The U.S. Department of Energy (DOE) is publishing Guidance for the Energy Policy Act of 2005 Section 242 program. The guidance describes the hydroelectric incentive payment requirements and explains the type of information that owners or authorized operators of qualified hydroelectric facilities can provide DOE when applying for hydroelectric incentive payments. This incentive is available for electric energy generated and sold for a specified 10-year period as authorized under section 242 of the Energy Policy Act of 2005. In Congressional appropriations for Federal fiscal year 2016, DOE received funds to support this hydroelectric incentive program. At this time, DOE is only accepting applications from owners and authorized operators of qualified hydroelectric facilities for hydroelectricity generated and sold in calendar year 2015.

Federal Register, Volume 81 Issue 80 (Tuesday, April 26, 2016)
[Federal Register Volume 81, Number 80 (Tuesday, April 26, 2016)]
[Notices]
[Pages 24591-24592]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-09700]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Office of Energy Efficiency and Renewable Energy


Guidance and Application for Hydroelectric Incentive Payments

AGENCY: Wind and Water Power Program, Office of Energy Efficiency and 
Renewable Energy, Department of Energy.

ACTION: Notice of availability of guidance and open application period.

-----------------------------------------------------------------------

SUMMARY: The U.S. Department of Energy (DOE) is publishing Guidance for 
the Energy Policy Act of 2005 Section 242 program. The guidance 
describes the hydroelectric incentive payment requirements and explains 
the type of information that owners or authorized operators of 
qualified hydroelectric facilities can provide DOE when applying for 
hydroelectric incentive payments. This incentive is available for 
electric energy generated and sold for a specified 10-year period as 
authorized under section 242 of the Energy Policy Act of 2005. In 
Congressional appropriations for Federal fiscal year 2016, DOE received 
funds to support this hydroelectric incentive program. At this time, 
DOE is only accepting applications from owners and authorized operators 
of qualified hydroelectric facilities for hydroelectricity generated 
and sold in calendar year 2015.

DATES: DOE is currently accepting applications from April 26, 2016 
through May 31, 2016 Applications must be sent to 
[email protected] by midnight EDT, May 31, 2016, or they will 
not be considered timely filed for calendar year 2015 incentive 
payments.

ADDRESSES: DOE's guidance is available at: http://energy.gov/eere/water/downloads/2014-electrical-production-epact-2005-section-242-hydroelectric-incentive. Written correspondence may be sent to the 
Office of Energy Efficiency and Renewable Energy (EE-4W), by email at 
[email protected].

FOR FURTHER INFORMATION CONTACT: Requests for additional information 
should be directed to Mr. Timothy Welch, Office of Energy Efficiency 
and Renewable Energy (EE-4W), U.S. Department of Energy, 1000 
Independence Avenue SW., Washington, DC 20585-0121, (202) 586-7055, 
[email protected]. Electronic communications are recommended 
for correspondence and required for submission of application 
information.

SUPPLEMENTARY INFORMATION: In the Energy Policy Act of 2005 (EPAct 
2005; Pub. L. 109-58), Congress established a new program to support 
the expansion of hydropower energy development at existing dams and 
impoundments through an incentive payment procedure. Under section 242 
of EPAct 2005, the Secretary of Energy is directed to provide incentive 
payments to the owner or authorized operator of qualified hydroelectric 
facilities for electric energy generated and sold by a qualified 
hydroelectric facility for a specified 10-year period (See 42 U.S.C. 
15881). The Consolidated Appropriations Act, 2016 authorized funding 
for the Section 242 program for conventional hydropower under EPAct 
2005. In FY 2016 DOE allocated $3.5M for this purpose.
    DOE finalized its Guidance for the Energy Policy Act of 2005 
Section 242 program in December 2015. The final guidance is available 
at: http://energy.gov/eere/water/water-power-program. Each application 
will be reviewed based on the Guidance. DOE notes that applicants that 
received payments for calendar year 2014 and that are eligible for 
calendar year 2015 payments must still submit a full calendar year 2015 
application. As authorized under section 242 of EPACT 2005, and as 
explained in the Guidance, DOE also notes that it will only accept 
applications from qualified hydroelectric facilities that began 
operations at an existing dam or conduit during the inclusive period 
beginning October 1, 2005 and ending on September 30, 2015. Therefore, 
although DOE is accepting applications for full calendar year 2015 
production, the qualified hydroelectric facility must have begun 
operations starting October 1, 2005 through September 30, 2015 for DOE 
to consider the application.
    When submitting information to DOE for the Section 242 program, it 
is recommended that applicants carefully read and review the complete 
content of the Guidance for this process. When reviewing applications, 
DOE may corroborate the information provided with information that DOE 
finds through FERC e-filings, contact with power off-taker, and other 
due diligence measures carried out by reviewing

[[Page 24592]]

officials. DOE may require the applicant to conduct and submit an 
independent audit at its own expense, or DOE may conduct an audit to 
verify the number of kilowatt-hours claimed to have been generated and 
sold by the qualified hydroelectric facility and for which an incentive 
payment has been requested or made.

    Issued in Washington, DC, on April 21, 2016.
Roland Risser,
Deputy Assistant Secretary for Renewable Power, Energy Efficiency and 
Renewable Energy.
[FR Doc. 2016-09700 Filed 4-25-16; 8:45 am]
BILLING CODE 6450-01-P



                                                                                 Federal Register / Vol. 81, No. 80 / Tuesday, April 26, 2016 / Notices                                          24591

                                                     Include contact information each time                  Issued in Washington, DC, on April 21,              Renewable Energy (EE–4W), U.S.
                                                  you submit comments, data, documents,                   2016.                                                 Department of Energy, 1000
                                                  and other information to DOE. If you                    April Salas,                                          Independence Avenue SW.,
                                                  submit via mail or hand delivery/                       QER Secretariat Director, Quadrennial Energy          Washington, DC 20585–0121, (202) 586–
                                                  courier, please provide all items on a                  Review Task Force, U.S. Department of                 7055, hydroincentive@ee.doe.gov.
                                                  CD, if feasible, in which case it is not                Energy.                                               Electronic communications are
                                                  necessary to submit printed copies. No                  [FR Doc. 2016–09689 Filed 4–25–16; 8:45 am]           recommended for correspondence and
                                                  telefacsimiles (faxes) will be accepted.                BILLING CODE 6450–01–P                                required for submission of application
                                                     Comments, data, and other                                                                                  information.
                                                  information submitted to DOE                                                                                  SUPPLEMENTARY INFORMATION: In the
                                                                                                          DEPARTMENT OF ENERGY
                                                  electronically should be provided in                                                                          Energy Policy Act of 2005 (EPAct 2005;
                                                  PDF (preferred), Microsoft Word or                      Office of Energy Efficiency and                       Pub. L. 109–58), Congress established a
                                                  Excel, WordPerfect, or text (ASCII) file                Renewable Energy                                      new program to support the expansion
                                                  format. Provide documents that are not                                                                        of hydropower energy development at
                                                  secured, written in English, and are free               Guidance and Application for                          existing dams and impoundments
                                                  of any defects or viruses. Documents                    Hydroelectric Incentive Payments                      through an incentive payment
                                                  should not contain special characters or                                                                      procedure. Under section 242 of EPAct
                                                                                                          AGENCY: Wind and Water Power                          2005, the Secretary of Energy is directed
                                                  any form of encryption and, if possible,
                                                                                                          Program, Office of Energy Efficiency and              to provide incentive payments to the
                                                  they should carry the electronic
                                                                                                          Renewable Energy, Department of                       owner or authorized operator of
                                                  signature of the author.
                                                                                                          Energy.                                               qualified hydroelectric facilities for
                                                     Confidential Business Information.                   ACTION: Notice of availability of                     electric energy generated and sold by a
                                                  Pursuant to 10 CFR 1004.11, any person                  guidance and open application period.                 qualified hydroelectric facility for a
                                                  submitting information that he or she
                                                                                                                                                                specified 10-year period (See 42 U.S.C.
                                                  believes to be confidential and exempt                  SUMMARY:    The U.S. Department of
                                                                                                                                                                15881). The Consolidated
                                                  by law from public disclosure should                    Energy (DOE) is publishing Guidance
                                                                                                                                                                Appropriations Act, 2016 authorized
                                                  submit via email, postal mail, or hand                  for the Energy Policy Act of 2005
                                                                                                                                                                funding for the Section 242 program for
                                                  delivery/courier two well-marked                        Section 242 program. The guidance
                                                                                                                                                                conventional hydropower under EPAct
                                                  copies: One copy of the document                        describes the hydroelectric incentive
                                                                                                                                                                2005. In FY 2016 DOE allocated $3.5M
                                                  marked ‘‘confidential’’ including all the               payment requirements and explains the
                                                                                                                                                                for this purpose.
                                                  information believed to be confidential,                type of information that owners or
                                                                                                                                                                   DOE finalized its Guidance for the
                                                  and one copy of the document marked                     authorized operators of qualified
                                                                                                                                                                Energy Policy Act of 2005 Section 242
                                                  ‘‘non-confidential’’ with the information               hydroelectric facilities can provide DOE
                                                                                                                                                                program in December 2015. The final
                                                  believed to be confidential deleted.                    when applying for hydroelectric
                                                                                                                                                                guidance is available at: http://
                                                  Submit these documents via email or on                  incentive payments. This incentive is
                                                                                                                                                                energy.gov/eere/water/water-power-
                                                  a CD, if feasible. DOE will make its own                available for electric energy generated
                                                                                                                                                                program. Each application will be
                                                  determination about the confidential                    and sold for a specified 10-year period
                                                                                                                                                                reviewed based on the Guidance. DOE
                                                  status of the information and treat it                  as authorized under section 242 of the
                                                                                                                                                                notes that applicants that received
                                                  according to its determination.                         Energy Policy Act of 2005. In
                                                                                                                                                                payments for calendar year 2014 and
                                                  Confidential information should be                      Congressional appropriations for
                                                                                                                                                                that are eligible for calendar year 2015
                                                  submitted to the Confidential QER email                 Federal fiscal year 2016, DOE received
                                                                                                                                                                payments must still submit a full
                                                  address: QERConfidential@hq.doe.gov.                    funds to support this hydroelectric
                                                                                                                                                                calendar year 2015 application. As
                                                     Factors of interest to DOE when                      incentive program. At this time, DOE is
                                                                                                                                                                authorized under section 242 of EPACT
                                                  evaluating requests to treat submitted                  only accepting applications from
                                                                                                                                                                2005, and as explained in the Guidance,
                                                  information as confidential include: (1)                owners and authorized operators of
                                                                                                                                                                DOE also notes that it will only accept
                                                  A description of the items; (2) whether                 qualified hydroelectric facilities for
                                                                                                                                                                applications from qualified
                                                  and why such items are customarily                      hydroelectricity generated and sold in
                                                                                                                                                                hydroelectric facilities that began
                                                  treated as confidential within the                      calendar year 2015.
                                                                                                                                                                operations at an existing dam or conduit
                                                  industry; (3) whether the information is                DATES: DOE is currently accepting                     during the inclusive period beginning
                                                  generally known by or available from                    applications from April 26, 2016                      October 1, 2005 and ending on
                                                  other sources; (4) whether the                          through May 31, 2016 Applications                     September 30, 2015. Therefore, although
                                                  information has previously been made                    must be sent to hydroincentive@                       DOE is accepting applications for full
                                                  available to others without obligation                  ee.doe.gov by midnight EDT, May 31,                   calendar year 2015 production, the
                                                  concerning its confidentiality; (5) an                  2016, or they will not be considered                  qualified hydroelectric facility must
                                                  explanation of the competitive injury to                timely filed for calendar year 2015                   have begun operations starting October
                                                  the submitting person which would                       incentive payments.                                   1, 2005 through September 30, 2015 for
                                                  result from public disclosure; (6) when                 ADDRESSES: DOE’s guidance is available                DOE to consider the application.
                                                  such information might lose its                         at: http://energy.gov/eere/water/                        When submitting information to DOE
                                                  confidential character due to the                       downloads/2014-electrical-production-                 for the Section 242 program, it is
                                                  passage of time; and (7) why disclosure                 epact-2005-section-242-hydroelectric-                 recommended that applicants carefully
                                                                                                          incentive. Written correspondence may
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  of the information would be contrary to                                                                       read and review the complete content of
                                                  the public interest. It is DOE’s policy                 be sent to the Office of Energy Efficiency            the Guidance for this process. When
                                                  that all comments may be included in                    and Renewable Energy (EE–4W), by                      reviewing applications, DOE may
                                                  the public docket, without change and                   email at hydroincentive@ee.doe.gov.                   corroborate the information provided
                                                  as received, including any personal                     FOR FURTHER INFORMATION CONTACT:                      with information that DOE finds
                                                  information provided in the comments                    Requests for additional information                   through FERC e-filings, contact with
                                                  (except information deemed to be                        should be directed to Mr. Timothy                     power off-taker, and other due diligence
                                                  exempt from public disclosure).                         Welch, Office of Energy Efficiency and                measures carried out by reviewing


                                             VerDate Sep<11>2014   22:08 Apr 25, 2016   Jkt 238001   PO 00000   Frm 00038   Fmt 4703   Sfmt 4703   E:\FR\FM\26APN1.SGM   26APN1


                                                  24592                          Federal Register / Vol. 81, No. 80 / Tuesday, April 26, 2016 / Notices

                                                  officials. DOE may require the applicant                and Indeck-Corinth to be effective 11/                   Accession Number: 20160419–5206.
                                                  to conduct and submit an independent                    19/2015.                                                 Comments Due: 5 p.m. ET 5/10/16.
                                                  audit at its own expense, or DOE may                        Filed Date: 4/20/16.                                 Docket Numbers: ER16–1462–000.
                                                  conduct an audit to verify the number                       Accession Number: 20160420–5051.                     Applicants: Palmco Power DE LLC.
                                                  of kilowatt-hours claimed to have been                      Comments Due: 5 p.m. ET 5/11/16.                     Description: Baseline eTariff Filing:
                                                  generated and sold by the qualified                         Docket Numbers: ER16–1129–002.                    Palmco Power DE FERC Electric Tariff
                                                  hydroelectric facility and for which an                     Applicants: VPI Enterprises, Inc.                 to be effective 5/19/2016.
                                                  incentive payment has been requested                        Description: Tariff Amendment:                       Filed Date: 4/19/16.
                                                  or made.                                                Supplement to Application for Order                      Accession Number: 20160419–5207.
                                                    Issued in Washington, DC, on April 21,                Accepting Initial Market-Based Rate                      Comments Due: 5 p.m. ET 5/10/16.
                                                  2016.                                                   Tariff to be effective 3/11/2016.                        Docket Numbers: ER16–1464–000.
                                                  Roland Risser,                                              Filed Date: 4/19/16.                                 Applicants: Palmco Power ME, LLC.
                                                  Deputy Assistant Secretary for Renewable                    Accession Number: 20160419–5158.                     Description: Baseline eTariff Filing:
                                                  Power, Energy Efficiency and Renewable                      Comments Due: 5 p.m. ET 5/10/16.                  Palmco Power ME FERC Electric Tariff
                                                  Energy.                                                     Docket Numbers: ER16–1130–002.                    to be effective 5/20/2016.
                                                  [FR Doc. 2016–09700 Filed 4–25–16; 8:45 am]                 Applicants: DifWind Farms Limited I.                 Filed Date: 4/20/16.
                                                  BILLING CODE 6450–01–P                                      Description: Tariff Amendment:                       Accession Number: 20160420–5049.
                                                                                                          Supplement to Application for Order                      Comments Due: 5 p.m. ET 5/11/16.
                                                                                                          Accepting Initial Market-Based Rate                      Docket Numbers: ER16–1465–000.
                                                  DEPARTMENT OF ENERGY                                    Tariff to be effective 3/11/2016.                        Applicants: Palmco Power MI LLC.
                                                                                                              Filed Date: 4/19/16.                                 Description: Baseline eTariff Filing:
                                                  Federal Energy Regulatory                                   Accession Number: 20160419–5149.                  Palmco Power MI FERC Electric Tariff
                                                  Commission                                                  Comments Due: 5 p.m. ET 5/10/16.                  to be effective 5/20/2016.
                                                  Combined Notice of Filings #1                               Docket Numbers: ER16–1131–002.                       Filed Date: 4/20/16.
                                                                                                              Applicants: DifWind Farms Limited                    Accession Number: 20160420–5050.
                                                     Take notice that the Commission                      II.                                                      Comments Due: 5 p.m. ET 5/11/16.
                                                  received the following electric corporate                   Description: Tariff Amendment:                       Docket Numbers: ER16–1466–000.
                                                  filings:                                                Supplement to Application for Order                      Applicants: Palmco Power NH LLC.
                                                     Docket Numbers: EC16–98–000.                         Accepting Initial Market-Based Rate                      Description: Baseline eTariff Filing:
                                                     Applicants: Chubu Electric Power                     Tariff to be effective 3/11/2016.                     Palmco Power NH FERC Electric Tariff
                                                  Company U.S.A. Inc., Tokyo Electric                         Filed Date: 4/19/16.                              to be effective 5/20/2016.
                                                  Power Company, Incorporated.                                Accession Number: 20160419–5153.                     Filed Date: 4/20/16.
                                                     Description: Supplement to March 31,                     Comments Due: 5 p.m. ET 5/10/16.                     Accession Number: 20160420–5052.
                                                  2016 Application for Authorization                          Docket Numbers: ER16–1132–002.                       Comments Due: 5 p.m. ET 5/11/16.
                                                  Under Section 203 of the Federal Power                      Applicants: DifWind Farms Limited                    Docket Numbers: ER16–1467–000.
                                                  Act of Chubu Electric Power Company                     V.                                                       Applicants: Palmco Power VA LLC.
                                                  U.S.A. Inc. et al.                                          Description: Tariff Amendment:                       Description: Baseline eTariff Filing:
                                                     Filed Date: 4/20/16.                                 Supplement to Application for Order                   Palmco Power VA FERC Electric Tariff
                                                     Accession Number: 20160420–5037.                     Accepting Initial Market-Based Rate                   to be effective 5/20/2016.
                                                     Comments Due: 5 p.m. ET 5/2/16.                      Tariff to be effective 3/11/2016.                        Filed Date: 4/20/16.
                                                     Take notice that the Commission                          Filed Date: 4/19/16.                                 Accession Number: 20160420–5053.
                                                  received the following electric rate                        Accession Number: 20160419–5157.                     Comments Due: 5 p.m. ET 5/11/16.
                                                  filings:                                                    Comments Due: 5 p.m. ET 5/10/16.                     Docket Numbers: ER16–1468–000.
                                                     Docket Numbers: ER13–2428–011.                           Docket Numbers: ER16–1459–000.                       Applicants: Palmco Power RI LLC.
                                                     Applicants: Kentucky Utilities                           Applicants: Southern California                      Description: Baseline eTariff Filing:
                                                  Company.                                                Edison Company.                                       Palmco Power RI FERC Electric Tariff to
                                                     Description: Compliance filing: Rate                     Description: § 205(d) Rate Filing:                be effective 5/20/2016.
                                                  Case Settlement Municipal Contracts to                  LGIA RE Gaskell West LLC Gaskell West                    Filed Date: 4/20/16.
                                                  be effective 4/23/2014.                                 Project to be effective 4/20/2016.                       Accession Number: 20160420–5054.
                                                     Filed Date: 12/31/15.                                    Filed Date: 4/19/16.                                 Comments Due: 5 p.m. ET 5/11/16.
                                                     Accession Number: 20151231–5087.                         Accession Number: 20160419–5187.                     Docket Numbers: ER16–1469–000.
                                                     Comments Due: 5 p.m. ET 5/2/16.                          Comments Due: 5 p.m. ET 5/10/16.                     Applicants: Southwest Power Pool,
                                                     Docket Numbers: ER13–2428–012.                           Docket Numbers: ER16–1460–000.                    Inc.
                                                     Applicants: Kentucky Utilities                           Applicants: Aspirity Energy Northeast                Description: § 205(d) Rate Filing:
                                                  Company.                                                LLC.                                                  1875R2 Kansas Electric Power
                                                     Description: Compliance filing: Tariffs                  Description: Tariff Cancellation:                 Cooperative, Inc. NITSA and NOA to be
                                                  Conforming to Settlement to be effective                Notice of Cancellation of Market-Based                effective 4/1/2016.
                                                  4/23/2014.                                              Rate Tariff to be effective 6/20/2016.                   Filed Date: 4/20/16.
                                                     Filed Date: 4/13/16.                                     Filed Date: 4/19/16.                                 Accession Number: 20160420–5076.
                                                     Accession Number: 20160413–5195.                         Accession Number: 20160419–5201.                     Comments Due: 5 p.m. ET 5/11/16.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                     Comments Due: 5 p.m. ET 5/2/16.                          Comments Due: 5 p.m. ET 5/10/16.                     The filings are accessible in the
                                                     Docket Numbers: ER16–925–001.                            Docket Numbers: ER16–1461–000.                    Commission’s eLibrary system by
                                                     Applicants: Niagara Mohawk Power                         Applicants: Tres Amigas, LLC.                     clicking on the links or querying the
                                                  Corporation, New York Independent                           Description: § 205(d) Rate Filing:                docket number.
                                                  System Operator, Inc.                                   Notice of Succession to be effective 12/                 Any person desiring to intervene or
                                                     Description: Compliance filing: NMPC                 10/2015.                                              protest in any of the above proceedings
                                                  compliance re: SA 2260 between NMPC                         Filed Date: 4/19/16.                              must file in accordance with Rules 211


                                             VerDate Sep<11>2014   22:08 Apr 25, 2016   Jkt 238001   PO 00000   Frm 00039   Fmt 4703   Sfmt 4703   E:\FR\FM\26APN1.SGM   26APN1



Document Created: 2016-04-26 01:36:20
Document Modified: 2016-04-26 01:36:20
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability of guidance and open application period.
DatesDOE is currently accepting applications from April 26, 2016 through May 31, 2016 Applications must be sent to [email protected] by midnight EDT, May 31, 2016, or they will not be considered timely filed for calendar year 2015 incentive payments.
ContactRequests for additional information should be directed to Mr. Timothy Welch, Office of Energy Efficiency and Renewable Energy (EE-4W), U.S. Department of Energy, 1000 Independence Avenue SW., Washington, DC 20585-0121, (202) 586-7055, [email protected] Electronic communications are recommended for correspondence and required for submission of application information.