 authorization and 
Presidential Permit that were issued to Eagle Rock on August 5, 2008, 
in Docket No. CP08-90-000; and (ii) amend the section 3 Authorization 
and Permit so that it reflects Crescent Point as the current owner and 
operator of the existing border crossing facility located at the 
international boundary between Glacier County, Montana, and the 
Province of Alberta, Canada (Border Crossing Facility). Additionally, 
Crescent Point

[[Page 63550]]

requests the Commission to vacate its section 3 authorization and 
terminate its Presidential Permit so that it may properly abandon in-
place the Border Crossing Facility, all as more fully set forth in the 
application which is on file with the Commission and open to public 
inspection. The filing may also be viewed on the web at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions concerning this application may be directed to Marcus 
Sisk, Dorsey & Whitney LLP, 1801 K Street NW., Suite 750, Washington, 
DC 20006, by telephone at (202) 442-3000, or by email at 
[email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made in the proceeding with the 
Commission and must mail a copy to the applicant and to every other 
party. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and five copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426.
    Comment Date: November 3, 2015.

    Dated: October 13, 2015.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-26540 Filed 10-19-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                                       Federal Register / Vol. 80, No. 202 / Tuesday, October 20, 2015 / Notices                                                                                     63549

                                                     b. Project No.: 13642–003.                                           serve a copy of the request on the                                        foot-high, 500- and 750-foot-long
                                                     c. Date filed: October 1, 2015.                                      applicant.                                                                concrete-faced rockfill dams; (6) a
                                                     d. Applicant: GB Energy Park, LLC.                                     l. Deadline for filing additional study                                 partially buried 338-foot-long, 109-foot-
                                                     e. Name of Project: Gordon Butte                                     requests and requests for cooperating                                     wide, 74-foot-high reinforced concrete
                                                  Pumped Storage Project.                                                 agency status: November 30, 2015.                                         and steel powerhouse with four 100-
                                                     f. Location: Approximately 3 miles                                     The Commission strongly encourages                                      megawatt (MW) ternary Pelton turbine/
                                                  west of the City of Martinsdale, Meagher                                electronic filing. Please file additional                                 pump/generators; (7) a 600-foot-long,
                                                  County, Montana. The proposed project                                   study requests and requests for                                           200-foot-wide substation at the
                                                  would not occupy any federal lands.                                     cooperating agency status using the                                       powerhouse site with 13.8- kilovolt (kV)
                                                     g. Filed Pursuant to: Federal Power                                  Commission’s eFiling system at http://                                    to 230–kV step-up transformers; (8) a
                                                  Act 16 U.S.C. 791(a)–825(r)                                             www.ferc.gov/docs-filing/efiling.asp. For                                 5.7-mile-long, 230-kV transmission line;
                                                     h. Applicant Contact: Carl. E.                                       assistance, please contact FERC Online                                    (9) a substation with a 230–kV to 500–
                                                  Borgquist, President, GB Energy Park,                                   Support at FERCOnlineSupport@                                             kV step-up transformer, connecting to
                                                  LLC, 209 Wilson Avenue, P.O. Box 309,                                   ferc.gov, (866) 208–3676 (toll free), or                                  an existing non-project 500-kV
                                                  Bozeman, MT 59771; (406) 585–3006;                                      (202) 502–8659 (TTY). In lieu of                                          transmission line; and (11) appurtenant
                                                  carl@absarokaenergy.com.                                                electronic filing, please send a paper                                    facilities. The project is estimated to
                                                     i. FERC Contact: Mike Tust; (202)                                    copy to: Secretary, Federal Energy                                        provide 1,300 gigawatt-hours annually.
                                                  502–6522; michael.tust@ferc.gov.                                        Regulatory Commission, 888 First Street                                   No federal lands are included in the
                                                     j. Cooperating agencies: Federal, state,                             NE., Washington, DC 20426. The first                                      project.
                                                  local, and tribal agencies with                                         page of any filing should include docket                                     o. A copy of the application is
                                                  jurisdiction and/or special expertise                                   number P–13642–003.                                                       available for review at the Commission
                                                  with respect to environmental issues                                       m. The application is not ready for
                                                                                                                                                                                                    in the Public Reference Room or may be
                                                  that wish to cooperate in the                                           environmental analysis at this time.
                                                                                                                                                                                                    viewed on the Commission’s Web site at
                                                  preparation of the environmental                                           n. The Gordon Butte Pumped Storage
                                                                                                                                                                                                    http://www.ferc.gov using the
                                                  document should follow the                                              Project would consist of the following
                                                                                                                                                                                                    ‘‘eLibrary’’ link. Enter the docket
                                                  instructions for filing such requests                                   new facilities: (1) A manually operated
                                                                                                                                                                                                    number excluding the last three digits in
                                                  described in item l below. Cooperating                                  head gate on an existing irrigation canal
                                                                                                                                                                                                    the docket number field to access the
                                                  agencies should note the Commission’s                                   that provides initial fill and annual
                                                                                                                                                                                                    document. For assistance, contact FERC
                                                  policy that agencies that cooperate in                                  make-up water to the lower reservoir
                                                                                                                                                                                                    Online Support. A copy is also available
                                                  the preparation of the environmental                                    from the existing irrigation canal; (2) a
                                                                                                                                                                                                    for inspection and reproduction at the
                                                  document cannot also intervene. See, 94                                 3,000-foot-long, 1,000-foot-wide upper
                                                                                                                                                                                                    address in item h above.
                                                  FERC ¶ 61,076 (2001).                                                   reservoir created by a 60-foot-high,
                                                     k. Pursuant to section 4.32(b)(7) of 18                              7,500-foot-long concrete-faced rockfill                                      You may also register online at http://
                                                  CFR of the Commission’s regulations, if                                 dam; (3) a reinforced concrete intake/                                    www.ferc.gov/docs-filing/
                                                  any resource agency, Indian Tribe, or                                   outlet structure at the upper reservoir                                   esubscription.asp to be notified via
                                                  person believes that an additional                                      with six gated intake bays converging                                     email of new filings and issuances
                                                  scientific study should be conducted in                                 into a central 18-foot-diameter, 750-foot-                                related to this or other pending projects.
                                                  order to form an adequate factual basis                                 long vertical shaft; (4) an 18-foot-                                      For assistance, contact FERC Online
                                                  for a complete analysis of the                                          diameter, 3,000-foot-long concrete and                                    Support.
                                                  application on its merit, the resource                                  steel-lined penstock tunnel leading from                                     p. Procedural schedule: The
                                                  agency, Indian Tribe, or person must file                               the upper reservoir to the lower                                          application will be processed according
                                                  a request for a study with the                                          reservoir; (5) a 2,300-foot-long, 1,900-                                  to the following preliminary Hydro
                                                  Commission not later than 60 days from                                  foot-wide lower reservoir created by a                                    Licensing Schedule. Revisions to the
                                                  the date of filing of the application, and                              combination of excavation and two 60-                                     schedule will be made as appropriate.

                                                  Issue Acceptance or Deficiency Letter (if needed) ...................................................................................................................                     November 2015.
                                                  Request for Additional Information ...........................................................................................................................................            November 2015.
                                                  Issue Notice of Acceptance/Notice of Ready for Environmental Analysis .............................................................................                                       January 2016.
                                                  Commission Issues EA ................................................................................................................................................................     July 2016.
                                                  Comments on EA ........................................................................................................................................................................   August 2016.


                                                    Dated: October 14, 2015.                                              DEPARTMENT OF ENERGY                                                      above-referenced docket seeking
                                                  Kimberly D. Bose,                                                                                                                                 authorization under section 3 of the
                                                  Secretary.                                                              Federal Energy Regulatory                                                 Natural Gas Act (NGA) and Part 153 of
                                                                                                                          Commission                                                                the Commission’s regulations to: (i)
                                                  [FR Doc. 2015–26544 Filed 10–19–15; 8:45 am]
                                                                                                                                                                                                    Transfer to Crescent Point the NGA
                                                  BILLING CODE 6717–01–P
                                                                                                                          [Docket No. CP15–561–000]                                                 section 3 authorization and Presidential
                                                                                                                                                                                                    Permit that were issued to Eagle Rock
                                                                                                                          Crescent Point Energy U.S. Corp.,
                                                                                                                                                                                                    on August 5, 2008, in Docket No. CP08–
                                                                                                                          Eagle Rock Exploration Ltd.; Notice of
                                                                                                                                                                                                    90–000; and (ii) amend the section 3
                                                                                                                          Application
                                                                                                                                                                                                    Authorization and Permit so that it
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                            Take notice that on September 29,                                       reflects Crescent Point as the current
                                                                                                                          2015, Crescent Point Energy U.S. Corp.                                    owner and operator of the existing
                                                                                                                          (Crescent Point), 555 17th Street, Suite                                  border crossing facility located at the
                                                                                                                          1800, Denver, Colorado 80202 and Eagle                                    international boundary between Glacier
                                                                                                                          Rock Exploration Ltd. (Eagle Rock), 300,                                  County, Montana, and the Province of
                                                                                                                          340–12th Avenue SW., Calgary, Alberta                                     Alberta, Canada (Border Crossing
                                                                                                                          T2R IL5, filed a joint application in the                                 Facility). Additionally, Crescent Point


                                             VerDate Sep<11>2014        17:55 Oct 19, 2015        Jkt 238001      PO 00000       Frm 00052       Fmt 4703      Sfmt 4703      E:\FR\FM\20OCN1.SGM              20OCN1


                                                  63550                             Federal Register / Vol. 80, No. 202 / Tuesday, October 20, 2015 / Notices

                                                  requests the Commission to vacate its                             the date of issuance of the Commission                                Persons who wish to comment only
                                                  section 3 authorization and terminate its                         staff’s FEIS or EA.                                                on the environmental review of this
                                                  Presidential Permit so that it may                                   There are two ways to become                                    project should submit an original and
                                                  properly abandon in-place the Border                              involved in the Commission’s review of                             two copies of their comments to the
                                                  Crossing Facility, all as more fully set                          this project. First, any person wishing to                         Secretary of the Commission.
                                                  forth in the application which is on file                         obtain legal status by becoming a party                            Environmental commentors will be
                                                  with the Commission and open to                                   to the proceedings for this project                                placed on the Commission’s
                                                  public inspection. The filing may also                            should, on or before the comment date                              environmental mailing list, will receive
                                                  be viewed on the web at http://                                                                                                      copies of the environmental documents,
                                                                                                                    stated below file with the Federal
                                                  www.ferc.gov using the ‘‘eLibrary’’ link.                                                                                            and will be notified of meetings
                                                                                                                    Energy Regulatory Commission, 888
                                                  Enter the docket number excluding the                                                                                                associated with the Commission’s
                                                                                                                    First Street NE., Washington, DC 20426,
                                                  last three digits in the docket number                                                                                               environmental review process.
                                                                                                                    a motion to intervene in accordance
                                                  field to access the document. For                                                                                                    Environmental commentors will not be
                                                                                                                    with the requirements of the
                                                  assistance, contact FERC at                                                                                                          required to serve copies of filed
                                                                                                                    Commission’s Rules of Practice and
                                                  FERCOnlineSupport@ferc.gov or call                                                                                                   documents on all other parties.
                                                                                                                    Procedure (18 CFR 385.214 or 385.211)
                                                  toll-free, (866) 208–3676 or TTY, (202)                                                                                              However, the non-party commentors
                                                                                                                    and the Regulations under the NGA (18
                                                  502–8659.                                                                                                                            will not receive copies of all documents
                                                                                                                    CFR 157.10). A person obtaining party
                                                                                                                                                                                       filed by other parties or issued by the
                                                     Any questions concerning this                                  status will be placed on the service list
                                                                                                                                                                                       Commission (except for the mailing of
                                                  application may be directed to Marcus                             maintained by the Secretary of the                                 environmental documents issued by the
                                                  Sisk, Dorsey & Whitney LLP, 1801 K                                Commission and will receive copies of                              Commission) and will not have the right
                                                  Street NW., Suite 750, Washington, DC                             all documents filed by the applicant and                           to seek court review of the
                                                  20006, by telephone at (202) 442–3000,                            by all other parties. A party must submit                          Commission’s final order.
                                                  or by email at sisk.marcus@dorsey.com.                            five copies of filings made in the                                    The Commission strongly encourages
                                                     Pursuant to section 157.9 of the                               proceeding with the Commission and                                 electronic filings of comments, protests
                                                  Commission’s rules, 18 CFR 157.9,                                 must mail a copy to the applicant and                              and interventions in lieu of paper using
                                                  within 90 days of this Notice the                                 to every other party. Only parties to the                          the ‘‘eFiling’’ link at http://
                                                  Commission staff will either: Complete                            proceeding can ask for court review of                             www.ferc.gov. Persons unable to file
                                                  its environmental assessment (EA) and                             Commission orders in the proceeding.                               electronically should submit an original
                                                  place it into the Commission’s public                                However, a person does not have to                              and five copies of the protest or
                                                  record (eLibrary) for this proceeding; or                         intervene in order to have comments                                intervention to the Federal Energy
                                                  issue a Notice of Schedule for                                    considered. The second way to                                      Regulatory Commission, 888 First Street
                                                  Environmental Review. If a Notice of                              participate is by filing with the                                  NE., Washington, DC 20426.
                                                  Schedule for Environmental Review is                              Secretary of the Commission, as soon as                               Comment Date: November 3, 2015.
                                                  issued, it will indicate, among other                             possible, an original and two copies of                              Dated: October 13, 2015.
                                                  milestones, the anticipated date for the                          comments in support of or in opposition                            Kimberly D. Bose,
                                                  Commission staff’s issuance of the final                          to this project. The Commission will
                                                                                                                                                                                       Secretary.
                                                  environmental impact statement (FEIS)                             consider these comments in
                                                                                                                                                                                       [FR Doc. 2015–26540 Filed 10–19–15; 8:45 am]
                                                  or EA for this proposal. The filing of the                        determining the appropriate action to be
                                                                                                                                                                                       BILLING CODE 6717–01–P
                                                  EA in the Commission’s public record                              taken, but the filing of a comment alone
                                                  for this proceeding or the issuance of a                          will not serve to make the filer a party
                                                  Notice of Schedule for Environmental                              to the proceeding. The Commission’s
                                                                                                                                                                                       DEPARTMENT OF ENERGY
                                                  Review will serve to notify federal and                           rules require that persons filing
                                                  state agencies of the timing for the                              comments in opposition to the project                              Federal Energy Regulatory
                                                  completion of all necessary reviews, and                          provide copies of their protests only to                           Commission
                                                  the subsequent need to complete all                               the party or parties directly involved in
                                                  federal authorizations within 90 days of                          the protest.                                                       Notice of Cultural Resource Meeting

                                                  Beverly Lock and Dam Water Power ...................................................................................................................   Project   No.   13404–002
                                                  Devola Lock and Dam Water Power Project .......................................................................................................        Project   No.   13405–002
                                                  Malta/McConnelsville Lock and Dam Water Power Project ..............................................................................                   Project   No.   13406–002
                                                  Lowell Lock and Dam Water Power Project .......................................................................................................        Project   No.   13407–002
                                                  Philo Lock and Dam Water Power Project ..........................................................................................................      Project   No.   13408–002
                                                  Rokeby Lock and Dam Water Power Project ......................................................................................................         Project   No.   13411–002


                                                    a. Project Name and Number: Beverly                               d. FERC Contact: Colleen Corballis,                                g. All local, state, and federal
                                                  Lock & Dam Water Power Project No.                                colleen.corballis@ferc.gov or (202) 502–                           agencies, Indian tribes, and other
                                                  13404; Devola Lock & Dam Water Power                              8598.                                                              interested parties are invited to
                                                  Project No. 13405; Malta Lock & Dam                                 e. Purpose of Meeting: Tribal                                    participate by phone. Please contact
                                                  Water Power Project No. 13406; Lowell                             consultation meeting to provide an                                 Colleen Corballis at colleen.corballis@
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Lock & Dam Water Power Project No.                                                                                                   ferc.gov or (202) 502–8598 by close of
                                                                                                                    overview of the above-listed six projects
                                                  13407; Philo Lock & Dam Water Power                                                                                                  business October 27, 2015, to R.S.V.P.
                                                                                                                    (Muskingum River Projects) and to
                                                  Project No. 13408; and Rokeby Lock &                                                                                                 and to receive specific instructions on
                                                                                                                    discuss the Seneca Nation’s comments
                                                  Dam Water Power Project No. 13411.                                                                                                   how to participate.
                                                    b. Date and Time of Meeting: October                            concerning the HPMPs.
                                                  29, 2015; 1:00 p.m. Eastern Time.                                   f. A summary of the meeting will be
                                                    c. Place: Telephone conference with                             prepared and filed in the Commission’s
                                                  the Seneca Nation.                                                public file for the project.


                                             VerDate Sep<11>2014      17:55 Oct 19, 2015      Jkt 238001    PO 00000      Frm 00053     Fmt 4703     Sfmt 4703     E:\FR\FM\20OCN1.SGM           20OCN1



Document Created: 2015-12-14 15:25:50
Document Modified: 2015-12-14 15:25:50
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesNovember 3, 2015.
FR Citation80 FR 63549 

2024 Federal Register | Disclaimer | Privacy Policy