81_FR_22663 81 FR 22589 - Wisconsin Public Service Corporation; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments

81 FR 22589 - Wisconsin Public Service Corporation; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 74 (April 18, 2016)

Page Range22589-22590
FR Document2016-08861

Federal Register, Volume 81 Issue 74 (Monday, April 18, 2016)
[Federal Register Volume 81, Number 74 (Monday, April 18, 2016)]
[Notices]
[Pages 22589-22590]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-08861]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1940-029]


Wisconsin Public Service Corporation; Notice of Application 
Tendered for Filing With the Commission and Establishing Procedural 
Schedule for Licensing and Deadline for Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: P-1940-029.
    c. Date filed: March 28, 2016.
    d. Applicant: Wisconsin Public Service Corporation.
    e. Name of Project: Tomahawk Hydroelectric Project.
    f. Location: The existing project is located on the Wisconsin River 
in

[[Page 22590]]

Lincoln County, Wisconsin. The project does not affect federal lands.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Todd P. Jastremski, Asset Manager Hydro 
Operations, WE Energies, 800 Industrial Park Drive, Iron Mountain, MI 
49801; or at (906) 779-4099.
    i. FERC Contact: Lee Emery at (202) 502-8379 or by email at 
[email protected].
    j. This application is not ready for environmental analysis at this 
time.
    k. The existing Tomahawk Hydroelectric Project consists of: (1) A 
27-foot-high, 3,400-foot-long reinforced concrete and embankment dam 
that includes a 2,450-foot-long left embankment section, a 300-foot-
long right embankment section, 9-foot-long sluice gate section, 267-
foot-long radial gate section, 160-foot-long slab and buttress section, 
and a 60-foot-long abutment section with a crest elevation of 1,441.0 
feet National Geodetic Vertical Datum (NGVD); (2) a 2,773-acre 
reservoir (Lake Mohawksin) at a full-pool elevation of 1,435.5 feet 
NGVD; (3) a 67-foot-long by 41-foot-wide powerhouse containing two 1.3-
megawatt (MW) generators providing a combined installed capacity of 2.6 
MW; (4) powerhouse intake trash racks with a 2.7-inch clear bar 
spacing; (5) two 2.4-kilovolt (kV) generator leads and an associated 
3.75-megavolt-ampere, 2.4/24.9-kV three phase transformer; (6) an 
interconnected substation located adjacent to the powerhouse; and (7) 
appurtenant facilities.
    The project is operated in a limited peaking mode, with maximum 
allowed daily reservoir fluctuations of approximately 0.8 feet (1,435.5 
feet NGVD to 1,434.7 feet NGVD). During normal peaking operations, the 
reservoir is drawn down from the maximum pond elevation during the day 
and refilled at night providing one peaking cycle per day. The amount 
of fluctuation is determined primarily by the volume of water which can 
normally be restored to the Tomahawk reservoir during off-peak hours. 
During low flow periods, the project is required to maintain a minimum 
flow of 162 cubic feet per second (cfs) or inflow, whichever is less. 
The operation of the Tomahawk Project is coordinated with the 
downstream WPS Projects (Grandfather Falls and Alexander Projects) and 
with the Grandmother Falls Project to make the most effective use of 
the available water resource.
    The normal tailwater elevation of the project is 1,419.5 feet NGVD. 
The impoundment provides about 14.5 feet of gross head for power 
generation purposes. The hydraulic capacity of the project is 2,634 cfs 
and water flowing through the turbines is discharged via the draft 
tubes into the tailrace immediately below the dam. Electricity 
generated from the project is transmitted from the powerhouse via two 
2.5-kV generator leads and a 3.75 MVA 2.4/24.9-kV three-phase 
transformer to the adjacent substation and into Wisconsin Public 
Service Corporation's distribution system. Wisconsin Public Service 
Corporation is proposing to continue current operations at the Project 
for the term of the new license.
    l. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
[email protected], (866) 208-3676 (toll free) or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at 
the address in item h above.
    m. You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Procedural schedule:
    The application will be processed according to the following 
preliminary Hydro Licensing Schedule. Revisions to the schedule may be 
made as appropriate.

------------------------------------------------------------------------
              Milestone                           Target date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready   June 2016.
 for Environmental Analysis.
Filing of recommendations,             August 2016.
 preliminary terms and conditions,
 and fishway prescriptions.
Issue Environmental Assessment (EA)..  December 2016.
Comments due on EA...................  January 2017.
Modified terms and conditions........  March 2017.
------------------------------------------------------------------------

    o. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: April 6, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-08861 Filed 4-15-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 81, No. 74 / Monday, April 18, 2016 / Notices                                                  22589

                                                  link of the Commission’s Web site at                    ready for environmental analysis,                        A copy of the EA may also be
                                                  http://www.ferc.gov/docs-filing/                        requesting comments,                                  accessed using this link: http://
                                                  elibrary.asp. Enter the docket number                   recommendations, terms and                            elibrary.ferc.gov/idmws/common/
                                                  (P–14758) in the docket number field to                 conditions, or prescriptions.                         OpenNat.asp?fileID=14010704.
                                                  access the document. For assistance,                      For further information, contact Alan                  You may also register online at http://
                                                  contact FERC Online Support.                            Mitchnick at (202) 502–6074.                          www.ferc.gov/docs-filing/
                                                    Dated: April 6, 2016.                                   Dated: April 6, 2016.                               esubsription.asp to be notified via email
                                                  Kimberly D. Bose,
                                                                                                                                                                of new filings and issuances related to
                                                                                                          Kimberly D. Bose,
                                                                                                                                                                this or other pending projects. For
                                                  Secretary.                                              Secretary.
                                                                                                                                                                assistance, contact FERC Online
                                                  [FR Doc. 2016–08860 Filed 4–15–16; 8:45 am]             [FR Doc. 2016–08857 Filed 4–15–16; 8:45 am]           Support.
                                                  BILLING CODE 6717–01–P                                  BILLING CODE 6717–01–P                                   All comments must be filed within 30
                                                                                                                                                                days of the date of this notice and
                                                                                                                                                                should reference Project No. 5891–009.
                                                  DEPARTMENT OF ENERGY                                    DEPARTMENT OF ENERGY                                  The Commission strongly encourages
                                                  Federal Energy Regulatory                                                                                     electronic filing. Please file comments
                                                                                                          Federal Energy Regulatory
                                                  Commission                                                                                                    using the Commission’s efiling system
                                                                                                          Commission
                                                                                                                                                                at http://www.ferc.gov/docs-filing/
                                                  [Project No. 2246–065]                                  [Project No. 5891–009]                                efiling.asp. Commenters can submit
                                                                                                                                                                brief comments up to 6,000 characters,
                                                  Yuba County Water Agency; Notice                        Deschutes Valley Water District; Notice               without prior registration, using the
                                                  Soliciting Comments on Final                            of Availability of Environmental                      eComment system at http://
                                                  Technical Memoranda                                     Assessment                                            www.ferc.gov/docs-filing/
                                                     On March 31, 2016, Yuba County                                                                             ecomment.asp. You must include your
                                                                                                             In accordance with the National
                                                  Water Agency, licensee for the Yuba                                                                           name and contact information at the end
                                                                                                          Environmental Policy Act of 1969 and
                                                  River Project, filed Technical                                                                                of your comments. For assistance,
                                                                                                          the Federal Energy Regulatory
                                                  Memoranda 7–11 and 7–11a, Fish                                                                                please contact FERC Online Support. In
                                                                                                          Commission’s (Commission)
                                                  Behavior and Hydraulics near Narrows                                                                          lieu of electronic filing, please send a
                                                                                                          regulations, 18 CFR part 380 (Order No.
                                                  2 Powerhouse and Radio Telemetry of                                                                           paper copy to: Kimberly D. Bose,
                                                                                                          486, 52 FR 47897), the Office of Energy
                                                  Spring- and Fall-Run Chinook Migratory                                                                        Secretary, Federal Energy Regulatory
                                                                                                          Projects has reviewed the Deschutes
                                                  Behavior Downstream of Narrows 2                                                                              Commission, 888 First Street NE.,
                                                                                                          Valley Water District’s (licensee)
                                                  Powerhouse.1 The memoranda were                                                                               Washington, DC 20426.
                                                                                                          application to amend the license in                      For further information, contact
                                                  required by studies approved by the
                                                                                                          order to construct and operate fish                   Jennifer Ambler at (202) 502–8586 or
                                                  Commission on September 30, 2011
                                                                                                          passage facilities at the Opal Springs                Jennifer.Ambler@ferc.gov.
                                                  (modified on December 28, 2011; April
                                                                                                          Hydroelectric Project No. 5891. The
                                                  12, 2012; and March 29, 2013) (Study                                                                            Dated: April 6, 2016.
                                                                                                          project is located on the Crooked River
                                                  11) and August 22, 2013 (Study 11a).                                                                          Kimberly D. Bose,
                                                                                                          in Jefferson County, Oregon. The project
                                                     The Commission is soliciting                                                                               Secretary.
                                                                                                          occupies federal lands administered by
                                                  comments on these memoranda. Any
                                                                                                          the U.S. Bureau of Land Management.                   [FR Doc. 2016–08859 Filed 4–15–16; 8:45 am]
                                                  comments should be filed within 30
                                                                                                             The application, filed with the                    BILLING CODE 6717–01–P
                                                  days from the date of this notice. The
                                                                                                          Commission on October 8, 2015,
                                                  Commission strongly encourages
                                                                                                          contains an Environmental Analysis in
                                                  electronic filing. Please file all                                                                            DEPARTMENT OF ENERGY
                                                                                                          its Exhibit E. After independent review
                                                  documents using the Commission’s
                                                                                                          of the licensee’s Exhibit E, Commission
                                                  eFiling system at http://www.ferc.gov/                                                                        Federal Energy Regulatory
                                                                                                          staff has decided to adopt the licensee’s
                                                  docs-filing/efiling.asp. Commenters can                                                                       Commission
                                                                                                          Environmental Analysis and issue it as
                                                  submit brief comments up to 6,000
                                                                                                          staff’s Environmental Assessment (EA).                [Project No. 1940–029]
                                                  characters, without prior registration,
                                                                                                          The EA analyzes the potential
                                                  using the eComment system at http://                                                                          Wisconsin Public Service Corporation;
                                                                                                          environmental impacts of construction
                                                  www.ferc.gov/docs-filing/                                                                                     Notice of Application Tendered for
                                                                                                          and operation of fish passage facilities
                                                  ecomment.asp. You must include your                                                                           Filing With the Commission and
                                                                                                          plus the proposed mitigation measures
                                                  name and contact information at the end                                                                       Establishing Procedural Schedule for
                                                                                                          and concludes that granting the
                                                  of your comments. For assistance,                                                                             Licensing and Deadline for
                                                                                                          proposed amendment would not
                                                  please contact FERC Online Support at                                                                         Submission of Final Amendments
                                                                                                          constitute a major federal action that
                                                  FERCOnlineSupport@ferc.gov. In lieu of
                                                                                                          would significantly affect the quality of               Take notice that the following
                                                  electronic filing, please send a paper
                                                                                                          the human environment.                                hydroelectric application has been filed
                                                  copy to: Secretary, Federal Energy
                                                                                                             A copy of the EA is on file with the
                                                  Regulatory Commission, 888 First Street                                                                       with the Commission and is available
                                                                                                          Commission and is available for public
                                                  NE., Washington, DC 20426. The first                                                                          for public inspection.
                                                                                                          inspection. The EA may be viewed on                     a. Type of Application: New Major
                                                  page of any filing should include docket
                                                                                                          the Commission’s Web site at http://                  License.
                                                  number P–2246–065.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                     Once the Commission has determined                   www.ferc.gov using the ‘‘eLibrary’’ link.               b. Project No.: P–1940–029.
                                                  that it has sufficient information to                   Enter the docket number (P–5891) in the                 c. Date filed: March 28, 2016.
                                                  process the license application, it will                docket number field to access the                       d. Applicant: Wisconsin Public
                                                  issue a notice that the application is                  document. For assistance, contact FERC                Service Corporation.
                                                                                                          Online Support at                                       e. Name of Project: Tomahawk
                                                    1 These technical memoranda can be viewed at          FERCOnlineSupport@ferc.gov or call                    Hydroelectric Project.
                                                  http://elibrary.ferc.gov/idmws/common/                  toll-free at 1–866–208–3676 or (202)                    f. Location: The existing project is
                                                  OpenNat.asp?fileID=14186240.                            502–8659 (for TTY).                                   located on the Wisconsin River in


                                             VerDate Sep<11>2014   17:54 Apr 15, 2016   Jkt 238001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\18APN1.SGM   18APN1


                                                  22590                                    Federal Register / Vol. 81, No. 74 / Monday, April 18, 2016 / Notices

                                                  Lincoln County, Wisconsin. The project                                  24.9-kV three phase transformer; (6) an                                 generated from the project is transmitted
                                                  does not affect federal lands.                                          interconnected substation located                                       from the powerhouse via two 2.5-kV
                                                     g. Filed Pursuant to: Federal Power                                  adjacent to the powerhouse; and (7)                                     generator leads and a 3.75 MVA 2.4/
                                                  Act 16 U.S.C. 791(a)–825(r).                                            appurtenant facilities.                                                 24.9-kV three-phase transformer to the
                                                     h. Applicant Contact: Todd P.                                           The project is operated in a limited                                 adjacent substation and into Wisconsin
                                                  Jastremski, Asset Manager Hydro                                         peaking mode, with maximum allowed                                      Public Service Corporation’s
                                                  Operations, WE Energies, 800 Industrial                                 daily reservoir fluctuations of                                         distribution system. Wisconsin Public
                                                  Park Drive, Iron Mountain, MI 49801; or                                 approximately 0.8 feet (1,435.5 feet                                    Service Corporation is proposing to
                                                  at (906) 779–4099.                                                      NGVD to 1,434.7 feet NGVD). During                                      continue current operations at the
                                                     i. FERC Contact: Lee Emery at (202)                                  normal peaking operations, the reservoir                                Project for the term of the new license.
                                                  502–8379 or by email at lee.emery@                                      is drawn down from the maximum pond                                        l. A copy of the application is
                                                  ferc.gov.                                                               elevation during the day and refilled at                                available for review at the Commission
                                                     j. This application is not ready for                                 night providing one peaking cycle per                                   in the Public Reference Room or may be
                                                  environmental analysis at this time.                                    day. The amount of fluctuation is                                       viewed on the Commission’s Web site at
                                                     k. The existing Tomahawk                                             determined primarily by the volume of                                   http://www.ferc.gov using the
                                                  Hydroelectric Project consists of: (1) A                                water which can normally be restored to                                 ‘‘eLibrary’’ link. Enter the docket
                                                  27-foot-high, 3,400-foot-long reinforced                                the Tomahawk reservoir during off-peak                                  number excluding the last three digits in
                                                  concrete and embankment dam that                                        hours. During low flow periods, the                                     the docket number field to access the
                                                  includes a 2,450-foot-long left                                         project is required to maintain a                                       document. For assistance, contact
                                                  embankment section, a 300-foot-long                                     minimum flow of 162 cubic feet per                                      FERCOnlineSupport@ferc.gov, (866)
                                                  right embankment section, 9-foot-long                                   second (cfs) or inflow, whichever is less.                              208–3676 (toll free) or (202) 502–8659
                                                  sluice gate section, 267-foot-long radial                               The operation of the Tomahawk Project                                   (TTY). A copy is also available for
                                                  gate section, 160-foot-long slab and                                    is coordinated with the downstream                                      inspection and reproduction at the
                                                  buttress section, and a 60-foot-long                                    WPS Projects (Grandfather Falls and                                     address in item h above.
                                                  abutment section with a crest elevation                                 Alexander Projects) and with the                                           m. You may also register online at
                                                  of 1,441.0 feet National Geodetic                                       Grandmother Falls Project to make the                                   http://www.ferc.gov/docs-filing/
                                                  Vertical Datum (NGVD); (2) a 2,773-acre                                 most effective use of the available water                               esubscription.asp to be notified via
                                                  reservoir (Lake Mohawksin) at a full-                                   resource.                                                               email of new filings and issuances
                                                  pool elevation of 1,435.5 feet NGVD; (3)                                   The normal tailwater elevation of the                                related to this or other pending projects.
                                                  a 67-foot-long by 41-foot-wide                                          project is 1,419.5 feet NGVD. The                                       For assistance, contact FERC Online
                                                  powerhouse containing two 1.3-                                          impoundment provides about 14.5 feet                                    Support.
                                                  megawatt (MW) generators providing a                                    of gross head for power generation                                         n. Procedural schedule:
                                                  combined installed capacity of 2.6 MW;                                  purposes. The hydraulic capacity of the                                    The application will be processed
                                                  (4) powerhouse intake trash racks with                                  project is 2,634 cfs and water flowing                                  according to the following preliminary
                                                  a 2.7-inch clear bar spacing; (5) two 2.4-                              through the turbines is discharged via                                  Hydro Licensing Schedule. Revisions to
                                                  kilovolt (kV) generator leads and an                                    the draft tubes into the tailrace                                       the schedule may be made as
                                                  associated 3.75-megavolt-ampere, 2.4/                                   immediately below the dam. Electricity                                  appropriate.

                                                                                                                                    Milestone                                                                                               Target date

                                                  Notice of Acceptance/Notice of Ready for Environmental Analysis ...........................................................................................                            June 2016.
                                                  Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ........................................................                                        August 2016.
                                                  Issue Environmental Assessment (EA) .......................................................................................................................................            December 2016.
                                                  Comments due on EA .................................................................................................................................................................   January 2017.
                                                  Modified terms and conditions ....................................................................................................................................................     March 2017.



                                                    o. Final amendments to the                                            DEPARTMENT OF ENERGY                                                    Dakota County, Minnesota. The
                                                  application must be filed with the                                                                                                              Commission will use this EA in its
                                                  Commission no later than 30 days from                                   Federal Energy Regulatory                                               decision-making process to determine
                                                  the issuance date of the notice of ready                                Commission                                                              whether the project is in the public
                                                  for environmental analysis.                                             [Docket No. PF15–33–000]                                                convenience and necessity.
                                                    Dated: April 6, 2016.                                                                                                                            This notice announces the opening of
                                                                                                                          Northern Natural Gas Company; Notice                                    the scoping process the Commission
                                                  Kimberly D. Bose,
                                                                                                                          of Intent To Prepare an Environmental                                   will use to gather input from the public
                                                  Secretary.                                                              Assessment for the Planned Northern                                     and interested agencies on the project.
                                                  [FR Doc. 2016–08861 Filed 4–15–16; 8:45 am]                             Lights 2017 Expansion Project,                                          You can make a difference by providing
                                                  BILLING CODE 6717–01–P                                                  Request for Comments on                                                 us with your specific comments or
                                                                                                                          Environmental Issues                                                    concerns about the project. Your
                                                                                                                            The staff of the Federal Energy                                       comments should focus on the potential
                                                                                                                                                                                                  environmental effects, reasonable
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                          Regulatory Commission (FERC or
                                                                                                                          Commission) will prepare an                                             alternatives, and measures to avoid or
                                                                                                                          environmental assessment (EA) that will                                 lessen environmental impacts. Your
                                                                                                                          discuss the environmental impacts of                                    input will help the Commission staff
                                                                                                                          the Northern Lights 2017 Expansion                                      determine what issues they need to
                                                                                                                          Project involving construction and                                      evaluate in the EA. To ensure that your
                                                                                                                          operation of facilities by Northern                                     comments are timely and properly
                                                                                                                          Natural Gas Company (Northern) in                                       recorded, please send your comments so


                                             VerDate Sep<11>2014        17:54 Apr 15, 2016       Jkt 238001      PO 00000       Frm 00024       Fmt 4703      Sfmt 4703      E:\FR\FM\18APN1.SGM            18APN1



Document Created: 2016-04-16 01:45:53
Document Modified: 2016-04-16 01:45:53
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 22589 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR