81_FR_21932 81 FR 21861 - Yuba County Water Agency; Notice of Authorization for Continued Project Operation

81 FR 21861 - Yuba County Water Agency; Notice of Authorization for Continued Project Operation

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 71 (April 13, 2016)

Page Range21861-21862
FR Document2016-08475

Federal Register, Volume 81 Issue 71 (Wednesday, April 13, 2016)
[Federal Register Volume 81, Number 71 (Wednesday, April 13, 2016)]
[Notices]
[Pages 21861-21862]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-08475]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2246-000]


Yuba County Water Agency; Notice of Authorization for Continued 
Project Operation

    On April 28, 2014 Yuba County Water Agency, licensee for the Yuba 
River Project, filed an Application for a New License pursuant to the 
Federal Power Act (FPA) and the Commission's regulations thereunder. 
The Yuba River Project facilities are located on the Yuba River, North 
Yuba River, the Middle

[[Page 21862]]

Yuba River, and Oregon Creek, in Yuba, Sierra, and Nevada Counties, 
California.
    The license for Project No. 2246 was issued for a period ending 
March 31, 2016. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 2246 is issued to 
the licensee for a period effective April 1, 2016 through March 31, 
2017 or until the issuance of a new license for the project or other 
disposition under the FPA, whichever comes first. If issuance of a new 
license (or other disposition) does not take place on or before March 
31, 2017, notice is hereby given that, pursuant to 18 CFR 16.18(c), an 
annual license under section 15(a)(1) of the FPA is renewed 
automatically without further order or notice by the Commission, unless 
the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that the licensee, Yuba County Water Agency., is 
authorized to continue operation of the Yuba River Project, until such 
time as the Commission acts on its application for a subsequent 
license.

    Dated: March 7, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-08475 Filed 4-12-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 81, No. 71 / Wednesday, April 13, 2016 / Notices                                                 21861

                                                       Applicants: Golden Pass Pipeline                     Additional Information                                tribes, and other stakeholders to provide
                                                    LLC.                                                       In order to receive notification of the            comments to GRDA on its draft of the
                                                       Description: Compliance filing                       issuance of the final EA and to keep                  amendment application mentioned
                                                    Revised Tariff Records per 03/29/2016                                                                         above before GRDA files it with the
                                                                                                            track of all formal issuances and
                                                    Order Re: Orders 587–W and 809 to be                                                                          Commission. The Commission’s
                                                                                                            submittals in specific dockets, the
                                                    effective 4/20/2016.                                                                                          regulations at 4.38(a)(7) require GRDA
                                                                                                            Commission offers a free service called
                                                       Filed Date: 4/4/16.                                                                                        to provide resource agencies, Indian
                                                       Accession Number: 20160404–5264.                     eSubscription. Go to www.ferc.gov/docs-
                                                                                                            filing/esubscription.asp.                             tribes, and other stakeholders 60 days to
                                                       Comments Due: 5 p.m. ET 4/18/16.                                                                           provide comments on the draft
                                                       Any person desiring to protest in any                  Dated: April 5, 2016.                               amendment application. GRDA requests
                                                    of the above proceedings must file in                   Nathaniel J. Davis, Sr.,                              Commission approval of a 30-day
                                                    accordance with Rule 211 of the                         Deputy Secretary.                                     comment period to expedite the
                                                    Commission’s Regulations (18 CFR                        [FR Doc. 2016–08411 Filed 4–12–16; 8:45 am]           Commission’s review of any final
                                                    385.211) on or before 5:00 p.m. Eastern                                                                       application filed with the Commission.
                                                                                                            BILLING CODE 6717–01–P
                                                    time on the specified comment date.                                                                              The Commission issued a public
                                                       The filings are accessible in the
                                                                                                                                                                  notice of GRDA’s waiver request on
                                                    Commission’s eLibrary system by                         DEPARTMENT OF ENERGY                                  March 16, 2016 requesting comments,
                                                    clicking on the links or querying the
                                                                                                                                                                  motions to intervene, and protests by
                                                    docket number.                                          Federal Energy Regulatory
                                                       eFiling is encouraged. More detailed                                                                       March 31, 2016. The Modoc Tribe of
                                                                                                            Commission                                            Oklahoma filed a protest and comments
                                                    information relating to filing
                                                    requirements, interventions, protests,                  [Project No. 1494–433]                                on March 31, 2016. However, the protest
                                                    service, and qualifying facilities filings                                                                    and comments are related to any final
                                                                                                            Grand River Dam Authority; Notice                     amendment application GRDA may file
                                                    can be found at: http://www.ferc.gov/
                                                                                                            Granting Waiver Request To Reduce                     with the Commission. The protest and
                                                    docs-filing/efiling/filing-req.pdf. For
                                                                                                            Comment Period From 60 to 30 Days                     comments did not address the waiver
                                                    other information, call (866) 208–3676
                                                                                                            on Draft Amendment Application                        request described in the Commission’s
                                                    (toll free). For TTY, call (202) 502–8659.
                                                                                                                                                                  public notice. No other protests or
                                                      Dated: April 5, 2016.                                    Take notice that the following
                                                                                                                                                                  comments were received. Since there
                                                    Nathaniel J. Davis, Sr.,                                hydroelectric application has been filed
                                                                                                                                                                  were no objections to GRDA’s waiver
                                                    Deputy Secretary.                                       with the Commission and is available
                                                                                                                                                                  request to reduce the comment period
                                                                                                            for public inspection:
                                                    [FR Doc. 2016–08416 Filed 4–12–16; 8:45 am]                                                                   from 60 to 30 days as described above,
                                                                                                               a. Application Type: Request to
                                                    BILLING CODE 6717–01–P                                                                                        the waiver is approved and comments
                                                                                                            reduce the comment period from 60 to
                                                                                                                                                                  on GRDA’s draft amendment
                                                                                                            30 days for a draft amendment
                                                                                                                                                                  application must be submitted to GRDA
                                                    DEPARTMENT OF ENERGY                                    application to permanently modify the
                                                                                                                                                                  within the requested 30-day period (due
                                                                                                            reservoir elevation rule curve under
                                                                                                                                                                  by April 14, 2016).
                                                    Federal Energy Regulatory                               Article 401 of the project license.
                                                                                                               b. Project No: 1494–433.                              Note that the Modoc Tribe’s concerns
                                                    Commission                                                                                                    and comments contained in its March
                                                                                                               c. Date Filed: March 15, 2016.
                                                    [Docket No. CP15–520–000]                                  d. Applicant: Grand River Dam                      31, 2016 letter, have been filed with the
                                                                                                            Authority (GRDA).                                     Commission and will be considered in
                                                    Tennessee Gas Pipeline Company,                                                                               the Commission’s review of any final
                                                                                                               e. Name of Project: Pensacola
                                                    L.L.C.; Notice of Revised Schedule for                                                                        amendment application GRDA files
                                                                                                            Hydroelectric Project.
                                                    Environmental Review of the Triad                                                                             with the Commission.
                                                                                                               f. Location: The project is located on
                                                    Expansion Project
                                                                                                            the Grand River in Craig, Delaware,                     Dated: April 5, 2016.
                                                       This notice identifies the Federal                   Mayes, and Ottawa Counties, Oklahoma.                 Nathaniel J. Davis, Sr.,
                                                    Energy Regulatory Commission staff’s                       g. Filed Pursuant to: Federal Power                Deputy Secretary.
                                                    revised schedule for the completion of                  Act, 16 U.S.C. 791(a)–825(r).                         [FR Doc. 2016–08412 Filed 4–12–16; 8:45 am]
                                                    the Environmental Assessment (EA) for                      h. Applicant Contact: Tamara Jahnke,               BILLING CODE 6717–01–P
                                                    Tennessee Gas Pipeline Company,                         Grand River Dam Authority, 226 West
                                                    L.L.C.’s (Tennessee) Triad Expansion                    Dwain Willis Ave., P.O. Box 409, Vinita,
                                                    Project. The previous notice of                         OK 74301; telephone (918) 256–5545.                   DEPARTMENT OF ENERGY
                                                    schedule, issued on December 9, 2015,                      i. FERC Contact: B. Peter Yarrington,
                                                    identified April 6, 2016 as the issuance                telephone (202) 502–6129 and email                    Federal Energy Regulatory
                                                    date of the EA. On February 12, 2016,                   peter.yarrington@ferc.gov; or Linda                   Commission
                                                    Commission staff received supplemental                  Stewart, telephone (202) 502–6680 and
                                                                                                                                                                  [Project No. 2246–000]
                                                    information regarding a route variation                 email linda.stewart@ferc.gov.
                                                    from Tennessee that requires a revised                     j. Description of Waiver Request and               Yuba County Water Agency; Notice of
                                                    schedule for issuance of the EA.                        Decision: On March 15, 2016, GRDA                     Authorization for Continued Project
                                                                                                            filed with the Commission: (1) A draft                Operation
                                                    Schedule for Environmental Review                       amendment application to permanently
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    Issuance of EA—June 15, 2016                            modify the reservoir elevation rule                     On April 28, 2014 Yuba County Water
                                                    90-Day Federal Authorization Decision                   curve under Article 401 of the Pensacola              Agency, licensee for the Yuba River
                                                       Deadline—September 13, 2016                          Project for Grand Lake O’ the Cherokees,              Project, filed an Application for a New
                                                       If a schedule change becomes                         (2) a request for a temporary variance                License pursuant to the Federal Power
                                                    necessary, additional notice will be                    contained in the draft amendment                      Act (FPA) and the Commission’s
                                                    provided so that the relevant agencies                  application, and (3) a waiver request to              regulations thereunder. The Yuba River
                                                    are kept informed of the Project’s                      reduce from 60 to 30 days the comment                 Project facilities are located on the Yuba
                                                    progress.                                               period for resource agencies, Indian                  River, North Yuba River, the Middle


                                               VerDate Sep<11>2014   17:41 Apr 12, 2016   Jkt 238001   PO 00000   Frm 00026   Fmt 4703   Sfmt 4703   E:\FR\FM\13APN1.SGM   13APN1


                                                    21862                        Federal Register / Vol. 81, No. 71 / Wednesday, April 13, 2016 / Notices

                                                    Yuba River, and Oregon Creek, in Yuba,                  DEPARTMENT OF ENERGY                                  FERCOnlineSupport@ferc.gov. or call
                                                    Sierra, and Nevada Counties, California.                                                                      (866) 208–3676 (toll free). For TTY, call
                                                                                                            Federal Energy Regulatory                             (202) 502–8659.
                                                       The license for Project No. 2246 was
                                                                                                            Commission                                              Dated: April 7, 2016.
                                                    issued for a period ending March 31,
                                                    2016. Section 15(a)(1) of the FPA, 16                   [Docket No. ER16–1354–000]                            Kimberly D. Bose,
                                                    U.S.C. 808(a)(1), requires the                                                                                Secretary.
                                                    Commission, at the expiration of a                      Live Oak Solar, LLC; Supplemental
                                                                                                                                                                  [FR Doc. 2016–08473 Filed 4–12–16; 8:45 am]
                                                    license term, to issue from year-to-year                Notice That Initial Market-Based Rate
                                                                                                                                                                  BILLING CODE 6717–01–P
                                                    an annual license to the then licensee                  Filing Includes Request for Blanket
                                                                                                            Section 204 Authorization
                                                    under the terms and conditions of the
                                                    prior license until a new license is                       This is a supplemental notice in the               ENVIRONMENTAL PROTECTION
                                                    issued, or the project is otherwise                     above-referenced proceeding of Grande                 AGENCY
                                                    disposed of as provided in section 15 or                Prairie Wind, LLC’s application for
                                                    any other applicable section of the FPA.                market-based rate authority, with an                  [FRL–9944–92–Region 1]
                                                    If the project’s prior license waived the               accompanying rate tariff, noting that
                                                    applicability of section 15 of the FPA,                 such application includes a request for               Availability of Final NPDES General
                                                    then, based on section 9(b) of the                      blanket authorization, under 18 CFR                   Permit for Stormwater Discharges
                                                    Administrative Procedure Act, 5 U.S.C.                  part 34, of future issuances of securities            From Small Municipal Separate Storm
                                                    558(c), and as set forth at 18 CFR                      and assumptions of liability.                         Sewer Systems in Massachusetts
                                                    16.21(a), if the licensee of such project                  Any person desiring to intervene or to
                                                                                                            protest should file with the Federal                  AGENCY: Environmental Protection
                                                    has filed an application for a subsequent                                                                     Agency (EPA).
                                                    license, the licensee may continue to                   Energy Regulatory Commission, 888
                                                                                                            First Street NE., Washington, DC 20426,               ACTION: Notice of availability of final
                                                    operate the project in accordance with                                                                        NPDES general permit.
                                                    the terms and conditions of the license                 in accordance with Rules 211 and 214
                                                    after the minor or minor part license                   of the Commission’s Rules of Practice
                                                                                                                                                                  SUMMARY:   The Director of the Office of
                                                    expires, until the Commission acts on                   and Procedure (18 CFR 385.211 and
                                                                                                                                                                  Ecosystem Protection, EPA—Region 1,
                                                    its application. If the licensee of such a              385.214). Anyone filing a motion to
                                                                                                                                                                  is providing a notice of availability of
                                                    project has not filed an application for                intervene or protest must serve a copy
                                                                                                                                                                  the final National Pollutant Discharge
                                                    a subsequent license, then it may be                    of that document on the Applicant.
                                                                                                               Notice is hereby given that the                    Elimination System (NPDES) general
                                                    required, pursuant to 18 CFR 16.21(b),                                                                        permit for stormwater discharges from
                                                                                                            deadline for filing protests with regard
                                                    to continue project operations until the                to the applicant’s request for blanket                small Municipal Separate Storm Sewer
                                                    Commission issues someone else a                        authorization, under 18 CFR part 34, of               systems (MS4s) to certain waters of the
                                                    license for the project or otherwise                    future issuances of securities and                    Commonwealth of Massachusetts. The
                                                    orders disposition of the project.                      assumptions of liability, is April 27,                final Massachusetts small MS4 general
                                                       If the project is subject to section 15              2016.                                                 permit establishes Notice of Intent (NOI)
                                                    of the FPA, notice is hereby given that                    The Commission encourages                          requirements, prohibitions, and
                                                    an annual license for Project No. 2246                  electronic submission of protests and                 management practices for stormwater
                                                    is issued to the licensee for a period                  interventions in lieu of paper, using the             discharges from small MS4s in
                                                                                                            FERC Online links at http://                          Massachusetts. The final Massachusetts
                                                    effective April 1, 2016 through March
                                                                                                            www.ferc.gov. To facilitate electronic                small MS4 general permit reflects
                                                    31, 2017 or until the issuance of a new
                                                                                                            service, persons with Internet access                 modifications to the draft small MS4
                                                    license for the project or other
                                                                                                            who will eFile a document and/or be                   general permit released for comment on
                                                    disposition under the FPA, whichever
                                                                                                            listed as a contact for an intervenor                 September 30, 2014 and replaces the
                                                    comes first. If issuance of a new license
                                                                                                            must create and validate an                           2003 small MS4 general permit for MS4
                                                    (or other disposition) does not take
                                                                                                            eRegistration account using the                       operators within the Commonwealth of
                                                    place on or before March 31, 2017,                                                                            Massachusetts.
                                                    notice is hereby given that, pursuant to                eRegistration link. Select the eFiling
                                                                                                            link to log on and submit the                         DATES: The Massachusetts small MS4
                                                    18 CFR 16.18(c), an annual license
                                                    under section 15(a)(1) of the FPA is                    intervention or protests.                             general permit shall be effective on July
                                                    renewed automatically without further                      Persons unable to file electronically              1, 2017 and will expire at midnight on
                                                                                                            should submit an original and 5 copies                June 30, 2022. In accordance with 40
                                                    order or notice by the Commission,
                                                                                                            of the intervention or protest to the                 CFR part 23, this permit shall be
                                                    unless the Commission orders
                                                                                                            Federal Energy Regulatory Commission,                 considered issued for the purpose of
                                                    otherwise.
                                                                                                            888 First Street NE., Washington, DC                  judicial review at 1:00 p.m. eastern
                                                       If the project is not subject to section             20426.                                                standard time on April 27, 2016. Under
                                                    15 of the FPA, notice is hereby given                      The filings in the above-referenced                section 509(b) of the Clean Water Act,
                                                    that the licensee, Yuba County Water                    proceeding are accessible in the                      judicial review of this general permit
                                                    Agency., is authorized to continue                      Commission’s eLibrary system by                       can be requested by filing a petition for
                                                    operation of the Yuba River Project,                    clicking on the appropriate link in the               review in the United States Court of
                                                    until such time as the Commission acts                  above list. They are also available for               Appeals within 120 days after the
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    on its application for a subsequent                     electronic review in the Commission’s                 permit is considered issued. Under
                                                    license.                                                Public Reference Room in Washington,                  section 509(b)(2) of the Clean Water Act,
                                                      Dated: March 7, 2016.                                 DC. There is an eSubscription link on                 the requirements in this permit may not
                                                                                                            the Web site that enables subscribers to              be challenged later in civil or criminal
                                                    Kimberly D. Bose,
                                                                                                            receive email notification when a                     proceedings to enforce these
                                                    Secretary.                                              document is added to a subscribed                     requirements. In addition, this permit
                                                    [FR Doc. 2016–08475 Filed 4–12–16; 8:45 am]             docket(s). For assistance with any FERC               may not be challenged in other agency
                                                    BILLING CODE 6717–01–P                                  Online service, please email                          proceedings.


                                               VerDate Sep<11>2014   17:41 Apr 12, 2016   Jkt 238001   PO 00000   Frm 00027   Fmt 4703   Sfmt 4703   E:\FR\FM\13APN1.SGM   13APN1



Document Created: 2016-04-13 03:11:23
Document Modified: 2016-04-13 03:11:23
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 21861 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR