80_FR_79278 80 FR 79035 - Intent To Prepare a Draft Feasibility Study and Environmental Impact Statement (EIS) for Navigational Improvements to Manatee Harbor in Manatee County, FL

80 FR 79035 - Intent To Prepare a Draft Feasibility Study and Environmental Impact Statement (EIS) for Navigational Improvements to Manatee Harbor in Manatee County, FL

DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers

Federal Register Volume 80, Issue 243 (December 18, 2015)

Page Range79035-79036
FR Document2015-31807

The purpose of the feasibility study is to improve navigation in Manatee Harbor.

Federal Register, Volume 80 Issue 243 (Friday, December 18, 2015)
[Federal Register Volume 80, Number 243 (Friday, December 18, 2015)]
[Notices]
[Pages 79035-79036]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-31807]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army, Corps of Engineers


Intent To Prepare a Draft Feasibility Study and Environmental 
Impact Statement (EIS) for Navigational Improvements to Manatee Harbor 
in Manatee County, FL

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DOD.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: The purpose of the feasibility study is to improve navigation 
in Manatee Harbor.

ADDRESSES: U.S. Army Corps of Engineers, Planning Division, 
Environmental Branch, P.O. Box 4970, Jacksonville, FL 32232-0019.

FOR FURTHER INFORMATION CONTACT: Dr. Aubree Hershorin at (904) 232-2136 
or email at [email protected].

SUPPLEMENTARY INFORMATION: 
    1. Description of the Proposed Action. Proposed navigational 
improvements to Manatee Harbor include deepening the harbor up to minus 
43 feet and widening the harbor.
    2. Reasonable Alternatives. Various increments of widening and 
deepening, as well as other alternatives will be evaluated. The dredged 
material is expected to be suitable for placement in the Ocean Dredged 
Material Disposal Site (ODMDS) located approximately 30 miles from the 
mouth of Tampa Bay. Some material may be suitable for placement in 
dredged holes and for other purposes, and the study may evaluate the 
expansion of existing dredged material management areas. Other 
alternatives as identified during the scoping and plan formulation 
process will be considered.
    3. Scoping Process:
    a. Public and Agency Involvement. A scoping letter is being sent to 
agencies, commercial interests, and the public.
    b. Issues to be Analyzed in Depth in the DEIS. Important issues 
expected include impacts to protected species, seagrass, hardgrounds, 
socio-economic factors, and any other factors that might be determined 
during the scoping and plan formulation process.
    c. Possible Assignments for Input into the EIS among Lead and 
Potential Cooperating Agencies.

--U.S. Fish and Wildlife Service: Input concerning listed species, 
critical habitat, and other fish and wildlife resources.
--National Marine Fisheries Service: Input concerning listed species,

[[Page 79036]]

critical habitat, and essential fish habitat.
--U.S. Environmental Protection Agency: Input concerning disposal in 
the Tampa ODMDS.
--The U.S. Army Corps of Engineers is the Lead agency and, together 
with the non-federal sponsor (Port Manatee), will assume responsibility 
for all other aspects of the EIS.

    d. Other Environmental Review and Consultation Requirements. The 
proposed action is subject to the requirements of the Endangered 
Species Act, Marine Mammal Protection Act, Essential Fish Habitat 
requirements, National Historic Preservation Act, numerous other laws 
and executive orders, and any other requirements that might be 
identified during the scoping and plan formulation process.
    4. Scoping Meeting. A public scoping meeting will be held on 
January 20, 2016, from 3:30 to 6:30 p.m. at the Port Manatee Intermodal 
Center, 1905 Intermodal Circle, Palmetto, FL 34221.
    5. Date the DEIS Will Be Made Available to the Public. Dependent on 
the issues, alternatives, investigations, and other requirements 
identified during the scoping and plan formulation process; the Draft 
EIS should be available by November 2017.

    Dated: December 10, 2015.
Eric P. Summa,
Chief, Planning Division.
[FR Doc. 2015-31807 Filed 12-17-15; 8:45 am]
BILLING CODE 3720-58-P



                                                                              Federal Register / Vol. 80, No. 243 / Friday, December 18, 2015 / Notices                                           79035

                                                  may also require modifications to Units                 process is available at http://planning.              DEPARTMENT OF DEFENSE
                                                  2 and 3.                                                usace.army.mil/toolbox/smart.cfm.
                                                     Pursuant to the California                              Additional information on this project             Department of the Army, Corps of
                                                  Environmental Quality Act (CEQA),                       can be found at http://www.marin                      Engineers
                                                  Marin County Flood Control and Water                    watersheds.org/documents_and_
                                                  Conservation District Zone 9                            reports/USACECorteMaderaCreek                         Intent To Prepare a Draft Feasibility
                                                  (MCFCWCD) is the lead agency and                        Project.html.                                         Study and Environmental Impact
                                                  local sponsor in preparing an                              Purpose and Need: The purpose of the               Statement (EIS) for Navigational
                                                  Environmental Impact Report (EIR). The                  project is to manage flood risk from                  Improvements to Manatee Harbor in
                                                  Corps and MCFCWCD have agreed to                        Corte Madera Creek associated with                    Manatee County, FL
                                                  jointly prepare a Draft EIS/EIR to                      Unit 4. The need of the project is to
                                                                                                                                                                AGENCY: Department of the Army, U.S.
                                                  optimize efficiency and avoid                           address channel modifications to Unit 4,
                                                                                                                                                                Army Corps of Engineers, DOD.
                                                  duplication. The Draft EIS/EIR is                       from the upstream end of the existing
                                                                                                          Unit 3 concrete channel to Sir Francis                ACTION: Notice of intent.
                                                  intended to be sufficient in scope to
                                                  address the Federal, state and local                    Drake Boulevard at the border of Ross                 SUMMARY:   The purpose of the feasibility
                                                  requirements and environmental issues                   and San Anselmo, which may also                       study is to improve navigation in
                                                  concerning the proposed activities and                  require modifications to Units 3 and 2.               Manatee Harbor.
                                                  permit approvals.                                       Unit 3 extends from the upstream end
                                                                                                                                                                ADDRESSES: U.S. Army Corps of
                                                     The USACE’s Corte Madera Creek                       of the concrete channel in Ross
                                                                                                          downstream to the College Avenue                      Engineers, Planning Division,
                                                  Flood Control Project is consistent and                                                                       Environmental Branch, P.O. Box 4970,
                                                  compatible with the District’s Ross                     Bridge. Unit 2 extends from College
                                                                                                          Avenue Bridge downstream to Bon Air                   Jacksonville, FL 32232–0019.
                                                  Valley Flood Control Program, the
                                                                                                          Bridge in Larkspur.                                   FOR FURTHER INFORMATION CONTACT: Dr.
                                                  purpose of which is to manage flood
                                                                                                             Issues: Potentially significant issues             Aubree Hershorin at (904) 232–2136 or
                                                  risk in the Ross Valley watershed.
                                                                                                          associated with the project may include:              email at
                                                     Project Site and Background
                                                                                                          hydrology, geology, land use and                      Aubree.G.Hershorin@usace.army.mil.
                                                  Information: Corte Madera Creek drains
                                                  an area of approximately 28 square                      planning, population and housing,                     SUPPLEMENTARY INFORMATION:
                                                  miles in Marin County, CA and                           water and air quality, climate change,                  1. Description of the Proposed Action.
                                                  discharges into the San Francisco Bay                   biological resources, transportation,                 Proposed navigational improvements to
                                                  nine miles north of the Golden Gate                     noise, aesthetics, utilities and service              Manatee Harbor include deepening the
                                                  Bridge. Unit 4 extends from downstream                  systems, cultural resources, human                    harbor up to minus 43 feet and
                                                  of the Lagunitas Road Bridge, near the                  health and safety, and social and                     widening the harbor.
                                                  upstream terminus of Unit 3, to the Sir                 economic effects, as well as cumulative                 2. Reasonable Alternatives. Various
                                                  Francis Drake Boulevard Bridge right                    impacts from past, present and                        increments of widening and deepening,
                                                  before the Ross/San Anselmo town line.                  reasonably foreseeable future projects.               as well as other alternatives will be
                                                  Although Units 1, 2, and 3 channel                      Alternative actions will be evaluated                 evaluated. The dredged material is
                                                  modifications were completed in 1971,                   that will consider fish passage for                   expected to be suitable for placement in
                                                  public concerns led to a delay in the                   threatened and endangered fish species                the Ocean Dredged Material Disposal
                                                  planned actions for Unit 4. In 1996,                    that migrate through the project area,                Site (ODMDS) located approximately 30
                                                  Marin County requested the completion                   riparian habitat, as well as other                    miles from the mouth of Tampa Bay.
                                                  of Unit 4 by the Corps, and damages                     potential environmental issues of                     Some material may be suitable for
                                                  incurred by the December 2005 flood                     concern.                                              placement in dredged holes and for
                                                                                                             Scoping Process: The Corps is seeking              other purposes, and the study may
                                                  also renewed public interest in finding
                                                                                                          participation of all interested Federal,              evaluate the expansion of existing
                                                  solutions to minimize the risk of future
                                                                                                          state, and local agencies, Native                     dredged material management areas.
                                                  floods.
                                                                                                          American groups, and other concerned                  Other alternatives as identified during
                                                     Additional studies conducted by the
                                                                                                          private organizations or individuals                  the scoping and plan formulation
                                                  Corps focused on evaluating the design
                                                                                                          through this public notice.                           process will be considered.
                                                  performance of Units 3 and 4. These                        The purpose of the public scoping
                                                  studies identified the abrupt transition                                                                        3. Scoping Process:
                                                                                                          meeting is to solicit comments regarding                a. Public and Agency Involvement. A
                                                  between Units 3 and 4 created by the                    the potential impacts, environmental
                                                  existing Denil fish ladder, the narrow                                                                        scoping letter is being sent to agencies,
                                                                                                          issues, and alternatives associated with              commercial interests, and the public.
                                                  channel condition on the east and west                  the proposed action to be considered in
                                                  bank, and the Lagunitas Road Bridge as                                                                          b. Issues to be Analyzed in Depth in
                                                                                                          the Draft EIS/EIR. The meeting place,                 the DEIS. Important issues expected
                                                  constrictions to flood flow. The Town of                date and time will be advertised in
                                                  Ross replaced the Lagunitas Road Bridge                                                                       include impacts to protected species,
                                                                                                          advance in local newspapers, and                      seagrass, hardgrounds, socio-economic
                                                  in 2010 with a higher bridge profile to                 meeting announcement letters will be
                                                  accommodate a greater flow capacity of                                                                        factors, and any other factors that might
                                                                                                          sent to interested parties. The Draft                 be determined during the scoping and
                                                  approximately 5,400 cubic feet per                      Integrated General Reevaluation Report
                                                  second.                                                                                                       plan formulation process.
                                                                                                          and EIS/EIR is expected to be available                 c. Possible Assignments for Input into
                                                     A charrette was held in 2013 to restart              for public review and comment in the                  the EIS among Lead and Potential
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  the project study under the Corps’                      Fall of 2016 and a public meeting will
                                                  SMART Planning principles. SMART                                                                              Cooperating Agencies.
                                                                                                          be held after its publication.
                                                  Planning is intended to be Specific,                                                                          —U.S. Fish and Wildlife Service: Input
                                                  Measureable, Attainable, Risk Informed,                 John C. Morrow,                                         concerning listed species, critical
                                                  and Timely planning to complete                         Lieutenant Colonel, U.S. Army District                  habitat, and other fish and wildlife
                                                  USACE feasibility studies in a cost-                    Engineer.                                               resources.
                                                  effective and efficient manner. More                    [FR Doc. 2015–31804 Filed 12–17–15; 8:45 am]          —National Marine Fisheries Service:
                                                  information on the SMART Planning                       BILLING CODE 3720–58–P                                  Input concerning listed species,


                                             VerDate Sep<11>2014   19:20 Dec 17, 2015   Jkt 238001   PO 00000   Frm 00008   Fmt 4703   Sfmt 4703   E:\FR\FM\18DEN1.SGM   18DEN1


                                                  79036                       Federal Register / Vol. 80, No. 243 / Friday, December 18, 2015 / Notices

                                                    critical habitat, and essential fish                  Marcus Hedrick, Office of the General                 Motion to Request Mediation, Waive
                                                    habitat.                                              Counsel, U.S. Department of Education,                81.39(a) and Suspend the Procedural
                                                  —U.S. Environmental Protection                          400 Maryland Avenue SW., Room                         Schedule (Joint Motion). Since the Joint
                                                    Agency: Input concerning disposal in                  6E220, Washington, DC 20202–2110.                     Motion was granted, Washington and
                                                    the Tampa ODMDS.                                      FOR FURTHER INFORMATION CONTACT:                      the Department have engaged in
                                                  —The U.S. Army Corps of Engineers is                    Marcus Hedrick. Telephone: 202–401–                   facilitated mediation to attempt to
                                                    the Lead agency and, together with                    8316 or by email: marcus.hedrick@                     resolve the recovery action.
                                                    the non-federal sponsor (Port                         ed.gov.                                                  The Department proposes to
                                                    Manatee), will assume responsibility                     If you use a telecommunications                    compromise the total claim to $530,053
                                                    for all other aspects of the EIS.                     device for the deaf or a text telephone,              (the fiscal year 2012 recovery will be
                                                    d. Other Environmental Review and                     you may call the Federal Relay Service,               reduced to $451,605 and the fiscal year
                                                  Consultation Requirements. The                          toll free, at 1–800–877–8339.                         2013 recovery will be reduced to
                                                  proposed action is subject to the                                                                             $78,447). The Department has
                                                                                                          SUPPLEMENTARY INFORMATION:
                                                  requirements of the Endangered Species                                                                        determined that it would not be
                                                                                                             Invitation To Comment: We invite
                                                  Act, Marine Mammal Protection Act,                                                                            practical or in the public interest to
                                                                                                          you to submit comments regarding this
                                                  Essential Fish Habitat requirements,                                                                          continue proceeding, based on litigation
                                                                                                          proposed action. During and after the
                                                  National Historic Preservation Act,                                                                           risks and the cost of proceeding through
                                                                                                          comment period you may inspect all
                                                  numerous other laws and executive                                                                             the administrative, and possible court,
                                                                                                          public comments in Room 6E312, FB–
                                                  orders, and any other requirements that                                                                       process for this appeal. Also, in light of
                                                                                                          6, 400 Maryland Avenue SW.,
                                                  might be identified during the scoping                                                                        corrective actions Washington has
                                                                                                          Washington, DC, between the hours of
                                                  and plan formulation process.                                                                                 taken, the Department does not
                                                                                                          8:30 a.m. and 4 p.m., Washington, DC
                                                    4. Scoping Meeting. A public scoping                                                                        anticipate this violation of the indirect
                                                                                                          time, Monday through Friday of each
                                                  meeting will be held on January 20,                                                                           cost provisions will recur. As a result,
                                                                                                          week except Federal holidays.
                                                  2016, from 3:30 to 6:30 p.m. at the Port                                                                      under the authority in 20 U.S.C.
                                                                                                             Assistance to Individuals With
                                                  Manatee Intermodal Center, 1905                                                                               1234a(j), the Department has
                                                                                                          Disabilities in Reviewing Comments: On
                                                  Intermodal Circle, Palmetto, FL 34221.                                                                        determined that compromise of this
                                                                                                          request we will provide an appropriate
                                                    5. Date the DEIS Will Be Made                                                                               claim to $530,053 is appropriate and in
                                                                                                          accommodation or auxiliary aid to an
                                                  Available to the Public. Dependent on                                                                         the public interest. The public is invited
                                                                                                          individual with a disability who needs
                                                  the issues, alternatives, investigations,                                                                     to comment on the Department’s intent
                                                                                                          assistance to review the comments for
                                                  and other requirements identified                                                                             to compromise this claim. Additional
                                                                                                          this notice. If you want to schedule an
                                                  during the scoping and plan formulation                                                                       information may be obtained by calling
                                                                                                          appointment for this type of
                                                  process; the Draft EIS should be                                                                              or writing the contact person listed
                                                                                                          accommodation or auxiliary aid, please
                                                  available by November 2017.                                                                                   under FOR FURTHER INFORMATION
                                                                                                          contact the person listed under FOR
                                                                                                                                                                CONTACT.
                                                    Dated: December 10, 2015.                             FURTHER INFORMATION CONTACT.
                                                                                                                                                                   Accessible Format: Individuals with
                                                  Eric P. Summa,
                                                                                                          Background                                            disabilities can obtain this document in
                                                  Chief, Planning Division.                                                                                     an accessible format (e.g., braille, large
                                                  [FR Doc. 2015–31807 Filed 12–17–15; 8:45 am]               On March 10, 2015, the Acting
                                                                                                                                                                print, audio tape, or compact disc) on
                                                                                                          Assistant Secretary for Special
                                                  BILLING CODE 3720–58–P                                                                                        request to the contact person listed
                                                                                                          Education and Rehabilitative Services
                                                                                                                                                                under FOR FURTHER INFORMATION
                                                                                                          (Assistant Secretary) issued two
                                                                                                                                                                CONTACT.
                                                                                                          program determination letters (PDLs)
                                                  DEPARTMENT OF EDUCATION                                                                                          Electronic Access to this Document:
                                                                                                          seeking to recover a total of $730,053 of
                                                                                                                                                                The official version of this document is
                                                  Intent To Compromise Claim Against                      Vocational Rehabilitation (VR) State
                                                                                                                                                                the document published in the Federal
                                                  the State of Washington Department of                   grant funds from Washington. Based on
                                                                                                                                                                Register. Free Internet access to the
                                                  Services for the Blind                                  findings in single audits of Washington
                                                                                                                                                                official edition of the Federal Register
                                                                                                          (Audit Control Numbers 10–12–38440
                                                  AGENCY:  Office of Special Education and                                                                      and the Code of Federal Regulations is
                                                                                                          and 10–13–48310), these funds were
                                                  Rehabilitative Services, Department of                                                                        available via the Federal Digital System
                                                                                                          determined by the Assistant Secretary to
                                                  Education.                                                                                                    at: www.gpo.gov/fdsys. At this site you
                                                                                                          have been expended, during the fiscal
                                                                                                                                                                can view this document, as well as all
                                                  ACTION: Notice.                                         years 2012 and 2013, in violation of the
                                                                                                                                                                other documents of this Department
                                                                                                          indirect cost provisions under the
                                                  SUMMARY:   The United States Department                                                                       published in the Federal Register, in
                                                                                                          Education Department General
                                                  of Education (Department) intends to                                                                          text or Portable Document Format
                                                                                                          Administrative Regulations at 34 CFR
                                                  compromise a claim against the State of                                                                       (PDF). To use PDF you must have
                                                                                                          76.560. Specifically, the PDLs indicated
                                                  Washington Department of Services for                                                                         Adobe Acrobat Reader, which is
                                                                                                          that Washington had charged indirect
                                                  the Blind (Washington) now pending                                                                            available free at the site.
                                                                                                          costs to the VR grant program without                    You may also access documents of the
                                                  before the Office of Administrative Law                 an approved indirect cost agreement,
                                                  Judges (OALJ), Docket No. 15–30–R.                                                                            Department published in the Federal
                                                                                                          and identified $621,871 for recovery in               Register by using the article search
                                                  Before compromising a claim, the                        fiscal year 2012 and $108,182 for
                                                  Department must publish its intent to                                                                         feature at: www.federalregister.gov.
                                                                                                          recovery in fiscal year 2013.                         Specifically, through the advanced
                                                  do so in the Federal Register and
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                             Washington filed Applications for                  search feature at this site, you can limit
                                                  provide the public an opportunity to                    Review of these PDLs with the OALJ on
                                                  comment on this action.                                                                                       your search to documents published by
                                                                                                          May 14, 2015. On June 9, 2015, the                    the Department.
                                                  DATES: We must receive your comments                    OALJ proposed processing the two
                                                  on the proposed action on or before                     appeals under one docket number, and                    Program Authority: 20 U.S.C. 1234a(j).
                                                  February 1, 2016.                                       with consent of the parties subsequently                Delegation of Authority: The Secretary
                                                  ADDRESSES: Address all comments                         combined the appeals. On June 27,                     of Education has delegated authority to
                                                  concerning the proposed action to                       2015, the OALJ granted the parties’ Joint             Thomas P. Skelly to perform the


                                             VerDate Sep<11>2014   19:20 Dec 17, 2015   Jkt 238001   PO 00000   Frm 00009   Fmt 4703   Sfmt 4703   E:\FR\FM\18DEN1.SGM   18DEN1



Document Created: 2015-12-18 01:38:46
Document Modified: 2015-12-18 01:38:46
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of intent.
ContactDr. Aubree Hershorin at (904) 232-2136 or email at [email protected]
FR Citation80 FR 79035 