81_FR_23150 81 FR 23075 - Notice of Buy America Waiver for Steel Excavator With a Continuous Wield Platform

81 FR 23075 - Notice of Buy America Waiver for Steel Excavator With a Continuous Wield Platform

DEPARTMENT OF TRANSPORTATION
Federal Transit Administration

Federal Register Volume 81, Issue 75 (April 19, 2016)

Page Range23075-23076
FR Document2016-08978

In response to the request of Metro North Railroad (MNR) for a Buy America non-availability waiver for the procurement of a steel excavator with a continuous wield platform (CWP), the Federal Transit Administration (FTA) hereby waives its Buy America requirements, finding that the materials for which the waiver is requested are not produced in the United States in sufficient and reasonably available quantities and of satisfactory quality. This waiver is limited to a single procurement by MNR for the CWP.

Federal Register, Volume 81 Issue 75 (Tuesday, April 19, 2016)
[Federal Register Volume 81, Number 75 (Tuesday, April 19, 2016)]
[Notices]
[Pages 23075-23076]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-08978]


-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Transit Administration

[Docket No. FTA-2016-0006]


Notice of Buy America Waiver for Steel Excavator With a 
Continuous Wield Platform

AGENCY: Federal Transit Administration, DOT.

ACTION: Notice of Buy America waiver.

-----------------------------------------------------------------------

SUMMARY: In response to the request of Metro North Railroad (MNR) for a 
Buy America non-availability waiver for the procurement of a steel 
excavator with a continuous wield platform (CWP), the Federal Transit 
Administration (FTA) hereby waives its Buy America requirements, 
finding that the materials for which the waiver is requested are not 
produced in the United States in sufficient and reasonably available 
quantities and of satisfactory quality. This waiver is limited to a 
single procurement by MNR for the CWP.

DATES: This waiver is effective immediately.

FOR FURTHER INFORMATION CONTACT: Laura Ames, FTA Attorney-Advisor, at 
(202) 366-2743 or [email protected].

SUPPLEMENTARY INFORMATION: The purpose of this notice is to announce 
that FTA has granted a Buy America non-availability waiver for MNR for 
the procurement of a steel excavator with a CWP, under 49 U.S.C. 
5323(j)(2)(B) and 49 CFR 661.7(c).
    With certain exceptions, FTA's Buy America requirements prevent FTA 
from obligating an amount that may be appropriated to carry out its 
program for a project unless ``the steel, iron, and manufactured goods 
used in the project are produced in the United States.'' 49 U.S.C. 
5323(j)(1). Under 49 U.S.C. 5323(j)(2)(C), rolling stock must contain 
more than 60 percent domestic content and final assembly must occur in 
the U.S. The CWP is subject to the rolling stock requirements. 49 CFR 
661.3.
    MNR operates commuter rail service spanning 787 track miles. MRN 
has a large length of track along the shore line and flooding along the 
line can occur regularly at many of these locations. The risk of 
flooding can be reduced by keeping drainage infrastructure clear of 
debris. Specialized equipment such as the CWP can quickly clear the 
right of way after storms enabling the resumption of passenger train 
service. After Hurricane Sandy, MNR leased a CWP, but given limited 
availability, as well as the higher cost of leasing, MNR believes that 
purchase of the CWP is necessary to ensure that it will be

[[Page 23076]]

available to expedite service restoration and was provided funding to 
purchase such equipment from FTA through the emergency relief funds 
allocated for Superstorm Sandy.
    A CWP is a support vehicle train which consists of several 
platforms suitable for holding/hauling and picking up or distributing a 
variety of materials, such as rocks, riprap, dirt or debris. The 
equipment is similar to an excavator which has an articulated arm, with 
the main difference being that it rides on rails and sits on a 
connected platform where it can dump or pick up material from in order 
to perform its functions. The main tasks for which the MNR uses the CWP 
is shoreline stabilization/restoration and for removing debris from the 
right-of-way after storms.
    MNR prepared and advertised a solicitation for the CWP on January 
9, 2015. On February 5, 2015, BRRI, a Canadian firm, submitted a 
Certificate of Non-Compliance because the final assembly of the 
equipment would take place in Canada, although content of the material 
used would be 77% domestic origin.
    MNR did extensive follow-up after receiving only one bid, including 
contacting seven vendors who did not submit bids and undertaking 
research to determine whether a CWP that met both the domestic content 
and the final assembly requirements of Buy America was available. One 
company that did not submit a bid stated that although it could meet 
the Buy America requirements, it was not interested in bidding on the 
project at this time. Accordingly, MNR requested a non-availability 
waiver of the Buy America requirements for final assembly pursuant to 
49 U.S.C. 5323 (j)(2)(B).
    On March 22, 2016, and in accordance with 49 U.S.C. 5323(j)(3)(A), 
FTA published a notice in the Federal Register announcing the MNR Buy 
America waiver request (81 FR 15407), seeking comment from all 
interested parties, including potential vendors and suppliers. The 
comment period closed on March 29, 2016, and no comments were received. 
Based on the representations from MNR and the lack of any comments, FTA 
is granting a non-availability waiver for final assembly only of the 
CWP. This waiver is limited to the final assembly requirement for a 
single procurement of the CWP described above by MNR.

    Issued on April 14, 2016.
Dana Nifosi,
Deputy Chief Counsel.
[FR Doc. 2016-08978 Filed 4-18-16; 8:45 am]
 BILLING CODE 4910-57-P



                                                                                 Federal Register / Vol. 81, No. 75 / Tuesday, April 19, 2016 / Notices                                           23075

                                                  procurement of a Horizontal Lifeline                    Bros. Building Group (WBBG) in early                  DEPARTMENT OF TRANSPORTATION
                                                  Fall Protection Maintenance Tie Back                    September 2014 for the construction of
                                                  System (System), the Federal Transit                    the DTC. WBBG certified in good faith                 Federal Transit Administration
                                                  Administration (FTA) hereby waives its                  that it would comply with Buy America.                [Docket No. FTA–2016–0006]
                                                  Buy America requirements, finding that                  As part of the project, IPTC issued an
                                                  the materials for which the waiver is                   RFP for the complete design, supply,                  Notice of Buy America Waiver for Steel
                                                  requested are not produced in the                       and installation of a fall protection                 Excavator With a Continuous Wield
                                                  United States in sufficient and                         maintenance tie-back system to                        Platform
                                                  reasonably available quantities and of                  safeguard personnel to include all cable,
                                                  satisfactory quality. This waiver is                                                                          AGENCY:    Federal Transit Administration,
                                                                                                          intermediate brackets, end terminations,              DOT.
                                                  limited to a single procurement by IPTC                 and modifications of structural steel as
                                                  for the System.                                                                                               ACTION:   Notice of Buy America waiver.
                                                                                                          required for supplementary support of
                                                  DATES: This waiver is effective                         stanchions, user equipment, and                       SUMMARY:   In response to the request of
                                                  immediately.                                            attachment to roof structure for a                    Metro North Railroad (MNR) for a Buy
                                                  FOR FURTHER INFORMATION CONTACT:                        complete and working fall protection                  America non-availability waiver for the
                                                  Laura Ames, FTA Attorney-Advisor, at                    maintenance tie-back system.                          procurement of a steel excavator with a
                                                  (202) 366–2743 or Laura.Ames@dot.gov.                      Two firms, American Anchor and Pro-                continuous wield platform (CWP), the
                                                  SUPPLEMENTARY INFORMATION: The                          Bel Group, responded to the RFP, but                  Federal Transit Administration (FTA)
                                                  purpose of this notice is to announce                   did not certify compliance with the Buy               hereby waives its Buy America
                                                  that FTA has granted a Buy America                      America regulations. The cables and                   requirements, finding that the materials
                                                  non-availability waiver for IPTC for the                tensioning system are not manufactured                for which the waiver is requested are
                                                  procurement of a Horizontal Lifeline                    domestically for Pro-Bel. The hands-free              not produced in the United States in
                                                  Fall Protection Maintenance Tie Back                                                                          sufficient and reasonably available
                                                                                                          set ups are not manufactured
                                                  System under 49 U.S.C. 5323(j)(2)(B)                                                                          quantities and of satisfactory quality.
                                                                                                          domestically for American Anchor.
                                                  and 49 CFR 661.7(c).                                                                                          This waiver is limited to a single
                                                     With certain exceptions, FTA’s Buy                   IPTC submitted a waiver request based
                                                                                                          on non-availability under 49 CFR                      procurement by MNR for the CWP.
                                                  America requirements prevent FTA                                                                              DATES: This waiver is effective
                                                  from obligating an amount that may be                   661.7(c). FTA also conducted a scouting
                                                                                                          search for the fall arrest system through             immediately.
                                                  appropriated to carry out its program for
                                                  a project unless ‘‘the steel, iron, and                 its Interagency Agreement with the U.S.               FOR FURTHER INFORMATION CONTACT:
                                                  manufactured goods used in the project                  Department of Commerce’s National                     Laura Ames, FTA Attorney-Advisor, at
                                                  are produced in the United States.’’ 49                 Institute of Standards and Technology                 (202) 366–2743 or laura.ames@dot.gov.
                                                  U.S.C. 5323(j)(1). A manufactured                       (NIST). The scouting search did not                   SUPPLEMENTARY INFORMATION: The
                                                  product is considered produced in the                   identify a domestic manufacturer of a                 purpose of this notice is to announce
                                                  United States if: (1) All of the                        system that met IPTC’s specifications.                that FTA has granted a Buy America
                                                  manufacturing processes for the product                    On Tuesday March 22, 2016, and in                  non-availability waiver for MNR for the
                                                  take place in the United States; and (2)                accordance with 49 U.S.C. 5323(j)(3)(A),              procurement of a steel excavator with a
                                                  all of the components of the product are                FTA published a notice in the Federal                 CWP, under 49 U.S.C. 5323(j)(2)(B) and
                                                  of U.S. origin. A component is                          Register announcing the Buy America                   49 CFR 661.7(c).
                                                  considered of U.S. origin if it is                      waiver request (81 FR 15411), seeking                    With certain exceptions, FTA’s Buy
                                                  manufactured in the United States,                      comment from all interested parties,                  America requirements prevent FTA
                                                  regardless of the origin of its                         including potential vendors and                       from obligating an amount that may be
                                                  subcomponents. 49 CFR 661.5(d). If,                     suppliers. The comment period closed                  appropriated to carry out its program for
                                                  however, FTA determines that ‘‘the                      on March 29, 2016, and no comments                    a project unless ‘‘the steel, iron, and
                                                  steel, iron, and goods produced in the                  were received.                                        manufactured goods used in the project
                                                  United States are not produced in a                                                                           are produced in the United States.’’ 49
                                                  sufficient and reasonably available                        Therefore, based on the information                U.S.C. 5323(j)(1). Under 49 U.S.C.
                                                  amount or are not of a satisfactory                     supplied in support of IPTC’s request                 5323(j)(2)(C), rolling stock must contain
                                                  quality,’’ then FTA may issue a non-                    for a Buy America waiver for the                      more than 60 percent domestic content
                                                  availability waiver. 49 U.S.C.                          System, including NIST’s inability to                 and final assembly must occur in the
                                                  5323(j)(2)(B); 49 CFR 661.7(c). ‘‘It will               locate a domestic manufacturer that                   U.S. The CWP is subject to the rolling
                                                  be presumed that the conditions exist to                currently produces a similar system and               stock requirements. 49 CFR 661.3.
                                                  grant this non-availability waiver if no                the lack of any comments, FTA hereby                     MNR operates commuter rail service
                                                  responsive and responsible bid is                       waives its Buy America requirements                   spanning 787 track miles. MRN has a
                                                  received offering an item produced in                   for the Horizontal Lifeline Fall                      large length of track along the shore line
                                                  the United States.’’ 49 CFR 661.7(c)(1).                Protection Maintenance Tie Back                       and flooding along the line can occur
                                                     IPTC is constructing a Downtown                      System on the grounds that the                        regularly at many of these locations. The
                                                  Transit Center (DTC) in Indianapolis,                   manufactured product is not available                 risk of flooding can be reduced by
                                                  Indiana, that will serve as the hub for                 in the U.S. This waiver is limited to a               keeping drainage infrastructure clear of
                                                  public transit. It will include a large                 single procurement for the Horizontal                 debris. Specialized equipment such as
                                                                                                          Lifeline Fall Protection Maintenance Tie
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  indoor public waiting area and bus bays                                                                       the CWP can quickly clear the right of
                                                  while serving pedestrians, cyclists, and                Back System by IPTC.                                  way after storms enabling the
                                                  bus riders. Per Occupational Safety and                   Issued on April 14, 2016.                           resumption of passenger train service.
                                                  Health Administration (OSHA)                                                                                  After Hurricane Sandy, MNR leased a
                                                                                                          Dana Nifosi,
                                                  regulations, IPTC is required to provide                                                                      CWP, but given limited availability, as
                                                  fall protection for employees performing                Deputy Chief Counsel.                                 well as the higher cost of leasing, MNR
                                                  maintenance on the new building. IPTC                   [FR Doc. 2016–08990 Filed 4–18–16; 8:45 am]           believes that purchase of the CWP is
                                                  entered into a contract with Weddle                     BILLING CODE 4910–57–P                                necessary to ensure that it will be


                                             VerDate Sep<11>2014   18:02 Apr 18, 2016   Jkt 238001   PO 00000   Frm 00112   Fmt 4703   Sfmt 4703   E:\FR\FM\19APN1.SGM   19APN1


                                                  23076                          Federal Register / Vol. 81, No. 75 / Tuesday, April 19, 2016 / Notices

                                                  available to expedite service restoration               DEPARTMENT OF TRANSPORTATION                          City, Missouri, metropolitan area,
                                                  and was provided funding to purchase                                                                          operating in seven counties. KCATA’s
                                                  such equipment from FTA through the                     Federal Transit Administration                        current radio system was purchased in
                                                  emergency relief funds allocated for                    [Docket No. FTA–2016–0002]                            2002 and fully activated in 2005. The
                                                  Superstorm Sandy.                                                                                             radio system is analog and operates on
                                                     A CWP is a support vehicle train                     Notice of Buy America Waiver for a                    two separate channels. It has limited
                                                  which consists of several platforms                     Radio Communications System                           growth capabilities, issues with ‘‘talk
                                                  suitable for holding/hauling and picking                                                                      over,’’ inaccessible voice connections,
                                                  up or distributing a variety of materials,              AGENCY:    Federal Transit Administration,            and escalating maintenance costs.
                                                  such as rocks, riprap, dirt or debris. The              DOT.                                                  KCATA is in the process of upgrading
                                                  equipment is similar to an excavator                    ACTION:   Notice of Buy America waiver.               its radio system.
                                                  which has an articulated arm, with the                                                                           As part of its plan to upgrade the
                                                                                                          SUMMARY:   In response to the request of              radio system, KCATA issued a Request
                                                  main difference being that it rides on                  the Kansas City Area Transportation
                                                  rails and sits on a connected platform                                                                        for Proposals (RFP) on December 16,
                                                                                                          Authority (KCATA) for a Buy America                   2014, seeking a ‘‘turnkey project that
                                                  where it can dump or pick up material                   waiver for a DMR Tier III Trunked UHF
                                                  from in order to perform its functions.                                                                       includes a DMR Tier III Trunked UHF
                                                                                                          Voice radio system that is compatible                 Voice radio system, full integration of
                                                  The main tasks for which the MNR uses                   with its current system, the Federal
                                                  the CWP is shoreline stabilization/                                                                           the radio system with the Trapeze
                                                                                                          Transit Administration (FTA) hereby                   TransitMaster CAD/AVL system, and
                                                  restoration and for removing debris from                waives its Buy America requirements
                                                  the right-of-way after storms.                                                                                extended maintenance and support.’’
                                                                                                          finding that the materials for which a                KCATA only received one response to
                                                     MNR prepared and advertised a                        waiver is requested are not produced in               the RFP. Tait North America (Tait)
                                                  solicitation for the CWP on January 9,                  the United States in sufficient and                   expressed interest in the project but
                                                  2015. On February 5, 2015, BRRI, a                      reasonably available quantities and of a              noted that it is headquartered in New
                                                  Canadian firm, submitted a Certificate of               satisfactory quality. This waiver is                  Zealand and that a majority of the
                                                  Non-Compliance because the final                        limited to a single procurement by                    products supplied for the project would
                                                  assembly of the equipment would take                    KCATA for the DMR Tier III Trunked                    be assembled in New Zealand, making
                                                  place in Canada, although content of the                UHF Voice radio system.                               them non-compliant with Buy America.
                                                  material used would be 77% domestic                                                                              Neither KCATA nor FTA has
                                                                                                          DATES: This waiver is effective
                                                  origin.                                                                                                       identified any companies in the United
                                                                                                          immediately.
                                                     MNR did extensive follow-up after                                                                          States that can meet the Buy America
                                                  receiving only one bid, including                       FOR FURTHER INFORMATION CONTACT:
                                                                                                                                                                requirements for this project. FTA also
                                                  contacting seven vendors who did not                    Laura Ames, FTA Attorney-Advisor, at                  conducted a scouting search for a U.S.
                                                  submit bids and undertaking research to                 (202) 366–2743 or laura.ames@dot.gov.                 manufacturer of a comparable radio
                                                  determine whether a CWP that met both                   SUPPLEMENTARY INFORMATION: The                        system through its Interagency
                                                  the domestic content and the final                      purpose of this notice is to announce                 Agreement with the U.S. Department of
                                                  assembly requirements of Buy America                    that FTA has granted a Buy America                    Commerce’s National Institute of
                                                  was available. One company that did                     non-availability waiver for KCATA’s                   Standards and Technology (NIST). The
                                                  not submit a bid stated that although it                procurement of a DMR Tier III Trunked                 scouting search did not result in
                                                  could meet the Buy America                              UHF radio system under 49 U.S.C.                      identifying any domestic manufacturers
                                                  requirements, it was not interested in                  5323(j)(2)(B) and 49 CFR 661.7(c).                    who could provide the equipment
                                                  bidding on the project at this time.                       With certain exceptions, FTA’s Buy                 required by KCATA.
                                                  Accordingly, MNR requested a non-                       America requirements prevent FTA                         On Wednesday, March 22, 2016, and
                                                  availability waiver of the Buy America                  from obligating an amount that may be                 in accordance with 49 U.S.C.
                                                  requirements for final assembly                         appropriated to carry out its program for             5323(j)(3)(A), FTA published a notice in
                                                  pursuant to 49 U.S.C. 5323 (j)(2)(B).                   a project unless ‘‘the steel, iron, and               the Federal Register (81 FR 15410)
                                                     On March 22, 2016, and in                            manufactured goods used in the project                requesting public comment on, among
                                                  accordance with 49 U.S.C. 5323(j)(3)(A),                are produced in the United States.’’ 49               other topics, the merits of KCATA’s
                                                  FTA published a notice in the Federal                   U.S.C. 5323(j)(1). A manufactured                     waiver request and potential effects of
                                                  Register announcing the MNR Buy                         product is considered produced in the                 granting the waiver. The public
                                                  America waiver request (81 FR 15407),                   United States if: (1) All of the                      comment period closed on March 29,
                                                  seeking comment from all interested                     manufacturing processes for the product               2016. FTA received only once comment.
                                                  parties, including potential vendors and                take place in the United States; and (2)                 Selex ES, a subsidiary of an Italian
                                                  suppliers. The comment period closed                    all of the components of the product are              company with its North America
                                                  on March 29, 2016, and no comments                      of U.S. origin. A component is                        headquarters in Overland Park, Kansas,
                                                  were received. Based on the                             considered of U.S. origin if it is                    commented that although it did not
                                                  representations from MNR and the lack                   manufactured in the United States,                    submit a proposal to KCATA’s RFP, it
                                                  of any comments, FTA is granting a                      regardless of the origin of its                       can supply a DMR Tier III Trunked
                                                  non-availability waiver for final                       subcomponents. 49 CFR 661.5(d). If,                   Radio Systems similar to the system
                                                  assembly only of the CWP. This waiver                   however, FTA determines that ‘‘the                    proposed by Tait, arguing that Selex ES
                                                  is limited to the final assembly                        steel, iron, and goods produced in the                is a ‘‘local’’ option for KCATA.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  requirement for a single procurement of                 United States are not produced in a                   Although Selex ES markets, designs,
                                                  the CWP described above by MNR.                         sufficient and reasonably available                   stages, ships, and services DMR Tier III
                                                                                                          amount or are not of a satisfactory                   Trunked Radio Systems and is based in
                                                    Issued on April 14, 2016.                                                                                   Kansas, Selex ES does not provide a
                                                                                                          quality,’’ then FTA may issue a non-
                                                  Dana Nifosi,                                            availability waiver. 49 U.S.C.                        system that is compliant with FTA’s
                                                  Deputy Chief Counsel.                                   5323(j)(2)(B); 49 CFR 661.7(c).                       Buy America requirement for
                                                  [FR Doc. 2016–08978 Filed 4–18–16; 8:45 am]                KCATA provides public                              manufactured goods. As noted above,
                                                  BILLING CODE 4910–57–P                                  transportation services in the Kansas                 Buy America applies to manufactured


                                             VerDate Sep<11>2014   18:02 Apr 18, 2016   Jkt 238001   PO 00000   Frm 00113   Fmt 4703   Sfmt 4703   E:\FR\FM\19APN1.SGM   19APN1



Document Created: 2016-04-19 00:15:49
Document Modified: 2016-04-19 00:15:49
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of Buy America waiver.
DatesThis waiver is effective immediately.
ContactLaura Ames, FTA Attorney-Advisor, at (202) 366-2743 or [email protected]
FR Citation81 FR 23075 