81_FR_15156 81 FR 15102 - Information Collection Request Submitted to OMB for Review and Approval; Comment Request; Emission Guidelines for Large Municipal Waste Combustors Constructed on or Before September 20, 1994 (Renewal)

81 FR 15102 - Information Collection Request Submitted to OMB for Review and Approval; Comment Request; Emission Guidelines for Large Municipal Waste Combustors Constructed on or Before September 20, 1994 (Renewal)

ENVIRONMENTAL PROTECTION AGENCY

Federal Register Volume 81, Issue 54 (March 21, 2016)

Page Range15102-15102
FR Document2016-06216

The Environmental Protection Agency has submitted an information collection request (ICR), ``Emission Guidelines for Large Municipal Waste Combustors Constructed on or Before September 20, 1994 (40 CFR part 60, subpart Cb) (Renewal)'' (EPA ICR No. 1847.07, OMB Control No. 2060-0390), to the Office of Management and Budget (OMB) for review and approval in accordance with the Paperwork Reduction Act (44 U.S.C. 3501 et seq.). This is a proposed extension of the ICR, which is currently approved through March 31, 2016. Public comments were previously requested via the Federal Register (80 FR 32116) on June 5, 2015 during a 60-day comment period. This notice allows for an additional 30 days for public comments. A fuller description of the ICR is given below, including its estimated burden and cost to the public. An Agency may not conduct or sponsor and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

Federal Register, Volume 81 Issue 54 (Monday, March 21, 2016)
[Federal Register Volume 81, Number 54 (Monday, March 21, 2016)]
[Notices]
[Page 15102]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-06216]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

[EPA-HQ-OECA-2012-0503; FRL-9943-97-OEI]


Information Collection Request Submitted to OMB for Review and 
Approval; Comment Request; Emission Guidelines for Large Municipal 
Waste Combustors Constructed on or Before September 20, 1994 (Renewal)

AGENCY: Environmental Protection Agency (EPA).

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: The Environmental Protection Agency has submitted an 
information collection request (ICR), ``Emission Guidelines for Large 
Municipal Waste Combustors Constructed on or Before September 20, 1994 
(40 CFR part 60, subpart Cb) (Renewal)'' (EPA ICR No. 1847.07, OMB 
Control No. 2060-0390), to the Office of Management and Budget (OMB) 
for review and approval in accordance with the Paperwork Reduction Act 
(44 U.S.C. 3501 et seq.). This is a proposed extension of the ICR, 
which is currently approved through March 31, 2016. Public comments 
were previously requested via the Federal Register (80 FR 32116) on 
June 5, 2015 during a 60-day comment period. This notice allows for an 
additional 30 days for public comments. A fuller description of the ICR 
is given below, including its estimated burden and cost to the public. 
An Agency may not conduct or sponsor and a person is not required to 
respond to, a collection of information unless it displays a currently 
valid OMB control number.

DATES: Additional comments may be submitted on or before April 20, 
2016.

ADDRESSES: Submit your comments, referencing Docket ID Number EPA-HQ-
OECA-2012-0503, to: (1) EPA online using www.regulations.gov (our 
preferred method), or by email to [email protected], or by mail to: 
EPA Docket Center, Environmental Protection Agency, Mail Code 28221T, 
1200 Pennsylvania Ave. NW., Washington, DC 20460; and (2) OMB via email 
to [email protected]. Address comments to OMB Desk Officer 
for EPA.
    EPA's policy is that all comments received will be included in the 
public docket without change including any personal information 
provided, unless the comment includes profanity, threats, information 
claimed to be Confidential Business Information (CBI), or other 
information whose disclosure is restricted by statute.

FOR FURTHER INFORMATION CONTACT: Patrick Yellin, Monitoring, 
Assistance, and Media Programs Division, Office of Compliance, Mail 
Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave. 
NW., Washington, DC 20460; telephone number: (202) 564-2970; fax 
number: (202) 564-0050; email address: [email protected].

SUPPLEMENTARY INFORMATION: Supporting documents which explain in detail 
the information that the EPA will be collecting are available in the 
public docket for this ICR. The docket can be viewed online at 
www.regulations.gov or in person at the EPA Docket Center, WJC West, 
Room 3334, 1301 Constitution Ave. NW., Washington, DC. The telephone 
number for the Docket Center is 202-566-1744. For additional 
information about EPA's public docket, visit: http://www.epa.gov/dockets.
    Abstract: Owners and operators of affected facilities are required 
to comply with reporting and record keeping requirements for the 
general provisions of 40 CFR part 60, subpart A, as well as for the 
specific requirements at 40 CFR part 60, subpart Cb. This includes 
submitting initial notifications, performance tests and periodic 
reports and results, and maintaining records of the occurrence and 
duration of any startup, shutdown, or malfunction in the operation of 
an affected facility, or any period during which the monitoring system 
is inoperative. These reports are used by EPA to determine compliance 
with the standards.
    Form Numbers: None.
    Respondents/affected entities: Large municipal waste combustors.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart Cb).
    Estimated number of respondents: 81 (total).
    Frequency of response: Initially, occasionally, semiannually and 
annually.
    Total estimated burden: 397,000 hours (per year). Burden is defined 
at 5 CFR 1320.3(b).
    Total estimated cost: $59,400,000 (per year), which includes 
$1,560,000 in annualized capital/startup and/or operation & maintenance 
costs.
    Changes in the Estimates: There is a small adjustment increase in 
the respondent labor hours and costs and the total O&M costs as 
currently identified in the OMB Inventory of Approved Burdens. The 
increase in labor hours and cost is due to a change in assumption. In 
this ICR, we assume all existing sources will take some time each year 
to re-familiarize themselves with the regulatory requirements. The 
increase in total O&M cost is due to rounding of all calculated values 
to three significant figures.

Courtney Kerwin,
Acting Director, Collection Strategies Division.
[FR Doc. 2016-06216 Filed 3-18-16; 8:45 am]
BILLING CODE 6560-50-P



                                                  15102                         Federal Register / Vol. 81, No. 54 / Monday, March 21, 2016 / Notices

                                                    Total estimated burden: 528,000                       Reduction Act (44 U.S.C. 3501 et seq.).               for the specific requirements at 40 CFR
                                                  hours (per year). Burden is defined at 5                This is a proposed extension of the ICR,              part 60, subpart Cb. This includes
                                                  CFR 1320.3(b).                                          which is currently approved through                   submitting initial notifications,
                                                    Total estimated cost: $54,800,000 (per                March 31, 2016. Public comments were                  performance tests and periodic reports
                                                  year), which includes $143,000 in                       previously requested via the Federal                  and results, and maintaining records of
                                                  annualized capital/startup and/or                       Register (80 FR 32116) on June 5, 2015                the occurrence and duration of any
                                                  operation & maintenance costs.                          during a 60-day comment period. This                  startup, shutdown, or malfunction in
                                                    Changes in the Estimates: There is a                  notice allows for an additional 30 days               the operation of an affected facility, or
                                                  decrease in respondent labor hours and                  for public comments. A fuller                         any period during which the monitoring
                                                  the total O&M costs from the most-                      description of the ICR is given below,                system is inoperative. These reports are
                                                  recently approved ICR. The decrease in                  including its estimated burden and cost               used by EPA to determine compliance
                                                  burden is due to adjusting the number                   to the public. An Agency may not                      with the standards.
                                                  of respondents from 148 to 142. The                     conduct or sponsor and a person is not                   Form Numbers: None.
                                                  updated number of respondents is based                  required to respond to, a collection of                  Respondents/affected entities: Large
                                                  on the Agency’s industry analysis                       information unless it displays a                      municipal waste combustors.
                                                  conducted for the recent RTR rule                       currently valid OMB control number.                      Respondent’s obligation to respond:
                                                  amendment, documented in EPA ICR                        DATES: Additional comments may be                     Mandatory (40 CFR part 60, subpart Cb).
                                                  Number 1692.08. This estimate is based                  submitted on or before April 20, 2016.                   Estimated number of respondents: 81
                                                  on information from EPA’s Petroleum                     ADDRESSES: Submit your comments,                      (total).
                                                  Refinery Database (contains data                        referencing Docket ID Number EPA–                        Frequency of response: Initially,
                                                  provided by each individual refinery in                 HQ–OECA–2012–0503, to: (1) EPA                        occasionally, semiannually and
                                                  response to an EPA survey of the                        online using www.regulations.gov (our                 annually.
                                                  petroleum refinery industry in 2011)                    preferred method), or by email to                        Total estimated burden: 397,000
                                                  and the Agency’s internal data sources.                 docket.oeca@epa.gov, or by mail to: EPA               hours (per year). Burden is defined at 5
                                                  However, there is a small adjustment                    Docket Center, Environmental                          CFR 1320.3(b).
                                                  increase in the number of responses due                 Protection Agency, Mail Code 28221T,                     Total estimated cost: $59,400,000 (per
                                                  to a correction. The previous ICR did                   1200 Pennsylvania Ave. NW.,                           year), which includes $1,560,000 in
                                                  not account for semiannual heat                         Washington, DC 20460; and (2) OMB via                 annualized capital/startup and/or
                                                  exchanger system reports in calculating                 email to oira_submission@omb.eop.gov.                 operation & maintenance costs.
                                                  the number of responses. This ICR                       Address comments to OMB Desk Officer                     Changes in the Estimates: There is a
                                                  renewal includes this item to be                        for EPA.                                              small adjustment increase in the
                                                  consistent with the Table 1 and Table 2                    EPA’s policy is that all comments                  respondent labor hours and costs and
                                                  burden calculations.                                    received will be included in the public               the total O&M costs as currently
                                                                                                          docket without change including any                   identified in the OMB Inventory of
                                                  Courtney Kerwin,
                                                                                                          personal information provided, unless                 Approved Burdens. The increase in
                                                  Acting Director, Collection Strategies                                                                        labor hours and cost is due to a change
                                                                                                          the comment includes profanity, threats,
                                                  Division.
                                                                                                          information claimed to be Confidential                in assumption. In this ICR, we assume
                                                  [FR Doc. 2016–06211 Filed 3–18–16; 8:45 am]
                                                                                                          Business Information (CBI), or other                  all existing sources will take some time
                                                  BILLING CODE 6560–50–P                                                                                        each year to re-familiarize themselves
                                                                                                          information whose disclosure is
                                                                                                          restricted by statute.                                with the regulatory requirements. The
                                                                                                          FOR FURTHER INFORMATION CONTACT:                      increase in total O&M cost is due to
                                                  ENVIRONMENTAL PROTECTION
                                                                                                          Patrick Yellin, Monitoring, Assistance,               rounding of all calculated values to
                                                  AGENCY
                                                                                                          and Media Programs Division, Office of                three significant figures.
                                                  [EPA–HQ–OECA–2012–0503; FRL–9943–                       Compliance, Mail Code 2227A,
                                                  97–OEI]                                                                                                       Courtney Kerwin,
                                                                                                          Environmental Protection Agency, 1200                 Acting Director, Collection Strategies
                                                                                                          Pennsylvania Ave. NW., Washington,                    Division.
                                                  Information Collection Request
                                                                                                          DC 20460; telephone number: (202)
                                                  Submitted to OMB for Review and                                                                               [FR Doc. 2016–06216 Filed 3–18–16; 8:45 am]
                                                                                                          564–2970; fax number: (202) 564–0050;
                                                  Approval; Comment Request;                                                                                    BILLING CODE 6560–50–P
                                                                                                          email address: yellin.patrick@epa.gov.
                                                  Emission Guidelines for Large
                                                                                                          SUPPLEMENTARY INFORMATION:
                                                  Municipal Waste Combustors
                                                  Constructed on or Before September                      Supporting documents which explain in                 ENVIRONMENTAL PROTECTION
                                                  20, 1994 (Renewal)                                      detail the information that the EPA will              AGENCY
                                                                                                          be collecting are available in the public
                                                  AGENCY: Environmental Protection                        docket for this ICR. The docket can be                [EPA–HQ–OECA–2012–0655; FRL–9943–
                                                  Agency (EPA).                                                                                                 75–OEI]
                                                                                                          viewed online at www.regulations.gov
                                                  ACTION: Notice.                                         or in person at the EPA Docket Center,                Information Collection Request
                                                                                                          WJC West, Room 3334, 1301                             Submitted to OMB for Review and
                                                  SUMMARY:   The Environmental Protection                 Constitution Ave. NW., Washington,                    Approval; Comment Request; NSPS
                                                  Agency has submitted an information                     DC. The telephone number for the                      for Ammonium Sulfate Manufacturing
                                                  collection request (ICR), ‘‘Emission                    Docket Center is 202–566–1744. For                    Plants (Renewal)
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Guidelines for Large Municipal Waste                    additional information about EPA’s
                                                  Combustors Constructed on or Before                     public docket, visit: http://                         AGENCY: Environmental Protection
                                                  September 20, 1994 (40 CFR part 60,                     www.epa.gov/dockets.                                  Agency (EPA).
                                                  subpart Cb) (Renewal)’’ (EPA ICR No.                       Abstract: Owners and operators of                  ACTION: Notice.
                                                  1847.07, OMB Control No. 2060–0390),                    affected facilities are required to comply
                                                  to the Office of Management and Budget                  with reporting and record keeping                     SUMMARY:   The Environmental Protection
                                                  (OMB) for review and approval in                        requirements for the general provisions               Agency has submitted an information
                                                  accordance with the Paperwork                           of 40 CFR part 60, subpart A, as well as              collection request (ICR), ‘‘NSPS for


                                             VerDate Sep<11>2014   17:46 Mar 18, 2016   Jkt 238001   PO 00000   Frm 00069   Fmt 4703   Sfmt 4703   E:\FR\FM\21MRN1.SGM   21MRN1



Document Created: 2016-03-19 01:00:11
Document Modified: 2016-03-19 01:00:11
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice.
DatesAdditional comments may be submitted on or before April 20, 2016.
ContactPatrick Yellin, Monitoring, Assistance, and Media Programs Division, Office of Compliance, Mail Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave. NW., Washington, DC 20460; telephone number: (202) 564-2970; fax
FR Citation81 FR 15102 