DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 247 (December 24, 2015)

Page Range80349-80350
FR Document2015-32405

Federal Register, Volume 80 Issue 247 (Thursday, December 24, 2015)
[Federal Register Volume 80, Number 247 (Thursday, December 24, 2015)]
[Notices]
[Pages 80349-80350]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-32405]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Swan Lake North Hydro LLCProject No. 13318-003; Notice of 
Application Accepted for Filing and Soliciting Motions To Intervene and 
Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Unconstructed major project.
    b. Project No.: 13318-003.
    c. Date filed: October 28, 2015.
    d. Applicant: Swan Lake North Hydro LLC.
    e. Name of Project: Swan Lake North Pumped Storage Hydroelectric 
Project.
    f. Location: Approximately 11 miles northeast of the city of 
Klamath Falls, Klamath County, Oregon. The proposed project boundary 
would include about 730 acres of federal land managed by the U.S. 
Bureau of Land Management.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Joe Eberhardt, EDF-Renewable Energy, 1000 SW 
Broadway Ave., Ste. 1800, Portland, OR 97205; phone: (503) 889-3838.
    i. FERC Contact: Dianne Rodman, Dianne.rodman@ferc.gov; phone: 
(202) 502-6077.
    j. Deadline for filing motions to intervene and protests: February 
16, 2016.
    The Commission strongly encourages electronic filing. Please file 
filing motions to intervene and protests using the Commission's eFiling 
system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, 
please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 
208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, please send a paper copy to: Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426. The 
first page of any filing should include docket number P-13318-003.
    The Commission's Rules of Practice and Procedures require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. This application has been accepted for filing, but is not ready 
for environmental analysis at this time.
    l. The proposed project would be a closed-loop system using 
groundwater for initial fill and consist of the following new 
facilities: (1) A 7,972-foot-long earthen embankment forming a 
geomembrane-lined upper reservoir with a surface area of 64.21 acres 
and a storage capacity of 2,568 acre-feet at a maximum surface 
elevation of 6,135 feet above mean sea level (msl); (2) a 8,003-foot-
long earthen embankment forming a geomembrane-lined lower reservoir 
with a surface area of 60.14 acres and a storage capacity of 3,206 
acre-feet at a maximum surface elevation of 4,457 feet msl; (3) a 500-
foot-long, rip-rap lined trapezoidal spillway built into the crest of 
each embankment; (4) a 0.5-percent slope perforated polyvinyl chloride 
tube of varying diameter and accompanying optical fiber drainage system 
designed to detect, collect, and monitor water leakage from the 
reservoirs; (5) a 25-inch-diameter bottom outlet with manual valve for 
gravitational dewatering of the lower reservoir; (6) an upper intake 
consisting of a bell mouth, 38.6-foot-wide by 29.8-foot-long inclined 
screen, head gate, and 13.8-foot-diameter foundational steel pipe; (7) 
a 36.5-foot-diameter, 9,655-foot-long steel high-pressure penstock from 
the upper reservoir to the powerhouse that is predominantly above 
ground with a 14-foot-long buried segment; (8) three 9.8-foot-diameter, 
1,430-foot-long steel low-pressure penstocks from the lower reservoir 
to the powerhouse that are predominantly above ground with a 78-foot-
long buried segment ; (9) a partially-buried powerhouse with three 
131.1-megawatt (MW) reversible pump-turbine units with a total 
installed capacity of 393.3 MW; (10) a 32.8 mile, 230-kilovolt above-
ground transmission line interconnecting to an existing non-project 
substation; (11) approximately 10.7 miles of improved project access 
road; (12) approximately 3.4 miles of new permanent project access 
road; (13) approximately 8.3 miles of temporary project access road; 
and (14) appurtenant facilities. The project would generate about 1,187 
gigawatt-hours annually.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the

[[Page 80350]]

``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC Online Support. A copy is also available for 
inspection and reproduction at the address in item h above.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application, or a notice of 
intent to file such an application. Submission of a timely notice of 
intent allows an interested person to file the competing development 
application no later than 120 days after the specified intervention 
deadline date. Applications for preliminary permits will not be 
accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant(s) named in this 
public notice.
    Anyone may submit a protest or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210, 385.211, and 385.214. In determining the appropriate action to 
take, the Commission will consider all protests filed, but only those 
who file a motion to intervene in accordance with the Commission's 
Rules may become a party to the proceeding. Any protests or motions to 
intervene must be received on or before the specified deadline date for 
the particular application.
    When the application is ready for environmental analysis, the 
Commission will issue a public notice requesting comments, 
recommendations, terms and conditions, or prescriptions.
    All filings must (1) bear in all capital letters the title 
``PROTEST'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE 
COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in 
the heading the name of the applicant and the project number of the 
application to which the filing responds; (3) furnish the name, 
address, and telephone number of the person protesting or intervening; 
and (4) otherwise comply with the requirements of 18 CFR 385.2001 
through 385.2005. Agencies may obtain copies of the application 
directly from the applicant. A copy of any protest or motion to 
intervene must be served upon each representative of the applicant 
specified in the particular application.

    Dated: December 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-32405 Filed 12-23-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                            Federal Register / Vol. 80, No. 247 / Thursday, December 24, 2015 / Notices                                           80349

                                                  analyzed the potential environmental                      Issued at Washington, DC on December 18,            files comments or documents with the
                                                  impacts for the No Action Alternative                   2015.                                                 Commission relating to the merits of an
                                                  and four action alternatives for                        Frank G. Klotz,                                       issue that may affect the responsibilities
                                                  disposition of 13.1 metric tons (MT) of                 Administrator, National Nuclear Security              of a particular resource agency, they
                                                  surplus plutonium, of which the 6 MT                    Administration.                                       must also serve a copy of the document
                                                  of non-pit plutonium is a subset (Final                 [FR Doc. 2015–32440 Filed 12–23–15; 8:45 am]          on that resource agency.
                                                  SPD Supplemental EIS Summary, figure                    BILLING CODE 6450–01–P                                   k. This application has been accepted
                                                  S–7). The four action alternatives that                                                                       for filing, but is not ready for
                                                  are applicable to the surplus non-pit                                                                         environmental analysis at this time.
                                                                                                          DEPARTMENT OF ENERGY                                     l. The proposed project would be a
                                                  plutonium are described in section S.9.2
                                                                                                                                                                closed-loop system using groundwater
                                                  of the Final SPD Supplemental EIS.
                                                                                                          Federal Energy Regulatory                             for initial fill and consist of the
                                                     The scope of this notice pertains only               Commission                                            following new facilities: (1) A 7,972–
                                                  to the 6 MT of surplus non-pit                                                                                foot-long earthen embankment forming
                                                  plutonium for which a disposition path                  Swan Lake North Hydro LLCProject                      a geomembrane-lined upper reservoir
                                                  is not assigned. DOE/NNSA has no                        No. 13318–003; Notice of Application                  with a surface area of 64.21 acres and
                                                  Preferred Alternative, at this time, for                Accepted for Filing and Soliciting                    a storage capacity of 2,568 acre-feet at a
                                                  other potential actions considered in the               Motions To Intervene and Protests                     maximum surface elevation of 6,135 feet
                                                  Final SPD Supplemental EIS.                                Take notice that the following                     above mean sea level (msl); (2) a 8,003-
                                                  Specifically, DOE/NNSA has no                           hydroelectric application has been filed              foot-long earthen embankment forming
                                                  Preferred Alternative for the disposition               with the Commission and is available                  a geomembrane-lined lower reservoir
                                                  of the remaining 7.1 MT of surplus                      for public inspection.                                with a surface area of 60.14 acres and
                                                  plutonium from pits, nor does it have a                    a. Type of Application: Unconstructed              a storage capacity of 3,206 acre-feet at a
                                                  Preferred Alternative among the                         major project.                                        maximum surface elevation of 4,457 feet
                                                  pathways analyzed for providing the                        b. Project No.: 13318–003.                         msl; (3) a 500-foot-long, rip-rap lined
                                                  capability to disassemble surplus pits                     c. Date filed: October 28, 2015.                   trapezoidal spillway built into the crest
                                                  and convert the plutonium from pits to                     d. Applicant: Swan Lake North Hydro                of each embankment; (4) a 0.5-percent
                                                  a form suitable for disposition.                        LLC.                                                  slope perforated polyvinyl chloride tube
                                                                                                             e. Name of Project: Swan Lake North                of varying diameter and accompanying
                                                  Preferred Alternative for Non-Pit                       Pumped Storage Hydroelectric Project.                 optical fiber drainage system designed
                                                  Plutonium                                                  f. Location: Approximately 11 miles                to detect, collect, and monitor water
                                                                                                          northeast of the city of Klamath Falls,               leakage from the reservoirs; (5) a 25-
                                                     DOE/NNSA’s Preferred Alternative                     Klamath County, Oregon. The proposed                  inch-diameter bottom outlet with
                                                  with regard to the disposition of 6 MT                  project boundary would include about                  manual valve for gravitational
                                                  of surplus non-pit plutonium is to                      730 acres of federal land managed by                  dewatering of the lower reservoir; (6) an
                                                  prepare this plutonium for eventual                     the U.S. Bureau of Land Management.                   upper intake consisting of a bell mouth,
                                                  disposal at WIPP in Carlsbad, New                          g. Filed Pursuant to: Federal Power                38.6-foot-wide by 29.8-foot-long
                                                  Mexico, a geologic repository for                       Act, 16 U.S.C. 791 (a)–825(r).                        inclined screen, head gate, and 13.8-
                                                  disposal of TRU waste generated by                         h. Applicant Contact: Joe Eberhardt,               foot-diameter foundational steel pipe;
                                                  atomic energy defense activities. This                  EDF-Renewable Energy, 1000 SW                         (7) a 36.5-foot-diameter, 9,655-foot-long
                                                  would allow the DOE/NNSA to                             Broadway Ave., Ste. 1800, Portland, OR                steel high-pressure penstock from the
                                                  continue progress on the disposition of                 97205; phone: (503) 889–3838.                         upper reservoir to the powerhouse that
                                                  surplus weapon usable plutonium in                         i. FERC Contact: Dianne Rodman,                    is predominantly above ground with a
                                                  furtherance of the policies of the United               Dianne.rodman@ferc.gov; phone: (202)                  14-foot-long buried segment; (8) three
                                                  States to ensure that surplus plutonium                 502–6077.                                             9.8-foot-diameter, 1,430-foot-long steel
                                                  is never used in a nuclear weapon, and                     j. Deadline for filing motions to                  low-pressure penstocks from the lower
                                                  to remove surplus plutonium from the                    intervene and protests: February 16,                  reservoir to the powerhouse that are
                                                  State of South Carolina. Surplus non-pit                2016.                                                 predominantly above ground with a 78-
                                                  plutonium would be prepared and                            The Commission strongly encourages                 foot-long buried segment ; (9) a
                                                  packaged at the Savannah River Site                     electronic filing. Please file filing                 partially-buried powerhouse with three
                                                  (SRS) using H-Canyon/HB-line and/or                     motions to intervene and protests using               131.1-megawatt (MW) reversible pump-
                                                  K-Area facilities to meet the WIPP waste                the Commission’s eFiling system at                    turbine units with a total installed
                                                  acceptance criteria and all other                       http://www.ferc.gov/docs-filing/                      capacity of 393.3 MW; (10) a 32.8 mile,
                                                  applicable regulatory requirements and                  efiling.asp. For assistance, please                   230-kilovolt above-ground transmission
                                                  would be temporarily stored in E-Area                   contact FERC Online Support at                        line interconnecting to an existing non-
                                                  at SRS until shipped. Shipments of this                 FERCOnlineSupport@ferc.gov, (866)                     project substation; (11) approximately
                                                  surplus plutonium to WIPP would not                     208–3676 (toll free), or (202) 502–8659               10.7 miles of improved project access
                                                  commence until WIPP is fully                            (TTY). In lieu of electronic filing, please           road; (12) approximately 3.4 miles of
                                                  operational, and would be placed in the                 send a paper copy to: Secretary, Federal              new permanent project access road; (13)
                                                                                                          Energy Regulatory Commission, 888                     approximately 8.3 miles of temporary
                                                  appropriate place in any queue of
                                                                                                          First Street NE., Washington, DC 20426.               project access road; and (14)
                                                  material to be shipped to WIPP.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                          The first page of any filing should                   appurtenant facilities. The project
                                                     DOE/NNSA may issue a ROD                             include docket number P–13318–003.                    would generate about 1,187 gigawatt-
                                                  containing its plan for disposition of the                 The Commission’s Rules of Practice                 hours annually.
                                                  6 MT of surplus non-pit plutonium                       and Procedures require all intervenors                   m. A copy of the application is
                                                  analyzed in Final SPD Supplemental                      filing documents with the Commission                  available for review at the Commission
                                                  EIS no sooner than 30 days from the                     to serve a copy of that document on                   in the Public Reference Room or may be
                                                  date of publication of this notice in the               each person on the official service list              viewed on the Commission’s Web site at
                                                  Federal Register.                                       for the project. Further, if an intervenor            http://www.ferc.gov using the


                                             VerDate Sep<11>2014   17:57 Dec 23, 2015   Jkt 238001   PO 00000   Frm 00038   Fmt 4703   Sfmt 4703   E:\FR\FM\24DEN1.SGM   24DEN1


                                                  80350                     Federal Register / Vol. 80, No. 247 / Thursday, December 24, 2015 / Notices

                                                  ‘‘eLibrary’’ link. Enter the docket                     385.2001 through 385.2005. Agencies                   Mills Operations to be effective 3/1/
                                                  number excluding the last three digits in               may obtain copies of the application                  2016.
                                                  the docket number field to access the                   directly from the applicant. A copy of                   Filed Date: 12/18/15.
                                                  document. For assistance, contact FERC                  any protest or motion to intervene must                  Accession Number: 20151218–5137.
                                                  Online Support. A copy is also available                be served upon each representative of                    Comments Due: 5 p.m. ET 1/8/16.
                                                  for inspection and reproduction at the                  the applicant specified in the particular                Docket Numbers: ER16–568–000.
                                                  address in item h above.                                application.                                             Applicants: Duke Energy Florida,
                                                     You may also register online at http://                Dated: December 18, 2015.                           LLC.
                                                  www.ferc.gov/docs-filing/                                                                                        Description: § 205(d) Rate Filing:
                                                                                                          Nathaniel J. Davis, Sr.,
                                                  esubscription.asp to be notified via                                                                          FMPA NITSA Amendment-OATT SA
                                                  email of new filings and issuances                      Deputy Secretary.
                                                                                                                                                                No. 148 to be effective 1/1/2016.
                                                  related to this or other pending projects.              [FR Doc. 2015–32405 Filed 12–23–15; 8:45 am]
                                                                                                                                                                   Filed Date: 12/18/15.
                                                  For assistance, contact FERC Online                     BILLING CODE 6717–01–P
                                                                                                                                                                   Accession Number: 20151218–5173.
                                                  Support.                                                                                                         Comments Due: 5 p.m. ET 1/8/16.
                                                     n. Any qualified applicant desiring to
                                                  file a competing application must                       DEPARTMENT OF ENERGY                                     Docket Numbers: ER16–569–000.
                                                  submit to the Commission, on or before                                                                           Applicants: NorthWestern
                                                  the specified intervention deadline date,               Federal Energy Regulatory                             Corporation.
                                                  a competing development application,                    Commission                                               Description: § 205(d) Rate Filing: SA
                                                  or a notice of intent to file such an                                                                         760 1st Rev—NITSA with Beartooth
                                                                                                          Combined Notice of Filings #2                         Electric Cooperative to be effective 3/1/
                                                  application. Submission of a timely
                                                  notice of intent allows an interested                      Take notice that the Commission                    2016.
                                                  person to file the competing                            received the following electric rate                     Filed Date: 12/18/15.
                                                  development application no later than                   filings:                                                 Accession Number: 20151218–5186.
                                                  120 days after the specified intervention                  Docket Numbers: ER11–4081–003.                        Comments Due: 5 p.m. ET 1/8/16.
                                                  deadline date. Applications for                            Applicants: Midcontinent                              Docket Numbers: ER16–570–000.
                                                  preliminary permits will not be                         Independent System Operator, Inc.                        Applicants: Tucson Electric Power
                                                  accepted in response to this notice.                       Description: Compliance filing: 2015–              Company.
                                                     A notice of intent must specify the                  12–18 RAR Compliance Filing to be                        Description: Compliance filing: Order
                                                  exact name, business address, and                       effective 10/1/2012.                                  No. 784 Compliance Filing to be
                                                  telephone number of the prospective                        Filed Date: 12/18/15.                              effective 2/17/2016.
                                                  applicant, and must include an                             Accession Number: 20151218–5211.                      Filed Date: 12/18/15.
                                                  unequivocal statement of intent to                         Comments Due: 5 p.m. ET 1/8/16.                       Accession Number: 20151218–5194.
                                                  submit a development application. A                        Docket Numbers: ER15–2101–003.                        Comments Due: 5 p.m. ET 1/8/16.
                                                  notice of intent must be served on the                     Applicants: Golden West Power                         Docket Numbers: ER16–571–000.
                                                  applicant(s) named in this public notice.               Partners, LLC.                                           Applicants: NorthWestern
                                                     Anyone may submit a protest or a                        Description: Compliance filing: Notice             Corporation.
                                                  motion to intervene in accordance with                  of Change in Status of Golden West                       Description: § 205(d) Rate Filing: SA
                                                  the requirements of Rules of Practice                   Power Partners, LLC to be effective 9/1/              312 8th Rev—NITSA with Southern
                                                  and Procedure, 18 CFR 385.210,                          2015.                                                 Montana to be effective 3/1/2016.
                                                  385.211, and 385.214. In determining                       Filed Date: 12/18/15.                                 Filed Date: 12/18/15.
                                                  the appropriate action to take, the                        Accession Number: 20151218–5120.                      Accession Number: 20151218–5195.
                                                  Commission will consider all protests                      Comments Due: 5 p.m. ET 1/8/16.                       Comments Due: 5 p.m. ET 1/8/16.
                                                  filed, but only those who file a motion                    Docket Numbers: ER16–565–000.
                                                  to intervene in accordance with the                                                                              Docket Numbers: ER16–572–000.
                                                                                                             Applicants: Midcontinent
                                                                                                                                                                   Applicants: UNS Electric, Inc.
                                                  Commission’s Rules may become a                         Independent System Operator, Inc.,
                                                                                                                                                                   Description: Compliance filing: Order
                                                  party to the proceeding. Any protests or                Ameren Illinois Company.
                                                                                                                                                                No. 784 Compliance Filing to be
                                                  motions to intervene must be received                      Description: § 205(d) Rate Filing:
                                                                                                                                                                effective 2/17/2016.
                                                  on or before the specified deadline date                2015–12–18_SA 2878 ATXI–AIC
                                                                                                                                                                   Filed Date: 12/18/15.
                                                  for the particular application.                         Construction Agreement (Faraday
                                                     When the application is ready for                                                                             Accession Number: 20151218–5196.
                                                                                                          Substation) to be effective 12/18/2015.
                                                  environmental analysis, the                                                                                      Comments Due: 5 p.m. ET 1/8/16.
                                                                                                             Filed Date: 12/18/15.
                                                  Commission will issue a public notice                      Accession Number: 20151218–5118.                      Docket Numbers: ER16–573–000.
                                                  requesting comments,                                       Comments Due: 5 p.m. ET 1/8/16.                       Applicants: UniSource Energy
                                                  recommendations, terms and                                 Docket Numbers: ER16–566–000.                      Development Company.
                                                  conditions, or prescriptions.                              Applicants: NorthWestern                              Description: Compliance filing: Order
                                                     All filings must (1) bear in all capital             Corporation.                                          No. 784 Compliance Filing to be
                                                  letters the title ‘‘PROTEST’’ or                           Description: § 205(d) Rate Filing: SA              effective 2/17/2016.
                                                  ‘‘MOTION TO INTERVENE,’’ ‘‘NOTICE                       767 1st Rev—NITSA with Basin Electric                    Filed Date: 12/18/15.
                                                  OF INTENT TO FILE COMPETING                             Power Cooperative to be effective 3/1/                   Accession Number: 20151218–5197.
                                                  APPLICATION,’’ or ‘‘COMPETING                           2016.                                                    Comments Due: 5 p.m. ET 1/8/16.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  APPLICATION;’’ (2) set forth in the                        Filed Date: 12/18/15.                                 Docket Numbers: ER16–574–000.
                                                  heading the name of the applicant and                      Accession Number: 20151218–5130.                      Applicants: NorthWestern
                                                  the project number of the application to                   Comments Due: 5 p.m. ET 1/8/16.                    Corporation.
                                                  which the filing responds; (3) furnish                     Docket Numbers: ER16–567–000.                         Description: § 205(d) Rate Filing: SA
                                                  the name, address, and telephone                           Applicants: NorthWestern                           605 5th Rev—NITSA with Bonneville
                                                  number of the person protesting or                      Corporation.                                          Power Administration to be effective 3/
                                                  intervening; and (4) otherwise comply                      Description: § 205(d) Rate Filing: SA              1/2016.
                                                  with the requirements of 18 CFR                         642 2nd Rev—NITSA with General                           Filed Date: 12/18/15.


                                             VerDate Sep<11>2014   17:57 Dec 23, 2015   Jkt 238001   PO 00000   Frm 00039   Fmt 4703   Sfmt 4703   E:\FR\FM\24DEN1.SGM   24DEN1



Document Created: 2015-12-24 02:24:46
Document Modified: 2015-12-24 02:24:46
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 80349 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR