DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 64 (April 4, 2016)

Page Range19167-19168
FR Document2016-07536

Federal Register, Volume 81 Issue 64 (Monday, April 4, 2016)
[Federal Register Volume 81, Number 64 (Monday, April 4, 2016)]
[Notices]
[Pages 19167-19168]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-07536]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-558-000]


PennEast Pipeline Company, LLC; Notice of Schedule for 
Environmental Review of the Penneast Pipeline Project

    On September 24, 2015, PennEast Pipeline Company, LLC (PennEast) 
filed an application in Docket No. CP15-558-000 under section 7(c) of 
the Natural Gas Act seeking a Certificate of Public Convenience and 
Necessity to construct, operate, and maintain a new natural gas 
pipeline system in Pennsylvania and New Jersey. The proposed project is 
known as the PennEast Pipeline Project and will provide approximately 
1.0 billion cubic feet per day of year-round transportation natural gas 
service to markets in eastern and southeastern Pennsylvania and New 
Jersey.
    On October 8, 2015, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the project. 
Among other things, that notice alerted other agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on the request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's final 
Environmental Impact Statement (EIS) for the PennEast Pipeline Project. 
This instant notice identifies the FERC staff's planned schedule for 
completion of the final EIS for the project.

Schedule for Environmental Review

    Issuance of Notice of Availability of the final EIS--December 16, 
2016.
    90-day Federal Authorization Decision Deadline--March 16, 2017.

    If a schedule change becomes necessary, additional notice will be 
provided so the relevant agencies are kept informed of the project's 
progress.

Project Description

    The project includes a total of 118.8 miles of pipeline and 
laterals composed of 115.0 miles of new, 36-inch-diameter pipeline 
extending from Luzerne County, Pennsylvania to Mercer County, New 
Jersey. The Project would also have three pipeline laterals: The 2.1-
mile Hellertown Lateral consisting of 24-inch-diameter pipeline in 
Northampton County, Pennsylvania; the 0.1-mile Gilbert Lateral 
consisting of 12-inch-diameter pipeline in Hunterdon County, 
Pennsylvania; and the 1.5-mile Lambertville Lateral consisting of 36-
inch-diameter pipeline in Hunterdon County, New Jersey.
    The proposed aboveground facilities consist of a new, 47,700 
horsepower compressor station in Kidder Township, Carbon County, 
Pennsylvania. The project would also include the construction of 8 
meter and regulator stations, 11 mainline valves, and 11 pig launcher/
receiver sites.

Background

    On October 10, 2014, the Commission staff granted PennEast's 
request to use the FERC's Pre-filing environmental review process and 
assigned the PennEast Pipeline Project Docket No. PF15-1-000. On 
January 13, 2015, the Commission issued, in that docket, a Notice of 
Intent to Prepare an Environmental Impact Statement for the Planned 
PennEast Pipeline Project, Request for Comments on Environmental 
Issues, and Notice of Public Scoping Meetings (NOI). The NOI was sent 
to affected landowners; federal, state, and local government agencies; 
elected officials; environmental and public interest groups; Native 
American tribes; other interested parties; and local libraries and 
newspapers.
    The primary issues raised by the commenters during scoping included 
concerns about potential impacts on agricultural farms, ground water 
resources on Sourland Region, protected conservation lands, threatened 
and endangered species, archaeological sites, forest (i.e., 
fragmentation), and impacts on property value. In addition, the added 
responsibility for emergency response teams; potential for arsenic 
release into groundwater; safety of local residents in the event of a 
pipeline incident; long-term impacts of compressor stations on human 
health and the environment; construction in karst areas; and need for 
alternatives were also raised.
    The U.S. Environmental Protection Agency, U.S. Army Corps of 
Engineers, U.S. Department of Agriculture, U.S. Fish and Wildlife 
Service, and U.S. Department of Transportation's Pipeline and Hazardous 
Materials Safety Administration are cooperating agencies in the 
preparation of the EIS.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with

[[Page 19168]]

notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP15-558), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
Web site also provides access to the texts of formal documents issued 
by the Commission, such as orders, notices, and rule makings.

    Dated: March 29, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-07536 Filed 4-1-16; 8:45 am]
BILLING CODE 6717-01-P



                                                                                              Federal Register / Vol. 81, No. 64 / Monday, April 4, 2016 / Notices                                                             19167

                                                                                                FERC FORM 6–Q—QUARTERLY FINANCIAL REPORT OF OIL COMPANIES
                                                                                                                                                    Annual                                               Total annual
                                                                                                                                                                       Total           Average                              Cost per
                                                                                                                                                   number of                                             burden hours
                                                                             Number of respondents                                                                  number of       burden & cost                          respondent
                                                                                                                                                responses per                                            & total annual
                                                                                                                                                                    responses       per response 4                             ($)
                                                                                                                                                  respondent                                                  cost

                                                                                             (1)                                                     (2)          (1) * (2) = (3)         (4)            (3) * (4) = (5)    (5) ÷ (1)

                                                  175 .......................................................................................                 3               525             150               78,750           32,400
                                                                                                                                                                                          $10,800           $5,670,000



                                                                                                                              markets in eastern and southeastern                     Background
                                                    Comments: Comments are invited on:                                        Pennsylvania and New Jersey.                               On October 10, 2014, the Commission
                                                  (1) Whether the collection of                                                  On October 8, 2015, the Federal                      staff granted PennEast’s request to use
                                                  information is necessary for the proper                                     Energy Regulatory Commission                            the FERC’s Pre-filing environmental
                                                  performance of the functions of the                                         (Commission or FERC) issued its Notice                  review process and assigned the
                                                  Commission, including whether the                                           of Application for the project. Among                   PennEast Pipeline Project Docket No.
                                                  information will have practical utility;                                    other things, that notice alerted other                 PF15–1–000. On January 13, 2015, the
                                                  (2) the accuracy of the agency’s estimate                                   agencies issuing federal authorizations                 Commission issued, in that docket, a
                                                  of the burden and cost of the collection                                    of the requirement to complete all                      Notice of Intent to Prepare an
                                                  of information, including the validity of                                   necessary reviews and to reach a final                  Environmental Impact Statement for the
                                                  the methodology and assumptions used;                                       decision on the request for a federal                   Planned PennEast Pipeline Project,
                                                  (3) ways to enhance the quality, utility                                    authorization within 90 days of the date                Request for Comments on
                                                  and clarity of the information collection;                                  of issuance of the Commission staff’s                   Environmental Issues, and Notice of
                                                  and (4) ways to minimize the burden of                                      final Environmental Impact Statement                    Public Scoping Meetings (NOI). The NOI
                                                  the collection of information on those                                      (EIS) for the PennEast Pipeline Project.                was sent to affected landowners; federal,
                                                  who are to respond, including the use                                       This instant notice identifies the FERC                 state, and local government agencies;
                                                  of automated collection techniques or                                       staff’s planned schedule for completion                 elected officials; environmental and
                                                  other forms of information technology.                                      of the final EIS for the project.                       public interest groups; Native American
                                                    Dated: March 29, 2016.                                                                                                            tribes; other interested parties; and local
                                                  Nathaniel J. Davis, Sr.,
                                                                                                                              Schedule for Environmental Review                       libraries and newspapers.
                                                  Deputy Secretary.                                                             Issuance of Notice of Availability of                    The primary issues raised by the
                                                  [FR Doc. 2016–07537 Filed 4–1–16; 8:45 am]                                  the final EIS—December 16, 2016.                        commenters during scoping included
                                                  BILLING CODE 6717–01–P
                                                                                                                                                                                      concerns about potential impacts on
                                                                                                                                90-day Federal Authorization                          agricultural farms, ground water
                                                                                                                              Decision Deadline—March 16, 2017.                       resources on Sourland Region, protected
                                                  DEPARTMENT OF ENERGY                                                          If a schedule change becomes                          conservation lands, threatened and
                                                                                                                              necessary, additional notice will be                    endangered species, archaeological
                                                  Federal Energy Regulatory                                                   provided so the relevant agencies are                   sites, forest (i.e., fragmentation), and
                                                  Commission                                                                  kept informed of the project’s progress.                impacts on property value. In addition,
                                                                                                                                                                                      the added responsibility for emergency
                                                                                                                              Project Description                                     response teams; potential for arsenic
                                                  [Docket No. CP15–558–000]
                                                                                                                                                                                      release into groundwater; safety of local
                                                                                                                                The project includes a total of 118.8
                                                  PennEast Pipeline Company, LLC;                                                                                                     residents in the event of a pipeline
                                                                                                                              miles of pipeline and laterals composed
                                                  Notice of Schedule for Environmental                                                                                                incident; long-term impacts of
                                                                                                                              of 115.0 miles of new, 36-inch-diameter
                                                  Review of the Penneast Pipeline                                                                                                     compressor stations on human health
                                                                                                                              pipeline extending from Luzerne
                                                  Project                                                                                                                             and the environment; construction in
                                                                                                                              County, Pennsylvania to Mercer County,
                                                                                                                                                                                      karst areas; and need for alternatives
                                                     On September 24, 2015, PennEast                                          New Jersey. The Project would also have
                                                                                                                                                                                      were also raised.
                                                  Pipeline Company, LLC (PennEast) filed                                      three pipeline laterals: The 2.1-mile                      The U.S. Environmental Protection
                                                  an application in Docket No. CP15–558–                                      Hellertown Lateral consisting of 24-                    Agency, U.S. Army Corps of Engineers,
                                                  000 under section 7(c) of the Natural                                       inch-diameter pipeline in Northampton                   U.S. Department of Agriculture, U.S.
                                                  Gas Act seeking a Certificate of Public                                     County, Pennsylvania; the 0.1-mile                      Fish and Wildlife Service, and U.S.
                                                  Convenience and Necessity to construct,                                     Gilbert Lateral consisting of 12-inch-                  Department of Transportation’s Pipeline
                                                  operate, and maintain a new natural gas                                     diameter pipeline in Hunterdon County,                  and Hazardous Materials Safety
                                                  pipeline system in Pennsylvania and                                         Pennsylvania; and the 1.5-mile                          Administration are cooperating agencies
                                                  New Jersey. The proposed project is                                         Lambertville Lateral consisting of 36-                  in the preparation of the EIS.
                                                  known as the PennEast Pipeline Project                                      inch-diameter pipeline in Hunterdon
                                                  and will provide approximately 1.0                                          County, New Jersey.                                     Additional Information
                                                  billion cubic feet per day of year-round
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                                The proposed aboveground facilities                      In order to receive notification of the
                                                  transportation natural gas service to                                       consist of a new, 47,700 horsepower                     issuance of the EIS and to keep track of
                                                                                                                              compressor station in Kidder Township,                  all formal issuances and submittals in
                                                     4 The estimates for cost per response are derived                        Carbon County, Pennsylvania. The                        specific dockets, the Commission offers
                                                  using the 2015 FERC average salary plus benefits of                         project would also include the                          a free service called eSubscription. This
                                                  $149,489/year (or $72.00/hour). Commission staff
                                                  finds that the work done for this information
                                                                                                                              construction of 8 meter and regulator                   can reduce the amount of time you
                                                  collection is typically done by wage categories                             stations, 11 mainline valves, and 11 pig                spend researching proceedings by
                                                  similar to those at FERC.                                                   launcher/receiver sites.                                automatically providing you with


                                             VerDate Sep<11>2014         19:03 Apr 01, 2016         Jkt 238001       PO 00000        Frm 00056    Fmt 4703   Sfmt 4703   E:\FR\FM\04APN1.SGM    04APN1


                                                  19168                           Federal Register / Vol. 81, No. 64 / Monday, April 4, 2016 / Notices

                                                  notification of these filings, document                   e. All local, state, and federal                       FERC Contact: Christiane Casey;
                                                  summaries, and direct links to the                      agencies, Indian tribes, and other                    phone: (202) 502–8577.
                                                  documents. Go to www.ferc.gov/docs-                     interested parties are invited to                        Deadline for filing comments and
                                                  filing/esubscription.asp.                               participate by phone. Please call Andy                motions to intervene: 60 days from the
                                                     Additional information about the                     Bernick at (202) 502–8660 by Thursday,                issuance of this notice.
                                                  Project is available from the                           April 21, 2016, to RSVP and to receive                   The Commission strongly encourages
                                                  Commission’s Office of External Affairs                 specific instructions on how to                       electronic filing. Please file comments
                                                  at (866) 208–FERC or on the FERC Web                    participate.                                          and motions to intervene using the
                                                  site (www.ferc.gov). Using the                                                                                Commission’s eFiling system at http://
                                                                                                            Dated: March 29, 2016.
                                                  ‘‘eLibrary’’ link, select ‘‘General Search’’                                                                  www.ferc.gov/docs-filing/efiling.asp.
                                                                                                          Nathaniel J. Davis, Sr.,
                                                  from the eLibrary menu, enter the                                                                             Commenters can submit brief comments
                                                  selected date range and ‘‘Docket                        Deputy Secretary.
                                                                                                                                                                up to 6,000 characters, without prior
                                                  Number’’ excluding the last three digits                [FR Doc. 2016–07533 Filed 4–1–16; 8:45 am]
                                                                                                                                                                registration, using the eComment system
                                                  (i.e., CP15–558), and follow the                        BILLING CODE 6717–01–P                                at http://www.ferc.gov/docs-filing/
                                                  instructions. For assistance with access                                                                      ecomment.asp. You must include your
                                                  to eLibrary, the helpline can be reached                                                                      name and contact information at the end
                                                  at (866) 208–3676, TTY (202) 502–8659,                  DEPARTMENT OF ENERGY
                                                                                                                                                                of your comments. For assistance,
                                                  or at FERCOnlineSupport@ferc.gov. The                                                                         please contact FERC Online Support at
                                                  eLibrary link on the FERC Web site also                 Federal Energy Regulatory
                                                                                                          Commission                                            FERCOnlineSupport@ferc.gov, (866)
                                                  provides access to the texts of formal                                                                        208–3676 (toll free), or (202) 502–8659
                                                  documents issued by the Commission,                     [Project No. 14744–000]                               (TTY). In lieu of electronic filing, please
                                                  such as orders, notices, and rule                                                                             send a paper copy to: Secretary, Federal
                                                  makings.                                                Energy Resources USA, Inc.; Notice of                 Energy Regulatory Commission, 888
                                                    Dated: March 29, 2016.                                Preliminary Permit Application                        First Street NE., Washington, DC 20426.
                                                                                                          Accepted for Filing and Soliciting                    The first page of any filing should
                                                  Nathaniel J. Davis, Sr.,
                                                                                                          Comments and Motions To Intervene                     include docket number P–14744–000.
                                                  Deputy Secretary.
                                                  [FR Doc. 2016–07536 Filed 4–1–16; 8:45 am]                 On December 22, 2015, Energy                          More information about this project,
                                                  BILLING CODE 6717–01–P                                  Resources USA, Inc. (Energy Resources)                including a copy of the application, can
                                                                                                          filed an application for a preliminary                be viewed or printed on the ‘‘eLibrary’’
                                                                                                          permit, pursuant to section 4(f) of the               link of the Commission’s Web site at
                                                  DEPARTMENT OF ENERGY                                    Federal Power Act (FPA), proposing to                 http://www.ferc.gov/docs-filing/
                                                                                                          study the feasibility of the Nolin Lake               elibrary.asp. Enter the docket number
                                                  Federal Energy Regulatory                               Dam Hydroelectric Project (Nolin                      (P–14744) in the docket number field to
                                                  Commission                                              Project or project) to be located at the              access the document. For assistance,
                                                  [Project No. 12796–004]                                 U.S. Army Corps of Engineers’ Nolin                   contact FERC Online Support.
                                                                                                          Lake Dam on the Nolin River in                          Dated: March 29, 2016.
                                                  City of Wadsworth, Ohio; Notice of                      Edmonson County, Kentucky. The sole                   Nathaniel J. Davis, Sr.,
                                                  Teleconference                                          purpose of a preliminary permit, if                   Deputy Secretary.
                                                    a. Project Name and Number: R.C.                      issued, is to grant the permit holder                 [FR Doc. 2016–07534 Filed 4–1–16; 8:45 am]
                                                  Byrd Hydroelectric Project No. 12796.                   priority to file a license application
                                                                                                                                                                BILLING CODE 6717–01–P
                                                    b. Date and Time of Meeting:                          during the permit term. A preliminary
                                                  Thursday, April 28, 2016 at 1:00 p.m.                   permit does not authorize the permit
                                                  (Eastern Daylight Time).                                holder to perform any land-disturbing                 DEPARTMENT OF ENERGY
                                                    c. FERC Contact: Andy Bernick,                        activities or otherwise enter upon lands
                                                  andrew.bernick@ferc.gov or (202) 502–                   or waters owned by others without the                 Federal Energy Regulatory
                                                  8660.                                                   owners’ express permission.                           Commission
                                                    d. Purpose of Meeting: Commission                        The proposed project would consist of
                                                                                                          the following: (1) A control structure                [Project No. 14750–000]
                                                  staff will hold a teleconference to
                                                  discuss: (1) The Indiana Bat and                        with three 9.5-foot-wide, 25-foot-long                Energy Resources USA, Inc.; Notice of
                                                  Northern Long Eared Bat Conservation                    spill gates; (2) one 10-foot-diameter, 65-            Preliminary Permit Application
                                                  Plan and Mussel Monitoring and                          foot-long penstock with a butterfly                   Accepted for Filing and Soliciting
                                                  Conservation Plan for the R.C. Byrd                     valve; (3) a bifurcation structure; (4) two           Comments and Motions To Intervene
                                                  Hydroelectric Project, filed in draft form              6.5-foot-diameter, 32-foot-long
                                                  on June 23, 2015, by American                           penstocks; (5) a powerhouse containing                   On December 22, 2015, Energy
                                                  Municipal Power, Inc. (or AMP, agent                    two generating units with a total                     Resources USA, Inc. (Energy Resources)
                                                  for the City of Wadsworth, Ohio); (2) the               capacity of 7 megawatts; (6) a 1000-foot-             filed an application for a preliminary
                                                  report entitled ‘‘Examining the Effect of               long, 220-foot-wide tailrace; (7) a                   permit, pursuant to section 4(f) of the
                                                  Potential Water Velocities on Mussel                    substation; and (8) a 3-mile-long, 69 kV              Federal Power Act (FPA), proposing to
                                                  Populations at R.C. Byrd Lock and Dam                   transmission line. The proposed project               study the feasibility of the Lake
                                                  on the Ohio River (ORM 279.2)’’                         would have an estimated average annual                Tuscaloosa Dam Hydroelectric Project
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  prepared for AMP and filed on February                  generation of 26,900 megawatt-hours,                  (Lake Tuscaloosa Project or project) to
                                                  10, 2016; and (3) the current status of                 and operate as directed by the Corps.                 be located at the U.S. Army Corps of
                                                  resolving the remaining information                        Applicant Contact: Mr. Ander                       Engineers’ Lake Tuscaloosa Dam on the
                                                  needs noted in U.S. Fish and Wildlife                   Gonzalez, Energy Resources USA Inc.,                  North River in Tuscaloosa County,
                                                  Service’s Ohio Ecological Services Field                2655 Le Jeune Road, Suite 804, Coral                  Alabama. The sole purpose of a
                                                  Office and West Virginia Field Office                   Gables, Florida 33134; Phone: (954)                   preliminary permit, if issued, is to grant
                                                  comments on the draft plans filed                       248–8425; Email: agonzalez@                           the permit holder priority to file a
                                                  August 26, 2015.                                        energyresources.es.                                   license application during the permit


                                             VerDate Sep<11>2014   19:03 Apr 01, 2016   Jkt 238001   PO 00000   Frm 00057   Fmt 4703   Sfmt 4703   E:\FR\FM\04APN1.SGM   04APN1



Document Created: 2016-04-02 03:54:33
Document Modified: 2016-04-02 03:54:33
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 19167 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR