81_FR_2215 81 FR 2205 - Hawks Nest Hydro, LLC; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments

81 FR 2205 - Hawks Nest Hydro, LLC; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 10 (January 15, 2016)

Page Range2205-2206
FR Document2016-00710

Federal Register, Volume 81 Issue 10 (Friday, January 15, 2016)
[Federal Register Volume 81, Number 10 (Friday, January 15, 2016)]
[Notices]
[Pages 2205-2206]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-00710]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14439-001]


Hawks Nest Hydro, LLC; Notice of Application Tendered for Filing 
With the Commission and Establishing Procedural Schedule for Licensing 
and Deadline for Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: 14439-001.
    c. Date Filed: December 29, 2015.
    d. Applicant: Hawks Nest Hydro, LLC (Hawks Nest Hydro).
    e. Name of Project: Glen Ferris Hydroelectric Project.
    f. Location: The existing project is located on the Kanawha River, 
in Fayette County, West Virginia. The project does not occupy any 
federal lands.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Steven Murphy, Manager, Licensing, Brookfield 
Renewable Energy Group, 33 West 1st Street South, Fulton, New York 
13069; Telephone (315) 598-6130.
    i. FERC Contact: Monir Chowdhury, (202) 502-6736 or 
[email protected].
    j. This application is not ready for environmental analysis at this 
time.
    k. Project Description: The existing Glen Ferris Hydroelectric 
Project consists of: (1) A low concrete dam with a maximum height of 12 
feet above the river bed and a crest elevation of 651.0 feet National 
Geodetic Vertical Datum of 1929 (NGVD29), consisting of (from left to 
right--looking downstream) (i) a 590-foot-long spillway section that 
generally curves upstream; (ii) a 128-foot-long five-bay stoplog 
sluice; (iii) a 2,132-foot-long right spillway that runs diagonally in 
a downstream direction; (iv) a trash sluice section; (v) a 54-foot-long 
by 38-foot-wide east powerhouse with a 62-foot-wide intake structure; 
and (vi) a 64.5-foot-long by 63-foot-wide west powerhouse with a 82.3-
foot-wide intake structure, with both powerhouses integral to the dam; 
(2) a 190-acre reservoir with a gross storage capacity of approximately 
1,500 acre-feet at the dam crest elevation of 651.0 feet NGVD29; (3) 
two turbine-generator units in the east powerhouse, each with a rated 
capacity of approximately 1.9 megawatts (MW); (4) six turbine-generator 
units in the west powerhouse, each with a rated capacity of 
approximately 0.4 MW; (5) a 4-mile-long, 13.8-kilovolt transmission 
line; and (6) appurtenant facilities.
    The project is currently operated in a run-of-river mode with no 
usable storage capacity. Hawks Nest Hydro proposes to continue run-of-
river operation. The project generates an annual average of 41,482 
megawatt-hours.
    l. Locations of the Application: A copy of the application is 
available for review at the Commission in the Public Reference Room or 
may be viewed on the Commission's Web site at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC Online Support at [email protected] 
or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Procedural Schedule: The application will be processed according 
to the following preliminary Hydro Licensing Schedule. Revisions to the 
schedule may be made as appropriate.

[[Page 2206]]



------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready     February 2016.
 for Environmental Analysis.
Filing of recommendations, preliminary   April 2016.
 terms and conditions, and fishway
 prescriptions.
Commission issues EA...................  August 2016.
Comments on EA.........................  September 2016.
Modified Terms and Conditions..........  November 2016.
Commission Issues Final EA, if           February 2017.
 necessary.
------------------------------------------------------------------------

    o. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: January 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-00710 Filed 1-14-16; 8:45 am]
BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 81, No. 10 / Friday, January 15, 2016 / Notices                                              2205

                                                  exceed 5 minutes. The Designated                          On January 5, 2016, Arkansas Electric                   j. This application is not ready for
                                                  Federal Officer is empowered to                         Cooperative Corporation; Mississippi                   environmental analysis at this time.
                                                  conduct the meeting in a fashion that                   Delta Energy Agency and its members,                      k. Project Description: The existing
                                                  will facilitate the orderly conduct of                  Clarksdale Public Utilities Commission                 Glen Ferris Hydroelectric Project
                                                  business.                                               of the City of Clarksdale, Mississippi                 consists of: (1) A low concrete dam with
                                                    This meeting is being published less                  and Public Service Commission of                       a maximum height of 12 feet above the
                                                  than 15 days prior to the scheduled                     Yazoo City, Mississippi; Hoosier Energy                river bed and a crest elevation of 651.0
                                                  meeting to allow the public and Board                   Rural Electric Cooperative, Inc.; and                  feet National Geodetic Vertical Datum of
                                                  to hear presentations that are unique to                South Mississippi Electric Power                       1929 (NGVD29), consisting of (from left
                                                  this facility, and for the Board to                     Association filed a motion for                         to right—looking downstream) (i) a 590-
                                                  continue to meet their deadlines and                    clarification regarding the submission of              foot-long spillway section that generally
                                                  reporting schedules. Scheduling                         briefs on exceptions, in the above-                    curves upstream; (ii) a 128-foot-long
                                                  conflicts resulted in a delay in securing               referenced proceeding (Motion). On                     five-bay stoplog sluice; (iii) a 2,132-foot-
                                                  the venue.                                              January 8, 2016, MISO Transmission                     long right spillway that runs diagonally
                                                    Those not able to attend the meeting                  Owners filed an answer to the Motion.                  in a downstream direction; (iv) a trash
                                                  or who have insufficient time to address                Notice is hereby given that the deadline               sluice section; (v) a 54-foot-long by 38-
                                                  the committee are invited to send a                     for submitting briefs on exceptions is set             foot-wide east powerhouse with a 62-
                                                  written statement to Karen Gibson, U.S.                 to and including January 21, 2016. The                 foot-wide intake structure; and (vi) a
                                                  Department of Energy, 1000                              deadline to file briefs opposing                       64.5-foot-long by 63-foot-wide west
                                                  Independence Avenue SW.,                                exceptions is set to and including                     powerhouse with a 82.3-foot-wide
                                                  Washington, DC 20585, email to seab@                    February 10, 2016.                                     intake structure, with both powerhouses
                                                  hq.doe.gov.                                                                                                    integral to the dam; (2) a 190-acre
                                                                                                            Dated: January 11, 2016.
                                                    Minutes: The minutes of the meeting                                                                          reservoir with a gross storage capacity of
                                                                                                          Nathaniel J. Davis, Sr.,                               approximately 1,500 acre-feet at the
                                                  will be available on the SEAB Web site
                                                                                                          Deputy Secretary.                                      dam crest elevation of 651.0 feet
                                                  or by contacting Ms. Gibson. She may be
                                                  reached at the postal address or email                  [FR Doc. 2016–00704 Filed 1–14–16; 8:45 am]            NGVD29; (3) two turbine-generator units
                                                  address above, or by visiting SEAB’s                    BILLING CODE 6717–01–P                                 in the east powerhouse, each with a
                                                  Web site at www.energy.gov/seab.                                                                               rated capacity of approximately 1.9
                                                                                                                                                                 megawatts (MW); (4) six turbine-
                                                    Issued in Washington, DC, on January 13,              DEPARTMENT OF ENERGY                                   generator units in the west powerhouse,
                                                  2016.
                                                                                                                                                                 each with a rated capacity of
                                                  Amy Bodette,                                            Federal Energy Regulatory                              approximately 0.4 MW; (5) a 4-mile-
                                                  Committee Management Officer.                           Commission                                             long, 13.8-kilovolt transmission line;
                                                  [FR Doc. 2016–00854 Filed 1–14–16; 8:45 am]             [Project No. 14439–001]                                and (6) appurtenant facilities.
                                                  BILLING CODE 6450–01–P                                                                                            The project is currently operated in a
                                                                                                          Hawks Nest Hydro, LLC; Notice of                       run-of-river mode with no usable
                                                                                                          Application Tendered for Filing With                   storage capacity. Hawks Nest Hydro
                                                  DEPARTMENT OF ENERGY                                    the Commission and Establishing                        proposes to continue run-of-river
                                                                                                          Procedural Schedule for Licensing and                  operation. The project generates an
                                                  Federal Energy Regulatory                               Deadline for Submission of Final                       annual average of 41,482 megawatt-
                                                  Commission                                              Amendments                                             hours.
                                                                                                                                                                    l. Locations of the Application: A
                                                  [Docket No. EL14–12–002]                                  Take notice that the following                       copy of the application is available for
                                                                                                          hydroelectric application has been filed               review at the Commission in the Public
                                                  Notice Setting Deadlines To File Briefs
                                                                                                          with the Commission and is available                   Reference Room or may be viewed on
                                                                                                          for public inspection.                                 the Commission’s Web site at http://
                                                    Association of Businesses Advocating
                                                  Tariff Equity, Coalition of MISO
                                                                                                            a. Type of Application: New Major                    www.ferc.gov using the ‘‘eLibrary’’ link.
                                                  Transmission Customers, Illinois Industrial             License.                                               Enter the docket number excluding the
                                                  Energy Consumers, Indiana Industrial Energy               b. Project No.: 14439–001.                           last three digits in the docket number
                                                  Consumers, Inc., Minnesota Large Industrial               c. Date Filed: December 29, 2015.                    field to access the document. For
                                                  Group, Wisconsin Industrial Energy Group v.               d. Applicant: Hawks Nest Hydro, LLC                  assistance, contact FERC Online
                                                  Midcontinent Independent System Operator,               (Hawks Nest Hydro).                                    Support at FERCOnlineSupport@
                                                  Inc., ALLETE, Inc., Ameren Illinois Company,              e. Name of Project: Glen Ferris                      ferc.gov or toll-free at 1–866–208–3676,
                                                  Ameren Missouri, Ameren Transmission                    Hydroelectric Project.
                                                  Company of Illinois, American Transmission
                                                                                                                                                                 or for TTY, (202) 502–8659. A copy is
                                                                                                            f. Location: The existing project is                 also available for inspection and
                                                  Company LLC, Cleco Power LLC, Duke
                                                  Energy Business Services, LLC, Entergy
                                                                                                          located on the Kanawha River, in                       reproduction at the address in item (h)
                                                  Arkansas, Inc., Entergy Gulf States Louisiana,          Fayette County, West Virginia. The                     above.
                                                  LLC, Entergy Louisiana, LLC, Entergy                    project does not occupy any federal                       m. You may also register online at
                                                  Mississippi, Inc., Entergy New Orleans, Inc.,           lands.                                                 http://www.ferc.gov/docs-filing/
                                                  Entergy Texas, Inc., Indianapolis Power &                 g. Filed Pursuant to: Federal Power                  esubscription.asp to be notified via
                                                  Light Company, International Transmission               Act, 16 U.S.C. 791 (a)–825(r).                         email of new filings and issuances
                                                  Company, ITC Midwest LLC, Michigan
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                            h. Applicant Contact: Steven Murphy,                 related to this or other pending projects.
                                                  Electric Transmission Company, LLC                      Manager, Licensing, Brookfield                         For assistance, contact FERC Online
                                                  MidAmerican Energy Company, Montana-                    Renewable Energy Group, 33 West 1st
                                                  Dakota Utilities Co., Northern Indiana Public
                                                                                                                                                                 Support.
                                                  Service Company, Northern States Power
                                                                                                          Street South, Fulton, New York 13069;                     n. Procedural Schedule: The
                                                  Company-Minnesota, Northern States Power                Telephone (315) 598–6130.                              application will be processed according
                                                  Company-Wisconsin, Otter Tail Power                       i. FERC Contact: Monir Chowdhury,                    to the following preliminary Hydro
                                                  Company, Southern Indiana Gas & Electric                (202) 502–6736 or monir.chowdhury@                     Licensing Schedule. Revisions to the
                                                  Company                                                 ferc.gov.                                              schedule may be made as appropriate.


                                             VerDate Sep<11>2014   20:01 Jan 14, 2016   Jkt 238001   PO 00000   Frm 00046   Fmt 4703   Sfmt 4703   E:\FR\FM\15JAN1.SGM   15JAN1


                                                  2206                            Federal Register / Vol. 81, No. 10 / Friday, January 15, 2016 / Notices

                                                           Milestone                    Target date       Schedule for Environmental Review                      site (www.ferc.gov). Using the
                                                                                                          Issuance of EA—February 12, 2016                       ‘‘eLibrary’’ link, select ‘‘General Search’’
                                                  Notice of Acceptance/No-         February 2016.
                                                                                                          90-day Federal Authorization Decision                  from the eLibrary menu, enter the
                                                     tice of Ready for Envi-                                                                                     selected date range and ‘‘Docket
                                                     ronmental Analysis.                                     Deadline—May 12, 2016
                                                                                                                                                                 Number’’ excluding the last three digits
                                                  Filing of recommendations,       April 2016.               If a schedule change becomes                        (i.e., CP15–560), and follow the
                                                     preliminary terms and                                necessary, additional notice will be                   instructions. For assistance with access
                                                     conditions, and fishway                              provided so that the relevant agencies
                                                     prescriptions.                                                                                              to eLibrary, the helpline can be reached
                                                                                                          are kept informed of the Project’s                     at (866) 208–3676, TTY (202) 502–8659,
                                                  Commission issues EA ......      August 2016.           progress.
                                                  Comments on EA ..............    September                                                                     or at FERCOnlineSupport@ferc.gov. The
                                                                                     2016.                Project Description                                    eLibrary link on the FERC Web site also
                                                  Modified Terms and Condi-        November 2016.
                                                                                                             Cameron LNG, LLC’s Project would                    provides access to the texts of formal
                                                    tions.                                                                                                       documents issued by the Commission,
                                                  Commission Issues Final          February 2017.         add an additional LNG storage tank
                                                                                                          (Tank 5) and two new systems to liquefy                such as orders, notices, and rule
                                                    EA, if necessary.                                                                                            makings.
                                                                                                          natural gas (Trains 4 and 5) to its
                                                                                                          existing LNG Terminal in Cameron and                     Dated: January 11, 2016.
                                                    o. Final amendments to the
                                                  application must be filed with the                      Calcasieu Parishes, Louisiana. No                      Nathaniel J. Davis, Sr.,
                                                  Commission no later than 30 days from                   construction would occur outside of the                Deputy Secretary.
                                                  the issuance date of the notice of ready                existing terminal and no new shipping                  [FR Doc. 2016–00703 Filed 1–14–16; 8:45 am]
                                                  for environmental analysis.                             is proposed as a result of this Project.               BILLING CODE 6717–01–P

                                                    Dated: January 11, 2016.                              Background
                                                  Nathaniel J. Davis, Sr.,                                   On June 18, 2015, the Commission                    DEPARTMENT OF ENERGY
                                                  Deputy Secretary.                                       issued a Notice of Intent to Prepare an
                                                  [FR Doc. 2016–00710 Filed 1–14–16; 8:45 am]             Environmental Assessment for the                       Federal Energy Regulatory
                                                  BILLING CODE 6717–01–P                                  Planned Cameron LNG Expansion                          Commission
                                                                                                          Project and Request for Comments on
                                                                                                          Environmental Issues (NOI). The NOI                    Combined Notice of Filings #2
                                                  DEPARTMENT OF ENERGY                                    was issued during the pre-filing review                   Take notice that the Commission
                                                                                                          of the Project in Docket No. PF15–13–                  received the following exempt
                                                  Federal Energy Regulatory                               000 and was sent to affected
                                                  Commission                                                                                                     wholesale generator filings:
                                                                                                          landowners; federal, state, and local
                                                                                                                                                                    Docket Numbers: EG16–36–000.
                                                                                                          government agencies; elected officials;
                                                                                                                                                                    Applicants: Kingbird Solar A, LLC.
                                                  [Docket No. CP15–560–000]                               environmental and public interest
                                                                                                                                                                    Description: Notice of Self-
                                                                                                          groups; Native American tribes; other
                                                  Cameron LNG, LLC; Notice of                                                                                    Certification of Exempt Wholesale
                                                                                                          interested parties; and local libraries
                                                  Schedule for Environmental Review of                                                                           Generator Status of Kingbird Solar A,
                                                                                                          and newspapers. In response to the NOI,
                                                  the Cameron LNG Terminal Expansion                                                                             LLC.
                                                                                                          the Commission received comments
                                                  Project                                                                                                           Filed Date: 1/11/16.
                                                                                                          from the U.S. Environmental Protection                    Accession Number: 20160111–5267.
                                                                                                          Agency (EPA). The primary issues                          Comments Due: 5 p.m. ET 2/1/16.
                                                     On September 28, 2015, Cameron                       raised by the EPA are alternatives,
                                                  LNG, LLC filed an application in Docket                 groundwater and water impacts,                            Docket Numbers: EG16–37–000.
                                                  No. CP15–560–000 requesting                             wildlife and habitat impacts, air quality,                Applicants: Kingbird Solar B, LLC.
                                                  Authorization pursuant to section 3 of                  hazardous materials, tribal and state                     Description: Notice of Self-
                                                  the Natural Gas Act to construct and                    historic preservation office consultation,             Certification of Exempt Wholesale
                                                  operate certain liquefied natural gas                   and environmental justice.                             Generator Status of Kingbird Solar B,
                                                  (LNG) facilities at the existing Cameron                   The U.S. Department of                              LLC.
                                                  LNG Terminal. The proposed project is                                                                             Filed Date: 1/11/16.
                                                                                                          Transportation and U.S. Department of
                                                  known as the Cameron LNG Terminal                                                                                 Accession Number: 20160111–5271.
                                                                                                          Energy are cooperating agencies in the
                                                  Expansion Project (Project), and would                                                                            Comments Due: 5 p.m. ET 2/1/16.
                                                                                                          preparation of the EA.
                                                  increase the terminal’s capability to                                                                             Take notice that the Commission
                                                  liquefy natural gas for export by 515                   Additional Information                                 received the following electric rate
                                                  billion cubic feet per year.                               In order to receive notification of the             filings:
                                                     On October 13, 2015, the Federal                     issuance of the EA and to keep track of                   Docket Numbers: ER16–38–001.
                                                  Energy Regulatory Commission                            all formal issuances and submittals in                    Applicants: Kingbird Solar A, LLC.
                                                  (Commission or FERC) issued its Notice                  specific dockets, the Commission offers                   Description: Compliance filing:
                                                  of Application for the Project. Among                   a free service called eSubscription. This              Application for Initial Market-Based
                                                  other things, that notice alerted agencies              can reduce the amount of time you                      Rate Tariff and Granting Certain
                                                  issuing federal authorizations of the                   spend researching proceedings by                       Waivers to be effective 1/12/2016.
                                                  requirement to complete all necessary                   automatically providing you with                          Filed Date: 1/11/16.
                                                                                                                                                                    Accession Number: 20160111–5265.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  reviews and to reach a final decision on                notification of these filings, document
                                                  a request for a federal authorization                   summaries, and direct links to the                        Comments Due: 5 p.m. ET 2/1/16.
                                                  within 90 days of the date of issuance                  documents. Go to www.ferc.gov/docs-                       Docket Numbers: ER16–705–001.
                                                  of the Commission staff’s Environmental                 filing/esubscription.asp.                                 Applicants: RE Garland LLC.
                                                  Assessment (EA) for the Project. This                      Additional information about the                       Description: Tariff Amendment:
                                                  instant notice identifies the FERC staff’s              Project is available from the                          Amendment to Application and Initial
                                                  planned schedule for the completion of                  Commission’s Office of External Affairs                Tariff Filing to be effective 2/12/2016.
                                                  the EA for the Project.                                 at (866) 208–FERC or on the FERC Web                      Filed Date: 1/11/16.


                                             VerDate Sep<11>2014   20:01 Jan 14, 2016   Jkt 238001   PO 00000   Frm 00047   Fmt 4703   Sfmt 4703   E:\FR\FM\15JAN1.SGM   15JAN1



Document Created: 2018-02-02 12:31:50
Document Modified: 2018-02-02 12:31:50
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 2205 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR