DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 240 (December 15, 2015)

Page Range77621-77623
FR Document2015-31473

Federal Register, Volume 80 Issue 240 (Tuesday, December 15, 2015)
[Federal Register Volume 80, Number 240 (Tuesday, December 15, 2015)]
[Notices]
[Pages 77621-77623]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-31473]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-12-000]


Tennessee Gas Pipeline Company, L.L.C.; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Southwest 
Louisiana Supply Project and Request for Comments on Environmental 
Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Southwest Louisiana Supply 
Project (Project) involving construction and operation of facilities by 
Tennessee Gas Pipeline Company, L.L.C. (Tennessee) in Madison, 
Franklin, Richland, and Rapides Parishes, Louisiana. The Commission 
will use this EA in its decision-making process to determine whether 
the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before January 11, 2016.
    If you sent comments on this project to the Commission before the 
opening of this docket on October 26, 2015, you will need to file those 
comments in Docket No. CP16-12-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Tennessee provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully

[[Page 77622]]

follow these instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP16-12-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    The purpose of the Southwest Louisiana Supply Project is to provide 
295,000 dekatherms per day of firm natural gas capacity to Tennessee's 
800 Line. The Southwest Louisiana Supply Project would consist of 
construction and modification of the following facilities:
     Construction of a new 2.4-mile-long, 30-inch-diameter 
lateral pipeline to be known as the Delhi North Lateral and two new 
meter station interconnects to be known as the Midcontinent Express 
Pipeline Meter Station (MEP Meter Station) and the Gulf Crossing 
Pipeline Meter Station (Gulf Crossing Meter Station) in Madison Parish, 
Louisiana;
     construction of a new 1.4-mile-long-30-inch-diameter 
lateral pipeline to be known as the Delhi South Latera, three new meter 
station interconnects to be known as the Enable Midstream Partners 
Meter Station (Enable Meter Station), the Gulf South Pipeline Meter 
Station (Gulf South Meter Station), and the Tiger Pipeline Meter 
Station (Tiger Meter Station) in Franklin and Richland Parishes, 
Louisiana;
     construction of a new compressor station to be known as 
the Delhi Compressor Station 836A in Franklin, Parish, Louisiana; and
     modifications at the Alexandria Compressor Station, 
including turbine replacement in Rapides Parish, Louisiana.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb approximately 
108.4 acres of land for the aboveground facilities and the pipeline. 
Following construction, Tennessee would maintain about 76.5 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries

[[Page 77623]]

and newspapers. This list also includes all affected landowners (as 
defined in the Commission's regulations) who are potential right-of-way 
grantors, whose property may be used temporarily for project purposes, 
or who own homes within certain distances of aboveground facilities, 
and anyone who submits comments on the project. We will update the 
environmental mailing list as the analysis proceeds to ensure that we 
send the information related to this environmental review to all 
individuals, organizations, and government entities interested in and/
or potentially affected by the proposed project.
    If we publish and distribute the EA, copies of the EA will be sent 
to the environmental mailing list for public review and comment. If you 
would prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP16-
12-000). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: December 9, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-31473 Filed 12-14-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                     Federal Register / Vol. 80, No. 240 / Tuesday, December 15, 2015 / Notices                                                77621

                                                                                                             1022ST—MEETING, REGULAR MEETING—Continued
                                                                                                                                    [December 17, 2015, 10 a.m.]

                                                     Item No.                              Docket No.                                                                        Company

                                                                                                                                              HYDRO

                                                    H–1 ........     P–349–173 ..................................................   Alabama Power Company.
                                                    H–2 ........     P–2210–252 ................................................    Appalachian Power Company.

                                                                                                                                          CERTIFICATES

                                                    C–1 ........     CP14–119–000 ............................................      Trunkline Gas Company, LLC.
                                                                     CP14–120–000 ............................................      Lake Charles LNG Export Company, LLC and Lake Charles LNG Company, LLC.
                                                                     CP14–122–000 ............................................      Lake Charles LNG Company, LLC.
                                                    C–2   ........   CP15–523–000 ............................................      American Midstream (Midla), LLC.
                                                    C–3   ........   CP14–501–000 ............................................      National Fuel Gas Supply Corporation.
                                                    C–4   ........   CP15–90–000 ..............................................     Texas Eastern Transmission, LP.
                                                    C–5   ........   CP15–132–000 ............................................      Kern River Gas Transmission Company.



                                                       A free webcast of this event is                                 DEPARTMENT OF ENERGY                                   this docket on October 26, 2015, you
                                                    available through www.ferc.gov. Anyone                                                                                    will need to file those comments in
                                                    with Internet access who desires to view                           Federal Energy Regulatory                              Docket No. CP16–12–000 to ensure they
                                                    this event can do so by navigating to                              Commission                                             are considered as part of this
                                                    www.ferc.gov’s Calendar of Events and                              [Docket No. CP16–12–000]                               proceeding.
                                                    locating this event in the Calendar. The                                                                                     This notice is being sent to the
                                                    event will contain a link to its webcast.                          Tennessee Gas Pipeline Company,                        Commission’s current environmental
                                                    The Capitol Connection provides                                    L.L.C.; Notice of Intent To Prepare an                 mailing list for this project. State and
                                                                                                                       Environmental Assessment for the                       local government representatives should
                                                    technical support for the free webcasts.
                                                                                                                       Proposed Southwest Louisiana Supply                    notify their constituents of this
                                                    It also offers access to this event via
                                                                                                                       Project and Request for Comments on                    proposed project and encourage them to
                                                    television in the DC area and via phone                                                                                   comment on their areas of concern.
                                                    bridge for a fee. If you have any                                  Environmental Issues
                                                                                                                                                                                 If you are a landowner receiving this
                                                    questions, visit                                                      The staff of the Federal Energy                     notice, a pipeline company
                                                    www.CapitolConnection.org or contact                               Regulatory Commission (FERC or                         representative may contact you about
                                                    Danelle Springer or David Reininger at                             Commission) will prepare an                            the acquisition of an easement to
                                                    703–993–3100.                                                      environmental assessment (EA) that will                construct, operate, and maintain the
                                                       Immediately following the conclusion                            discuss the environmental impacts of                   proposed facilities. The company would
                                                    of the Commission Meeting, a press                                 the Southwest Louisiana Supply Project                 seek to negotiate a mutually acceptable
                                                    briefing will be held in the Commission                            (Project) involving construction and                   agreement. However, if the Commission
                                                                                                                       operation of facilities by Tennessee Gas               approves the project, that approval
                                                    Meeting Room. Members of the public
                                                                                                                       Pipeline Company, L.L.C. (Tennessee)                   conveys with it the right of eminent
                                                    may view this briefing in the designated
                                                                                                                       in Madison, Franklin, Richland, and                    domain. Therefore, if easement
                                                    overflow room. This statement is
                                                                                                                       Rapides Parishes, Louisiana. The                       negotiations fail to produce an
                                                    intended to notify the public that the                             Commission will use this EA in its                     agreement, the pipeline company could
                                                    press briefings that follow Commission                             decision-making process to determine                   initiate condemnation proceedings
                                                    meetings may now be viewed remotely                                whether the project is in the public                   where compensation would be
                                                    at Commission headquarters, but will                               convenience and necessity.                             determined in accordance with state
                                                    not be telecast through the Capitol                                   This notice announces the opening of                law.
                                                    Connection service.                                                the scoping process the Commission                        Tennessee provided landowners with
                                                      Issued: December 10, 2015.                                       will use to gather input from the public               a fact sheet prepared by the FERC
                                                    Nathaniel J. Davis, Sr.,
                                                                                                                       and interested agencies on the project.                entitled ‘‘An Interstate Natural Gas
                                                                                                                       You can make a difference by providing                 Facility On My Land? What Do I Need
                                                    Deputy Secretary.
                                                                                                                       us with your specific comments or                      To Know?’’ This fact sheet addresses a
                                                    [FR Doc. 2015–31605 Filed 12–11–15; 4:15 pm]                       concerns about the project. Your                       number of typically asked questions,
                                                    BILLING CODE 6717–01–P                                             comments should focus on the potential                 including the use of eminent domain
                                                                                                                       environmental effects, reasonable                      and how to participate in the
                                                                                                                       alternatives, and measures to avoid or                 Commission’s proceedings. It is also
                                                                                                                       lessen environmental impacts. Your                     available for viewing on the FERC Web
                                                                                                                       input will help the Commission staff                   site (www.ferc.gov).
                                                                                                                       determine what issues they need to
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                       evaluate in the EA. To ensure that your                Public Participation
                                                                                                                       comments are timely and properly                         For your convenience, there are three
                                                                                                                       recorded, please send your comments so                 methods you can use to submit your
                                                                                                                       that the Commission receives them in                   comments to the Commission. The
                                                                                                                       Washington, DC on or before January 11,                Commission encourages electronic filing
                                                                                                                       2016.                                                  of comments and has expert staff
                                                                                                                          If you sent comments on this project                available to assist you at (202) 502–8258
                                                                                                                       to the Commission before the opening of                or efiling@ferc.gov. Please carefully


                                               VerDate Sep<11>2014       17:08 Dec 14, 2015      Jkt 238001     PO 00000      Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\15DEN1.SGM   15DEN1


                                                    77622                      Federal Register / Vol. 80, No. 240 / Tuesday, December 15, 2015 / Notices

                                                    follow these instructions so that your                    The general location of the project                  received during the scoping process, we
                                                    comments are properly recorded.                         facilities is shown in appendix 1.1                    may also publish and distribute the EA
                                                       (1) You can file your comments                                                                              to the public for an allotted comment
                                                    electronically using the eComment                       Land Requirements for Construction
                                                                                                                                                                   period. We will consider all comments
                                                    feature on the Commission’s Web site                      Construction of the proposed facilities              on the EA before making our
                                                    (www.ferc.gov) under the link to                        would disturb approximately 108.4                      recommendations to the Commission.
                                                    Documents and Filings. This is an easy                  acres of land for the aboveground                      To ensure we have the opportunity to
                                                    method for submitting brief, text-only                  facilities and the pipeline. Following                 consider and address your comments,
                                                    comments on a project;                                  construction, Tennessee would                          please carefully follow the instructions
                                                       (2) You can file your comments                       maintain about 76.5 acres for permanent                in the Public Participation section,
                                                    electronically by using the eFiling                     operation of the project’s facilities; the             beginning on page 2.
                                                    feature on the Commission’s Web site                    remaining acreage would be restored                      With this notice, we are asking
                                                    (www.ferc.gov) under the link to                        and revert to former uses.                             agencies with jurisdiction by law and/
                                                    Documents and Filings. With eFiling,                                                                           or special expertise with respect to the
                                                    you can provide comments in a variety                   The EA Process                                         environmental issues of this project to
                                                    of formats by attaching them as a file                     The National Environmental Policy                   formally cooperate with us in the
                                                    with your submission. New eFiling                       Act (NEPA) requires the Commission to                  preparation of the EA.3 Agencies that
                                                    users must first create an account by                   take into account the environmental                    would like to request cooperating
                                                    clicking on ‘‘eRegister.’’ If you are filing            impacts that could result from an action               agency status should follow the
                                                    a comment on a particular project,                      whenever it considers the issuance of a                instructions for filing comments
                                                    please select ‘‘Comment on a Filing’’ as                Certificate of Public Convenience and                  provided under the Public Participation
                                                    the filing type; or                                     Necessity. NEPA also requires us 2 to                  section of this notice.
                                                       (3) You can file a paper copy of your                discover and address concerns the
                                                                                                                                                                   Consultations Under Section 106 of the
                                                    comments by mailing them to the                         public may have about proposals. This
                                                                                                                                                                   National Historic Preservation Act
                                                    following address. Be sure to reference                 process is referred to as ‘‘scoping.’’ The
                                                    the project docket number (CP16–12–                     main goal of the scoping process is to                   In accordance with the Advisory
                                                    000) with your submission: Kimberly D.                  focus the analysis in the EA on the                    Council on Historic Preservation’s
                                                    Bose, Secretary, Federal Energy                         important environmental issues. By this                implementing regulations for section
                                                    Regulatory Commission, 888 First Street                 notice, the Commission requests public                 106 of the National Historic
                                                    NE., Room 1A, Washington, DC 20426.                     comments on the scope of the issues to                 Preservation Act, we are using this
                                                                                                            address in the EA. We will consider all                notice to initiate consultation with the
                                                    Summary of the Proposed Project                                                                                applicable State Historic Preservation
                                                                                                            filed comments during the preparation
                                                      The purpose of the Southwest                          of the EA.                                             Office (SHPO), and to solicit their views
                                                    Louisiana Supply Project is to provide                     In the EA we will discuss impacts that              and those of other government agencies,
                                                    295,000 dekatherms per day of firm                      could occur as a result of the                         interested Indian tribes, and the public
                                                    natural gas capacity to Tennessee’s 800                 construction and operation of the                      on the project’s potential effects on
                                                    Line. The Southwest Louisiana Supply                    proposed project under these general                   historic properties.4 We will define the
                                                    Project would consist of construction                   headings:                                              project-specific Area of Potential Effects
                                                    and modification of the following                          • Geology and soils;                                (APE) in consultation with the SHPO as
                                                    facilities:                                                • land use;                                         the project develops. On natural gas
                                                      • Construction of a new 2.4-mile-                        • water resources, fisheries, and                   facility projects, the APE at a minimum
                                                    long, 30-inch-diameter lateral pipeline                 wetlands;                                              encompasses all areas subject to ground
                                                    to be known as the Delhi North Lateral                     • cultural resources;                               disturbance (examples include
                                                    and two new meter station                                  • vegetation and wildlife;                          construction right-of-way, contractor/
                                                    interconnects to be known as the                           • air quality and noise;                            pipe storage yards, compressor stations,
                                                    Midcontinent Express Pipeline Meter                        • endangered and threatened species;                and access roads). Our EA for this
                                                    Station (MEP Meter Station) and the                        • public safety; and                                project will document our findings on
                                                    Gulf Crossing Pipeline Meter Station                       • cumulative impacts                                the impacts on historic properties and
                                                    (Gulf Crossing Meter Station) in                           We will also evaluate reasonable                    summarize the status of consultations
                                                    Madison Parish, Louisiana;                              alternatives to the proposed project or                under section 106.
                                                      • construction of a new 1.4-mile-long-                portions of the project, and make                      Environmental Mailing List
                                                    30-inch-diameter lateral pipeline to be                 recommendations on how to lessen or
                                                    known as the Delhi South Latera, three                  avoid impacts on the various resource                    The environmental mailing list
                                                    new meter station interconnects to be                   areas.                                                 includes federal, state, and local
                                                    known as the Enable Midstream                              The EA will present our independent                 government representatives and
                                                    Partners Meter Station (Enable Meter                    analysis of the issues. The EA will be                 agencies; elected officials;
                                                    Station), the Gulf South Pipeline Meter                 available in the public record through                 environmental and public interest
                                                    Station (Gulf South Meter Station), and                 eLibrary. Depending on the comments                    groups; Native American Tribes; other
                                                    the Tiger Pipeline Meter Station (Tiger                                                                        interested parties; and local libraries
                                                    Meter Station) in Franklin and Richland                   1 The appendices referenced in this notice will

                                                                                                            not appear in the Federal Register. Copies of            3 The Council on Environmental Quality
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    Parishes, Louisiana;
                                                      • construction of a new compressor                    appendices were sent to all those receiving this
                                                                                                            notice in the mail and are available at www.ferc.gov
                                                                                                                                                                   regulations addressing cooperating agency
                                                                                                                                                                   responsibilities are at Title 40, Code of Federal
                                                    station to be known as the Delhi                        using the link called ‘‘eLibrary’’ or from the         Regulations, Part 1501.6.
                                                    Compressor Station 836A in Franklin,                    Commission’s Public Reference Room, 888 First            4 The Advisory Council on Historic Preservation’s

                                                    Parish, Louisiana; and                                  Street NE., Washington, DC 20426, or call (202)        regulations are at Title 36, Code of Federal
                                                      • modifications at the Alexandria                     502–8371. For instructions on connecting to            Regulations, Part 800. Those regulations define
                                                                                                            eLibrary, refer to the last page of this notice.       historic properties as any prehistoric or historic
                                                    Compressor Station, including turbine                     2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the           district, site, building, structure, or object included
                                                    replacement in Rapides Parish,                          environmental staff of the Commission’s Office of      in or eligible for inclusion in the National Register
                                                    Louisiana.                                              Energy Projects.                                       of Historic Places.



                                               VerDate Sep<11>2014   17:08 Dec 14, 2015   Jkt 238001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\15DEN1.SGM    15DEN1


                                                                               Federal Register / Vol. 80, No. 240 / Tuesday, December 15, 2015 / Notices                                                77623

                                                    and newspapers. This list also includes                 allows you to keep track of all formal                FERC Online links at http://
                                                    all affected landowners (as defined in                  issuances and submittals in specific                  www.ferc.gov. To facilitate electronic
                                                    the Commission’s regulations) who are                   dockets. This can reduce the amount of                service, persons with Internet access
                                                    potential right-of-way grantors, whose                  time you spend researching proceedings                who will eFile a document and/or be
                                                    property may be used temporarily for                    by automatically providing you with                   listed as a contact for an intervenor
                                                    project purposes, or who own homes                      notification of these filings, document               must create and validate an
                                                    within certain distances of aboveground                 summaries, and direct links to the                    eRegistration account using the
                                                    facilities, and anyone who submits                      documents. Go to www.ferc.gov/docs-                   eRegistration link. Select the eFiling
                                                    comments on the project. We will                        filing/esubscription.asp.                             link to log on and submit the
                                                    update the environmental mailing list as                   Finally, public meetings or site visits            intervention or protests.
                                                    the analysis proceeds to ensure that we                 will be posted on the Commission’s                       Persons unable to file electronically
                                                    send the information related to this                    calendar located at www.ferc.gov/                     should submit an original and 5 copies
                                                    environmental review to all individuals,                EventCalendar/EventsList.aspx along                   of the intervention or protest to the
                                                    organizations, and government entities                  with other related information.                       Federal Energy Regulatory Commission,
                                                    interested in and/or potentially affected                 Dated: December 9, 2015.                            888 First Street NE., Washington, DC
                                                    by the proposed project.                                                                                      20426.
                                                       If we publish and distribute the EA,                 Nathaniel J. Davis, Sr.,
                                                                                                                                                                     The filings in the above proceeding
                                                    copies of the EA will be sent to the                    Deputy Secretary.
                                                                                                                                                                  are accessible in the Commission’s
                                                    environmental mailing list for public                   [FR Doc. 2015–31473 Filed 12–14–15; 8:45 am]
                                                                                                                                                                  eLibrary system by clicking on the
                                                    review and comment. If you would                        BILLING CODE 6717–01–P                                appropriate link in the above list. They
                                                    prefer to receive a paper copy of the                                                                         are also available for review in the
                                                    document instead of the CD version or                                                                         Commission’s Public Reference Room in
                                                    would like to remove your name from                     DEPARTMENT OF ENERGY                                  Washington, DC. There is an
                                                    the mailing list, please return the                                                                           eSubscription link on the Web site that
                                                    attached Information Request (appendix                  Federal Energy Regulatory
                                                                                                            Commission                                            enables subscribers to receive email
                                                    2).                                                                                                           notification when a document is added
                                                    Becoming an Intervenor                                  [Docket No. OR16–7–000]                               to a subscribed docket(s). For assistance
                                                                                                                                                                  with any FERC Online service, please
                                                       In addition to involvement in the EA                 Chicap Pipe Line Company; Notice Of                   email FERCOnlineSupport@ferc.gov or
                                                    scoping process, you may want to                        Petiton For Declaratory Order                         call (866) 208–3676 (toll free). For TTY,
                                                    become an ‘‘intervenor’’ which is an
                                                                                                               Take notice that on December 8, 2015,              call (202) 502–8659.
                                                    official party to the Commission’s
                                                                                                            pursuant to Rule 207(a)(2) of the                        Comment Date: 5:00 p.m. Eastern time
                                                    proceeding. Intervenors play a more
                                                                                                            Commission’s Rules of Practice and                    on January 8, 2016.
                                                    formal role in the process and are able
                                                    to file briefs, appear at hearings, and be              Procedure, 18 CFR 385.207(a)(2)(2015),                  Dated: December 9, 2015.
                                                    heard by the courts if they choose to                   Chicap Pipe Line Company (Chicap)                     Nathaniel J. Davis, Sr.,
                                                    appeal the Commission’s final ruling.                   filed a petition requesting a declaratory             Deputy Secretary.
                                                    An intervenor formally participates in                  order approving the overall tariff and                [FR Doc. 2015–31477 Filed 12–14–15; 8:45 am]
                                                    the proceeding by filing a request to                   rate structure, prorationing provisions,
                                                                                                                                                                  BILLING CODE 6717–01–P
                                                    intervene. Instructions for becoming an                 and other terms of service for the
                                                    intervenor are in the ‘‘Document-less                   expansion of Chicap’s existing Blue
                                                    Intervention Guide’’ under the ‘‘e-filing’’             Island Lateral crude oil pipeline                     DEPARTMENT OF ENERGY
                                                    link on the Commission’s Web site.                      (Project). The Project is intended to
                                                    Motions to intervene are more fully                     increase flow rates and add new bi-                   Federal Energy Regulatory
                                                    described at http://www.ferc.gov/                       directional capability between Blue                   Commission
                                                    resources/guides/how-to/intervene.asp.                  Island, Illinois to Mokena, Illinois, as
                                                                                                            more fully explained in the petition.                 Combined Notice of Filings #1
                                                    Additional Information                                     Any person desiring to intervene or to
                                                                                                                                                                     Take notice that the Commission
                                                       Additional information about the                     protest in this proceeding must file in
                                                                                                                                                                  received the following electric rate
                                                    project is available from the                           accordance with Rules 211 and 214 of
                                                                                                                                                                  filings:
                                                    Commission’s Office of External Affairs,                the Commission’s Rules of Practice and
                                                    at (866) 208–FERC, or on the FERC Web                   Procedure (18 CFR 385.211 and                         Docket Numbers: ER10–2633–022; ER10–
                                                    site at www.ferc.gov using the                          385.214) on or before 5:00 p.m. Eastern               2570–022; ER10–2717–022; ER10–3140–
                                                    ‘‘eLibrary’’ link. Click on the eLibrary                time on the specified comment date.                   021;ER13–55–012.
                                                    link, click on ‘‘General Search’’ and                   Protests will be considered by the                      Applicants: Birchwood Power
                                                    enter the docket number, excluding the                  Commission in determining the                         Partners, L.P., Shady Hills Power
                                                    last three digits in the Docket Number                  appropriate action to be taken, but will              Company, L.L.C., EFS Parlin Holdings,
                                                    field (i.e., CP16–12–000). Be sure you                  not serve to make protestants parties to              LLC, Inland Empire Energy Center, LLC,
                                                    have selected an appropriate date range.                the proceeding. Any person wishing to                 Homer City Generation, L.P.
                                                    For assistance, please contact FERC                     become a party must file a notice of                    Description: Notice of Non-Material
                                                    Online Support at FercOnlineSupport@                    intervention or motion to intervene, as               Change in Status of the GE Companies.
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    ferc.gov or toll free at (866) 208–3676, or             appropriate. Such notices, motions, or                  Filed Date: 12/8/15.
                                                    for TTY, contact (202) 502–8659. The                    protests must be filed on or before the                 Accession Number: 20151208–5217.
                                                    eLibrary link also provides access to the               comment date. Anyone filing a motion                    Comments Due: 5 p.m. ET 12/29/15.
                                                    texts of formal documents issued by the                 to intervene or protest must serve a copy               Docket Numbers: ER15–192–002.
                                                    Commission, such as orders, notices,                    of that document on the Petitioner.                     Applicants: Arizona Public Service
                                                    and rulemakings.                                           The Commission encourages                          Company.
                                                       In addition, the Commission offers a                 electronic submission of protests and                   Description: Compliance filing:
                                                    free service called eSubscription which                 interventions in lieu of paper, using the             Service Agreement Nos. 338, 339, 349,


                                               VerDate Sep<11>2014   17:08 Dec 14, 2015   Jkt 238001   PO 00000   Frm 00024   Fmt 4703   Sfmt 4703   E:\FR\FM\15DEN1.SGM   15DEN1



Document Created: 2018-03-02 09:16:40
Document Modified: 2018-03-02 09:16:40
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 77621 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR