81_FR_12137 81 FR 12092 - PacifiCorp Energy; Notice of Authorization for Continued Project Operation

81 FR 12092 - PacifiCorp Energy; Notice of Authorization for Continued Project Operation

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 45 (March 8, 2016)

Page Range12092-12093
FR Document2016-05099

Federal Register, Volume 81 Issue 45 (Tuesday, March 8, 2016)
[Federal Register Volume 81, Number 45 (Tuesday, March 8, 2016)]
[Notices]
[Pages 12092-12093]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-05099]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 308-000]


PacifiCorp Energy; Notice of Authorization for Continued Project 
Operation

    On February 28, 2014, PacifiCorp Energy, licensee for the Wallowa 
Falls Hydroelectric Project, filed an Application for a New License 
pursuant to the Federal Power Act (FPA) and the Commission's 
regulations thereunder. The Wallowa Falls Hydroelectric Project is 
located on the East and West Forks of the Wallowa River and Royal 
Purple Creek in Wallowa County, Oregon.
    The license for Project No. 308 was issued for a period ending 
February 28, 2016. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 308 is issued to 
the licensee for a period effective March 1, 2016 through February 28, 
2017 or until the issuance of a new license for the project or other 
disposition under the FPA, whichever comes first. If issuance of a new 
license (or other disposition) does not take place on or before 
February 28, 2017, notice is hereby given that, pursuant to 18 CFR 
16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission,

[[Page 12093]]

unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that the licensee, PacifiCorp Energy, is authorized to 
continue operation of the Wallowa Falls Hydroelectric Project, until 
such time as the Commission acts on its application for a subsequent 
license.

    Dated: March 2, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-05099 Filed 3-7-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                    12092                          Federal Register / Vol. 81, No. 45 / Tuesday, March 8, 2016 / Notices

                                                    [FR Doc. 2016–05155 Filed 3–7–16; 8:45 am]              liquefaction capacity for the                         DEPARTMENT OF ENERGY
                                                    BILLING CODE 4000–01–P                                  Liquefaction Project was determined by
                                                                                                            Freeport LNG during the early stages                  Federal Energy Regulatory
                                                                                                            engineering design. This amendment                    Commission
                                                    DEPARTMENT OF ENERGY                                    identifies and requests that the
                                                                                                            maximum quantity of LNG that could be                 [Project No. 308–000]
                                                    Federal Energy Regulatory                               produced in a particular year under
                                                    Commission                                                                                                    PacifiCorp Energy; Notice of
                                                                                                            well-developed engineering design                     Authorization for Continued Project
                                                    [Docket No. CP15–518–000]                               parameters and specific operating                     Operation
                                                                                                            conditions be used as the approved
                                                    Freeport LNG Development, L.P., FLNG                    volumes.                                                 On February 28, 2014, PacifiCorp
                                                    Liquefaction, LLC, FLNG Liquefaction                                                                          Energy, licensee for the Wallowa Falls
                                                    2, LLC, FLNG Liquefaction 3, LLC;                       Background                                            Hydroelectric Project, filed an
                                                    Notice of Schedule for Environmental                                                                          Application for a New License pursuant
                                                    Review of the Freeport LNG Capacity                       Freeport LNG identified no additional
                                                                                                                                                                  to the Federal Power Act (FPA) and the
                                                    Uprate Project                                          facilities or modification that would be
                                                                                                                                                                  Commission’s regulations thereunder.
                                                                                                            necessary to enable the uprate. We                    The Wallowa Falls Hydroelectric Project
                                                       On June 15, 2015, Freeport LNG                       received a request to intervene from the
                                                    Development, L.P., FLNG Liquefaction,                                                                         is located on the East and West Forks of
                                                                                                            Sierra Club that included some                        the Wallowa River and Royal Purple
                                                    LLC, FLNG Liquefaction 2, LLC, and                      environmental comments.
                                                    FLNG Liquefaction 3, LLC (collectively                                                                        Creek in Wallowa County, Oregon.
                                                    referred to as Freeport LNG) filed an                   Additional Information                                   The license for Project No. 308 was
                                                    application pursuant to Section 3(a) of                                                                       issued for a period ending February 28,
                                                    the Natural Gas Act to amend the                           In order to receive notification of the            2016. Section 15(a)(1) of the FPA, 16
                                                    existing authorization for the                          issuance of the EA and to keep track of               U.S.C. 808(a)(1), requires the
                                                    Liquefaction Project, located in Brazoria               all formal issuances and submittals in                Commission, at the expiration of a
                                                    County near Freeport, Texas. The                        specific dockets, the Commission offers               license term, to issue from year-to-year
                                                    proposed project is known as the                        a free service called eSubscription. This             an annual license to the then licensee
                                                    Capacity Uprate Project (Project), and                  can reduce the amount of time you                     under the terms and conditions of the
                                                    would allow for the liquefaction and                    spend researching proceedings by                      prior license until a new license is
                                                    export of an additional 0.34 billion                    automatically providing you with                      issued, or the project is otherwise
                                                    cubic feet per day (bcf/d) equivalent of                notification of these filings, document               disposed of as provided in section 15 or
                                                    liquefied natural gas.                                  summaries, and direct links to the                    any other applicable section of the FPA.
                                                       On June 24, 2015, the Federal Energy                 documents. Go to www.ferc.gov/docs-                   If the project’s prior license waived the
                                                    Regulatory Commission (Commission or                    filing/esubscription.asp.                             applicability of section 15 of the FPA,
                                                    FERC) issued its Notice of Application                                                                        then, based on section 9(b) of the
                                                                                                               Additional information about the                   Administrative Procedure Act, 5 U.S.C.
                                                    for the Project. Among other things, that               Project is available from the
                                                    notice alerted agencies issuing federal                                                                       558(c), and as set forth at 18 CFR
                                                                                                            Commission’s Office of External Affairs               16.21(a), if the licensee of such project
                                                    authorizations of the requirement to
                                                                                                            at (866) 208–FERC or on the FERC Web                  has filed an application for a subsequent
                                                    complete all necessary reviews and to
                                                    reach a final decision on a request for                 site (www.ferc.gov). Using the                        license, the licensee may continue to
                                                    a federal authorization within 90 days of               ‘‘eLibrary’’ link, select ‘‘General Search’’          operate the project in accordance with
                                                    the date of issuance of the Commission                  from the eLibrary menu, enter the                     the terms and conditions of the license
                                                    staff’s Environmental Assessment (EA)                   selected date range and ‘‘Docket                      after the minor or minor part license
                                                    for the Project. This instant notice                    Number’’ excluding the last three digits              expires, until the Commission acts on
                                                    identifies the FERC staff’s planned                     (i.e., CP15–518), and follow the                      its application. If the licensee of such a
                                                    schedule for the completion of the EA                   instructions. For assistance with access              project has not filed an application for
                                                    for the Project.                                        to eLibrary, the helpline can be reached              a subsequent license, then it may be
                                                                                                            at (866) 208–3676, TTY (202) 502–8659,                required, pursuant to 18 CFR 16.21(b),
                                                    Schedule for Environmental Review                                                                             to continue project operations until the
                                                                                                            or at FERCOnlineSupport@ferc.gov. The
                                                    Issuance of EA March 31, 2016                           eLibrary link on the FERC Web site also               Commission issues someone else a
                                                    90-day Federal Authorization Decision                   provides access to the texts of formal                license for the project or otherwise
                                                       Deadline June 29, 2016                               documents issued by the Commission,                   orders disposition of the project.
                                                       If a schedule change becomes                                                                                  If the project is subject to section 15
                                                                                                            such as orders, notices, and rule
                                                    necessary, additional notice will be                                                                          of the FPA, notice is hereby given that
                                                                                                            makings.
                                                    provided so that the relevant agencies                                                                        an annual license for Project No. 308 is
                                                    are kept informed of the Project’s                        Dated: March 2, 2016.                               issued to the licensee for a period
                                                    progress.                                               Nathaniel J. Davis, Sr.,                              effective March 1, 2016 through
                                                                                                            Deputy Secretary.                                     February 28, 2017 or until the issuance
                                                    Project Description                                                                                           of a new license for the project or other
                                                                                                            [FR Doc. 2016–05098 Filed 3–7–16; 8:45 am]
                                                      Freeport LNG is seeking approval of                                                                         disposition under the FPA, whichever
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                                                                            BILLING CODE 6717–01–P
                                                    an increase in the LNG production                                                                             comes first. If issuance of a new license
                                                    capacity of the previously approved                                                                           (or other disposition) does not take
                                                    Liquefaction Project from 1.8 bcf/d to                                                                        place on or before February 28, 2017,
                                                    about 2.14 Bcf/d. This is the estimated                                                                       notice is hereby given that, pursuant to
                                                    maximum LNG production capacity of                                                                            18 CFR 16.18(c), an annual license
                                                    the Liquefaction Project available for                                                                        under section 15(a)(1) of the FPA is
                                                    export under optimal operating                                                                                renewed automatically without further
                                                    conditions. The currently authorized                                                                          order or notice by the Commission,


                                               VerDate Sep<11>2014   17:02 Mar 07, 2016   Jkt 238001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\08MRN1.SGM   08MRN1


                                                                                   Federal Register / Vol. 81, No. 45 / Tuesday, March 8, 2016 / Notices                                                  12093

                                                    unless the Commission orders                            of your comments. For assistance,                        o. Filing and Service of Responsive
                                                    otherwise.                                              please contact FERC Online Support at                 Documents: Any filing must (1) bear in
                                                       If the project is not subject to section             FERCOnlineSupport@ferc.gov, (866)                     all capital letters the title
                                                    15 of the FPA, notice is hereby given                   208–3676 (toll free), or (202) 502–8659               ‘‘COMMENTS’’, ‘‘PROTEST’’, or
                                                    that the licensee, PacifiCorp Energy, is                (TTY). In lieu of electronic filing, please           ‘‘MOTION TO INTERVENE’’ as
                                                    authorized to continue operation of the                 send a paper copy to: Secretary, Federal              applicable; (2) set forth in the heading
                                                    Wallowa Falls Hydroelectric Project,                    Energy Regulatory Commission, 888                     the name of the applicant and the
                                                    until such time as the Commission acts                  First Street, NE., Washington, DC 20426.              project number of the application to
                                                    on its application for a subsequent                     Please include the project number (P–                 which the filing responds; (3) furnish
                                                    license.                                                6795–019) on any comments, motions to                 the name, address, and telephone
                                                      Dated: March 2, 2016.                                 intervene, or protests filed.                         number of the person protesting or
                                                    Nathaniel J. Davis, Sr.,                                   k. Description of Request: The                     intervening; and (4) otherwise comply
                                                                                                            applicant proposes to replace the                     with the requirements of 18 CFR
                                                    Deputy Secretary.
                                                                                                            project’s existing, non-operable                      385.2001 through 385.2005. All
                                                    [FR Doc. 2016–05099 Filed 3–7–16; 8:45 am]
                                                                                                            horizontal-double-runner turbine with a               comments, motions to intervene, or
                                                    BILLING CODE 6717–01–P
                                                                                                            double-regulated Kaplan unit. The                     protests must set forth their evidentiary
                                                                                                            existing unit has a rated generating                  basis and otherwise comply with the
                                                                                                            capacity of 400 kilowatts (kW) and a                  requirements of 18 CFR 4.34(b). All
                                                    DEPARTMENT OF ENERGY
                                                                                                            maximum hydraulic capacity of 355
                                                                                                                                                                  comments, motions to intervene, or
                                                    Federal Energy Regulatory                               cubic feet per second (cfs). The new unit
                                                                                                                                                                  protests should relate to project works
                                                    Commission                                              would have a rated generating capacity
                                                                                                                                                                  which are the subject of the amendment
                                                                                                            of 500 kW and would operate with
                                                    [Project No. 6795–019]                                  flows ranging from approximately 100                  application. Agencies may obtain copies
                                                                                                            cfs to 332 cfs.                                       of the application directly from the
                                                    Town of Pownal; Notice of Application                                                                         applicant. A copy of any protest or
                                                                                                               l. Locations of the Application: A
                                                    Accepted for Filing, Soliciting                                                                               motion to intervene must be served
                                                                                                            copy of the application is available for
                                                    Comments, Motions To Intervene, and                                                                           upon each representative of the
                                                                                                            inspection and reproduction at the
                                                    Protests                                                                                                      applicant specified in the particular
                                                                                                            Commission’s Public Reference Room,
                                                       Take notice that the following                       located at 888 First Street, NE., Room                application. If an intervener files
                                                    hydroelectric application has been filed                2A, Washington, DC 20426, or by calling               comments or documents with the
                                                    with the Commission and is available                    (202) 502–8371. This filing may also be               Commission relating to the merits of an
                                                    for public inspection:                                  viewed on the Commission’s Web site at                issue that may affect the responsibilities
                                                       a. Type of Application: Amendment                    http://www.ferc.gov/docs-filing/                      of a particular resource agency, they
                                                    of Exemption.                                           elibrary.asp. Enter the docket number                 must also serve a copy of the document
                                                       b. Project No: 6795–019.                             excluding the last three digits in the                on that resource agency. A copy of all
                                                       c. Date Filed: February 3, 2016, as                  docket number field to access the                     other filings in reference to this
                                                    supplemented February 16, 2016.                         document. You may also register online                application must be accompanied by
                                                       d. Applicant: Town of Pownal.                        at http://www.ferc.gov/docs-filing/                   proof of service on all persons listed in
                                                       e. Name of Project: Pownal                           esubscription.asp to be notified via                  the service list prepared by the
                                                    Hydroelectric Project.                                  email of new filings and issuances                    Commission in this proceeding, in
                                                       f. Location: The project is located on               related to this or other pending projects.            accordance with 18 CFR 4.34(b) and
                                                    the Hoosic River, in Bennington County,                 For assistance, call 1 (866) 208- 3676 or             385.2010.
                                                    Vermont.                                                email FERCOnlineSupport@ferc.gov, for                   Dated: March 2, 2016.
                                                       g. Filed Pursuant to: Federal Power                  TTY, call (202) 502–8659. A copy is also
                                                                                                                                                                  Nathaniel J. Davis, Sr.,
                                                    Act, 16 U.S.C. 791a–825r.                               available for inspection and
                                                       h. Applicant Contact: William F.                     reproduction at the address in item (h)               Deputy Secretary.
                                                    Scully, Operating Manager, Hoosic                       above.                                                [FR Doc. 2016–05096 Filed 3–7–16; 8:45 am]
                                                    River Hydro, LLC, P.O. Box 338 North                       m. Individuals desiring to be included             BILLING CODE 6717–01–P
                                                    Bennington, VT 05257 (802) 379–2469.                    on the Commission’s mailing list should
                                                       i. FERC Contact: B. Peter Yarrington,                so indicate by writing to the Secretary
                                                    (202) 502–6129 or peter.yarrington@                     of the Commission.                                    DEPARTMENT OF ENERGY
                                                    ferc.gov.                                                  n. Comments, Protests, or Motions to
                                                       j. Deadline for filing comments,                     Intervene: Anyone may submit                          Federal Energy Regulatory
                                                    motions to intervene, and protests is 15                comments, a protest, or a motion to                   Commission
                                                    days from the issuance date of this                     intervene in accordance with the
                                                    notice by the Commission. The                           requirements of Rules of Practice and                 Notice of Commission Staff
                                                    Commission strongly encourages                          Procedure, 18 CFR 385.210, .211, .214.                Attendance
                                                    electronic filing. Please file motions to               In determining the appropriate action to
                                                    intervene, protests, or comments using                  take, the Commission will consider all                   The Federal Energy Regulatory
                                                    the Commission’s eFiling system at                      protests or other comments filed, but                 Commission hereby gives notice that
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    http://www.ferc.gov/docs-filing/                        only those who file a motion to                       members of the Commission’s staff may
                                                    efiling.asp. Commenters can submit                      intervene in accordance with the                      attend the following meetings related to
                                                    brief comments up to 6,000 characters,                  Commission’s Rules may become a                       the transmission planning activities of
                                                    without prior registration, using the                   party to the proceeding. Any comments,                the PJM Interconnection, L.L.C. (PJM):
                                                    eComment system at http://                              protests, or motions to intervene must                PJM Planning Committee
                                                    www.ferc.gov/docs-filing/                               be received on or before the specified
                                                    ecomment.asp. You must include your                     comment date for the particular                       March 10, 2016, 9:30 a.m.–12:00 p.m.
                                                    name and contact information at the end                 application.                                           (EST)


                                               VerDate Sep<11>2014   17:02 Mar 07, 2016   Jkt 238001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\08MRN1.SGM   08MRN1



Document Created: 2018-02-02 15:10:17
Document Modified: 2018-02-02 15:10:17
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 12092 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR