81_FR_2218 81 FR 2208 - Algonquin Power (Beaver Falls), LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments

81 FR 2208 - Algonquin Power (Beaver Falls), LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 10 (January 15, 2016)

Page Range2208-2209
FR Document2016-00707

Federal Register, Volume 81 Issue 10 (Friday, January 15, 2016)
[Federal Register Volume 81, Number 10 (Friday, January 15, 2016)]
[Notices]
[Pages 2208-2209]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-00707]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project Nos. 2593-031; 2823-020]


Algonquin Power (Beaver Falls), LLC; Notice of Application 
Tendered for Filing With the Commission and Soliciting Additional Study 
Requests and Establishing Procedural Schedule for Relicensing and a 
Deadline for Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project Nos.: 2593-031 and 2823-020.
    c. Date filed: December 30, 2015.
    d. Applicant: Algonquin Power (Beaver Falls), LLC.
    e. Name of Projects: Upper Beaver Falls and Lower Beaver Falls 
projects.
    f. Location: On the Beaver River, in the towns of Croghan and New 
Bremen, Lewis County, New York. The project does not occupy lands of 
the United States.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Robert A. Gates, Executive Vice President, 
Eagle Creek Renewable Energy, 65 Madison Avenue, Suite 500, Morristown, 
New Jersey 07960; (973) 998-8400; [email protected].
    i. FERC Contact: Andy Bernick, (202) 502-8660 or 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of the Commission's regulations, 
if any resource agency, Indian Tribe, or person believes that an 
additional scientific study should be conducted in order to form an 
adequate factual basis for a complete analysis of the application on 
its merit, the resource agency, Indian Tribe, or person must file a 
request for a study with the Commission not later than 60 days from the 
date of filing of the application, and serve a copy of the request on 
the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: February 28, 2016.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE., Washington, DC 20426. The first page of any filing should include 
docket numbers P-2593-031 and P-2823-020.
    m. The application is not ready for environmental analysis at this 
time.
    n. The existing project works are as follows:
    The Upper Beaver Falls Project consists of: (1) A 328-foot-long, 
25-foot-high concrete gravity dam with an uncontrolled overflow 
spillway; (2) a 48-acre reservoir with a storage capacity of 800 acre-
feet at elevation 799.4 feet North American Vertical Datum of 1988 
(NAVD 88); (3) a 17-foot-high, 26.5-foot-wide, 27.5-foot-long intake 
structure with a steel trash rack; (4) a 90-foot-long, 16-foot-wide, 8-
foot-high concrete penstock; (5) a powerhouse containing one turbine-
generator with a nameplate rating of 1,500 kilowatts (kW); (6) a 
tailrace excavated in the riverbed; (7) a 2,120-foot-long, 2.4-kilovolt 
(kV) overhead transmission line connecting to an existing National Grid 
substation; and (8) other appurtenances. The project generates about 
8,685 megawatt-hours (MWh) annually.
    The Lower Beaver Falls Hydroelectric Project consists of: (1) A 
400-foot-long concrete gravity dam with a maximum height of 14 feet, 
including: (i) A 240-foot-long non-overflow section containing an 8-
foot-wide spillway topped with flashboards ranging from 6 to 8 inches 
in height and (ii) a 160-foot-long overflow section with an ice sluice 
opening; (2) a 4-acre reservoir with a storage capacity of 27.9 acre-
feet at a normal elevation of 769.6 feet NAVD 88; (3) an intake 
structure with a steel trash rack, integral with a powerhouse 
containing two 500-kW turbine and generator units; (4) a tailrace; (5) 
a 250-foot-long, 2.4-kV transmission line connected to the Upper Beaver 
Falls powerhouse; and (6) appurtenant facilities. The project generates 
about 5,617 MWh annually.
    The Lower Beaver Falls Project is located approximately 600 feet 
downstream of the Upper Beaver Falls Project. The dams and existing 
project facilities for both projects are owned by the applicant. The 
applicant proposes no new project facilities or operational changes, 
but proposes that both projects be combined under a single license.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter one of the docket numbers excluding the last three digits 
in the docket number field to access the document. For assistance, 
please contact FERC Online Support at [email protected], (866) 
208-3676 (toll free), or (202) 502-8659 (TTY). A copy is also available 
for inspection and reproduction at the address in item (h) above.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to these or other pending projects. For assistance, contact 
FERC Online Support.
    p. Procedural Schedule: The application will be processed according 
to the following preliminary Hydro Licensing Schedule. Revisions to the 
schedule will be made as appropriate.

Issue Deficiency Letter (if necessary)--February 2016
Request Additional Information--February 2016
Issue Acceptance Letter--May 2016
Issue Scoping Document 1 for comments--May 2016
Request Additional Information (if necessary)--July 2016
Issue Scoping Document 2--September 2016
Issue notice of ready for environmental analysis--September 2016
Commission issues EA, draft EA, or draft EIS--March 2017
Comments on EA, draft EA, or draft EIS--April 2017
Commission issues final EA or EIS--June 2017


[[Page 2209]]


    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: January 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-00707 Filed 1-14-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                  2208                           Federal Register / Vol. 81, No. 10 / Friday, January 15, 2016 / Notices

                                                           Milestone                    Target date       described in item l below. Cooperating                 topped with flashboards ranging from 6
                                                                                                          agencies should note the Commission’s                  to 8 inches in height and (ii) a 160-foot-
                                                  Modified Terms and Condi-        November 2016.         policy that agencies that cooperate in                 long overflow section with an ice sluice
                                                    tions.                                                the preparation of the environmental                   opening; (2) a 4-acre reservoir with a
                                                  Commission Issues Final          February 2017.         document cannot also intervene. See, 94                storage capacity of 27.9 acre-feet at a
                                                    EA, if necessary.                                     FERC ¶ 61,076 (2001).                                  normal elevation of 769.6 feet NAVD 88;
                                                                                                             k. Pursuant to section 4.32(b)(7) of the            (3) an intake structure with a steel trash
                                                    o. Final amendments to the                            Commission’s regulations, if any                       rack, integral with a powerhouse
                                                  application must be filed with the                      resource agency, Indian Tribe, or person               containing two 500-kW turbine and
                                                  Commission no later than 30 days from                   believes that an additional scientific                 generator units; (4) a tailrace; (5) a 250-
                                                  the issuance date of the notice of ready                study should be conducted in order to                  foot-long, 2.4-kV transmission line
                                                  for environmental analysis.                             form an adequate factual basis for a                   connected to the Upper Beaver Falls
                                                    Dated: January 11, 2016.                              complete analysis of the application on                powerhouse; and (6) appurtenant
                                                  Nathaniel J. Davis, Sr.,                                its merit, the resource agency, Indian                 facilities. The project generates about
                                                  Deputy Secretary.                                       Tribe, or person must file a request for               5,617 MWh annually.
                                                  [FR Doc. 2016–00706 Filed 1–14–16; 8:45 am]             a study with the Commission not later                     The Lower Beaver Falls Project is
                                                                                                          than 60 days from the date of filing of                located approximately 600 feet
                                                  BILLING CODE 6717–01–P
                                                                                                          the application, and serve a copy of the               downstream of the Upper Beaver Falls
                                                                                                          request on the applicant.                              Project. The dams and existing project
                                                  DEPARTMENT OF ENERGY                                       l. Deadline for filing additional study
                                                                                                                                                                 facilities for both projects are owned by
                                                                                                          requests and requests for cooperating
                                                                                                                                                                 the applicant. The applicant proposes
                                                  Federal Energy Regulatory                               agency status: February 28, 2016.
                                                                                                             The Commission strongly encourages                  no new project facilities or operational
                                                  Commission                                                                                                     changes, but proposes that both projects
                                                                                                          electronic filing. Please file additional
                                                  [Project Nos. 2593–031; 2823–020]                       study requests and requests for                        be combined under a single license.
                                                                                                          cooperating agency status using the                       o. A copy of the application is
                                                  Algonquin Power (Beaver Falls), LLC;                    Commission’s eFiling system at http://                 available for review at the Commission
                                                  Notice of Application Tendered for                      www.ferc.gov/docs-filing/efiling.asp. For              in the Public Reference Room or may be
                                                  Filing With the Commission and                          assistance, please contact FERC Online                 viewed on the Commission’s Web site at
                                                  Soliciting Additional Study Requests                    Support at FERCOnlineSupport@                          http://www.ferc.gov using the
                                                  and Establishing Procedural Schedule                    ferc.gov, (866) 208–3676 (toll free), or               ‘‘eLibrary’’ link. Enter one of the docket
                                                  for Relicensing and a Deadline for                      (202) 502–8659 (TTY). In lieu of                       numbers excluding the last three digits
                                                  Submission of Final Amendments                          electronic filing, please send a paper                 in the docket number field to access the
                                                    Take notice that the following                        copy to: Secretary, Federal Energy                     document. For assistance, please contact
                                                  hydroelectric application has been filed                Regulatory Commission, 888 First Street                FERC Online Support at
                                                  with the Commission and is available                    NE., Washington, DC 20426. The first                   FERCOnlineSupport@ferc.gov, (866)
                                                  for public inspection.                                  page of any filing should include docket               208–3676 (toll free), or (202) 502–8659
                                                    a. Type of Application: New Major                     numbers P–2593–031 and P–2823–020.                     (TTY). A copy is also available for
                                                  License.                                                   m. The application is not ready for                 inspection and reproduction at the
                                                    b. Project Nos.: 2593–031 and 2823–                   environmental analysis at this time.                   address in item (h) above.
                                                  020.                                                       n. The existing project works are as                   You may also register online at
                                                    c. Date filed: December 30, 2015.                     follows:                                               http://www.ferc.gov/docs-filing/
                                                    d. Applicant: Algonquin Power                            The Upper Beaver Falls Project                      esubscription.asp to be notified via
                                                  (Beaver Falls), LLC.                                    consists of: (1) A 328-foot-long, 25-foot-             email of new filings and issuances
                                                    e. Name of Projects: Upper Beaver                     high concrete gravity dam with an                      related to these or other pending
                                                  Falls and Lower Beaver Falls projects.                  uncontrolled overflow spillway; (2) a                  projects. For assistance, contact FERC
                                                    f. Location: On the Beaver River, in                  48-acre reservoir with a storage capacity              Online Support.
                                                  the towns of Croghan and New Bremen,                    of 800 acre-feet at elevation 799.4 feet
                                                                                                                                                                    p. Procedural Schedule: The
                                                  Lewis County, New York. The project                     North American Vertical Datum of 1988
                                                                                                                                                                 application will be processed according
                                                  does not occupy lands of the United                     (NAVD 88); (3) a 17-foot-high, 26.5-foot-
                                                                                                                                                                 to the following preliminary Hydro
                                                  States.                                                 wide, 27.5-foot-long intake structure
                                                                                                                                                                 Licensing Schedule. Revisions to the
                                                    g. Filed Pursuant to: Federal Power                   with a steel trash rack; (4) a 90-foot-
                                                                                                                                                                 schedule will be made as appropriate.
                                                  Act 16 U.S.C. 791 (a)–825(r).                           long, 16-foot-wide, 8-foot-high concrete
                                                    h. Applicant Contact: Robert A. Gates,                penstock; (5) a powerhouse containing                  Issue Deficiency Letter (if necessary)—
                                                                                                                                                                    February 2016
                                                  Executive Vice President, Eagle Creek                   one turbine-generator with a nameplate                 Request Additional Information—February
                                                  Renewable Energy, 65 Madison Avenue,                    rating of 1,500 kilowatts (kW); (6) a                     2016
                                                  Suite 500, Morristown, New Jersey                       tailrace excavated in the riverbed; (7) a              Issue Acceptance Letter—May 2016
                                                  07960; (973) 998–8400; bob.gates@                       2,120-foot-long, 2.4-kilovolt (kV)                     Issue Scoping Document 1 for comments—
                                                  eaglecreekre.com.                                       overhead transmission line connecting                     May 2016
                                                    i. FERC Contact: Andy Bernick, (202)                  to an existing National Grid substation;               Request Additional Information (if
                                                  502–8660 or andrew.bernick@ferc.gov.                    and (8) other appurtenances. The project                  necessary)—July 2016
                                                                                                                                                                 Issue Scoping Document 2—September 2016
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                    j. Cooperating agencies: Federal, state,              generates about 8,685 megawatt-hours
                                                  local, and tribal agencies with                         (MWh) annually.                                        Issue notice of ready for environmental
                                                  jurisdiction and/or special expertise                      The Lower Beaver Falls Hydroelectric                   analysis—September 2016
                                                                                                                                                                 Commission issues EA, draft EA, or draft
                                                  with respect to environmental issues                    Project consists of: (1) A 400-foot-long                  EIS—March 2017
                                                  that wish to cooperate in the                           concrete gravity dam with a maximum                    Comments on EA, draft EA, or draft EIS—
                                                  preparation of the environmental                        height of 14 feet, including: (i) A 240-                  April 2017
                                                  document should follow the                              foot-long non-overflow section                         Commission issues final EA or EIS—June
                                                  instructions for filing such requests                   containing an 8-foot-wide spillway                        2017



                                             VerDate Sep<11>2014   20:01 Jan 14, 2016   Jkt 238001   PO 00000   Frm 00049   Fmt 4703   Sfmt 4703   E:\FR\FM\15JAN1.SGM   15JAN1


                                                                                 Federal Register / Vol. 81, No. 10 / Friday, January 15, 2016 / Notices                                           2209

                                                     Final amendments to the application                     Applicants: NorthWestern                               The second meeting will be held on
                                                  must be filed with the Commission no                    Corporation.                                           January 29, 2016, from 11:00 a.m. to
                                                  later than 30 days from the issuance                       Description: Section 205(d) Rate                    4:00 p.m. Eastern at the Illinois
                                                  date of the notice of ready for                         Filing: Ministerial Revisions to Montana               Commerce Commission Hearing Room,
                                                  environmental analysis.                                 OATT to be effective 3/12/2016.                        160 North LaSalle, Suite C–800,
                                                    Dated: January 11, 2016.
                                                                                                             Filed Date: 1/11/16.                                Chicago, IL 60601.
                                                                                                             Accession Number: 20160111–5134.                       The discussions may address matters
                                                  Nathaniel J. Davis, Sr.,                                   Comments Due: 5 p.m. ET 2/1/16.                     at issue in the following proceedings:
                                                  Deputy Secretary.                                          Docket Numbers: ER16–709–000.
                                                  [FR Doc. 2016–00707 Filed 1–14–16; 8:45 am]
                                                                                                                                                                 Docket No. ER11–4081, Midwest
                                                                                                             Applicants: No Applicants listed for                   Independent System Operator, Inc.
                                                  BILLING CODE 6717–01–P                                  this docket/subdocket.                                 Docket No. EL12–54, Viridity Energy,
                                                                                                             Description: Section 205(d) Rate                       Inc. v. PJM Interconnection, L.L.C.
                                                                                                          Filing: 607R26 Westar Energy, Inc.                     Docket No. ER13–535, PJM
                                                  DEPARTMENT OF ENERGY                                    NITSA NOA to be effective 1/1/2016.                       Interconnection, L.L.C.
                                                                                                             Filed Date: 1/11/16.
                                                  Federal Energy Regulatory                                                                                      Docket No. ER13–2108, PJM
                                                                                                             Accession Number: 20160111–5167.
                                                  Commission                                                 Comments Due: 5 p.m. ET 2/1/16.                        Interconnection, L.L.C.
                                                                                                                                                                 Docket No. ER14–504, PJM
                                                  Combined Notice of Filings #1                              The filings are accessible in the                      Interconnection, L.L.C.
                                                                                                          Commission’s eLibrary system by                        Docket No. ER14–822, PJM
                                                     Take notice that the Commission                      clicking on the links or querying the                     Interconnection, L.L.C.
                                                  received the following electric rate                    docket number.                                         Docket Nos. ER14–1461 and EL14–48,
                                                  filings:                                                   Any person desiring to intervene or
                                                                                                                                                                    PJM Interconnection, L.L.C.
                                                     Docket Numbers: ER13–1356–002.                       protest in any of the above proceedings
                                                                                                                                                                 Docket No. ER14–2940, PJM
                                                     Applicants: Duke Energy Florida,                     must file in accordance with Rules 211
                                                                                                                                                                    Interconnection, L.L.C.
                                                  LLC.                                                    and 214 of the Commission’s
                                                                                                                                                                 Docket No. ER15–135, PJM
                                                     Description: Amendment to December                   Regulations (18 CFR 385.211 and
                                                                                                                                                                    Interconnection, L.L.C.
                                                  21, 2015 Compliance filing [including                   385.214) on or before 5:00 p.m. Eastern                Docket Nos. ER15–623 and EL15–29,
                                                  Pro Forma sheets] of Duke Energy                        time on the specified comment date.                       PJM Interconnection, L.L.C.
                                                  Florida, LLC.                                           Protests may be considered, but                        Docket No. EL14–20, Independent
                                                     Filed Date: 1/8/16.                                  intervention is necessary to become a                     Market Monitor for PJM v. PJM
                                                     Accession Number: 20160108–5264.                     party to the proceeding.                                  Interconnection, L.L.C.
                                                     Comments Due: 5 p.m. ET 1/29/16.                        eFiling is encouraged. More detailed
                                                                                                                                                                 Docket Nos. EL14–94 and EL14–36,
                                                     Docket Numbers: ER15–1618–003.                       information relating to filing
                                                                                                                                                                    FirstEnergy Solutions Corp. and PJM
                                                     Applicants: Duke Energy Florida,                     requirements, interventions, protests,
                                                                                                                                                                    Interconnection, L.L.C.
                                                  LLC.                                                    service, and qualifying facilities filings
                                                                                                                                                                 Docket No. EL14–55, FirstEnergy
                                                     Description: Compliance filing: ROE                  can be found at: http://www.ferc.gov/
                                                                                                                                                                    Service Company v. PJM
                                                  Settlement IA’s Amendment RS 80, 82                     docs-filing/efiling/filing-req.pdf. For
                                                                                                                                                                    Interconnection, L.L.C.
                                                  & 105 to be effective 5/1/2015.                         other information, call (866) 208–3676
                                                                                                                                                                 Docket No. EL15–41, Essential Power
                                                     Filed Date: 1/8/16.                                  (toll free). For TTY, call (202) 502–8659.
                                                                                                                                                                    Rock Springs, L.L.C. et al. v. PJM
                                                     Accession Number: 20160108–5124.                       Dated: January 11, 2016.                                Interconnection, L.L.C.
                                                     Comments Due: 5 p.m. ET 1/29/16.                     Nathaniel J. Davis, Sr.,                               Docket No. EL15–46, Champion Energy
                                                     Docket Numbers: ER16–704–000.                        Deputy Secretary.                                         Marketing L.L.C. v. PJM
                                                     Applicants: Southwest Power Pool,                    [FR Doc. 2016–00708 Filed 1–14–16; 8:45 am]               Interconnection, L.L.C.
                                                  Inc.                                                    BILLING CODE 6717–01–P                                 Docket No. EL15–80, Advanced Energy
                                                     Description: Section 205(d) Rate                                                                               Management Alliance Coalition v.
                                                  Filing: Revisions to Identify US/Canada                                                                           PJM Interconnection, L.L.C.
                                                  Border as a Point-of-Delivery/Point-of-                 DEPARTMENT OF ENERGY                                   Docket No. EL15–83, National
                                                  Receipt to be effective 3/8/2016.                                                                                 Resources Defense Council, et al., v.
                                                     Filed Date: 1/8/16.                                  Federal Energy Regulatory                                 PJM Interconnection, L.L.C.
                                                     Accession Number: 20160108–5231.                     Commission                                             Docket No. EL15–70, Public Citizen, Inc.
                                                     Comments Due: 5 p.m. ET 1/29/16.                                                                               v. Midcontinent Independent System
                                                     Docket Numbers: ER16–705–000.                        Notice of Staff Attendance at the                         Operator, Inc.
                                                     Applicants: RE Garland LLC.                          Midcontinent Independent System                        Docket No. EL15–71, People of the State
                                                     Description: Baseline eTariff Filing:                Operator, Inc. (MISO) Meetings of the                     of Illinois v. Midcontinent
                                                  Application and Initial Baseline Tariff                 Miso Competitive Retail Solution Task                     Independent System Operator, Inc.
                                                  Filing to be effective 2/12/2016.                       Team (CSRTT)                                           Docket No. EL15–72, Southwestern
                                                     Filed Date: 1/8/16.                                     The Federal Energy Regulatory                          Electric Cooperative, Inc. v.
                                                     Accession Number: 20160108–5238.                     Commission (Commission) hereby gives                      Midcontinent Independent System
                                                     Comments Due: 5 p.m. ET 1/29/16.                     notice that members of its staff may                      Operator, Inc.
                                                     Docket Numbers: ER16–706–000.                        attend the January meetings of the MISO                Docket No. EL15–82, Illinois Industrial
                                                     Applicants: RE Garland A LLC.                                                                                  Energy Consumers v. Midcontinent
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                          CSRTT. Their attendance is part of the
                                                     Description: Baseline eTariff Filing:                Commission’s ongoing outreach efforts.                    Independent System Operator, Inc.
                                                  Application and Initial Baseline Tariff                    The first meeting will be held by                      The meeting is open to the public.
                                                  Filing to be effective 2/12/2016.                       conference call on January 15, 2016,                      For more information, contact Patrick
                                                     Filed Date: 1/8/16.                                  from 10:00 a.m. to 12:00 p.m. Eastern.                 Clarey, Office of Energy Market
                                                     Accession Number: 20160108–5239.                     Dial-in and webcast information may be                 Regulation, Federal Energy Regulatory
                                                     Comments Due: 5 p.m. ET 1/29/16.                     found at https://www.misoenergy.org/                   Commission at (317) 249–5937 or
                                                     Docket Numbers: ER16–707–000.                        Events/Pages/CSRTT20160115.aspx.                       patrick.clarey@ferc.gov.


                                             VerDate Sep<11>2014   20:01 Jan 14, 2016   Jkt 238001   PO 00000   Frm 00050   Fmt 4703   Sfmt 4703   E:\FR\FM\15JAN1.SGM   15JAN1



Document Created: 2018-02-02 12:32:13
Document Modified: 2018-02-02 12:32:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 2208 