DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 249 (December 29, 2015)

Page Range81308-81308
FR Document2015-32696

Federal Register, Volume 80 Issue 249 (Tuesday, December 29, 2015)
[Federal Register Volume 80, Number 249 (Tuesday, December 29, 2015)]
[Notices]
[Page 81308]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-32696]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2531-075]


Brookfield White Pine Hydro LLC; Notice of Application Tendered 
for Filing With the Commission and Establishing Procedural Schedule for 
Licensing and Deadline for Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: 2531-075.
    c. Date Filed: December 18, 2015.
    d. Applicant: Brookfield White Pine Hydro LLC (White Pine Hydro).
    e. Name of Project: West Buxton Hydroelectric Project.
    f. Location: The existing project is located on the Saco River in 
the Towns of Buxton, Hollis, and Standish, within York and Cumberland 
Counties, Maine. No federal lands are occupied by project works or 
located within the project boundary.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Frank Dunlap, Licensing Specialist, 
Brookfield White Pine Hydro LLC, 150 Main Street, Lewiston, ME 04240; 
Telephone--(207) 755-5603; [email protected]. 
OR Kelley Maloney, Manager of licensing and Compliance, Brookfield 
White Pine Hydro LLC, 150 Maine Street, Lewiston, ME 04240; Telephone--
(207) 755-5606.
    i. FERC Contact: Allan Creamer, (202) 502-8365, or 
[email protected].
    j. This application is not ready for environmental analysis (EA) at 
this time.
    k. Project Description: The West Buxton Project consists of: (1) A 
585-foot-long by 30-foot-high concrete gravity dam with a crest 
elevation of 173.8 feet (United States Geological Survey or USGS 
datum), consisting of (i) two overflow sections topped with three 
inflatable rubber dam sections that have a crest elevation of 178.1 
feet (USGS datum) when fully inflated, (ii) a gated section containing 
a 20-foot-wide by 15-foot-high vertical lift gate, (iii) two 40-foot-
wide by 11-foot-high stanchion sections, (iv) an 11-foot-wide log 
sluice section, and (v) an intake structure comprised of two vertical 
lift gates regulating the flow of water to the lower powerhouse and 
five gate openings (two sealed by stoplogs) controlling water flow to 
the upper powerhouse; (2) a 118-acre impoundment at a normal pool 
elevation of 177.8 feet (USGS datum); (3) a 105 feet long by 39 feet 
wide upper powerhouse integral with the dam, containing five horizontal 
axis Francis turbine generating units that total 3,812 kW; (4) a 241.5-
foot-long concrete conduit leading from the intake structure to a 74-
foot-long by 30 to 45-foot wide surge chamber, and then to the lower 
powerhouse; (5) a 51.2 feet long by 45.5 feet wide lower powerhouse, 
containing one 4,000 kW vertical axis Kaplan turbine generating unit; 
(6) two 38-kV transmission lines, connecting the upper and lower 
powerhouses to the non-project West Buxton switching station; and (7) 
appurtenant facilities.
    White Pine Hydro operates the project in a run-of-river mode, in 
accordance with the 1997 Saco River Instream Flow Agreement, which 
provides that outflow approximate inflow from the upstream Bonny Eagle 
Project No. 2529 and act to minimize impoundment level fluctuations. 
White Pine Hydro also operates the project with a minimum outflow of 
768 cfs, or inflow, whichever is less, in accordance with the project's 
current water quality certificate. The project generates an annual 
average of 34,007 MWh.
    l. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov, using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support at [email protected], (866)-208-3676 (toll 
free), or (202) 502-8659 (TTY). A copy is also available for inspection 
and reproduction at the address in item (h) above.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    m. Procedural Schedule: The application will be processed according 
to the following preliminary Hydro Licensing Schedule. Revisions to the 
schedule will be made as appropriate.

Notice of Acceptance/Notice of Ready    February 2016.
 for Environmental Analysis.
Filing of recommendations, preliminary  April 2016.
 terms and conditions, and fishway
 prescriptions.
Commission issues EA..................  August 2016.
Comments on EA........................  September 2016.
Modified Terms and Conditions.........  November 2016.
Commission Issues Final EA, if          February 2017.
 necessary.
 

    o. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: December 22, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-32696 Filed 12-28-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                    81308                      Federal Register / Vol. 80, No. 249 / Tuesday, December 29, 2015 / Notices

                                                    service, and qualifying facilities filings              inflatable rubber dam sections that have                m. Procedural Schedule: The
                                                    can be found at: http://www.ferc.gov/                   a crest elevation of 178.1 feet (USGS                 application will be processed according
                                                    docs-filing/efiling/filing-req.pdf. For                 datum) when fully inflated, (ii) a gated              to the following preliminary Hydro
                                                    other information, call (866) 208–3676                  section containing a 20-foot-wide by 15-              Licensing Schedule. Revisions to the
                                                    (toll free). For TTY, call (202) 502–8659.              foot-high vertical lift gate, (iii) two 40-           schedule will be made as appropriate.
                                                      Dated: December 22, 2015.                             foot-wide by 11-foot-high stanchion                   Notice of Acceptance/        February 2016.
                                                    Nathaniel J. Davis, Sr.,
                                                                                                            sections, (iv) an 11-foot-wide log sluice               Notice of Ready for
                                                                                                            section, and (v) an intake structure                    Environmental Anal-
                                                    Deputy Secretary.                                                                                               ysis.
                                                                                                            comprised of two vertical lift gates
                                                    [FR Doc. 2015–32691 Filed 12–28–15; 8:45 am]
                                                                                                            regulating the flow of water to the lower             Filing of recommenda-        April 2016.
                                                    BILLING CODE 6717–01–P                                                                                          tions, preliminary
                                                                                                            powerhouse and five gate openings (two
                                                                                                                                                                    terms and conditions,
                                                                                                            sealed by stoplogs) controlling water                   and fishway prescrip-
                                                                                                            flow to the upper powerhouse; (2) a 118-                tions.
                                                    DEPARTMENT OF ENERGY
                                                                                                            acre impoundment at a normal pool                     Commission issues EA         August 2016.
                                                    Federal Energy Regulatory                               elevation of 177.8 feet (USGS datum);                 Comments on EA .........     September 2016.
                                                                                                            (3) a 105 feet long by 39 feet wide upper             Modified Terms and           November 2016.
                                                    Commission
                                                                                                            powerhouse integral with the dam,                       Conditions.
                                                    [Project No. 2531–075]                                  containing five horizontal axis Francis               Commission Issues            February 2017.
                                                                                                                                                                    Final EA, if nec-
                                                                                                            turbine generating units that total 3,812
                                                    Brookfield White Pine Hydro LLC;                                                                                essary.
                                                                                                            kW; (4) a 241.5-foot-long concrete
                                                    Notice of Application Tendered for                      conduit leading from the intake                         o. Final amendments to the
                                                    Filing With the Commission and                          structure to a 74-foot-long by 30 to 45-              application must be filed with the
                                                    Establishing Procedural Schedule for                    foot wide surge chamber, and then to                  Commission no later than 30 days from
                                                    Licensing and Deadline for                              the lower powerhouse; (5) a 51.2 feet                 the issuance date of the notice of ready
                                                    Submission of Final Amendments                          long by 45.5 feet wide lower                          for environmental analysis.
                                                      Take notice that the following                        powerhouse, containing one 4,000 kW                     Dated: December 22, 2015.
                                                    hydroelectric application has been filed                vertical axis Kaplan turbine generating               Nathaniel J. Davis, Sr.,
                                                    with the Commission and is available                    unit; (6) two 38-kV transmission lines,               Deputy Secretary.
                                                    for public inspection.                                  connecting the upper and lower                        [FR Doc. 2015–32696 Filed 12–28–15; 8:45 am]
                                                      a. Type of Application: New Major                     powerhouses to the non-project West                   BILLING CODE 6717–01–P
                                                    License.                                                Buxton switching station; and (7)
                                                      b. Project No.: 2531–075.                             appurtenant facilities.
                                                      c. Date Filed: December 18, 2015.                        White Pine Hydro operates the project              DEPARTMENT OF ENERGY
                                                      d. Applicant: Brookfield White Pine                   in a run-of-river mode, in accordance
                                                    Hydro LLC (White Pine Hydro).                           with the 1997 Saco River Instream Flow                Federal Energy Regulatory
                                                      e. Name of Project: West Buxton                       Agreement, which provides that outflow                Commission
                                                    Hydroelectric Project.                                  approximate inflow from the upstream                  [Docket No. EL15–44–000]
                                                      f. Location: The existing project is                  Bonny Eagle Project No. 2529 and act to
                                                    located on the Saco River in the Towns                  minimize impoundment level                            Sage Grouse Energy Project, LLC;
                                                    of Buxton, Hollis, and Standish, within                 fluctuations. White Pine Hydro also                   Notice Rejecting Request for
                                                    York and Cumberland Counties, Maine.                    operates the project with a minimum                   Extension of Time
                                                    No federal lands are occupied by project                outflow of 768 cfs, or inflow, whichever
                                                                                                            is less, in accordance with the project’s             December 22, 2015.
                                                    works or located within the project
                                                    boundary.                                               current water quality certificate. The                  On December 3, 2015, the
                                                      g. Filed Pursuant to: Federal Power                   project generates an annual average of                Commission issued an order denying a
                                                                                                            34,007 MWh.                                           complaint filed by Sage Grouse Energy
                                                    Act, 16 U.S.C. 791(a)–825(r).
                                                                                                               l. A copy of the application is                    Project, LLC (Sage Grouse) against
                                                      h. Applicant Contact: Frank Dunlap,
                                                                                                            available for review at the Commission                PacifiCorp under Rule 206(a) of the
                                                    Licensing Specialist, Brookfield White
                                                                                                            in the Public Reference Room or may be                Commission’s Rules of Practice and
                                                    Pine Hydro LLC, 150 Main Street,
                                                                                                            viewed on the Commission’s Web site at                Procedure.1 On December 16, 2015,
                                                    Lewiston, ME 04240; Telephone—(207)
                                                                                                            http://www.ferc.gov, using the                        Sage Grouse filed a motion for extension
                                                    755–5603; Email—Frank.Dunlap@
                                                                                                                                                                  of time and waiver, asking the
                                                    BrookfieldRenewable.com. OR Kelley                      ‘‘eLibrary’’ link. Enter the docket
                                                                                                                                                                  Commission to grant a 30-day extension
                                                    Maloney, Manager of licensing and                       number excluding the last three digits in
                                                                                                                                                                  of time for Sage Grouse to determine
                                                    Compliance, Brookfield White Pine                       the docket number field to access the
                                                                                                                                                                  whether to file a request for rehearing of
                                                    Hydro LLC, 150 Maine Street, Lewiston,                  document. For assistance, contact FERC
                                                                                                                                                                  the December 3 Order.
                                                    ME 04240; Telephone—(207) 755–5606.                     Online Support at                                       Pursuant to section 313(a) of the
                                                      i. FERC Contact: Allan Creamer, (202)                 FERCOnlineSupport@ferc.gov, (866)–                    Federal Power Act,2 an aggrieved party
                                                    502–8365, or allan.creamer@ferc.gov.                    208–3676 (toll free), or (202) 502–8659               must file an application for rehearing
                                                      j. This application is not ready for                  (TTY). A copy is also available for                   within thirty days after the issuance of
                                                    environmental analysis (EA) at this                     inspection and reproduction at the
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                                                                  the Commission’s order. Moreover, the
                                                    time.                                                   address in item (h) above.                            courts and the Commission have
                                                      k. Project Description: The West                         You may also register online at http://            repeatedly recognized that the time
                                                    Buxton Project consists of: (1) A 585-                  www.ferc.gov/docs-filing/                             period by which a party may file an
                                                    foot-long by 30-foot-high concrete                      esubscription.asp to be notified via                  application for rehearing of a
                                                    gravity dam with a crest elevation of                   email of new filings and issuances
                                                    173.8 feet (United States Geological                    related to this or other pending projects.              1 Sage Grouse Energy Project, LLC, 153 FERC
                                                    Survey or USGS datum), consisting of (i)                For assistance, contact FERC Online                   ¶ 61,272 (2015) (December 3 Order).
                                                    two overflow sections topped with three                 Support.                                                2 16 U.S.C. 825l(a) (2012).




                                               VerDate Sep<11>2014   19:17 Dec 28, 2015   Jkt 238001   PO 00000   Frm 00037   Fmt 4703   Sfmt 4703   E:\FR\FM\29DEN1.SGM   29DEN1



Document Created: 2015-12-29 10:15:47
Document Modified: 2015-12-29 10:15:47
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 81308 