81_FR_12943 81 FR 12895 - Rover Pipeline, LLC; Panhandle Eastern Pipe Line Company, LP; Trunkline Gas Company, LLC; Notice of Public Meetings for Comments on the Draft Environmental Impact Statement for the Proposed Rover Pipeline, Panhandle Backhaul, and Trunkline Backhaul Projects

81 FR 12895 - Rover Pipeline, LLC; Panhandle Eastern Pipe Line Company, LP; Trunkline Gas Company, LLC; Notice of Public Meetings for Comments on the Draft Environmental Impact Statement for the Proposed Rover Pipeline, Panhandle Backhaul, and Trunkline Backhaul Projects

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 48 (March 11, 2016)

Page Range12895-12896
FR Document2016-05498

Federal Register, Volume 81 Issue 48 (Friday, March 11, 2016)
[Federal Register Volume 81, Number 48 (Friday, March 11, 2016)]
[Notices]
[Pages 12895-12896]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-05498]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-93-000; Docket No. CP15-94-000; Docket No. CP15-96-
000]


Rover Pipeline, LLC; Panhandle Eastern Pipe Line Company, LP; 
Trunkline Gas Company, LLC; Notice of Public Meetings for Comments on 
the Draft Environmental Impact Statement for the Proposed Rover 
Pipeline, Panhandle Backhaul, and Trunkline Backhaul Projects

    On February 19, 2016 the staff of the Federal Energy Regulatory 
Commission (FERC or Commission) issued a draft environmental impact 
statement (EIS) for the Rover Pipeline, Panhandle Backhaul, and 
Trunkline Backhaul Projects (Projects). The draft EIS assesses the 
potential environmental effects of the construction and operation of 
the Projects in accordance with the requirements of the National 
Environmental Policy Act (NEPA). The draft EIS was mailed to the 
parties on the Commission's environmental mailing list and placed on 
the FERC's Web site (www.ferc.gov).
    The Commission invites you to attend one of the public comment 
meetings its staff will conduct in the Projects' area to receive verbal 
comments on the draft EIS, scheduled as follows:

------------------------------------------------------------------------
               Date                               Location
------------------------------------------------------------------------
Monday, March 21, 2016............  Patrick Henry Middle School, 7 E-050
                                     Rd., Hamler, OH 43524, (419) 274-
                                     3431.
Tuesday, March 22, 2016...........  Fayette High School, 400 Gamble Rd.,
                                     Fayette, OH 43521, (419) 237-2114.
Wednesday, March 23, 2016.........  Chelsea High School, 740 N. Freer
                                     Rd., Chelsea, MI 48118, (734) 433-
                                     2201.
Monday, April 4, 2016.............  Barker Memorial Building, 214 North
                                     4th Avenue, Paden City, WV 26159,
                                     (304) 771-2280.
Tuesday, April 5, 2016............  Harrison Central High School, 440
                                     East Market Street, Cadiz, OH
                                     43907, (740) 942-7700.
Wednesday, April 6, 2016..........  Buckeye Central High School, 938
                                     Kibler St., New Washington, OH
                                     44854, (419) 492-2266.
Thursday, April 7, 2016...........  Fairless High School, 11885 Navarre
                                     Rd. SW., Navarre, OH 44662, (330)
                                     767-3444.
------------------------------------------------------------------------

    We will begin our sign up of speakers at 5:30 p.m. The comments 
meetings will begin at 6:00 p.m. with a description of our 
environmental review process by Commission staff, after which speakers 
will be called. The meetings will end once all speakers have provided 
their comments or at 10 p.m., whichever comes first. Please note that 
there may be a time limit of three minutes to present comments, and 
speakers should structure their comments accordingly. If time limits 
are implemented, they will be strictly enforced to ensure that as many 
individuals as possible are given an opportunity to comment. The 
meetings will be recorded by a court reporter to ensure comments are 
accurately recorded. Transcripts will be entered into the formal record 
of the Commission proceeding.
    You do not need to attend one of the above comment meetings to 
provide comment to the Commission on the draft EIS. For your 
convenience, there are three additional methods you can use to submit 
your comments to the Commission. The Commission will provide equal 
consideration to all comments received, whether filed in written form 
or provided verbally. The Commission encourages electronic filing of 
comments and has expert staff available to assist you at (202) 502-8258 
or [email protected]. Please carefully follow these instructions so that 
your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site

[[Page 12896]]

(www.ferc.gov) under the link to Documents and Filings. With eFiling, 
you can provide comments in a variety of formats by attaching them as a 
file with your submission. New eFiling users must first create an 
account by clicking on ``eRegister.'' If you are filing a comment on a 
particular project, please select ``Comment on a Filing'' as the filing 
type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the applicable project 
docket number (CP15-93-000, CP15-94-000, or CP15-96-000) with your 
submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE., Room 1A, Washington, DC 20426.
    To ensure consideration of your comments on the proposals in the 
final EIS, it is important that the Commission receive your comments on 
or before April 11, 2016. Please take note that on February 26, 2016, 
Commission staff issued a correction to Appendix I-1 of the EIS and 
placed the document in the public record under accession number 
20160226-3005.

 Questions?

    Additional information about the projects is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP15-
93, CP15-94, or CP15-96). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676; for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription that allows you to keep track of all formal issuances and 
submittals in specific dockets. This can reduce the amount of time you 
spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: February 29, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-05498 Filed 3-10-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                      Federal Register / Vol. 81, No. 48 / Friday, March 11, 2016 / Notices                                            12895

                                                      Comments Due: 5 p.m. ET 3/14/16.                          Description: Compliance filing                      DEPARTMENT OF ENERGY
                                                      Docket Numbers: RP16–713–000.                          Cameron Interstate Pipeline FERC
                                                      Applicants: Columbia Gulf                              January 19, 2016 Order Compliance                      Federal Energy Regulatory
                                                    Transmission, LLC.                                       Filing to be effective 3/1/2016.                       Commission
                                                      Description: Section 4(d) Rate Filing:                    Filed Date: 3/2/16.
                                                    Negotiated Rate Service Agreement—                          Accession Number: 20160302–5115.                    [Docket No. CP15–93–000; Docket No.
                                                    Kaiser to be effective 4/1/2016.                            Comments Due: 5 p.m. ET 3/14/16.                    CP15–94–000; Docket No. CP15–96–000]
                                                      Filed Date: 3/2/16.                                       Docket Numbers: RP16–131–001.
                                                      Accession Number: 20160302–5195.                          Applicants: Gulf South Pipeline                     Rover Pipeline, LLC; Panhandle
                                                      Comments Due: 5 p.m. ET 3/14/16.                       Company, LP.                                           Eastern Pipe Line Company, LP;
                                                      Docket Numbers: RP16–714–000.                             Description: Compliance filing                      Trunkline Gas Company, LLC; Notice
                                                      Applicants: Monroe Gas Storage                         Compliance Filing in Docket No. RP16–                  of Public Meetings for Comments on
                                                    Company, LLC.                                            131–000 (Establish Fuel Tracker) to be
                                                      Description: Section 4(d) Rate Filing:                                                                        the Draft Environmental Impact
                                                                                                             effective 4/1/2016.                                    Statement for the Proposed Rover
                                                    MGS—Clean up to be effective 3/3/                           Filed Date: 3/4/16.
                                                    2016.                                                                                                           Pipeline, Panhandle Backhaul, and
                                                                                                                Accession Number: 20160304–5084.                    Trunkline Backhaul Projects
                                                      Filed Date: 3/3/16.
                                                      Accession Number: 20160303–5127.                          Comments Due: 5 p.m. ET 3/16/16.
                                                      Comments Due: 5 p.m. ET 3/15/16.                          Any person desiring to protest in any                  On February 19, 2016 the staff of the
                                                      Docket Numbers: RP16–715–000.                          of the above proceedings must file in                  Federal Energy Regulatory Commission
                                                      Applicants: Empire Pipeline, Inc.                      accordance with Rule 211 of the                        (FERC or Commission) issued a draft
                                                      Description: Section 4(d) Rate Filing:                 Commission’s Regulations (18 CFR                       environmental impact statement (EIS)
                                                    Fuel Tracker—Empire to be effective 4/                   385.211) on or before 5:00 p.m. Eastern                for the Rover Pipeline, Panhandle
                                                    1/2016.                                                  time on the specified comment date.                    Backhaul, and Trunkline Backhaul
                                                      Filed Date: 3/4/16.                                       The filings are accessible in the                   Projects (Projects). The draft EIS
                                                      Accession Number: 20160304–5245.                       Commission’s eLibrary system by                        assesses the potential environmental
                                                      Comments Due: 5 p.m. ET 3/16/16.                       clicking on the links or querying the                  effects of the construction and operation
                                                      Any person desiring to intervene or                    docket number.
                                                                                                                                                                    of the Projects in accordance with the
                                                    protest in any of the above proceedings                     eFiling is encouraged. More detailed
                                                                                                                                                                    requirements of the National
                                                    must file in accordance with Rules 211                   information relating to filing
                                                    and 214 of the Commission’s                              requirements, interventions, protests,                 Environmental Policy Act (NEPA). The
                                                    Regulations (18 CFR 385.211 and                          service, and qualifying facilities filings             draft EIS was mailed to the parties on
                                                    385.214) on or before 5:00 p.m. Eastern                  can be found at: http://www.ferc.gov/                  the Commission’s environmental
                                                    time on the specified date(s). Protests                  docs-filing/efiling/filing-req.pdf. For                mailing list and placed on the FERC’s
                                                    may be considered, but intervention is                   other information, call (866) 208–3676                 Web site (www.ferc.gov).
                                                    necessary to become a party to the                       (toll free). For TTY, call (202) 502–8659.                The Commission invites you to attend
                                                    proceeding.                                                Dated: March 7, 2016.                                one of the public comment meetings its
                                                    Filings in Existing Proceedings                          Nathaniel J. Davis, Sr.,                               staff will conduct in the Projects’ area to
                                                                                                             Deputy Secretary.                                      receive verbal comments on the draft
                                                      Docket Numbers: RP16–184–002.                                                                                 EIS, scheduled as follows:
                                                      Applicants: Cameron Interstate                         [FR Doc. 2016–05503 Filed 3–10–16; 8:45 am]
                                                    Pipeline, LLC.                                           BILLING CODE 6717–01–P


                                                                      Date                                                                               Location

                                                    Monday, March 21, 2016 ................       Patrick Henry Middle School, 7 E–050 Rd., Hamler, OH 43524, (419) 274–3431.
                                                    Tuesday, March 22, 2016 ...............       Fayette High School, 400 Gamble Rd., Fayette, OH 43521, (419) 237–2114.
                                                    Wednesday, March 23, 2016 ..........          Chelsea High School, 740 N. Freer Rd., Chelsea, MI 48118, (734) 433–2201.
                                                    Monday, April 4, 2016 .....................   Barker Memorial Building, 214 North 4th Avenue, Paden City, WV 26159, (304) 771–2280.
                                                    Tuesday, April 5, 2016 ....................   Harrison Central High School, 440 East Market Street, Cadiz, OH 43907, (740) 942–7700.
                                                    Wednesday, April 6, 2016 ..............       Buckeye Central High School, 938 Kibler St., New Washington, OH 44854, (419) 492–2266.
                                                    Thursday, April 7, 2016 ..................    Fairless High School, 11885 Navarre Rd. SW., Navarre, OH 44662, (330) 767–3444.



                                                       We will begin our sign up of speakers                 opportunity to comment. The meetings                   Commission encourages electronic filing
                                                    at 5:30 p.m. The comments meetings                       will be recorded by a court reporter to                of comments and has expert staff
                                                    will begin at 6:00 p.m. with a                           ensure comments are accurately                         available to assist you at (202) 502–8258
                                                    description of our environmental review                  recorded. Transcripts will be entered                  or efiling@ferc.gov. Please carefully
                                                    process by Commission staff, after                       into the formal record of the                          follow these instructions so that your
                                                    which speakers will be called. The                       Commission proceeding.                                 comments are properly recorded.
                                                    meetings will end once all speakers                        You do not need to attend one of the                   (1) You can file your comments
                                                    have provided their comments or at 10                    above comment meetings to provide                      electronically using the eComment
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    p.m., whichever comes first. Please note                 comment to the Commission on the                       feature on the Commission’s Web site
                                                    that there may be a time limit of three                  draft EIS. For your convenience, there                 (www.ferc.gov) under the link to
                                                    minutes to present comments, and                         are three additional methods you can                   Documents and Filings. This is an easy
                                                    speakers should structure their                          use to submit your comments to the                     method for submitting brief, text-only
                                                    comments accordingly. If time limits are                 Commission. The Commission will                        comments on a project;
                                                    implemented, they will be strictly                       provide equal consideration to all                       (2) You can file your comments
                                                    enforced to ensure that as many                          comments received, whether filed in                    electronically by using the eFiling
                                                    individuals as possible are given an                     written form or provided verbally. The                 feature on the Commission’s Web site


                                               VerDate Sep<11>2014    17:56 Mar 10, 2016   Jkt 238001   PO 00000   Frm 00038   Fmt 4703   Sfmt 4703   E:\FR\FM\11MRN1.SGM   11MRN1


                                                    12896                           Federal Register / Vol. 81, No. 48 / Friday, March 11, 2016 / Notices

                                                    (www.ferc.gov) under the link to                        DEPARTMENT OF ENERGY                                  Planned Dalton Expansion Project,
                                                    Documents and Filings. With eFiling,                                                                          Request for Comments on
                                                    you can provide comments in a variety                   Federal Energy Regulatory                             Environmental Issues, and Notice of
                                                    of formats by attaching them as a file                  Commission                                            Public Scoping Meetings (NOI). FERC
                                                    with your submission. New eFiling                       [Docket Nos. CP15–117–000]                            staff also issued two supplemental NOIs
                                                    users must first create an account by                                                                         for the Project on November 14, 2014
                                                    clicking on ‘‘eRegister.’’ If you are filing            Transcontinental Gas Pipe Line                        and February 13, 2015. The original NOI
                                                    a comment on a particular project,                      Company, LLC; Notice of Schedule for                  was issued during the pre-filing review
                                                    please select ‘‘Comment on a Filing’’ as                Environmental Review of the Dalton                    of the Project in Docket No. PF14–10–
                                                    the filing type; or                                     Expansion Project                                     000. All three NOIs were sent to affected
                                                       (3) You can file a paper copy of your                                                                      landowners; applicable federal, state,
                                                                                                               On March 19, 2015, Transcontinental                and local government agencies; elected
                                                    comments by mailing them to the
                                                                                                            Gas Pipe Line Company, LLC (Transco)                  officials; environmental and public
                                                    following address. Be sure to reference
                                                                                                            filed an application in Docket No.
                                                    the applicable project docket number                                                                          interest groups; Native American tribes;
                                                                                                            CP15–117–000 requesting a Certificate
                                                    (CP15–93–000, CP15–94–000, or CP15–                                                                           other interested parties; and local
                                                                                                            of Public Convenience and Necessity
                                                    96–000) with your submission:                                                                                 libraries and newspapers. In response to
                                                                                                            pursuant to Section 7(c) of the Natural
                                                    Kimberly D. Bose, Secretary, Federal                                                                          the NOIs, the Commission received
                                                                                                            Gas Act to construct and operate certain
                                                    Energy Regulatory Commission, 888                                                                             comments from federal, state, and local
                                                                                                            natural gas pipeline facilities. The
                                                    First Street NE., Room 1A, Washington,                                                                        agencies, the Tuscarora Nation, and
                                                                                                            proposed project is known as the Dalton
                                                    DC 20426.                                                                                                     several landowners. The primary issues
                                                                                                            Expansion Project (Project), and would
                                                       To ensure consideration of your                                                                            raised by the commentors are alternative
                                                                                                            provide 448,000 dekatherms per day of
                                                    comments on the proposals in the final                                                                        routes to minimize impacts on known
                                                                                                            incremental firm transportation service
                                                    EIS, it is important that the Commission                                                                      rare species habitat, alternative routes to
                                                                                                            to markets in northwest Georgia.
                                                    receive your comments on or before                         On April 2, 2015, the Federal Energy               follow the existing utility corridor,
                                                    April 11, 2016. Please take note that on                Regulatory Commission (Commission or                  mitigation measures to minimize right-
                                                    February 26, 2016, Commission staff                     FERC) issued its Notice of Application                of-way erosion and stormwater runoff
                                                    issued a correction to Appendix I–1 of                  for the Project. Among other things, that             into streams, air emissions, safety, and
                                                    the EIS and placed the document in the                  notice alerted agencies issuing federal               cultural resources.
                                                    public record under accession number                    authorizations of the requirement to                  Additional Information
                                                    20160226–3005.                                          complete all necessary reviews and to
                                                    Questions?                                              reach a final decision on a request for                  In order to receive notification of the
                                                                                                            a federal authorization within 90 days of             issuance of the EA and to keep track of
                                                       Additional information about the                     the date of issuance of the Commission                all formal issuances and submittals in
                                                    projects is available from the                          staff’s Environmental Assessment (EA)                 specific dockets, the Commission offers
                                                    Commission’s Office of External Affairs,                for the Project. This instant notice                  a free service called eSubscription. This
                                                    at (866) 208–FERC, or on the FERC Web                   identifies the FERC staff’s planned                   can reduce the amount of time you
                                                    site (www.ferc.gov) using the eLibrary                  schedule for the completion of the EA                 spend researching proceedings by
                                                    link. Click on the eLibrary link, click on              for the Project.                                      automatically providing you with
                                                    ‘‘General Search,’’ and enter the docket                                                                      notification of these filings, document
                                                    number excluding the last three digits in               Schedule for Environmental Review
                                                                                                                                                                  summaries, and direct links to the
                                                    the Docket Number field (i.e., CP15–93,                 Issuance of EA March 31, 2016                         documents. Go to www.ferc.gov/docs-
                                                    CP15–94, or CP15–96). Be sure you have                  90-day Federal Authorization Decision                 filing/esubscription.asp.
                                                    selected an appropriate date range. For                    Deadline June 29, 2016
                                                    assistance, please contact FERC Online                                                                           Additional information about the
                                                                                                               If a schedule change becomes
                                                    Support at FercOnlineSupport@ferc.gov                                                                         Project is available from the
                                                                                                            necessary, additional notice will be
                                                    or toll free at (866) 208–3676; for TTY,                                                                      Commission’s Office of External Affairs
                                                                                                            provided so that the relevant agencies
                                                    contact (202) 502–8659. The eLibrary                                                                          at (866) 208–FERC or on the FERC Web
                                                                                                            are kept informed of the Project’s
                                                    link also provides access to the texts of                                                                     site (www.ferc.gov). Using the
                                                                                                            progress.
                                                    formal documents issued by the                                                                                ‘‘eLibrary’’ link, select ‘‘General Search’’
                                                    Commission, such as orders, notices,                    Project Description                                   from the eLibrary menu, enter the
                                                    and rulemakings.                                           Transco plans to construct and                     selected date range and ‘‘Docket
                                                       In addition, the Commission offers a                 operate about 113 miles of new natural                Number’’ excluding the last three digits
                                                    free service called eSubscription that                  gas pipeline, and associated facilities in            (i.e., CP15–117), and follow the
                                                    allows you to keep track of all formal                  Coweta, Carroll, Douglas, Paulding,                   instructions. For assistance with access
                                                    issuances and submittals in specific                    Bartow, Gordon, and Murray Counties,                  to eLibrary, the helpline can be reached
                                                    dockets. This can reduce the amount of                  Georgia and install a new 21,830                      at (866) 208–3676, TTY (202) 502–8659,
                                                    time you spend researching proceedings                  horsepower compressor station in                      or at FERCOnlineSupport@ferc.gov. The
                                                    by automatically providing you with                     Carroll County, Georgia. Additionally,                eLibrary link on the FERC Web site also
                                                    notification of these filings, document                 Transco plans to modify existing                      provides access to the texts of formal
                                                                                                                                                                  documents issued by the Commission,
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    summaries, and direct links to the                      facilities along its mainline transmission
                                                    documents. Go to www.ferc.gov/docs-                     system in Maryland, Virginia, and North               such as orders, notices, and rule
                                                    filing/esubscription.asp.                               Carolina to accommodate bidirectional                 makings.
                                                      Dated: February 29, 2016.
                                                                                                            flow.                                                   Dated: March 7, 2016.
                                                    Nathaniel J. Davis, Sr.,                                Background                                            Nathaniel J. Davis, Sr.,
                                                    Deputy Secretary.                                          On October 21, 2014, FERC staff                    Deputy Secretary.
                                                    [FR Doc. 2016–05498 Filed 3–10–16; 8:45 am]             issued a Notice of Intent To Prepare an               [FR Doc. 2016–05504 Filed 3–10–16; 8:45 am]
                                                    BILLING CODE 6717–01–P                                  Environmental Assessment for the                      BILLING CODE 6717–01–P




                                               VerDate Sep<11>2014   17:56 Mar 10, 2016   Jkt 238001   PO 00000   Frm 00039   Fmt 4703   Sfmt 4703   E:\FR\FM\11MRN1.SGM   11MRN1



Document Created: 2016-03-11 01:51:40
Document Modified: 2016-03-11 01:51:40
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 12895 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR