[Federal Register Volume 81, Number 74 (Monday, April 18, 2016)]
[Notices]
[Pages 22587-22588]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-08858]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2512-075; Project No. 14439-001]


Hawks Nest Hydro, LLC; Notice of Application Accepted for Filing, 
Soliciting Motions To Intervene and Protests, Ready for Environmental 
Analysis, and Soliciting Comments, Recommendations, Preliminary Terms 
and Conditions, and Preliminary Fishway Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major Licenses.
    b. Project Nos.: 2512-075 and 14439-001.
    c. Date filed: December 29, 2015.
    d. Applicant: Hawks Nest Hydro, LLC (Hawks Nest Hydro).
    e. Name of Project: Hawks Nest and Glen Ferris Hydroelectric 
Projects.
    f. Location: The existing Hawks Nest and Glen Ferris projects are 
located on the New and Kanawha rivers, respectively. Both projects are 
located in Fayette County, West Virginia. The projects do not occupy 
any federal lands.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Steven Murphy, Manager, Licensing, Brookfield 
Renewable Energy Group, 33 West 1st Street South, Fulton, New York 
13069; Telephone (315) 598-6130.
    i. FERC Contact: Monir Chowdhury, (202) 502-6736, or 
[email protected].
    j. Deadline for filing motions to intervene and protests, comments, 
recommendations, preliminary terms and conditions, and preliminary 
prescriptions: 60 days from the issuance date of this notice; reply 
comments are due 105 days from the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests, comments, recommendations, preliminary 
terms and conditions, and preliminary fishway prescriptions using the 
Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include the 
applicable project name(s) and docket number(s) (e.g., Hawks Nest P-
2512-075).
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. The existing project works consist of the following:
    The existing Hawks Nest Hydroelectric Project consists of: (1) A 
948-foot-long concrete-gravity dam with a crest elevation of 795.0 feet 
National Geodetic Vertical Datum of 1929 (NGVD29); (2) 14 ogee-type 
spillway bays extending almost the entire length of the dam, each with 
a 25-foot-high by 50-foot-wide Stoney-type steel lift gate and 
separated by a 9-foot-wide concrete pier; (3) a 243-acre reservoir with 
a gross storage capacity of 7,323 acre-feet at a normal pool elevation 
of 819.9 feet NGVD29; (4) an intake structure located at the right 
shoreline (looking downstream) of the reservoir just upstream of the 
dam and consisting of a 110-foot-wide by 50-foot-high trashrack 
structure and a Stoney-type 42-foot-high by 50-foot-wide bulkhead 
intake gate that sits back approximately 50 feet from the opening where 
the trashrack is located; (5) a 16,240-foot-long tunnel that runs along 
the right side of the river to convey water from the intake to the 
powerhouse downstream on the New River; (6) a 600-foot-long by 170-
foot-wide surge basin located at a point on the tunnel approximately 60 
percent of the distance from the intake to the powerhouse; (7) a 116-
foot-diameter and 56-foot-high differential surge tank located at the 
downstream end of the tunnel and before the powerhouse; (8) a 210-foot-
long by 74.5-foot-wide powerhouse containing four turbine-generator 
units, each with a rated capacity of approximately 25.5 megawatts (MW); 
(9) two parallel approximately 5.5-mile-long, 69-kilovolt (kV) 
transmission lines; and (10) appurtenant facilities. Hawks Nest Hydro 
operates the project in a run-of-river mode.
    The existing license for the Hawks Nest Hydroelectric Project 
requires that the project release a continuous minimum flow of 100 
cubic feet per second into the bypassed reach between the dam and the 
powerhouse (Article 402). Hawks Nest Hydro proposes to continue run-of-
river operation and increase the existing minimum flow for the bypassed 
reach. The project generates an annual average of 544,253 megawatt-
hours.
    The existing Glen Ferris Hydroelectric Project consists of: (1) A 
low concrete dam with a maximum height of 12 feet above the river bed 
and a crest elevation of 651.0 feet NGVD29, consisting of (from left to 
right--looking downstream) (i) a 590-foot-long spillway section that 
generally curves upstream; (ii) a 128-foot-long five-bay stoplog 
sluice; (iii) a 2,132-foot-long right spillway that runs diagonally in 
a downstream direction; (iv) a trash sluice section; (v) a 54-foot-long 
by 38-foot-wide east powerhouse with a 62-foot-wide intake structure; 
and (vi) a 64.5-foot-long by 63-foot-wide west powerhouse with an 82.3-
foot-wide intake structure, with both powerhouses integral to the dam; 
(2) a 190-acre reservoir with a gross storage capacity of approximately 
1,500 acre-feet at the dam crest elevation of 651.0 feet NGVD29; (3) 
two turbine-generator units in the east powerhouse, each with a rated 
capacity of approximately 1.9 MW; (4) six turbine-generator units in 
the west powerhouse, each with a rated capacity of approximately 0.4 
MW; (5) a 4-mile-long, 13.8-kV transmission line; and (6) appurtenant 
facilities.
    The Glen Ferris Hydroelectric Project is currently operated in a 
run-of-river mode with no usable storage capacity. Hawks Nest Hydro 
proposes to continue run-of-river operation. The project generates an 
annual average of 41,482 megawatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in

[[Page 22588]]

the docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Anyone may submit comments, a protest, or a motion to intervene 
in accordance with the requirements of Rules of Practice and Procedure, 
18 CFR 385.210, .211, and .214. In determining the appropriate action 
to take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the proceeding. Any 
comments, protests, or motions to intervene must be received on or 
before the specified comment date for the particular application.
    All filings must (1) bear in all capital letters the title 
``PROTEST,'' ``MOTION TO INTERVENE,'' ``COMMENTS,'' ``REPLY COMMENTS,'' 
``RECOMMENDATIONS,'' ``PRELIMINARY TERMS AND CONDITIONS,'' or 
``PRELIMINARY FISHWAY PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. A copy of any protest or 
motion to intervene must be served upon each representative of the 
applicant specified in the particular application. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.
    o. Procedural Schedule:
    The application will be processed according to the following 
revised Hydro Licensing Schedule. Revisions to the schedule may be made 
as appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Filing of recommendations, preliminary   June 2016.
 terms and conditions, and preliminary
 fishway prescriptions.
Commission Issues Draft EA.............  December 2016.
Comments on Draft EA...................  January 2017.
Modified Terms and Conditions..........  March 2017.
Commission Issues Final EA.............  June 2017.
------------------------------------------------------------------------

    p. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of this notice.
    q. A license applicant must file no later than 60 days following 
the date of issuance of the notice of acceptance and ready for 
environmental analysis provided for in 5.22: (1) A copy of the water 
quality certification; (2) a copy of the request for certification, 
including proof of the date on which the certifying agency received the 
request; or (3) evidence of waiver of water quality certification.

    Dated: April 6, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-08858 Filed 4-15-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 81, No. 74 / Monday, April 18, 2016 / Notices                                             22587

                                                  Commission, 888 First Street NE.,                       fishway prescriptions using the                       powerhouse; (7) a 116-foot-diameter and
                                                  Washington, DC 20426, (202) 502–6044,                   Commission’s eFiling system at http://                56-foot-high differential surge tank
                                                  katharine.lindner@ferc.gov.                             www.ferc.gov/docs-filing/efiling.asp.                 located at the downstream end of the
                                                                                                          Commenters can submit brief comments                  tunnel and before the powerhouse; (8) a
                                                  Kimberly D. Bose,
                                                                                                          up to 6,000 characters, without prior                 210-foot-long by 74.5-foot-wide
                                                  Secretary.                                              registration, using the eComment system               powerhouse containing four turbine-
                                                  [FR Doc. 2016–08863 Filed 4–15–16; 8:45 am]             at http://www.ferc.gov/docs-filing/                   generator units, each with a rated
                                                  BILLING CODE 6717–01–P                                  ecomment.asp. You must include your                   capacity of approximately 25.5
                                                                                                          name and contact information at the end               megawatts (MW); (9) two parallel
                                                                                                          of your comments. For assistance,                     approximately 5.5-mile-long, 69-kilovolt
                                                  DEPARTMENT OF ENERGY                                    please contact FERC Online Support at                 (kV) transmission lines; and (10)
                                                                                                          FERCOnlineSupport@ferc.gov, (866)                     appurtenant facilities. Hawks Nest
                                                  Federal Energy Regulatory                               208–3676 (toll free), or (202) 502–8659               Hydro operates the project in a run-of-
                                                  Commission                                              (TTY). In lieu of electronic filing, please           river mode.
                                                  [Project No. 2512–075; Project No. 14439–               send a paper copy to: Secretary, Federal                 The existing license for the Hawks
                                                  001]                                                    Energy Regulatory Commission, 888                     Nest Hydroelectric Project requires that
                                                                                                          First Street NE., Washington, DC 20426.               the project release a continuous
                                                  Hawks Nest Hydro, LLC; Notice of                        The first page of any filing should                   minimum flow of 100 cubic feet per
                                                  Application Accepted for Filing,                        include the applicable project name(s)                second into the bypassed reach between
                                                  Soliciting Motions To Intervene and                     and docket number(s) (e.g., Hawks Nest                the dam and the powerhouse (Article
                                                  Protests, Ready for Environmental                       P–2512–075).                                          402). Hawks Nest Hydro proposes to
                                                  Analysis, and Soliciting Comments,                         The Commission’s Rules of Practice                 continue run-of-river operation and
                                                  Recommendations, Preliminary Terms                      require all intervenors filing documents              increase the existing minimum flow for
                                                  and Conditions, and Preliminary                         with the Commission to serve a copy of                the bypassed reach. The project
                                                  Fishway Prescriptions                                   that document on each person on the                   generates an annual average of 544,253
                                                                                                          official service list for the project.                megawatt-hours.
                                                    Take notice that the following                                                                                 The existing Glen Ferris Hydroelectric
                                                                                                          Further, if an intervenor files comments
                                                  hydroelectric application has been filed                                                                      Project consists of: (1) A low concrete
                                                                                                          or documents with the Commission
                                                  with the Commission and is available                    relating to the merits of an issue that               dam with a maximum height of 12 feet
                                                  for public inspection.                                  may affect the responsibilities of a                  above the river bed and a crest elevation
                                                    a. Type of Application: New Major                     particular resource agency, they must                 of 651.0 feet NGVD29, consisting of
                                                  Licenses.                                               also serve a copy of the document on                  (from left to right—looking downstream)
                                                    b. Project Nos.: 2512–075 and 14439–                  that resource agency.                                 (i) a 590-foot-long spillway section that
                                                  001.                                                       k. This application has been accepted              generally curves upstream; (ii) a 128-
                                                    c. Date filed: December 29, 2015.                     for filing and is now ready for                       foot-long five-bay stoplog sluice; (iii) a
                                                    d. Applicant: Hawks Nest Hydro, LLC                   environmental analysis.                               2,132-foot-long right spillway that runs
                                                  (Hawks Nest Hydro).                                        l. The existing project works consist of           diagonally in a downstream direction;
                                                    e. Name of Project: Hawks Nest and                    the following:                                        (iv) a trash sluice section; (v) a 54-foot-
                                                  Glen Ferris Hydroelectric Projects.                        The existing Hawks Nest                            long by 38-foot-wide east powerhouse
                                                    f. Location: The existing Hawks Nest                  Hydroelectric Project consists of: (1) A              with a 62-foot-wide intake structure;
                                                  and Glen Ferris projects are located on                 948-foot-long concrete-gravity dam with               and (vi) a 64.5-foot-long by 63-foot-wide
                                                  the New and Kanawha rivers,                             a crest elevation of 795.0 feet National              west powerhouse with an 82.3-foot-
                                                  respectively. Both projects are located in              Geodetic Vertical Datum of 1929                       wide intake structure, with both
                                                  Fayette County, West Virginia. The                      (NGVD29); (2) 14 ogee-type spillway                   powerhouses integral to the dam; (2) a
                                                  projects do not occupy any federal                      bays extending almost the entire length               190-acre reservoir with a gross storage
                                                  lands.                                                  of the dam, each with a 25-foot-high by               capacity of approximately 1,500 acre-
                                                    g. Filed Pursuant to: Federal Power                   50-foot-wide Stoney-type steel lift gate              feet at the dam crest elevation of 651.0
                                                  Act 16 U.S.C. 791(a)–825(r).                            and separated by a 9-foot-wide concrete               feet NGVD29; (3) two turbine-generator
                                                    h. Applicant Contact: Steven Murphy,                  pier; (3) a 243-acre reservoir with a gross           units in the east powerhouse, each with
                                                  Manager, Licensing, Brookfield                          storage capacity of 7,323 acre-feet at a              a rated capacity of approximately 1.9
                                                  Renewable Energy Group, 33 West 1st                     normal pool elevation of 819.9 feet                   MW; (4) six turbine-generator units in
                                                  Street South, Fulton, New York 13069;                   NGVD29; (4) an intake structure located               the west powerhouse, each with a rated
                                                  Telephone (315) 598–6130.                               at the right shoreline (looking                       capacity of approximately 0.4 MW; (5)
                                                    i. FERC Contact: Monir Chowdhury,                     downstream) of the reservoir just                     a 4-mile-long, 13.8-kV transmission line;
                                                  (202) 502–6736, or monir.chowdhury@                     upstream of the dam and consisting of                 and (6) appurtenant facilities.
                                                  ferc.gov.                                               a 110-foot-wide by 50-foot-high                          The Glen Ferris Hydroelectric Project
                                                    j. Deadline for filing motions to                     trashrack structure and a Stoney-type                 is currently operated in a run-of-river
                                                  intervene and protests, comments,                       42-foot-high by 50-foot-wide bulkhead                 mode with no usable storage capacity.
                                                  recommendations, preliminary terms                      intake gate that sits back approximately              Hawks Nest Hydro proposes to continue
                                                  and conditions, and preliminary                         50 feet from the opening where the                    run-of-river operation. The project
                                                  prescriptions: 60 days from the issuance                trashrack is located; (5) a 16,240-foot-              generates an annual average of 41,482
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  date of this notice; reply comments are                 long tunnel that runs along the right                 megawatt-hours.
                                                  due 105 days from the issuance date of                  side of the river to convey water from                   m. A copy of the application is
                                                  this notice.                                            the intake to the powerhouse                          available for review at the Commission
                                                    The Commission strongly encourages                    downstream on the New River; (6) a                    in the Public Reference Room or may be
                                                  electronic filing. Please file motions to               600-foot-long by 170-foot-wide surge                  viewed on the Commission’s Web site at
                                                  intervene, protests, comments,                          basin located at a point on the tunnel                http://www.ferc.gov using the
                                                  recommendations, preliminary terms                      approximately 60 percent of the                       ‘‘eLibrary’’ link. Enter the docket
                                                  and conditions, and preliminary                         distance from the intake to the                       number excluding the last three digits in


                                             VerDate Sep<11>2014   17:54 Apr 15, 2016   Jkt 238001   PO 00000   Frm 00021   Fmt 4703   Sfmt 4703   E:\FR\FM\18APN1.SGM   18APN1


                                                  22588                                    Federal Register / Vol. 81, No. 74 / Monday, April 18, 2016 / Notices

                                                  the docket number field to access the                                   Rules may become a party to the                                         and conditions or prescriptions must set
                                                  document. For assistance, contact FERC                                  proceeding. Any comments, protests, or                                  forth their evidentiary basis and
                                                  Online Support. A copy is also available                                motions to intervene must be received                                   otherwise comply with the requirements
                                                  for inspection and reproduction at the                                  on or before the specified comment date                                 of 18 CFR 4.34(b). Agencies may obtain
                                                  address in item h above.                                                for the particular application.                                         copies of the application directly from
                                                    Register online at http://                                               All filings must (1) bear in all capital                             the applicant. A copy of any protest or
                                                  www.ferc.gov/docs-filing/                                               letters the title ‘‘PROTEST,’’ ‘‘MOTION                                 motion to intervene must be served
                                                  esubscription.asp to be notified via                                    TO INTERVENE,’’ ‘‘COMMENTS,’’                                           upon each representative of the
                                                  email of new filings and issuances                                      ‘‘REPLY COMMENTS,’’                                                     applicant specified in the particular
                                                  related to this or other pending projects.                              ‘‘RECOMMENDATIONS,’’                                                    application. A copy of all other filings
                                                  For assistance, contact FERC Online                                     ‘‘PRELIMINARY TERMS AND                                                 in reference to this application must be
                                                  Support.                                                                CONDITIONS,’’ or ‘‘PRELIMINARY                                          accompanied by proof of service on all
                                                    n. Anyone may submit comments, a                                      FISHWAY PRESCRIPTIONS;’’ (2) set                                        persons listed in the service list
                                                  protest, or a motion to intervene in                                    forth in the heading the name of the                                    prepared by the Commission in this
                                                  accordance with the requirements of                                     applicant and the project number of the                                 proceeding, in accordance with 18 CFR
                                                  Rules of Practice and Procedure, 18 CFR                                 application to which the filing                                         4.34(b) and 385.2010.
                                                  385.210, .211, and .214. In determining                                 responds; (3) furnish the name, address,                                  o. Procedural Schedule:
                                                  the appropriate action to take, the                                     and telephone number of the person                                        The application will be processed
                                                  Commission will consider all protests or                                protesting or intervening; and (4)                                      according to the following revised
                                                  other comments filed, but only those                                    otherwise comply with the requirements                                  Hydro Licensing Schedule. Revisions to
                                                  who file a motion to intervene in                                       of 18 CFR 385.2001 through 385.2005.                                    the schedule may be made as
                                                  accordance with the Commission’s                                        All comments, recommendations, terms                                    appropriate.

                                                                                                                                       Milestone                                                                                                Target date

                                                  Filing of recommendations, preliminary terms and conditions, and preliminary fishway prescriptions ...........................................                                              June 2016.
                                                  Commission Issues Draft EA ............................................................................................................................................................     December 2016.
                                                  Comments on Draft EA ....................................................................................................................................................................   January 2017.
                                                  Modified Terms and Conditions ........................................................................................................................................................      March 2017.
                                                  Commission Issues Final EA ............................................................................................................................................................     June 2017.



                                                     p. Final amendments to the                                           for a preliminary permit, pursuant to                                   Beach, FL 33139; phone: (954) 248–
                                                  application must be filed with the                                      section 4(f) of the Federal Power Act                                   5425.
                                                  Commission no later than 30 days from                                   (FPA), proposing to study the feasibility                                  FERC Contact: Woohee Choi; phone:
                                                  the issuance date of this notice.                                       of the Bosher Dam Hydroelectric Project                                 (202) 502–6336.
                                                     q. A license applicant must file no                                  (Bosher Project or project) to be located                                  Deadline for filing comments, motions
                                                  later than 60 days following the date of                                at the existing Bosher Dam on the James                                 to intervene, competing applications
                                                  issuance of the notice of acceptance and                                River, about 2 miles southwest of                                       (without notices of intent), or notices of
                                                  ready for environmental analysis                                        Tuckahoe, in Henrico County, Virginia.                                  intent to file competing applications: 60
                                                  provided for in 5.22: (1) A copy of the                                 The sole purpose of a preliminary                                       days from the issuance of this notice.
                                                  water quality certification; (2) a copy of                              permit, if issued, is to grant the permit                               Competing applications and notices of
                                                  the request for certification, including                                holder priority to file a license                                       intent must meet the requirements of 18
                                                  proof of the date on which the certifying                               application during the permit term. A                                   CFR 4.36.
                                                  agency received the request; or (3)                                     preliminary permit does not authorize                                      The Commission strongly encourages
                                                  evidence of waiver of water quality                                     the permit holder to perform any land-                                  electronic filing. Please file comments,
                                                  certification.                                                          disturbing activities or otherwise enter                                motions to intervene, notices of intent,
                                                                                                                          upon lands or waters owned by others                                    and competing applications using the
                                                    Dated: April 6, 2016.
                                                                                                                          without the owners’ express permission.                                 Commission’s eFiling system at http://
                                                  Kimberly D. Bose,                                                                                                                               www.ferc.gov/docs-filing/efiling.asp.
                                                  Secretary.                                                                 The proposed project would consist of                                Commenters can submit brief comments
                                                  [FR Doc. 2016–08858 Filed 4–15–16; 8:45 am]                             the following: (1) An existing 12-foot-                                 up to 6,000 characters, without prior
                                                  BILLING CODE 6717–01–P
                                                                                                                          high dam; (2) an 1,000-acre-size                                        registration, using the eComment system
                                                                                                                          impoundment with a storage capacity of                                  at http://www.ferc.gov/docs-filing/
                                                                                                                          2,100-acre-foot and drainage area of                                    ecomment.asp. You must include your
                                                  DEPARTMENT OF ENERGY                                                    6,753 square miles; (3) a new 700-foot-                                 name and contact information at the end
                                                                                                                          long, 180-foot-wide intake; (4) a new                                   of your comments. For assistance,
                                                  Federal Energy Regulatory                                               300-foot-long, 180-foot-wide tailrace; (5)                              please contact FERC Online Support at
                                                  Commission                                                              four new 2-megawatt (MW) turbines; (6)                                  FERCOnlineSupport@ferc.gov, (866)
                                                                                                                          a new 65-foot-long, 197-foot-wide                                       208–3676 (toll free), or (202) 502–8659
                                                  [Project No. 14758–000]                                                 powerhouse; (7) a new 60-foot-long, 50-                                 (TTY). In lieu of electronic filing, please
                                                                                                                          foot-wide substation; (8) a new 528-foot-
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Energy Resources USA Inc.; Notice of                                                                                                            send a paper copy to: Secretary, Federal
                                                                                                                          long, 69-kilovolt transmission line; and                                Energy Regulatory Commission, 888
                                                  Preliminary Permit Application
                                                                                                                          (9) appurtenant facilities. The estimated                               First Street NE., Washington, DC 20426.
                                                  Accepted for Filing and Soliciting
                                                                                                                          annual generation of the Bosher Project                                 The first page of any filing should
                                                  Comments, Motions To Intervene, and
                                                                                                                          would be 68,500 megawatt-hours.                                         include docket number P–14758–000.
                                                  Competing Applications
                                                                                                                             Applicant Contact: Mr. Ander                                            More information about this project,
                                                    On February 19, 2016, Energy                                          Gonzalez, Energy Resources USA Inc.,                                    including a copy of the application, can
                                                  Resources USA Inc. filed an application                                 350 Lincoln Road, 2nd Floor, Miami                                      be viewed or printed on the ‘‘eLibrary’’


                                             VerDate Sep<11>2014        17:54 Apr 15, 2016       Jkt 238001      PO 00000       Frm 00022       Fmt 4703      Sfmt 4703      E:\FR\FM\18APN1.SGM            18APN1



Document Created: 2016-04-16 01:46:12
Document Modified: 2016-04-16 01:46:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 22587 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR