80_FR_65942 80 FR 65735 - Dominion Transmission, Inc.; Notice of Availability of the Environmental Assessment for the Proposed New Market Project

80 FR 65735 - Dominion Transmission, Inc.; Notice of Availability of the Environmental Assessment for the Proposed New Market Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 207 (October 27, 2015)

Page Range65735-65735
FR Document2015-27179

Federal Register, Volume 80 Issue 207 (Tuesday, October 27, 2015)
[Federal Register Volume 80, Number 207 (Tuesday, October 27, 2015)]
[Notices]
[Page 65735]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-27179]



[[Page 65735]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP14-497-000]


Dominion Transmission, Inc.; Notice of Availability of the 
Environmental Assessment for the Proposed New Market Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the New 
Market Project, proposed by Dominion Transmission, Inc. (DTI) in the 
above-referenced docket. DTI requests authorization to construct and 
operate new compressors and associated improvements at new and existing 
facilities in several counties in New York.
    The EA assesses the potential environmental effects of the 
construction and operation of the New Market Project in accordance with 
the requirements of the National Environmental Policy Act. The FERC 
staff concludes that approval of the proposed project, with appropriate 
mitigating measures, would not constitute a major federal action 
significantly affecting the quality of the human environment.
    The proposed New Market Project includes the following facilities:
     Construction of the new Horseheads Compressor Station in 
Chemung County;
     installation of gas coolers and filter/separator at the 
existing Borger Compressor Station in Tompkins County;
     construction of the new Sheds Compressor Station in 
Madison County;
     installation of gas coolers and filter/separator at the 
existing Utica Compressor Station in Herkimer County;
     installation of additional engine and turbine driven 
compressor units at the existing Brookman Corners Compressor Station in 
Montgomery County; and
     modifications to the existing West Schenectady Meter 
Station in Schenectady County.
    The FERC staff mailed copies of the EA to federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; newspapers and libraries in the project area; and parties to 
this proceeding. In addition, the EA is available for public viewing on 
the FERC's Web site (www.ferc.gov) using the eLibrary link. A limited 
number of copies of the EA are available for distribution and public 
inspection at: Federal Energy Regulatory Commission, Public Reference 
Room, 888 First Street NE., Room 2A, Washington, DC 20426, (202) 502-
8371.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that the Commission has the opportunity to consider your 
comments prior to making its decision on this project, it is important 
that we receive your comments in Washington, DC on or before November 
19, 2015.
    For your convenience, there are three methods you can use to file 
your comments to the Commission. In all instances, please reference the 
project docket number (CP14-497) with your submission. The Commission 
encourages electronic filing of comments and has expert staff available 
to assist you at (202) 502-8258 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the Commission's Rules of 
Practice and Procedures (18 CFR 385.214).\1\ Only intervenors have the 
right to seek rehearing of the Commission's decision. The Commission 
grants affected landowners and others with environmental concerns 
intervenor status upon showing good cause by stating that they have a 
clear and direct interest in this proceeding which no other party can 
adequately represent. Simply filing environmental comments will not 
give you intervenor status, but you do not need intervenor status to 
have your comments considered.
---------------------------------------------------------------------------

    \1\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP14-
497). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: October 20, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-27179 Filed 10-26-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                           Federal Register / Vol. 80, No. 207 / Tuesday, October 27, 2015 / Notices                                               65735

                                              DEPARTMENT OF ENERGY                                    viewing on the FERC’s Web site                        The Commission grants affected
                                                                                                      (www.ferc.gov) using the eLibrary link.               landowners and others with
                                              Federal Energy Regulatory                               A limited number of copies of the EA                  environmental concerns intervenor
                                              Commission                                              are available for distribution and public             status upon showing good cause by
                                              [Docket No. CP14–497–000]                               inspection at: Federal Energy Regulatory              stating that they have a clear and direct
                                                                                                      Commission, Public Reference Room,                    interest in this proceeding which no
                                              Dominion Transmission, Inc.; Notice of                  888 First Street NE., Room 2A,                        other party can adequately represent.
                                              Availability of the Environmental                       Washington, DC 20426, (202) 502–8371.                 Simply filing environmental comments
                                              Assessment for the Proposed New                            Any person wishing to comment on                   will not give you intervenor status, but
                                              Market Project                                          the EA may do so. Your comments                       you do not need intervenor status to
                                                                                                      should focus on the potential                         have your comments considered.
                                                The staff of the Federal Energy                       environmental effects, reasonable                        Additional information about the
                                              Regulatory Commission (FERC or                          alternatives, and measures to avoid or                project is available from the
                                              Commission) has prepared an                             lessen environmental impacts. The more                Commission’s Office of External Affairs,
                                              environmental assessment (EA) for the                   specific your comments, the more useful               at (866) 208–FERC, or on the FERC Web
                                              New Market Project, proposed by                         they will be. To ensure that the                      site (www.ferc.gov) using the eLibrary
                                              Dominion Transmission, Inc. (DTI) in                    Commission has the opportunity to                     link. Click on the eLibrary link, click on
                                              the above-referenced docket. DTI                        consider your comments prior to                       ‘‘General Search,’’ and enter the docket
                                              requests authorization to construct and                 making its decision on this project, it is            number excluding the last three digits in
                                              operate new compressors and associated                  important that we receive your                        the Docket Number field (i.e., CP14–
                                              improvements at new and existing                        comments in Washington, DC on or                      497). Be sure you have selected an
                                              facilities in several counties in New                   before November 19, 2015.                             appropriate date range. For assistance,
                                              York.                                                      For your convenience, there are three              please contact FERC Online Support at
                                                The EA assesses the potential                         methods you can use to file your                      FercOnlineSupport@ferc.gov or toll free
                                              environmental effects of the                            comments to the Commission. In all                    at (866) 208–3676, or for TTY, contact
                                              construction and operation of the New                   instances, please reference the project               (202) 502–8659. The eLibrary link also
                                              Market Project in accordance with the                   docket number (CP14–497) with your                    provides access to the texts of formal
                                              requirements of the National                            submission. The Commission                            documents issued by the Commission,
                                              Environmental Policy Act. The FERC                      encourages electronic filing of                       such as orders, notices, and
                                              staff concludes that approval of the                    comments and has expert staff available               rulemakings.
                                              proposed project, with appropriate                      to assist you at (202) 502–8258 or                       In addition, the Commission offers a
                                              mitigating measures, would not                          efiling@ferc.gov.                                     free service called eSubscription which
                                              constitute a major federal action                          (1) You can file your comments
                                                                                                                                                            allows you to keep track of all formal
                                              significantly affecting the quality of the              electronically using the eComment
                                                                                                                                                            issuances and submittals in specific
                                              human environment.                                      feature on the Commission’s Web site
                                                                                                                                                            dockets. This can reduce the amount of
                                                The proposed New Market Project                       (www.ferc.gov) under the link to
                                                                                                                                                            time you spend researching proceedings
                                              includes the following facilities:                      Documents and Filings. This is an easy
                                                                                                                                                            by automatically providing you with
                                                • Construction of the new Horseheads                  method for submitting brief, text-only
                                                                                                                                                            notification of these filings, document
                                              Compressor Station in Chemung                           comments on a project;
                                                                                                         (2) You can also file your comments                summaries, and direct links to the
                                              County;
                                                • installation of gas coolers and filter/             electronically using the eFiling feature              documents. Go to www.ferc.gov/docs-
                                              separator at the existing Borger                        on the Commission’s Web site                          filing/esubscription.asp.
                                              Compressor Station in Tompkins                          (www.ferc.gov) under the link to                        Dated: October 20, 2015.
                                              County;                                                 Documents and Filings. With eFiling,                  Kimberly D. Bose,
                                                • construction of the new Sheds                       you can provide comments in a variety                 Secretary.
                                              Compressor Station in Madison County;                   of formats by attaching them as a file                [FR Doc. 2015–27179 Filed 10–26–15; 8:45 am]
                                                • installation of gas coolers and filter/             with your submission. New eFiling                     BILLING CODE 6717–01–P
                                              separator at the existing Utica                         users must first create an account by
                                              Compressor Station in Herkimer                          clicking on ‘‘eRegister.’’ You must select
                                              County;                                                 the type of filing you are making. If you             DEPARTMENT OF ENERGY
                                                • installation of additional engine                   are filing a comment on a particular
                                              and turbine driven compressor units at                  project, please select ‘‘Comment on a                 Federal Energy Regulatory
                                              the existing Brookman Corners                           Filing’’; or                                          Commission
                                              Compressor Station in Montgomery                           (3) You can file a paper copy of your
                                              County; and                                             comments by mailing them to the                       [Docket No. ER16–89–000]
                                                • modifications to the existing West                  following address: Kimberly D. Bose,
                                              Schenectady Meter Station in                            Secretary, Federal Energy Regulatory                  Jether Energy Research, Ltd.;
                                              Schenectady County.                                     Commission, 888 First Street NE., Room                Supplemental Notice That Initial
                                                The FERC staff mailed copies of the                   1A, Washington, DC 20426.                             Market-Based Rate Filing Includes
                                              EA to federal, state, and local                            Any person seeking to become a party               Request for Blanket Section 204
                                              government representatives and                          to the proceeding must file a motion to               Authorization
                                              agencies; elected officials;                            intervene pursuant to Rule 214 of the
tkelley on DSK3SPTVN1PROD with NOTICES




                                              environmental and public interest                       Commission’s Rules of Practice and                      This is a supplemental notice in the
                                              groups; Native American tribes;                         Procedures (18 CFR 385.214).1 Only                    above-referenced proceeding of Jether
                                              potentially affected landowners and                     intervenors have the right to seek                    Energy Research, Ltd.’s application for
                                              other interested individuals and groups;                rehearing of the Commission’s decision.               market-based rate authority, with an
                                              newspapers and libraries in the project                                                                       accompanying rate tariff, noting that
                                              area; and parties to this proceeding. In                   1 See the previous discussion on the methods for   such application includes a request for
                                              addition, the EA is available for public                filing comments.                                      blanket authorization, under 18 CFR


                                         VerDate Sep<11>2014   19:58 Oct 26, 2015   Jkt 238001   PO 00000   Frm 00049   Fmt 4703   Sfmt 4703   E:\FR\FM\27OCN1.SGM   27OCN1



Document Created: 2015-12-14 15:36:41
Document Modified: 2015-12-14 15:36:41
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 65735 