80_FR_81559 80 FR 81310 - Central Arizona Project-Rate Order No. WAPA-172

80 FR 81310 - Central Arizona Project-Rate Order No. WAPA-172

DEPARTMENT OF ENERGY
Western Area Power Administration

Federal Register Volume 80, Issue 249 (December 29, 2015)

Page Range81310-81314
FR Document2015-32792

The Deputy Secretary of Energy confirmed and approved Rate Order No. WAPA-172 and Rate Schedules CAP-FT3, CAP-NFT3, and CAP-NITS3, placing transmission service formula rates for the Central Arizona Project (CAP) of the Western Area Power Administration (Western) into effect on an interim basis. The provisional rates will be in effect until the Federal Energy Regulatory Commission (FERC) confirms, approves, and places them into effect on a final basis, or until they are replaced by other rates. The provisional rates will provide sufficient revenue to pay all annual costs, including interest expense, and repay required investment within the allowable periods.

Federal Register, Volume 80 Issue 249 (Tuesday, December 29, 2015)
[Federal Register Volume 80, Number 249 (Tuesday, December 29, 2015)]
[Notices]
[Pages 81310-81314]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-32792]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Western Area Power Administration


Central Arizona Project--Rate Order No. WAPA-172

AGENCY: Western Area Power Administration, DOE.

ACTION: Notice of final transmission service formula rates.

-----------------------------------------------------------------------

SUMMARY: The Deputy Secretary of Energy confirmed and approved Rate 
Order No. WAPA-172 and Rate Schedules CAP-FT3, CAP-NFT3, and CAP-NITS3, 
placing transmission service formula rates for the Central Arizona 
Project (CAP) of the Western Area Power Administration (Western) into 
effect on an interim basis. The provisional rates will be in effect 
until the Federal Energy Regulatory Commission (FERC) confirms, 
approves, and places them into effect on a final basis, or until they 
are replaced by other rates. The provisional rates will provide 
sufficient revenue to pay all annual costs, including interest expense, 
and repay required investment within the allowable periods.

DATES: Rate Schedules CAP-FT3, CAP-NFT3, and CAP-NITS3 are effective on 
the first day of the first full billing period beginning on or after 
January 1, 2016, and will be in effect until FERC confirms, approves, 
and places the rate schedules in effect on a final basis through 
December 31, 2020, or until the rate schedules are superseded.

FOR FURTHER INFORMATION CONTACT: Mr. Jack Murray, Vice President of 
Power Marketing, Desert Southwest Customer Service Regional Office, 
Western Area Power Administration, P.O. Box 6457, Phoenix, AZ 85005-
6457, (602) 605-2555, email [email protected].

SUPPLEMENTARY INFORMATION: An FRN was published on July 24, 2015 (80 FR 
44100) announcing the proposed rates for transmission service and 
initiating a public consultation and comment period. On July 29, 2015, 
Western notified all CAP customers and interested parties of the rate 
adjustment and provided a copy of the published FRN. On August 27, 
2015, Western held a public information forum in Phoenix, Arizona, 
explained the proposed rates and potential changes to the proposed 
rates, answered questions, and provided handouts. On September 24, 
2015, Western held a public comment forum in Phoenix, Arizona, to give 
the public an opportunity to comment for the record. No comments were 
received at the forum.
    Previous Rate Schedules CAP-FT2, CAP-NFT2, and CAP-NITS2 for Rate 
Order No. WAPA-124 \1\ were approved by FERC for a 5-year period 
through December 31, 2010. These Rate Schedules were extended through 
December 31, 2012, under Rate Order No. WAPA-153,\2\ and extended again 
through December 31, 2015, under Rate Order No. WAPA-158.\3\ Rate 
Schedules CAP-FT2, CAP-NFT2, and CAP-NITS2 are being superseded by Rate 
Schedules CAP-FT3, CAP-NFT3, and CAP-NITS3. Under Rate Schedule CAP-
FT2, the rate for firm point-to-point transmission service is $13.56 
per kilowatt year (kW-year). The provisional rate for firm point-to-
point transmission service under Rate Schedule CAP-FT3 is $14.88/kW-
year, which represents an increase of 10 percent when compared with the 
existing rate. Under Rate Schedule CAP-NFT2, the rate for non-firm 
point-to-point transmission service is 1.55 mills per kilowatt hour 
(mills/kWh). The provisional rate for non-firm point-to-point 
transmission service under Rate Schedule CAP-NFT3 is 1.70 mills/kWh, 
which represents an increase of 10 percent when compared with the 
existing rate. There will be no changes to the rate formula under CAP-
NITS3.
---------------------------------------------------------------------------

    \1\ Rate Order No. WAPA-124 was approved by FERC on a final 
basis on June 29, 2006, in Docket No. EF06-5111-000 (115 FERC ] 
62,326).
    \2\ 76 FR 548 (January 5, 2011).
    \3\ 78 FR 18335 (March 26, 2013).
---------------------------------------------------------------------------

    By Delegation Order No. 00-037.00A, effective October 25, 2013, the 
Secretary of Energy delegated: (1) The authority to develop power and 
transmission rates to Western's Administrator, (2) the authority to 
confirm, approve, and place such rates into effect on an interim basis 
to the Deputy Secretary of Energy, and

[[Page 81311]]

(3) the authority to confirm, approve, and place into effect on a final 
basis, to remand, or to disapprove such rates to FERC. Existing 
Department of Energy procedures for public participation in power rate 
adjustments (10 CFR part 903) were published on September 18, 1985.
    Under Delegation Order Nos. 00-037.00A and 00-001.00F, and in 
compliance with 10 CFR part 903 and 18 CFR part 300, I hereby confirm, 
approve, and place provisional rates for transmission service under 
Rate Order No. WAPA-172 into effect on an interim basis. New Rate 
Schedules CAP-FT3, CAP-NFT3, and CAP-NITS3 will be submitted promptly 
to FERC for confirmation and approval on a final basis.

    Dated: December 21, 2015.
Elizabeth Sherwood-Randall,
Deputy Secretary of Energy.

DEPARTMENT OF ENERGY

DEPUTY SECRETARY

    In the matter of: Western Area Power Administration Rate 
Adjustment for the Central Arizona Project

Rate Order No. WAPA-172

ORDER CONFIRMING, APPROVING, AND PLACING THE CENTRAL ARIZONA PROJECT 
TRANSMISSION SERVICE FORMULA RATES INTO EFFECT ON AN INTERIM BASIS

    These rates were established in accordance with section 302 of the 
Department of Energy (DOE) Organization Act (42 U.S.C. 7152). This Act 
transferred to and vested in the Secretary of Energy the power 
marketing functions of the Secretary of the Department of the Interior 
and the Bureau of Reclamation under the Reclamation Act of 1902 (ch. 
1093, 32 Stat. 388), as amended and supplemented by subsequent laws, 
particularly section 9(c) of the Reclamation Project Act of 1939 (43 
U.S.C. 485h(c)), and other Acts that specifically apply to the project 
involved.
    By Delegation Order No. 00-037.00A, effective October 25, 2013, the 
Secretary of Energy delegated: (1) The authority to develop power and 
transmission rates to Western Area Power Administration's (Western) 
Administrator, (2) the authority to confirm, approve, and place such 
rates into effect on an interim basis to the Deputy Secretary of 
Energy, and (3) the authority to confirm, approve, and place into 
effect on a final basis, to remand, or to disapprove such rates to the 
Federal Energy Regulatory Commission. Existing DOE procedures for 
public participation in power rate adjustments (10 CFR part 903) were 
published on September 18, 1985.

Acronyms and Definitions

    As used in this Rate Order, the following acronyms and definitions 
apply:
    Administrator: Administrator for the Western Area Power 
Administration.
    Capacity: The electric capability of a transformer, transmission 
circuit, or other equipment, expressed in kilowatts (kW).
    CAP: Central Arizona Project, one of three related water 
development projects that make up the Colorado River Basin Project.
    Customer: An entity with a contract or service agreement that 
receives service from Western's Desert Southwest Region.
    DOE: United States Department of Energy.
    DOE Order RA 6120.2: A DOE order outlining power marketing 
administration financial reporting and ratemaking procedures.
    Desert Southwest Region: The Desert Southwest Customer Service 
Region of Western.
    FERC: Federal Energy Regulatory Commission.
    Firm: A type of product and/or service that is available at the 
time requested by the customer.
    Formula Rates: A rate which is based upon a formula calculated 
yearly.
    FRN: Federal Register notice.
    Kilovolt (kV): Electrical unit of measure of potential difference 
that equals 1,000 volts.
    Kilowatt (kW): Electrical unit of capacity that equals 1,000 watts.
    Kilowatt hour (kWh): Electrical unit of energy that equals 1,000 
watts in 1 hour.
    Kilowatt month (kW-month): Electrical unit of the monthly amount of 
capacity.
    Kilowatt year (kW-year): Electrical unit of the yearly amount of 
capacity.
    Mill: A monetary denomination of the United States that equals one 
tenth of a cent or one thousandth of a dollar.
    Mills per kilowatt hour (mills/kWh): A unit of charge.
    Non-firm: A type of product and/or service not always available at 
the time requested by the customer.
    O&M: Operation and Maintenance.
    Proposed Rate: A rate that has been recommended by Western to the 
Deputy Secretary of Energy for approval.
    Provisional Rate: A rate that has been confirmed, approved, and 
placed into effect on an interim basis by the Deputy Secretary of 
Energy.
    Reclamation: United States Department of Interior, Bureau of 
Reclamation.
    Western: Western Area Power Administration.

Effective Date

    The new provisional rates will take effect on the first day of the 
first full billing period beginning on or after January 1, 2016, and 
will remain in effect until FERC confirms, approves, and places the 
rate schedules in effect on a final basis through December 31, 2020, or 
until the rate schedules are superseded.

Public Notice and Comment

    Western followed the Procedures for Public Participation in Power 
and Transmission Rate Adjustments and Extensions, 10 CFR part 903, in 
developing these rates. The steps Western took to involve interested 
parties in the rate process were:
    1. An FRN was published on July 24, 2015 (80 FR 44100) announcing 
the proposed rates for transmission service, initiating a public 
consultation and comment period, and setting forth the dates and 
locations of public information and public comment forums.
    2. On July 29, 2015, Western notified all CAP customers and 
interested parties of the rate adjustment and provided a copy of the 
published FRN.
    3. On August 27, 2015, Western held a public information forum in 
Phoenix, Arizona. Western explained the proposed rates and potential 
changes to the proposed rates, answered questions, and provided 
handouts.
    4. On September 24, 2015, Western held a public comment forum in 
Phoenix, Arizona, to give the public an opportunity to comment for the 
record. There were no comments received at this forum.
    5. Western created a CAP rate adjustment Web site to provide 
interested parties with information about this rate adjustment process. 
The Web site is located at https://www.wapa.gov/regions/DSW/Rates/Pages/central-arizona-rates.aspx
    6. On October 6, 2015, Western provided answers to a list of 
questions concerning the proposed rates and posted the answers on the 
CAP rate adjustment Web site.

Project Description

    The CAP is one of three related water development projects that 
make up the Colorado River Basin Project. The others are the Dixie and 
the Upper Basin projects. The CAP was developed for Arizona and western 
New Mexico; the Dixie Project for southeastern Utah; and the Upper 
Basin Project for Colorado and New Mexico.

[[Page 81312]]

    Congress authorized the Colorado River Basin Project in 1968 to 
improve water resources in the Colorado River Basin. Segments of the 
1968 authorization allowed Federal participation in the Navajo 
Generating Station (Navajo), which has three coal-fired steam electric 
generating units with a combined capacity of 2,250 MW. Construction of 
the plant, located near Lake Powell at Page, Arizona, began in 1970 and 
generation began in 1976.
    The 24.3 percent Federal Share of Navajo, or 546,750 kW, is used to 
power the pumps that move Colorado River water through CAP canals. 
Surplus generation is currently marketed under the Navajo Power 
Marketing Plan adopted on Dec. 1, 1987. Surplus Navajo short-term firm 
and non-firm transmission service will be marketed at the CAP 115/230-
kV transmission rate during the term of the rate schedules.

Existing and Provisional Rates

    The existing rates for point-to-point transmission service consist 
of a firm rate and a non-firm rate. The existing rate for firm point-
to-point transmission service under Rate Schedule CAP-FT2 is $13.56/kW-
year. The existing rate for non-firm point-to-point transmission 
service under Rate Schedule CAP-NFT2 is 1.55 mills/kWh. The existing 
rates under Rate Schedules CAP-FT2, CAP-NFT2, and CAP-NITS2 expire 
December 31, 2015.
    The provisional rates will supersede the existing rates and become 
effective on an interim basis on the first day of the first full 
billing period beginning on or after January 1, 2016. The provisional 
rate for firm point-to-point transmission service under Rate Schedule 
CAP-FT3 is $14.88/kW-year. The provisional rate for non-firm point-to-
point transmission service under Rate Schedule CAP-NFT3 is 1.70 mills/
kWh. The provisional rates will result in a rate increase of 10 percent 
when compared to the existing rates. A comparison of the existing and 
provisional rates for transmission service follows:

                      Comparison of Existing and Provisional Rates Central Arizona Project
----------------------------------------------------------------------------------------------------------------
                                                                           Provisional rates
          Transmission service                  Existing rates            (effective 1/1/16)          Change
----------------------------------------------------------------------------------------------------------------
Firm Point-to-Point.....................  $13.56/kW-year............  $14.88/kW-year............             10%
Non-firm Point-to-Point.................  1.55 mills/kWh............  1.70 mills/kWh............             10%
----------------------------------------------------------------------------------------------------------------

Certification of Rates

    Western's Administrator certified that the provisional rates for 
CAP transmission service under Rate Schedules CAP-FT3, CAP-NFT3, and 
CAP-NITS3 are the lowest possible rates consistent with sound business 
principles. The provisional rates were developed following 
administrative policies and applicable laws.

Transmission Rate Discussion

    According to Reclamation law, Western must establish rates which 
provide sufficient revenue to recover annual O&M, purchase power, 
transmission service and other costs, interest expense, and repay 
investments. Western calculates the rates each year to determine if the 
existing rates will provide adequate revenue to repay all power system 
costs within the required time. Repayment criteria are based on 
existing law and applicable policies, including DOE Order RA 6120.2. To 
meet the cost recovery criteria outlined in DOE Order RA 6120.2, a rate 
calculation was completed to demonstrate that sufficient revenues will 
be collected under the provisional rates to meet future obligations.
    The existing rates are insufficient and do not provide adequate 
revenue to cover costs due primarily to the replacement of the aging 
ED2-Saguaro line. Construction of this line started in 2015, and the 
costs will be spread over a 5-year period.
    A secondary factor for the rate increase is a decrease in projected 
sales of long-term firm point-to-point transmission service. The 
provisional rates include the reduction in the sales forecast for 115/
230-kV transmission service over the 5-year cost evaluation period.

Availability of Information

    All brochures, studies, comments, letters, memorandums, and other 
documents that Western used to develop the provisional rates are 
available for inspection and copying at the Desert Southwest Customer 
Service Regional Office, Western Area Power Administration, 615 South 
43rd Avenue, Phoenix, AZ 85009-5313. Many of these documents and 
supporting information are available on Western's Web site at https://www.wapa.gov/regions/DSW/Rates/Pages/central-arizona-rates.aspx.

RATEMAKING PROCEDURE REQUIREMENTS

Environmental Compliance

    In compliance with the National Environmental Policy Act (NEPA) of 
1969, (42 U.S.C. 4321, et seq.), Council on Environmental Quality 
Regulations (40 CFR parts 1500-1508), and DOE NEPA Regulations (10 CFR 
part 1021), Western has determined that this action is categorically 
excluded from the preparation of an environmental assessment or an 
environmental impact statement.

Determination Under Executive Order 12866

    Western has an exemption from centralized regulatory review under 
Executive Order 12866; accordingly, no clearance of this notice by the 
Office of Management and Budget is required.

Submission to the Federal Energy Regulatory Commission

    The interim rates confirmed, approved, and placed into effect 
herein, together with supporting documents, will be submitted to FERC 
for confirmation and final approval.

ORDER

    In view of the foregoing and under the authority delegated to me, I 
confirm and approve on an interim basis Rate Schedules CAP-FT3, CAP-
NFT3, and CAP-NITS3 to become effective on the first day of the first 
full-billing period beginning on or after January 1, 2016, and to 
remain in effect until FERC confirms, approves, and places the rate 
schedules in effect on a final basis through December 31, 2020, or 
until the rate schedules are superseded.


Dated: December 21, 2015

Elizabeth Sherwood-Randall,

Deputy Secretary of Energy

Rate Schedule CAP-FT3
SCHEDULE 7 to Tariff
(Supersedes Schedule CAP-FT2)

[[Page 81313]]

UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION

DESERT SOUTHWEST CUSTOMER SERVICE REGION CENTRAL ARIZONA PROJECT

FIRM POINT-TO-POINT TRANSMISSION SERVICE

Effective:

    The first day of the first full billing period beginning on or 
after January 1,
    2016, through December 31, 2020, or until superseded by another 
rate schedule, whichever occurs earlier.

Applicable:

    The transmission customer will compensate the Central Arizona 
Project (CAP) each month for Reserved Capacity under the applicable 
Firm Point-To-Point Transmission Service Agreement and the formula rate 
described herein.

Formula Rate:
[GRAPHIC] [TIFF OMITTED] TN29DE15.008

    A recalculated rate will go into effect every January 1 based on 
the above formula and updated financial and operational data. Western 
will notify the transmission customer annually of the recalculated rate 
on or before December 1. Discounts may be offered from time-to-time in 
accordance with Western's Open Access Transmission Tariff.

Character and Conditions of Service:

    Alternating current at 60 Hertz, three-phase, delivered and metered 
at the voltages and points of delivery established by contract or 
service agreement over the CAP 115/230-kV transmission system.

Adjustment for Reactive Power:

    There shall be no entitlement to transfer of reactive kilovolt 
amperes at delivery points, except when such transfers may be mutually 
agreed upon by the parties and contracting officer or their authorized 
representatives.

Billing:

    Billing determinants for the formula rate above will be as 
specified in the contract or service agreement. Billing will occur 
monthly under the formula rate.

Adjustment for Losses:

    Losses incurred for service under this rate schedule will be 
accounted for as agreed to by the parties in accordance with the 
contract or service agreement. If losses are not fully provided by a 
Transmission Customer, charges for financial compensation may apply.

Unreserved Use:

    Western will assess a charge for any unreserved use of the 
transmission system. Unreserved use occurs when a customer uses 
transmission service that it has not reserved or uses transmission 
service in excess of its reserved capacity. Unreserved use may also 
include a customer's failure to curtail transmission when requested.
    The charge assessed for unreserved use is two times the maximum 
allowable rate for the service at issue as follows: The penalty for a 
single hour of unreserved use is based on the daily short-term rate. 
The penalty for more than one assessment of unreserved use for any 
given duration (e.g., daily) increases to next longest duration (e.g., 
weekly). The penalty for multiple instances of unreserved use (e.g., 
more than one hour) within a day is based on the daily short-term rate. 
The penalty for multiple instances of unreserved use isolated to one 
calendar week is based on the weekly short-term rate. The penalty for 
multiple instances of unreserved use during more than one week in a 
calendar month is based on the monthly short-term rate.
    A customer that exceeds its reserved capacity at any point of 
receipt or point of delivery, or a customer that uses transmission 
service at a point of receipt or point of delivery that it has not 
reserved, is required to pay for all ancillary services provided by the 
Western Area Lower Colorado (WALC) Balancing Authority and associated 
with the unreserved use. The customer will pay for ancillary services 
based on the amount of transmission service used and not reserved.
Rate Schedule CAP-NFT3
SCHEDULE 7 to Tariff
(Supersedes Schedule CAP-NFT2)

UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION

DESERT SOUTHWEST CUSTOMER SERVICE REGION CENTRAL ARIZONA PROJECT

NON-FIRM POINT-TO-POINT TRANSMISSION SERVICE

Effective:

    The first day of the first full billing period beginning on or 
after January 1, 2016, through December 31, 2020, or until superseded 
by another rate schedule, whichever occurs earlier.

Applicable:

    The transmission customer will compensate the Central Arizona 
Project (CAP) each month for Non-Firm Point-To-Point Transmission 
Service under the applicable agreement and the formula rate described 
herein.

Formula Rate:

Maximum Non-Firm Point-To-Point Transmission Rate = Firm Point-To-Point 
Transmission Rate

A recalculated rate will go into effect every January 1 based on the 
above formula and updated financial and operational data. Western will 
notify the transmission customer annually of the recalculated rate on 
or before December 1. Discounts may be offered from time-to-time in 
accordance with Western's Open Access Transmission Tariff.

Character and Conditions of Service:

    Alternating current at 60 Hertz, three-phase, delivered and metered 
at the voltages and points of delivery established by contract or 
service agreement over the CAP 115/230-kV transmission system.

[[Page 81314]]

Adjustment for Reactive Power:

    There shall be no entitlement to transfer of reactive kilovolt 
amperes at delivery points, except when such transfers may be mutually 
agreed upon by the parties and contracting officer or their authorized 
representatives.

Billing:

    Billing determinants for the formula rate above will be as 
specified in the service agreement. Billing will occur monthly under 
the formula rate.

Adjustment for Losses:

    Losses incurred for service under this rate schedule will be 
accounted for as agreed to by the parties in accordance with the 
contract or service agreement. If losses are not fully provided by a 
transmission customer, charges for financial compensation may apply.

Navajo Transmission Service (500-kV):

    Western will market excess transmission service from the Navajo 
(500-kV) portion of the CAP on a short-term basis at the formula rate 
described herein.

Rate Schedule CAP-NITS3
ATTACHMENT H to Tariff
(Supersedes Schedule CAP-NITS2)

UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION

DESERT SOUTHWEST CUSTOMER SERVICE REGION CENTRAL ARIZONA PROJECT

NETWORK INTEGRATION TRANSMISSION SERVICE

Effective:

    The first day of the first full billing period beginning on or 
after January 1, 2016, through December 31, 2020, or until superseded 
by another rate schedule, whichever occurs earlier.

Applicable:

    The transmission customer will compensate the Central Arizona 
Project (CAP) each month for Network Integration Transmission Service 
(NITS) under the applicable agreement and the formula rate described 
herein.

Formula Rate:
[GRAPHIC] [TIFF OMITTED] TN29DE15.009

A recalculated Annual Transmission Revenue Requirement for Network 
Integration Transmission Service will go into effect every January 1 
based on the above formula and updated financial and load data. Western 
will notify the transmission customer annually of the recalculated 
annual revenue requirement on or before December 1.

Billing:

    Billing determinants for the formula rate above will be as 
specified in the service agreement. Billing will occur monthly under 
the formula rate.

Adjustment for Losses:

    Losses incurred for service under this rate schedule will be 
accounted for as agreed to by the parties in accordance with the 
contract or service agreement. If losses are not fully provided by a 
transmission customer, charges for financial compensation may apply.

[FR Doc. 2015-32792 Filed 12-28-15; 8:45 am]
BILLING CODE 6450-01-P



                                                    81310                      Federal Register / Vol. 80, No. 249 / Tuesday, December 29, 2015 / Notices

                                                       Applicants: Sierra Pacific Power                     must file in accordance with Rules 211                Phoenix, AZ 85005–6457, (602) 605–
                                                    Company.                                                and 214 of the Commission’s                           2555, email jmurray@wapa.gov.
                                                       Description: Compliance filing:                      Regulations (18 CFR 385.211 and                       SUPPLEMENTARY INFORMATION: An FRN
                                                    Market-Based Rate Tariff Volume No. 7                   § 385.214) on or before 5:00 p.m. Eastern             was published on July 24, 2015 (80 FR
                                                    to be effective 12/1/2015.                              time on the specified comment date.                   44100) announcing the proposed rates
                                                       Filed Date: 12/21/15.                                Protests may be considered, but                       for transmission service and initiating a
                                                       Accession Number: 20151221–5308.                     intervention is necessary to become a                 public consultation and comment
                                                       Comments Due: 5 p.m. ET 1/11/16.                     party to the proceeding.                              period. On July 29, 2015, Western
                                                       Docket Numbers: ER16–606–000.                           eFiling is encouraged. More detailed               notified all CAP customers and
                                                       Applicants: PacifiCorp.                              information relating to filing                        interested parties of the rate adjustment
                                                       Description: Compliance filing:                      requirements, interventions, protests,                and provided a copy of the published
                                                    Amendment to Market-Based Rate                          service, and qualifying facilities filings            FRN. On August 27, 2015, Western held
                                                    Tariff—EIM Compliance Filing to be                      can be found at: http://www.ferc.gov/                 a public information forum in Phoenix,
                                                    effective 12/1/2015.                                    docs-filing/efiling/filing-req.pdf. For               Arizona, explained the proposed rates
                                                       Filed Date: 12/21/15.                                other information, call (866) 208–3676                and potential changes to the proposed
                                                       Accession Number: 20151221–5310.                     (toll free). For TTY, call (202) 502–8659.            rates, answered questions, and provided
                                                       Comments Due: 5 p.m. ET 1/11/16.                                                                           handouts. On September 24, 2015,
                                                                                                              Dated: December 22, 2015.
                                                       Docket Numbers: ER16–607–000.                                                                              Western held a public comment forum
                                                                                                            Nathaniel J. Davis, Sr.,
                                                       Applicants: 67RK 8me LLC.                                                                                  in Phoenix, Arizona, to give the public
                                                       Description: § 205(d) Rate Filing: SFA               Deputy Secretary.
                                                                                                                                                                  an opportunity to comment for the
                                                    to be effective 12/22/2015.                             [FR Doc. 2015–32689 Filed 12–28–15; 8:45 am]
                                                                                                                                                                  record. No comments were received at
                                                       Filed Date: 12/21/15.                                BILLING CODE 6717–01–P                                the forum.
                                                       Accession Number: 20151221–5311.                                                                              Previous Rate Schedules CAP–FT2,
                                                       Comments Due: 5 p.m. ET 1/11/16.                                                                           CAP–NFT2, and CAP–NITS2 for Rate
                                                       Docket Numbers: ER16–608–000.                        DEPARTMENT OF ENERGY                                  Order No. WAPA–124 1 were approved
                                                       Applicants: 65HK 8me LLC.                            Western Area Power Administration                     by FERC for a 5-year period through
                                                       Description: § 205(d) Rate Filing:                                                                         December 31, 2010. These Rate
                                                    65HK 8me LLC Hayworth SFA to be                         Central Arizona Project—Rate Order                    Schedules were extended through
                                                    effective 12/22/2015.                                   No. WAPA–172                                          December 31, 2012, under Rate Order
                                                       Filed Date: 12/21/15.                                                                                      No. WAPA–153,2 and extended again
                                                       Accession Number: 20151221–5312.                     AGENCY:  Western Area Power                           through December 31, 2015, under Rate
                                                       Comments Due: 5 p.m. ET 1/11/16.                     Administration, DOE.                                  Order No. WAPA–158.3 Rate Schedules
                                                       Docket Numbers: ER16–609–000.                        ACTION: Notice of final transmission                  CAP–FT2, CAP–NFT2, and CAP–NITS2
                                                       Applicants: 87RL 8me LLC.                            service formula rates.                                are being superseded by Rate Schedules
                                                       Description: § 205(d) Rate Filing:                                                                         CAP–FT3, CAP–NFT3, and CAP–NITS3.
                                                    87RL 8me LLC Woodmere SFA to be                         SUMMARY:    The Deputy Secretary of                   Under Rate Schedule CAP–FT2, the rate
                                                    effective 12/22/2015.                                   Energy confirmed and approved Rate                    for firm point-to-point transmission
                                                       Filed Date: 12/21/15.                                Order No. WAPA–172 and Rate                           service is $13.56 per kilowatt year (kW-
                                                       Accession Number: 20151221–5313.                     Schedules CAP–FT3, CAP–NFT3, and                      year). The provisional rate for firm
                                                       Comments Due: 5 p.m. ET 1/11/16.                     CAP–NITS3, placing transmission                       point-to-point transmission service
                                                       Docket Numbers: ER16–610–000.                        service formula rates for the Central                 under Rate Schedule CAP–FT3 is
                                                       Applicants: Northern Indiana Public                  Arizona Project (CAP) of the Western                  $14.88/kW-year, which represents an
                                                    Service Company.                                        Area Power Administration (Western)                   increase of 10 percent when compared
                                                       Description: § 205(d) Rate Filing:                   into effect on an interim basis. The                  with the existing rate. Under Rate
                                                    Filing of a CIAC Agreement to be                        provisional rates will be in effect until             Schedule CAP–NFT2, the rate for non-
                                                    effective 1/4/2016.                                     the Federal Energy Regulatory                         firm point-to-point transmission service
                                                       Filed Date: 12/21/15.                                Commission (FERC) confirms, approves,                 is 1.55 mills per kilowatt hour (mills/
                                                       Accession Number: 20151221–5314.                     and places them into effect on a final                kWh). The provisional rate for non-firm
                                                       Comments Due: 5 p.m. ET 1/11/16.                     basis, or until they are replaced by other            point-to-point transmission service
                                                       Take notice that the Commission                      rates. The provisional rates will provide             under Rate Schedule CAP–NFT3 is 1.70
                                                    received the following electric                         sufficient revenue to pay all annual                  mills/kWh, which represents an
                                                    reliability filings:                                    costs, including interest expense, and                increase of 10 percent when compared
                                                                                                            repay required investment within the                  with the existing rate. There will be no
                                                       Docket Numbers: RR15–12–001.
                                                       Applicants: North American Electric                  allowable periods.                                    changes to the rate formula under CAP–
                                                    Reliability Corporation.                                DATES: Rate Schedules CAP–FT3, CAP–                   NITS3.
                                                       Description: Compliance Filing of                    NFT3, and CAP–NITS3 are effective on                     By Delegation Order No. 00–037.00A,
                                                    North American Electric Reliability                     the first day of the first full billing               effective October 25, 2013, the Secretary
                                                    Corporation in Accordance with the                      period beginning on or after January 1,               of Energy delegated: (1) The authority to
                                                    Commission’s November 2, 2015 Order.                    2016, and will be in effect until FERC                develop power and transmission rates to
                                                       Filed Date: 12/18/15.                                confirms, approves, and places the rate               Western’s Administrator, (2) the
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                       Accession Number: 20151218–5315.                     schedules in effect on a final basis                  authority to confirm, approve, and place
                                                       Comments Due: 5 p.m. ET 1/8/16.                      through December 31, 2020, or until the               such rates into effect on an interim basis
                                                       The filings are accessible in the                    rate schedules are superseded.                        to the Deputy Secretary of Energy, and
                                                    Commission’s eLibrary system by                         FOR FURTHER INFORMATION CONTACT: Mr.
                                                                                                                                                                    1 Rate Order No. WAPA–124 was approved by
                                                    clicking on the links or querying the                   Jack Murray, Vice President of Power                  FERC on a final basis on June 29, 2006, in Docket
                                                    docket number.                                          Marketing, Desert Southwest Customer                  No. EF06–5111–000 (115 FERC ¶ 62,326).
                                                       Any person desiring to intervene or                  Service Regional Office, Western Area                   2 76 FR 548 (January 5, 2011).

                                                    protest in any of the above proceedings                 Power Administration, P.O. Box 6457,                    3 78 FR 18335 (March 26, 2013).




                                               VerDate Sep<11>2014   20:53 Dec 28, 2015   Jkt 238001   PO 00000   Frm 00039   Fmt 4703   Sfmt 4703   E:\FR\FM\29DEN1.SGM   29DEN1


                                                                               Federal Register / Vol. 80, No. 249 / Tuesday, December 29, 2015 / Notices                                            81311

                                                    (3) the authority to confirm, approve,                  adjustments (10 CFR part 903) were                     Western: Western Area Power
                                                    and place into effect on a final basis, to              published on September 18, 1985.                      Administration.
                                                    remand, or to disapprove such rates to
                                                                                                            Acronyms and Definitions                              Effective Date
                                                    FERC. Existing Department of Energy
                                                    procedures for public participation in                     As used in this Rate Order, the                       The new provisional rates will take
                                                    power rate adjustments (10 CFR part                     following acronyms and definitions                    effect on the first day of the first full
                                                    903) were published on September 18,                    apply:                                                billing period beginning on or after
                                                    1985.                                                      Administrator: Administrator for the               January 1, 2016, and will remain in
                                                       Under Delegation Order Nos. 00–                      Western Area Power Administration.                    effect until FERC confirms, approves,
                                                    037.00A and 00–001.00F, and in                             Capacity: The electric capability of a             and places the rate schedules in effect
                                                    compliance with 10 CFR part 903 and                     transformer, transmission circuit, or                 on a final basis through December 31,
                                                    18 CFR part 300, I hereby confirm,                      other equipment, expressed in kilowatts               2020, or until the rate schedules are
                                                    approve, and place provisional rates for                (kW).                                                 superseded.
                                                    transmission service under Rate Order                      CAP: Central Arizona Project, one of
                                                                                                            three related water development                       Public Notice and Comment
                                                    No. WAPA–172 into effect on an interim
                                                    basis. New Rate Schedules CAP–FT3,                      projects that make up the Colorado                       Western followed the Procedures for
                                                    CAP–NFT3, and CAP–NITS3 will be                         River Basin Project.                                  Public Participation in Power and
                                                    submitted promptly to FERC for                             Customer: An entity with a contract or             Transmission Rate Adjustments and
                                                    confirmation and approval on a final                    service agreement that receives service               Extensions, 10 CFR part 903, in
                                                    basis.                                                  from Western’s Desert Southwest                       developing these rates. The steps
                                                                                                            Region.                                               Western took to involve interested
                                                      Dated: December 21, 2015.
                                                                                                               DOE: United States Department of                   parties in the rate process were:
                                                    Elizabeth Sherwood-Randall,                                                                                      1. An FRN was published on July 24,
                                                                                                            Energy.
                                                    Deputy Secretary of Energy.                                DOE Order RA 6120.2: A DOE order                   2015 (80 FR 44100) announcing the
                                                    DEPARTMENT OF ENERGY                                    outlining power marketing                             proposed rates for transmission service,
                                                                                                            administration financial reporting and                initiating a public consultation and
                                                    DEPUTY SECRETARY
                                                                                                            ratemaking procedures.                                comment period, and setting forth the
                                                      In the matter of: Western Area Power                     Desert Southwest Region: The Desert                dates and locations of public
                                                    Administration Rate Adjustment for the                  Southwest Customer Service Region of                  information and public comment
                                                    Central Arizona Project                                 Western.                                              forums.
                                                    Rate Order No. WAPA–172                                    FERC: Federal Energy Regulatory                       2. On July 29, 2015, Western notified
                                                    ORDER CONFIRMING, APPROVING,                            Commission.                                           all CAP customers and interested parties
                                                    AND PLACING THE CENTRAL                                    Firm: A type of product and/or service             of the rate adjustment and provided a
                                                    ARIZONA PROJECT TRANSMISSION                            that is available at the time requested by            copy of the published FRN.
                                                                                                            the customer.                                            3. On August 27, 2015, Western held
                                                    SERVICE FORMULA RATES INTO
                                                                                                               Formula Rates: A rate which is based               a public information forum in Phoenix,
                                                    EFFECT ON AN INTERIM BASIS
                                                                                                            upon a formula calculated yearly.                     Arizona. Western explained the
                                                       These rates were established in                         FRN: Federal Register notice.                      proposed rates and potential changes to
                                                    accordance with section 302 of the                         Kilovolt (kV): Electrical unit of                  the proposed rates, answered questions,
                                                    Department of Energy (DOE)                              measure of potential difference that                  and provided handouts.
                                                    Organization Act (42 U.S.C. 7152). This                 equals 1,000 volts.                                      4. On September 24, 2015, Western
                                                    Act transferred to and vested in the                       Kilowatt (kW): Electrical unit of                  held a public comment forum in
                                                    Secretary of Energy the power marketing                 capacity that equals 1,000 watts.                     Phoenix, Arizona, to give the public an
                                                    functions of the Secretary of the                          Kilowatt hour (kWh): Electrical unit of            opportunity to comment for the record.
                                                    Department of the Interior and the                      energy that equals 1,000 watts in 1 hour.             There were no comments received at
                                                    Bureau of Reclamation under the                            Kilowatt month (kW-month):                         this forum.
                                                    Reclamation Act of 1902 (ch. 1093, 32                   Electrical unit of the monthly amount of                 5. Western created a CAP rate
                                                    Stat. 388), as amended and                              capacity.                                             adjustment Web site to provide
                                                    supplemented by subsequent laws,                           Kilowatt year (kW-year): Electrical                interested parties with information
                                                    particularly section 9(c) of the                        unit of the yearly amount of capacity.                about this rate adjustment process. The
                                                    Reclamation Project Act of 1939 (43                        Mill: A monetary denomination of the               Web site is located at https://
                                                    U.S.C. 485h(c)), and other Acts that                    United States that equals one tenth of a              www.wapa.gov/regions/DSW/Rates/
                                                    specifically apply to the project                       cent or one thousandth of a dollar.                   Pages/central-arizona-rates.aspx
                                                    involved.                                                  Mills per kilowatt hour (mills/kWh): A                6. On October 6, 2015, Western
                                                       By Delegation Order No. 00–037.00A,                  unit of charge.                                       provided answers to a list of questions
                                                    effective October 25, 2013, the Secretary                  Non-firm: A type of product and/or                 concerning the proposed rates and
                                                    of Energy delegated: (1) The authority to               service not always available at the time              posted the answers on the CAP rate
                                                    develop power and transmission rates to                 requested by the customer.                            adjustment Web site.
                                                    Western Area Power Administration’s                        O&M: Operation and Maintenance.
                                                    (Western) Administrator, (2) the                           Proposed Rate: A rate that has been                Project Description
                                                    authority to confirm, approve, and place                recommended by Western to the Deputy                    The CAP is one of three related water
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    such rates into effect on an interim basis              Secretary of Energy for approval.                     development projects that make up the
                                                    to the Deputy Secretary of Energy, and                     Provisional Rate: A rate that has been             Colorado River Basin Project. The others
                                                    (3) the authority to confirm, approve,                  confirmed, approved, and placed into                  are the Dixie and the Upper Basin
                                                    and place into effect on a final basis, to              effect on an interim basis by the Deputy              projects. The CAP was developed for
                                                    remand, or to disapprove such rates to                  Secretary of Energy.                                  Arizona and western New Mexico; the
                                                    the Federal Energy Regulatory                              Reclamation: United States                         Dixie Project for southeastern Utah; and
                                                    Commission. Existing DOE procedures                     Department of Interior, Bureau of                     the Upper Basin Project for Colorado
                                                    for public participation in power rate                  Reclamation.                                          and New Mexico.


                                               VerDate Sep<11>2014   19:17 Dec 28, 2015   Jkt 238001   PO 00000   Frm 00040   Fmt 4703   Sfmt 4703   E:\FR\FM\29DEN1.SGM   29DEN1


                                                    81312                           Federal Register / Vol. 80, No. 249 / Tuesday, December 29, 2015 / Notices

                                                       Congress authorized the Colorado                              adopted on Dec. 1, 1987. Surplus Navajo                            NFT2, and CAP–NITS2 expire
                                                    River Basin Project in 1968 to improve                           short-term firm and non-firm                                       December 31, 2015.
                                                    water resources in the Colorado River                            transmission service will be marketed at                              The provisional rates will supersede
                                                    Basin. Segments of the 1968                                      the CAP 115/230-kV transmission rate                               the existing rates and become effective
                                                    authorization allowed Federal                                    during the term of the rate schedules.                             on an interim basis on the first day of
                                                    participation in the Navajo Generating                                                                                              the first full billing period beginning on
                                                    Station (Navajo), which has three coal-                          Existing and Provisional Rates                                     or after January 1, 2016. The provisional
                                                    fired steam electric generating units                                                                                               rate for firm point-to-point transmission
                                                                                                                        The existing rates for point-to-point
                                                    with a combined capacity of 2,250 MW.                                                                                               service under Rate Schedule CAP–FT3
                                                                                                                     transmission service consist of a firm
                                                    Construction of the plant, located near                                                                                             is $14.88/kW-year. The provisional rate
                                                                                                                     rate and a non-firm rate. The existing
                                                    Lake Powell at Page, Arizona, began in                                                                                              for non-firm point-to-point transmission
                                                    1970 and generation began in 1976.                               rate for firm point-to-point transmission                          service under Rate Schedule CAP–NFT3
                                                       The 24.3 percent Federal Share of                             service under Rate Schedule CAP–FT2                                is 1.70 mills/kWh. The provisional rates
                                                    Navajo, or 546,750 kW, is used to power                          is $13.56/kW-year. The existing rate for                           will result in a rate increase of 10
                                                    the pumps that move Colorado River                               non-firm point-to-point transmission                               percent when compared to the existing
                                                    water through CAP canals. Surplus                                service under Rate Schedule CAP–NFT2                               rates. A comparison of the existing and
                                                    generation is currently marketed under                           is 1.55 mills/kWh. The existing rates                              provisional rates for transmission
                                                    the Navajo Power Marketing Plan                                  under Rate Schedules CAP–FT2, CAP–                                 service follows:

                                                                                    COMPARISON OF EXISTING AND PROVISIONAL RATES CENTRAL ARIZONA PROJECT
                                                                                                                                                                                         Provisional rates
                                                                 Transmission service                                           Existing rates                                                                                      Change
                                                                                                                                                                                         (effective 1/1/16)

                                                    Firm Point-to-Point ...................................   $13.56/kW-year .......................................     $14.88/kW-year .......................................          10%
                                                    Non-firm Point-to-Point ............................      1.55 mills/kWh .........................................   1.70 mills/kWh .........................................        10%



                                                    Certification of Rates                                           transmission service. The provisional                              Executive Order 12866; accordingly, no
                                                       Western’s Administrator certified that                        rates include the reduction in the sales                           clearance of this notice by the Office of
                                                    the provisional rates for CAP                                    forecast for 115/230-kV transmission                               Management and Budget is required.
                                                    transmission service under Rate                                  service over the 5-year cost evaluation
                                                                                                                     period.                                                            Submission to the Federal Energy
                                                    Schedules CAP–FT3, CAP–NFT3, and                                                                                                    Regulatory Commission
                                                    CAP–NITS3 are the lowest possible                                Availability of Information
                                                    rates consistent with sound business                                                                                                  The interim rates confirmed,
                                                                                                                        All brochures, studies, comments,
                                                    principles. The provisional rates were                                                                                              approved, and placed into effect herein,
                                                                                                                     letters, memorandums, and other
                                                    developed following administrative                                                                                                  together with supporting documents,
                                                    policies and applicable laws.                                    documents that Western used to
                                                                                                                     develop the provisional rates are                                  will be submitted to FERC for
                                                    Transmission Rate Discussion                                     available for inspection and copying at                            confirmation and final approval.
                                                       According to Reclamation law,                                 the Desert Southwest Customer Service                              ORDER
                                                    Western must establish rates which                               Regional Office, Western Area Power
                                                    provide sufficient revenue to recover                            Administration, 615 South 43rd                                        In view of the foregoing and under the
                                                    annual O&M, purchase power,                                      Avenue, Phoenix, AZ 85009–5313.                                    authority delegated to me, I confirm and
                                                    transmission service and other costs,                            Many of these documents and                                        approve on an interim basis Rate
                                                    interest expense, and repay investments.                         supporting information are available on                            Schedules CAP–FT3, CAP–NFT3, and
                                                    Western calculates the rates each year to                        Western’s Web site at https://                                     CAP–NITS3 to become effective on the
                                                    determine if the existing rates will                             www.wapa.gov/regions/DSW/Rates/                                    first day of the first full-billing period
                                                    provide adequate revenue to repay all                            Pages/central–arizona–rates.aspx.                                  beginning on or after January 1, 2016,
                                                    power system costs within the required                           RATEMAKING PROCEDURE                                               and to remain in effect until FERC
                                                    time. Repayment criteria are based on                            REQUIREMENTS                                                       confirms, approves, and places the rate
                                                    existing law and applicable policies,                                                                                               schedules in effect on a final basis
                                                    including DOE Order RA 6120.2. To                                Environmental Compliance
                                                                                                                                                                                        through December 31, 2020, or until the
                                                    meet the cost recovery criteria outlined                            In compliance with the National                                 rate schedules are superseded.
                                                    in DOE Order RA 6120.2, a rate                                   Environmental Policy Act (NEPA) of
                                                    calculation was completed to                                     1969, (42 U.S.C. 4321, et seq.), Council                           Dated: December 21, 2015
                                                    demonstrate that sufficient revenues                             on Environmental Quality Regulations                               Elizabeth Sherwood-Randall,
                                                    will be collected under the provisional                          (40 CFR parts 1500–1508), and DOE                                  Deputy Secretary of Energy
                                                    rates to meet future obligations.                                NEPA Regulations (10 CFR part 1021),
                                                       The existing rates are insufficient and                       Western has determined that this action                            Rate Schedule CAP–FT3
                                                    do not provide adequate revenue to
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                     is categorically excluded from the                                 SCHEDULE 7 to Tariff
                                                    cover costs due primarily to the                                 preparation of an environmental
                                                    replacement of the aging ED2-Saguaro                                                                                                (Supersedes Schedule CAP–FT2)
                                                                                                                     assessment or an environmental impact
                                                    line. Construction of this line started in                       statement.
                                                    2015, and the costs will be spread over
                                                    a 5-year period.                                                 Determination Under Executive Order
                                                       A secondary factor for the rate                               12866
                                                    increase is a decrease in projected sales                          Western has an exemption from
                                                    of long-term firm point-to-point                                 centralized regulatory review under


                                               VerDate Sep<11>2014      19:17 Dec 28, 2015      Jkt 238001    PO 00000      Frm 00041     Fmt 4703     Sfmt 4703     E:\FR\FM\29DEN1.SGM           29DEN1


                                                                               Federal Register / Vol. 80, No. 249 / Tuesday, December 29, 2015 / Notices                                            81313

                                                    UNITED STATES DEPARTMENT OF                               2016, through December 31, 2020, or
                                                    ENERGY WESTERN AREA POWER                               until superseded by another rate
                                                    ADMINISTRATION                                          schedule, whichever occurs earlier.
                                                    DESERT SOUTHWEST CUSTOMER                               Applicable:
                                                    SERVICE REGION CENTRAL
                                                    ARIZONA PROJECT                                           The transmission customer will
                                                                                                            compensate the Central Arizona Project
                                                    FIRM POINT-TO-POINT                                     (CAP) each month for Reserved Capacity
                                                    TRANSMISSION SERVICE                                    under the applicable Firm Point-To-
                                                    Effective:                                              Point Transmission Service Agreement
                                                                                                            and the formula rate described herein.
                                                      The first day of the first full billing
                                                    period beginning on or after January 1,                 Formula Rate:




                                                       A recalculated rate will go into effect              capacity. Unreserved use may also                     UNITED STATES DEPARTMENT OF
                                                    every January 1 based on the above                      include a customer’s failure to curtail               ENERGY WESTERN AREA POWER
                                                    formula and updated financial and                       transmission when requested.                          ADMINISTRATION
                                                    operational data. Western will notify the                  The charge assessed for unreserved                 DESERT SOUTHWEST CUSTOMER
                                                    transmission customer annually of the                   use is two times the maximum                          SERVICE REGION CENTRAL
                                                    recalculated rate on or before December
                                                                                                            allowable rate for the service at issue as            ARIZONA PROJECT
                                                    1. Discounts may be offered from time-
                                                                                                            follows: The penalty for a single hour of
                                                    to-time in accordance with Western’s                                                                          NON-FIRM POINT-TO-POINT
                                                    Open Access Transmission Tariff.                        unreserved use is based on the daily
                                                                                                                                                                  TRANSMISSION SERVICE
                                                                                                            short-term rate. The penalty for more
                                                    Character and Conditions of Service:                    than one assessment of unreserved use                 Effective:
                                                       Alternating current at 60 Hertz, three-              for any given duration (e.g., daily)
                                                                                                            increases to next longest duration (e.g.,               The first day of the first full billing
                                                    phase, delivered and metered at the
                                                    voltages and points of delivery                         weekly). The penalty for multiple                     period beginning on or after January 1,
                                                    established by contract or service                      instances of unreserved use (e.g., more               2016, through December 31, 2020, or
                                                    agreement over the CAP 115/230-kV                                                                             until superseded by another rate
                                                                                                            than one hour) within a day is based on
                                                    transmission system.                                                                                          schedule, whichever occurs earlier.
                                                                                                            the daily short-term rate. The penalty
                                                    Adjustment for Reactive Power:                          for multiple instances of unreserved use              Applicable:
                                                                                                            isolated to one calendar week is based
                                                       There shall be no entitlement to                     on the weekly short-term rate. The                      The transmission customer will
                                                    transfer of reactive kilovolt amperes at                penalty for multiple instances of                     compensate the Central Arizona Project
                                                    delivery points, except when such                                                                             (CAP) each month for Non-Firm Point-
                                                                                                            unreserved use during more than one
                                                    transfers may be mutually agreed upon                                                                         To-Point Transmission Service under
                                                                                                            week in a calendar month is based on
                                                    by the parties and contracting officer or                                                                     the applicable agreement and the
                                                    their authorized representatives.                       the monthly short-term rate.
                                                                                                                                                                  formula rate described herein.
                                                                                                               A customer that exceeds its reserved
                                                    Billing:                                                capacity at any point of receipt or point             Formula Rate:
                                                      Billing determinants for the formula                  of delivery, or a customer that uses
                                                    rate above will be as specified in the                                                                        Maximum Non-Firm Point-To-Point
                                                                                                            transmission service at a point of receipt               Transmission Rate = Firm Point-To-
                                                    contract or service agreement. Billing                  or point of delivery that it has not
                                                    will occur monthly under the formula                                                                             Point Transmission Rate
                                                                                                            reserved, is required to pay for all
                                                    rate.                                                   ancillary services provided by the                    A recalculated rate will go into effect
                                                    Adjustment for Losses:                                  Western Area Lower Colorado (WALC)                    every January 1 based on the above
                                                                                                            Balancing Authority and associated                    formula and updated financial and
                                                       Losses incurred for service under this                                                                     operational data. Western will notify the
                                                    rate schedule will be accounted for as                  with the unreserved use. The customer
                                                                                                            will pay for ancillary services based on              transmission customer annually of the
                                                    agreed to by the parties in accordance                                                                        recalculated rate on or before December
                                                    with the contract or service agreement.                 the amount of transmission service used
                                                                                                            and not reserved.                                     1. Discounts may be offered from time-
                                                    If losses are not fully provided by a                                                                         to-time in accordance with Western’s
                                                    Transmission Customer, charges for                      Rate Schedule CAP–NFT3                                Open Access Transmission Tariff.
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    financial compensation may apply.                       SCHEDULE 7 to Tariff
                                                    Unreserved Use:                                                                                               Character and Conditions of Service:
                                                                                                            (Supersedes Schedule CAP–NFT2)
                                                       Western will assess a charge for any                                                                          Alternating current at 60 Hertz, three-
                                                    unreserved use of the transmission                                                                            phase, delivered and metered at the
                                                    system. Unreserved use occurs when a                                                                          voltages and points of delivery
                                                    customer uses transmission service that                                                                       established by contract or service
                                                    it has not reserved or uses transmission                                                                      agreement over the CAP 115/230-kV
                                                                                                                                                                                                               EN29DE15.008</GPH>




                                                    service in excess of its reserved                                                                             transmission system.


                                               VerDate Sep<11>2014   19:17 Dec 28, 2015   Jkt 238001   PO 00000   Frm 00042   Fmt 4703   Sfmt 4703   E:\FR\FM\29DEN1.SGM   29DEN1


                                                    81314                      Federal Register / Vol. 80, No. 249 / Tuesday, December 29, 2015 / Notices

                                                    Adjustment for Reactive Power:                          Navajo Transmission Service (500-kV):                 2016, through December 31, 2020, or
                                                                                                               Western will market excess                         until superseded by another rate
                                                       There shall be no entitlement to
                                                                                                            transmission service from the Navajo                  schedule, whichever occurs earlier.
                                                    transfer of reactive kilovolt amperes at
                                                    delivery points, except when such                       (500-kV) portion of the CAP on a short-               Applicable:
                                                    transfers may be mutually agreed upon                   term basis at the formula rate described
                                                    by the parties and contracting officer or               herein.                                                 The transmission customer will
                                                    their authorized representatives.                       Rate Schedule CAP–NITS3                               compensate the Central Arizona Project
                                                                                                            ATTACHMENT H to Tariff                                (CAP) each month for Network
                                                    Billing:                                                                                                      Integration Transmission Service (NITS)
                                                                                                            (Supersedes Schedule CAP–NITS2)
                                                      Billing determinants for the formula                                                                        under the applicable agreement and the
                                                                                                            UNITED STATES DEPARTMENT OF                           formula rate described herein.
                                                    rate above will be as specified in the
                                                                                                            ENERGY WESTERN AREA POWER
                                                    service agreement. Billing will occur
                                                                                                            ADMINISTRATION                                        Formula Rate:
                                                    monthly under the formula rate.
                                                                                                            DESERT SOUTHWEST CUSTOMER
                                                    Adjustment for Losses:                                  SERVICE REGION CENTRAL
                                                       Losses incurred for service under this               ARIZONA PROJECT
                                                    rate schedule will be accounted for as                  NETWORK INTEGRATION
                                                    agreed to by the parties in accordance                  TRANSMISSION SERVICE
                                                    with the contract or service agreement.
                                                    If losses are not fully provided by a                   Effective:
                                                    transmission customer, charges for                        The first day of the first full billing
                                                    financial compensation may apply.                       period beginning on or after January 1,




                                                    A recalculated Annual Transmission                      ENVIRONMENTAL PROTECTION                              and a person is not required to respond
                                                    Revenue Requirement for Network                         AGENCY                                                to a collection of information unless it
                                                    Integration Transmission Service will go                                                                      displays a currently valid OMB control
                                                                                                            [EPA–HQ–OECA–2011–0275; FRL–9940–                     number.
                                                    into effect every January 1 based on the                68–OEI]
                                                    above formula and updated financial                                                                           DATES:Additional comments may be
                                                    and load data. Western will notify the                  Information Collection Request                        submitted on or before January 28, 2016.
                                                    transmission customer annually of the                   Submitted to OMB for Review and
                                                    recalculated annual revenue                             Approval; Comment Request; NESHAP                     ADDRESSES:   Submit your comments,
                                                    requirement on or before December 1.                    for Hydrochloric Acid Production                      referencing Docket ID Number EPA–
                                                                                                            (Renewal)                                             HQ–OECA–2011–0275, to (1) EPA
                                                    Billing:                                                                                                      online using www.regulations.gov (our
                                                                                                            AGENCY: Environmental Protection                      preferred method), by email to
                                                      Billing determinants for the formula                  Agency (EPA).                                         docket.oeca@epa.gov, or by mail to: EPA
                                                    rate above will be as specified in the                                                                        Docket Center, Environmental
                                                                                                            ACTION: Notice.
                                                    service agreement. Billing will occur                                                                         Protection Agency, Mail Code 28221T,
                                                    monthly under the formula rate.                         SUMMARY:   The Environmental Protection               1200 Pennsylvania Ave., NW.,
                                                    Adjustment for Losses:                                  Agency has submitted an information                   Washington, DC 20460, and (2) OMB via
                                                                                                            collection request (ICR), ‘‘NESHAP for                email to oira_submission@omb.eop.gov.
                                                       Losses incurred for service under this               Hydrochloric Acid Production (40 CFR                  Address comments to OMB Desk Officer
                                                    rate schedule will be accounted for as                  part 63, subpart NNNNN) (Renewal)’’                   for EPA.
                                                    agreed to by the parties in accordance                  (EPA ICR No. 2032.08, OMB Control No.
                                                                                                                                                                    EPA’s policy is that all comments
                                                    with the contract or service agreement.                 2060–0529) to the Office of Management
                                                                                                                                                                  received will be included in the public
                                                    If losses are not fully provided by a                   and Budget (OMB) for review and
                                                                                                                                                                  docket without change including any
                                                    transmission customer, charges for                      approval in accordance with the
                                                                                                                                                                  personal information provided, unless
                                                    financial compensation may apply.                       Paperwork Reduction Act (44 U.S.C.
                                                                                                                                                                  the comment includes profanity, threats,
                                                                                                            3501 et seq.). This is a proposed
                                                    [FR Doc. 2015–32792 Filed 12–28–15; 8:45 am]                                                                  information claimed to be Confidential
                                                                                                            extension of the ICR, which is currently
                                                    BILLING CODE 6450–01–P                                                                                        Business Information (CBI) or other
                                                                                                            approved through December 31, 2015.
                                                                                                                                                                  information whose disclosure is
                                                                                                            Public comments were previously
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                                                                  restricted by statute.
                                                                                                            requested via the Federal Register (80
                                                                                                            FR 32116) on June 5, 2015 during a 60-                FOR FURTHER INFORMATION CONTACT:
                                                                                                            day comment period. This notice allows                Patrick Yellin, Monitoring, Assistance,
                                                                                                            for an additional 30 days for public                  and Media Programs Division, Office of
                                                                                                            comments. A fuller description of the                 Compliance, Mail Code 2227A,
                                                                                                            ICR is given below, including its                     Environmental Protection Agency, 1200
                                                                                                            estimated burden and cost to the public.              Pennsylvania Ave., NW., Washington,
                                                                                                                                                                                                             EN29DE15.009</GPH>




                                                                                                            An Agency may not conduct or sponsor                  DC 20460; telephone number: (202)


                                               VerDate Sep<11>2014   19:17 Dec 28, 2015   Jkt 238001   PO 00000   Frm 00043   Fmt 4703   Sfmt 4703   E:\FR\FM\29DEN1.SGM   29DEN1



Document Created: 2015-12-29 10:14:52
Document Modified: 2015-12-29 10:14:52
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of final transmission service formula rates.
DatesRate Schedules CAP-FT3, CAP-NFT3, and CAP-NITS3 are effective on the first day of the first full billing period beginning on or after January 1, 2016, and will be in effect until FERC confirms, approves, and places the rate schedules in effect on a final basis through December 31, 2020, or until the rate schedules are superseded.
ContactMr. Jack Murray, Vice President of Power Marketing, Desert Southwest Customer Service Regional Office, Western Area Power Administration, P.O. Box 6457, Phoenix, AZ 85005- 6457, (602) 605-2555, email [email protected]
FR Citation80 FR 81310 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR