DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 99 (May 23, 2016)

Page Range32324-32324
FR Document2016-12047

Federal Register, Volume 81 Issue 99 (Monday, May 23, 2016)
[Federal Register Volume 81, Number 99 (Monday, May 23, 2016)]
[Notices]
[Page 32324]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-12047]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Schedule for Environmental Review of the Nexus Gas 
Transmission and Texas Eastern Appalachian Lease Projects

------------------------------------------------------------------------
                                                     Docket Nos.
------------------------------------------------------------------------
NEXUS Gas Transmission, LLC...............  CP16-22-000
Texas Eastern Transmission, LP............  CP16-23-000
------------------------------------------------------------------------

    On November 20, 2015, NEXUS Gas Transmission, LLC (NEXUS) and Texas 
Eastern Transmission, LP (Texas Eastern) filed applications in Docket 
Nos. CP16-22-000 and CP16-23-000 requesting a Certificate of Public 
Convenience and Necessity pursuant to Section 7(c) of the Natural Gas 
Act to construct, operate, and maintain certain natural gas pipeline 
facilities. The proposed projects are known as the NEXUS Gas 
Transmission (NGT) Project and Texas Eastern Appalachian Lease (TEAL) 
Project (jointly referred to as ``Projects'') and would provide 
transportation of 1.5 million dekatherms per day of Appalachian Basin 
shale gas to consuming markets in Northern Ohio, Southeastern Michigan, 
and Midwestern markets, as well as the Dawn Hub in Ontario, Canada.
    On December 7, 2015, the Federal Energy Regulatory Commission (FERC 
or Commission) issued its Notice of Application for the Projects. Among 
other things, that notice alerted other agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on the request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's final 
Environmental Impact Statement (EIS) for the Projects. This instant 
notice identifies the FERC staff's planned schedule for completion of 
the final EIS for the Projects, which is based on an issuance of the 
draft EIS in July 2016.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--November 30, 2016

90-day Federal Authorization Decision Deadline--February 28, 2017

    If a schedule change becomes necessary for the final EIS, an 
additional notice will be provided so that the relevant agencies are 
kept informed of the Projects' progress.

Project Description

    The NGT Project would include about 255 miles of new 36-inch-
diameter mainline pipeline, including about 208 miles in Columbiana, 
Stark, Summit, Wayne, Medina, Lorain, Huron, Erie, Sandusky, Wood, 
Lucas, Henry, and Fulton Counties, Ohio and about 47 miles in Lenawee, 
Monroe, Washtenaw, and Wayne Counties, Michigan. The NGT Project also 
would include about one mile of new 36-inch-diameter interconnecting 
pipeline in Columbiana County, Ohio. In addition, NEXUS proposes to 
construct and operate four new compressor stations and other 
aboveground facilities.
    The TEAL Project would include about 4.4 miles of new 36-inch-
diameter loop pipeline in Monroe County, Ohio; and about 0.3 mile of 
new 30-inch-diameter interconnecting pipeline between in Columbiana 
County, Ohio. The TEAL Project also would include construction of one 
new compressor station, modification of one existing compressor 
station, and construction and modification of other aboveground 
facilities.

Background

    On January 9, 2015 and January 26, 2015, the Commission staff 
granted NEXUS and Texas Eastern's requests to use the FERC's Pre-filing 
environmental review process and assigned the NGT Project and TEAL 
Project Docket Nos. PF15-10-000 and PF15-11-000, respectively. On April 
8, 2015, the Commission issued a Notice of Intent to Prepare an 
Environmental Impact Statement for the Planned Nexus Gas Transmission 
Project and Texas Eastern Appalachian Lease Project, Request for 
Comments on Environmental Issues, and Notice of Public Scoping Meetings 
(NOI).
    The NOI was issued during the pre-filing review of the Projects and 
was sent to federal, state, and local government agencies; elected 
officials; affected landowners; environmental and public interest 
groups; Native American tribes and regional organizations; commentors 
and other interested parties; and local libraries and newspapers. Major 
issues raised during scoping include underground mines, karst geology, 
topsoil, drain tiles, drinking water, waterbodies, wetlands, 
vegetation, wildlife, threatened and endangered species, Oak Openings 
ecosystem, residential development, socioeconomic resources, cultural 
resources, public safety, air quality, as well as potential cumulative 
resource impacts and recommended project alternatives.
    The U.S. Fish and Wildlife Service and U.S. Environmental 
Protection Agency are cooperating agencies in the preparation of the 
EIS.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription (http://www.ferc.gov/docs-filing/esubscription.asp). Additional information 
about the Project is available from the Commission's Office of External 
Affairs at (866) 208-FERC or on the FERC Web site (www.ferc.gov). Using 
the ``eLibrary'' link, select ``General Search'' from the eLibrary 
menu, enter the selected date range and ``Docket Number'' excluding the 
last three digits (i.e., CP16-22 or CP16-23), and follow the 
instructions.

    Dated: May 17, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-12047 Filed 5-20-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                32324                           Federal Register / Vol. 81, No. 99 / Monday, May 23, 2016 / Notices

                                                3). Be sure you have selected an                         markets, as well as the Dawn Hub in                   respectively. On April 8, 2015, the
                                                appropriate date range. For assistance,                  Ontario, Canada.                                      Commission issued a Notice of Intent to
                                                please contact FERC Online Support at                       On December 7, 2015, the Federal                   Prepare an Environmental Impact
                                                FercOnlineSupport@ferc.gov or toll free                  Energy Regulatory Commission (FERC                    Statement for the Planned Nexus Gas
                                                at (866) 208–3676, or for TTY, contact                   or Commission) issued its Notice of                   Transmission Project and Texas Eastern
                                                (202) 502–8659. The eLibrary link also                   Application for the Projects. Among                   Appalachian Lease Project, Request for
                                                provides access to the texts of formal                   other things, that notice alerted other               Comments on Environmental Issues,
                                                documents issued by the Commission,                      agencies issuing federal authorizations               and Notice of Public Scoping Meetings
                                                such as orders, notices, and                             of the requirement to complete all
                                                                                                                                                               (NOI).
                                                rulemakings.                                             necessary reviews and to reach a final
                                                   In addition, the Commission offers a                  decision on the request for a federal                    The NOI was issued during the pre-
                                                free service called eSubscription which                  authorization within 90 days of the date              filing review of the Projects and was
                                                allows you to keep track of all formal                   of issuance of the Commission staff’s                 sent to federal, state, and local
                                                issuances and submittals in specific                     final Environmental Impact Statement                  government agencies; elected officials;
                                                dockets. This can reduce the amount of                   (EIS) for the Projects. This instant notice           affected landowners; environmental and
                                                time you spend researching proceedings                   identifies the FERC staff’s planned                   public interest groups; Native American
                                                by automatically providing you with                      schedule for completion of the final EIS              tribes and regional organizations;
                                                notification of these filings, document                  for the Projects, which is based on an                commentors and other interested
                                                summaries, and direct links to the                       issuance of the draft EIS in July 2016.               parties; and local libraries and
                                                documents. Go to www.ferc.gov/docs-                      Schedule for Environmental Review                     newspapers. Major issues raised during
                                                filing/esubscription.asp.                                                                                      scoping include underground mines,
                                                   Finally, public meetings or site visits               Issuance of Notice of Availability of the
                                                                                                                                                               karst geology, topsoil, drain tiles,
                                                will be posted on the Commission’s                          final EIS—November 30, 2016
                                                                                                                                                               drinking water, waterbodies, wetlands,
                                                calendar located at www.ferc.gov/                        90-day Federal Authorization Decision
                                                                                                                                                               vegetation, wildlife, threatened and
                                                EventCalendar/EventsList.aspx along                         Deadline—February 28, 2017
                                                                                                                                                               endangered species, Oak Openings
                                                with other related information.                             If a schedule change becomes
                                                                                                                                                               ecosystem, residential development,
                                                  Dated: May 17, 2016.                                   necessary for the final EIS, an additional
                                                                                                                                                               socioeconomic resources, cultural
                                                                                                         notice will be provided so that the
                                                Kimberly D. Bose,                                                                                              resources, public safety, air quality, as
                                                                                                         relevant agencies are kept informed of
                                                Secretary.                                               the Projects’ progress.                               well as potential cumulative resource
                                                [FR Doc. 2016–12062 Filed 5–20–16; 8:45 am]                                                                    impacts and recommended project
                                                BILLING CODE 6717–01–P
                                                                                                         Project Description                                   alternatives.
                                                                                                           The NGT Project would include about                    The U.S. Fish and Wildlife Service
                                                                                                         255 miles of new 36-inch-diameter                     and U.S. Environmental Protection
                                                DEPARTMENT OF ENERGY                                     mainline pipeline, including about 208                Agency are cooperating agencies in the
                                                                                                         miles in Columbiana, Stark, Summit,                   preparation of the EIS.
                                                Federal Energy Regulatory                                Wayne, Medina, Lorain, Huron, Erie,
                                                Commission                                               Sandusky, Wood, Lucas, Henry, and                     Additional Information
                                                                                                         Fulton Counties, Ohio and about 47
                                                Notice of Schedule for Environmental                                                                              In order to receive notification of the
                                                                                                         miles in Lenawee, Monroe, Washtenaw,
                                                Review of the Nexus Gas Transmission                                                                           issuance of the EIS and to keep track of
                                                                                                         and Wayne Counties, Michigan. The
                                                and Texas Eastern Appalachian Lease                                                                            all formal issuances and submittals in
                                                                                                         NGT Project also would include about
                                                Projects                                                                                                       specific dockets, the Commission offers
                                                                                                         one mile of new 36-inch-diameter
                                                                                                         interconnecting pipeline in Columbiana                a free service called eSubscription
                                                                                      Docket Nos.
                                                                                                         County, Ohio. In addition, NEXUS                      (http://www.ferc.gov/docs-filing/
                                                NEXUS Gas Transmission,               CP16–22–000        proposes to construct and operate four                esubscription.asp). Additional
                                                  LLC.                                                   new compressor stations and other                     information about the Project is
                                                Texas Eastern Transmission,           CP16–23–000        aboveground facilities.                               available from the Commission’s Office
                                                  LP.                                                      The TEAL Project would include                      of External Affairs at (866) 208–FERC or
                                                                                                         about 4.4 miles of new 36-inch-diameter               on the FERC Web site (www.ferc.gov).
                                                   On November 20, 2015, NEXUS Gas                       loop pipeline in Monroe County, Ohio;                 Using the ‘‘eLibrary’’ link, select
                                                Transmission, LLC (NEXUS) and Texas                      and about 0.3 mile of new 30-inch-                    ‘‘General Search’’ from the eLibrary
                                                Eastern Transmission, LP (Texas                          diameter interconnecting pipeline                     menu, enter the selected date range and
                                                Eastern) filed applications in Docket                    between in Columbiana County, Ohio.
                                                Nos. CP16–22–000 and CP16–23–000                                                                               ‘‘Docket Number’’ excluding the last
                                                                                                         The TEAL Project also would include                   three digits (i.e., CP16–22 or CP16–23),
                                                requesting a Certificate of Public                       construction of one new compressor
                                                Convenience and Necessity pursuant to                                                                          and follow the instructions.
                                                                                                         station, modification of one existing
                                                Section 7(c) of the Natural Gas Act to                   compressor station, and construction                    Dated: May 17, 2016.
                                                construct, operate, and maintain certain                 and modification of other aboveground                 Nathaniel J. Davis, Sr.,
                                                natural gas pipeline facilities. The                     facilities.                                           Deputy Secretary.
                                                proposed projects are known as the
                                                                                                         Background                                            [FR Doc. 2016–12047 Filed 5–20–16; 8:45 am]
                                                NEXUS Gas Transmission (NGT) Project
sradovich on DSK3TPTVN1PROD with NOTICES




                                                                                                                                                               BILLING CODE 6717–01–P
                                                and Texas Eastern Appalachian Lease                        On January 9, 2015 and January 26,
                                                (TEAL) Project (jointly referred to as                   2015, the Commission staff granted
                                                ‘‘Projects’’) and would provide                          NEXUS and Texas Eastern’s requests to
                                                transportation of 1.5 million dekatherms                 use the FERC’s Pre-filing environmental
                                                per day of Appalachian Basin shale gas                   review process and assigned the NGT
                                                to consuming markets in Northern Ohio,                   Project and TEAL Project Docket Nos.
                                                Southeastern Michigan, and Midwestern                    PF15–10–000 and PF15–11–000,


                                           VerDate Sep<11>2014   18:25 May 20, 2016    Jkt 238001   PO 00000   Frm 00051   Fmt 4703   Sfmt 9990   E:\FR\FM\23MYN1.SGM   23MYN1



Document Created: 2018-02-07 15:07:32
Document Modified: 2018-02-07 15:07:32
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 32324 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR