The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of amendments to Facility Operating License Nos. DPR-70 and 75, issued to PSEG Nuclear LLC (PSEG or the licensee) for operation of the Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2. The proposed amendments would extend the implementation period for Salem, Unit No. 1, License Amendment No. 311, and Salem, Unit No. 2, License Amendment No. 292, from July 5, 2016 (120 days from the March 7, 2016, date of issuance of the amendments), to prior to Mode 6 entry for the Salem, Unit No. 1, fall 2017 (1R25) outage and prior to Mode 6 entry for the Salem, Unit No. 2, spring 2017 (2R22) outage to align with the outages for the replacement of the source range and intermediate range detectors.

Federal Register, Volume 81 Issue 99 (Monday, May 23, 2016)
[Federal Register Volume 81, Number 99 (Monday, May 23, 2016)]
[Notices]
[Pages 32351-32355]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-12054]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-272 and 50-311; NRC-2016-0102]


PSEG Nuclear LLC; Salem Nuclear Generating Station, Unit Nos. 1 
and 2

AGENCY: Nuclear Regulatory Commission.

ACTION: License amendment application; opportunity to comment, request 
a hearing, and petition for leave to intervene.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering 
issuance of amendments to Facility Operating License Nos. DPR-70 and 
75, issued to PSEG Nuclear LLC (PSEG or the licensee) for operation of 
the Salem

[[Page 32352]]

Nuclear Generating Station (Salem), Unit Nos. 1 and 2. The proposed 
amendments would extend the implementation period for Salem, Unit No. 
1, License Amendment No. 311, and Salem, Unit No. 2, License Amendment 
No. 292, from July 5, 2016 (120 days from the March 7, 2016, date of 
issuance of the amendments), to prior to Mode 6 entry for the Salem, 
Unit No. 1, fall 2017 (1R25) outage and prior to Mode 6 entry for the 
Salem, Unit No. 2, spring 2017 (2R22) outage to align with the outages 
for the replacement of the source range and intermediate range 
detectors.

DATES: Submit comments by June 22, 2016. Requests for a hearing or 
petition for leave to intervene must be filed by July 22, 2016.

ADDRESSES: You may submit comments by any of the following methods 
(unless this document describes a different method for submitting 
comments on a specific subject):
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0102. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     Mail comments to: Cindy Bladey, Office of Administration, 
Mail Stop: OWFN-12-H08, U.S. Nuclear Regulatory Commission, Washington, 
DC 20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Thomas J. Wengert, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-4037, email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2016-0102 when contacting the NRC 
about the availability of information for this action. You may obtain 
publicly-available information related to this action by any of the 
following methods:
     Federal rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0102.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it is available 
in ADAMS) is provided the first time that it is mentioned in the 
SUPPLEMENTARY INFORMATION section of this document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2016-0102 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC posts all comment submissions at http://www.regulations.gov as well as entering the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Introduction

    The NRC is considering issuance of amendments to Facility Operating 
License Nos. DPR-70 and 75, issued to PSEG Nuclear LLC for operation of 
Salem, Unit Nos. 1 and 2, located in Salem County, New Jersey.
    The proposed amendments would extend the implementation period for 
Salem, Unit No. 1, License Amendment No. 311, and Salem, Unit No. 2, 
License Amendment No. 292, from July 5, 2016 (120 days from March 7, 
2016, date of issuance of the amendments), to prior to Mode 6 entry for 
the Salem, Unit No. 1, fall 2017 (1R25) outage and prior to Mode 6 
entry for the Salem, Unit No. 2, spring 2017 (2R22) outage to align 
with the outages for the replacement of the source range and 
intermediate range detectors.
    Before any issuance of the proposed license amendments, the NRC 
will need to make the findings required by the Atomic Energy Act of 
1954, as amended (the Act), and the NRC's regulations.
    The NRC has made a proposed determination that the license 
amendment request involves no significant hazards consideration. Under 
the NRC's regulations in Sec.  50.92 of title 10 of the Code of Federal 
Regulations (10 CFR), this means that operation of the facility in 
accordance with the proposed amendments would not (1) involve a 
significant increase in the probability or consequences of an accident 
previously evaluated; or (2) create the possibility of a new or 
different kind of accident from any accident previously evaluated; or 
(3) involve a significant reduction in a margin of safety. As required 
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue 
of no significant hazards consideration, which is presented below:

    1. Do the proposed changes involve a significant increase in the 
probability or consequences of an accident previously evaluated?
    Response: No.
    The proposed amendment implementation schedule extension is 
administrative in nature and does not require any modifications to 
or change in operation of plant systems or components. The extension 
of the amendment implementation period does not increase the 
probability or consequences of an accident previously evaluated in 
the Updated Final Safety Analysis (UFSAR). Current Technical 
Specification (TS) 3.9.2 requirements will continue to ensure the 
plant is operated consistent with the UFSAR accident analysis for a 
boron dilution event.
    Therefore, the proposed change does not involve a significant 
increase in the probability or consequences of an accident 
previously evaluated.
    2. Do the proposed changes create the possibility of a new or 
different kind of accident from any accident previously evaluated?
    Response: No.
    The proposed amendment implementation schedule extension is 
administrative in nature. The extension of the amendment 
implementation does not require any physical plant modifications, 
does not alter any plant systems or components, and does not change 
the operation of the plant. Current TS 3.9.2 requirements will 
continue to ensure the plant is operated consistent with the UFSAR 
accident analysis for a boron dilution event.
    Therefore, the proposed change does not create the possibility 
of a new or different kind of accident from any previously 
evaluated.

[[Page 32353]]

    3. Do the proposed changes involve a significant reduction in a 
margin of safety?
    Response: No.
    Margin of safety is related to the confidence in the ability of 
the fission product barriers to perform their intended functions. 
These barriers include the fuel cladding, the reactor coolant system 
pressure boundary, and the containment. The proposed TS change is 
administrative in nature and does not affect any of these barriers. 
Current TS 3.9.2 requirements will continue to ensure the plant is 
operated consistent with the UFSAR accident analysis for a boron 
dilution event.
    Therefore, the proposed change does not involve a significant 
reduction in the margin of safety.

    The NRC staff has reviewed the licensee's analysis and, based on 
this review, it appears that the three standards of 10 CFR 50.92(c) are 
satisfied. Therefore, the NRC staff proposes to determine that the 
license amendment request involves a no significant hazards 
consideration.
    The NRC is seeking public comments on this proposed determination 
that the license amendment request involves no significant hazards 
consideration. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendments until the 
expiration of 60 days after the date of publication of this notice. The 
Commission may issue the license amendments before expiration of the 
60-day notice period if the Commission concludes the amendments involve 
no significant hazards consideration. In addition, the Commission may 
issue the amendments prior to the expiration of the 30-day comment 
period if circumstances change during the 30-day comment period such 
that failure to act in a timely way would result, for example, in 
derating or shutdown of the facility. If the Commission takes action 
prior to the expiration of either the comment period or the notice 
period, it will publish in the Federal Register a notice of issuance. 
If the Commission makes a final no significant hazards consideration 
determination, any hearing will take place after issuance. The 
Commission expects that the need to take this action will occur very 
infrequently.

III. Opportunity To Request a Hearing and Petition for Leave To 
Intervene

    Within 60 days after the date of publication of this notice, any 
person(s) whose interest may be affected by this action may file a 
request for a hearing and a petition to intervene with respect to 
issuance of the amendments to the subject facility operating licenses 
or combined license. Requests for a hearing and a petition for leave to 
intervene shall be filed in accordance with the Commission's ``Agency 
Rules of Practice and Procedure'' in 10 CFR part 2. Interested 
person(s) should consult a current copy of 10 CFR 2.309, which is 
available at the NRC's PDR, located at One White Flint North, Room O1-
F21, 11555 Rockville Pike (first floor), Rockville, Maryland 20852. The 
NRC's regulations are accessible electronically from the NRC Library on 
the NRC's Web site at http://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is 
filed within 60 days, the Commission or a presiding officer designated 
by the Commission or by the Chief Administrative Judge of the Atomic 
Safety and Licensing Board Panel, will rule on the request and/or 
petition; and the Secretary or the Chief Administrative Judge of the 
Atomic Safety and Licensing Board will issue a notice of a hearing or 
an appropriate order.
    As required by 10 CFR 2.309, a petition for leave to intervene 
shall set forth with particularity the interest of the petitioner in 
the proceeding, and how that interest may be affected by the results of 
the proceeding. The petition should specifically explain the reasons 
why intervention should be permitted with particular reference to the 
following general requirements: (1) The name, address, and telephone 
number of the requestor or petitioner; (2) the nature of the 
requestor's/petitioner's right under the Act to be made a party to the 
proceeding; (3) the nature and extent of the requestor's/petitioner's 
property, financial, or other interest in the proceeding; and (4) the 
possible effect of any decision or order which may be entered in the 
proceeding on the requestor's/petitioner's interest. The petition must 
also set forth the specific contentions which the requestor/petitioner 
seeks to have litigated at the proceeding.
    Each contention must consist of a specific statement of the issue 
of law or fact to be raised or controverted. In addition, the 
requestor/petitioner shall provide a brief explanation of the bases for 
the contention and a concise statement of the alleged facts or expert 
opinion which support the contention and on which the requestor/
petitioner intends to rely in proving the contention at the hearing. 
The requestor/petitioner must also provide references to those specific 
sources and documents of which the petitioner is aware and on which the 
requestor/petitioner intends to rely to establish those facts or expert 
opinion. The petition must include sufficient information to show that 
a genuine dispute exists with the applicant on a material issue of law 
or fact. Contentions shall be limited to matters within the scope of 
the amendments under consideration. The contention must be one which, 
if proven, would entitle the requestor/petitioner to relief. A 
requestor/petitioner who fails to satisfy these requirements with 
respect to at least one contention will not be permitted to participate 
as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing with respect to resolution of that person's admitted 
contentions, including the opportunity to present evidence and to 
submit a cross-examination plan for cross-examination of witnesses, 
consistent with NRC regulations, policies and procedures.
    Petitions for leave to intervene must be filed no later than 60 
days from the date of publication of this notice. Requests for hearing, 
petitions for leave to intervene, and motions for leave to file new or 
amended contentions that are filed after the 60-day deadline will not 
be entertained absent a determination by the presiding officer that the 
filing demonstrates good cause by satisfying the three factors in 10 
CFR 2.309(c)(1)(i)-(iii).
    If a hearing is requested, and the Commission has not made a final 
determination on the issue of no significant hazards consideration, the 
Commission will make a final determination on the issue of no 
significant hazards consideration. The final determination will serve 
to decide when the hearing is held. If the final determination is that 
the amendment request involves no significant hazards consideration, 
the Commission may issue the amendments and make them immediately 
effective, notwithstanding the request for a hearing. Any hearing held 
would take place after issuance of the amendments. If the final 
determination is that the amendment request involves a significant 
hazards consideration, then any hearing held would take place before 
the issuance of any amendments unless the Commission finds an imminent 
danger to the health or safety of the public, in which case it will 
issue an appropriate order or rule under 10 CFR part 2.
    A State, local governmental body, Federally-recognized Indian 
Tribe, or agency thereof, may submit a petition to the Commission to 
participate as a party

[[Page 32354]]

under 10 CFR 2.309(h)(1). The petition should state the nature and 
extent of the petitioner's interest in the proceeding. The petition 
should be submitted to the Commission by July 22, 2016. The petition 
must be filed in accordance with the filing instructions in the 
``Electronic Submissions (E-Filing)'' section of this document, and 
should meet the requirements for petitions for leave to intervene set 
forth in this section, except that under Sec.  2.309(h)(2) a State, 
local governmental body, or Federally-recognized Indian Tribe, or 
agency thereof does not need to address the standing requirements in 10 
CFR 2.309(d) if the facility is located within its boundaries. A State, 
local governmental body, Federally-recognized Indian Tribe, or agency 
thereof may also have the opportunity to participate under 10 CFR 
2.315(c).
    If a hearing is granted, any person who does not wish, or is not 
qualified, to become a party to the proceeding may, in the discretion 
of the presiding officer, be permitted to make a limited appearance 
pursuant to the provisions of 10 CFR 2.315(a). A person making a 
limited appearance may make an oral or written statement of position on 
the issues, but may not otherwise participate in the proceeding. A 
limited appearance may be made at any session of the hearing or at any 
prehearing conference, subject to the limits and conditions as may be 
imposed by the presiding officer. Persons desiring to make a limited 
appearance are requested to inform the Secretary of the Commission by 
July 22, 2016.

IV. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings, including a 
request for hearing, a petition for leave to intervene, any motion or 
other document filed in the proceeding prior to the submission of a 
request for hearing or petition to intervene, and documents filed by 
interested governmental entities participating under 10 CFR 2.315(c), 
must be filed in accordance with the NRC's E-Filing rule (72 FR 49139; 
August 28, 2007). The E-Filing process requires participants to submit 
and serve all adjudicatory documents over the Internet, or in some 
cases to mail copies on electronic storage media. Participants may not 
submit paper copies of their filings unless they seek an exemption in 
accordance with the procedures described below.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at [email protected], or by 
telephone at 301-415-1677, to request (1) a digital identification (ID) 
certificate, which allows the participant (or its counsel or 
representative) to digitally sign documents and access the E-Submittal 
server for any proceeding in which it is participating; and (2) advise 
the Secretary that the participant will be submitting a request or 
petition for hearing (even in instances in which the participant, or 
its counsel or representative, already holds an NRC-issued digital ID 
certificate). Based upon this information, the Secretary will establish 
an electronic docket for the hearing in this proceeding if the 
Secretary has not already established an electronic docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals/getting-started.html. System requirements for accessing 
the E-Submittal server are detailed in the NRC's ``Guidance for 
Electronic Submission,'' which is available on the agency's public Web 
site at http://www.nrc.gov/site-help/e-submittals.html. Participants 
may attempt to use other software not listed on the Web site, but 
should note that the NRC's E-Filing system does not support unlisted 
software, and the NRC Meta System Help Desk will not be able to offer 
assistance in using unlisted software.
    If a participant is electronically submitting a document to the NRC 
in accordance with the E-Filing rule, the participant must file the 
document using the NRC's online, Web-based submission form. In order to 
serve documents through the Electronic Information Exchange System, 
users will be required to install a Web browser plug-in from the NRC's 
Web site. Further information on the Web-based submission form, 
including the installation of the Web browser plug-in, is available on 
the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html.
    Once a participant has obtained a digital ID certificate and a 
docket has been created, the participant can then submit a request for 
hearing or petition for leave to intervene. Submissions should be in 
Portable Document Format (PDF) in accordance with NRC guidance 
available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the 
documents are submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of 
a transmission, the E-Filing system time-stamps the document and sends 
the submitter an email notice confirming receipt of the document. The 
E-Filing system also distributes an email notice that provides access 
to the document to the NRC's Office of the General Counsel and any 
others who have advised the Office of the Secretary that they wish to 
participate in the proceeding, so that the filer need not serve the 
documents on those participants separately. Therefore, applicants and 
other participants (or their counsel or representative) must apply for 
and receive a digital ID certificate before a hearing request/petition 
to intervene is filed so that they can obtain access to the document 
via the E-Filing system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System 
Help Desk through the ``Contact Us'' link located on the NRC's public 
Web site at http://www.nrc.gov/site-help/e-submittals.html, by email to 
[email protected], or by a toll-free call at 1-866-672-7640. The 
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., 
Eastern Time, Monday through Friday, excluding government holidays.
    Participants who believe that they have a good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted by: (1) First class mail 
addressed to the Office of the Secretary of the Commission, U.S. 
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemaking and Adjudications Staff; or (2) courier, express mail, or 
expedited delivery service to the Office of the Secretary, Sixteenth 
Floor, One White Flint North, 11555 Rockville Pike, Rockville, 
Maryland, 20852, Attention: Rulemaking and Adjudications Staff. 
Participants filing a document in this manner are responsible for 
serving the document on all other participants. Filing is considered 
complete by first-class mail as of the time of deposit in the mail, or 
by courier, express mail, or expedited delivery service upon depositing 
the document with the provider of the service. A presiding officer, 
having granted an exemption request from using E-Filing, may require a 
participant or party to use E-Filing if the presiding officer 
subsequently determines that the reason for granting

[[Page 32355]]

the exemption from use of E-Filing no longer exists.
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket which is available to the public at 
http://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the 
Commission, or the presiding officer. Participants are requested not to 
include personal privacy information, such as social security numbers, 
home addresses, or home phone numbers in their filings, unless an NRC 
regulation or other law requires submission of such information. 
However, in some instances, a request to intervene will require 
including information on local residence in order to demonstrate a 
proximity assertion of interest in the proceeding. With respect to 
copyrighted works, except for limited excerpts that serve the purpose 
of the adjudicatory filings and would constitute a Fair Use 
application, participants are requested not to include copyrighted 
materials in their submission.
    For further details with respect to this action, see the 
application for license amendment dated May 10, 2016 (ADAMS Accession 
No. ML16131A555).
    Attorney for licensee: Jeffrie J. Keenan, PSEG Nuclear LLC--N21, 
P.O. Box 236, Hancocks Bridge, NJ 08038.
    NRC Branch Chief: Douglas A. Broaddus.

    Dated at Rockville, Maryland, this 17th day of May 2016.

    For the Nuclear Regulatory Commission.
Andrew Hon,
Acting Chief, Plant Licensing Branch I-2, Division of Operating Reactor 
Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2016-12054 Filed 5-20-16; 8:45 am]
 BILLING CODE 7590-01-P



                                                                                Federal Register / Vol. 81, No. 99 / Monday, May 23, 2016 / Notices                                                   32351

                                                   The transfer of the licenses includes                the issuance of the proposed amendments               of the closing. Should the proposed transfer
                                                elements of both a direct and indirect                  will be in accordance with 10 CFR part 51             not be completed within 1 year from the date
                                                transfer. The transfer of ownership is a direct         of the Commission’s regulations and all               of this order, this order shall become null
                                                transfer because ownership is changing from             applicable requirements have been satisfied.          and void, provided, however, upon written
                                                one entity to another new and different                 The findings set forth above are supported by         application and good cause shown, such date
                                                entity. Ownership is being transferred from             a safety evaluation dated May 6, 2016                 may be extended by order. The conditions of
                                                Luminant Power to a new company, CP LLC.                (ADAMS Accession No. ML16096A266).                    this order may be amended upon application
                                                The transfer of operations is an indirect                                                                     by the licensee and approval by the Director
                                                transfer because the operator is not changing;          III.                                                  of the Office of Nuclear Reactor Regulation.
                                                it is being absorbed into another entity (OpCo             Accordingly, pursuant to Sections 161b,               IT IS FURTHER ORDERED that, consistent
                                                LLC), and the operator’s parent companies               161i, 161o, and 184 of the Atomic Energy Act          with 10 CFR 2.1315(b), license amendments
                                                are changing. Luminant Power’s parent                   of 1954, as amended, 42 U.S.C. 2201(b),               that make changes, as indicated in Enclosure
                                                companies are currently Luminant Holding                2201(i), 2201(o), and 2234; and 10 CFR 50.80,         2 to the cover letter forwarding this order, to
                                                Company LLC and its parent, Texas                       IT IS HEREBY ORDERED that the application             conform the licenses to reflect the subject
                                                Competitive Electric Holdings Company LLC.              regarding the direct transfer of ownership            transfer are approved. The amendments will
                                                These companies will cease to exist and in              and the indirect transfer of control of the           be revised only to reflect the final company
                                                their place, new companies—Intermediate                 licenses is approved, subject to the following        names (yet to be decided), and shall be
                                                Holding Company LLC and its parent,                     conditions:                                           issued and made effective at the time the
                                                Reorganized TCEH—will be created. The                      1. The licensees must notify the NRC of the        proposed license transfer is completed.
                                                operator will change to the extent that its             names of the directors and principal officers            This order is effective upon issuance.
                                                name will change from Luminant Power to                 of Reorganized TCEH and any other changes                For further details with respect to this
                                                OpCo LLC; however, the management and                   to these positions that occur before                  order, see the initial application dated
                                                technical personnel of the facility will not            emergence from bankruptcy as soon as they             November 12, 2015, as supplemented by
                                                change. The change of the parent company of             have been identified, but no later than 7 days        letters dated December 9, 2015, and March
                                                a licensed entity is considered an indirect             before implementation of the transfer.                14, March 29, April 7, and April 20, 2016,
                                                transfer of control of the operating licenses.          Additional changes to these positions may             and the safety evaluation dated the same date
                                                   Approval of the transfer of the facility             occur post-emergence. The Applicants will             as this order, which are available for public
                                                operating licenses and conforming license               notify the NRC no later than 120 days after           inspection at the Commission’s Public
                                                amendments was requested by the                         the transfer of any changes in these personnel        Document Room (PDR), located at One White
                                                Applicants pursuant to 10 CFR 50.80 and 10              made during the first 90 days following               Flint North, Public File Area 01 F21, 11555
                                                CFR 50.90, ‘‘Application for amendment of               emergence from bankruptcy.                            Rockville Pike (first floor), Rockville,
                                                license, construction permit, or early site                2. Following the subject transfer of control       Maryland. Publicly available documents
                                                permit.’’ A notice entitled, ‘‘Comanche Peak            of the licenses, all of the directors of CP LLC       created or received at the NRC are accessible
                                                Nuclear Power Plant, Units 1 and 2, and                 and OpCo LLC who can vote on activities               electronically through ADAMS in the NRC
                                                Independent Spent Fuel Storage Installation;            governed by the CPNPP licenses and all of             Library at http://www.nrc.gov/reading-rm/
                                                Consideration of Approval of Transfer of                the officers of CP LLC and OpCo LLC with              adams.html. Persons who do not have access
                                                Licenses and Conforming Amendments,’’ was               direct responsibility for activities governed         to ADAMS or who encounter problems in
                                                published in the Federal Register on                    by the CPNPP licenses shall (1) be U.S.               accessing the documents located in ADAMS,
                                                February 8, 2016 (81 FR 6545). The NRC                  citizens and not appointed by a foreign entity        should contact the NRC PDR reference staff
                                                received no comments or hearing requests.               and (2) have exclusive authority to ensure            by telephone at 1–800–397–4209, or 301–
                                                   Under 10 CFR 50.80, no license, or any               and shall ensure that the business and                415–4737, or by email to pdr.resource@
                                                right thereunder, shall be transferred, directly        activities of OpCo LLC and CP LLC with                nrc.gov.
                                                or indirectly, through transfer of control of           respect to the CPNPP licenses is at all times           Dated at Rockville, Maryland this 6th day
                                                the license, unless the NRC shall give its              conducted in a manner consistent with the             of May 2016.
                                                consent in writing. Upon review of the                  public health and safety and common                     For the Nuclear Regulatory Commission.
                                                information in the licensee’s application, and          defense and security of the United States.
                                                                                                                                                              Michele G. Evans,
                                                other information before the Commission, the               3. The Reorganized TCEH Board of
                                                NRC staff has determined that the Applicants            Directors shall adopt resolutions that any            Acting Director, Office of Nuclear Reactor
                                                are qualified to hold the licenses to the extent        non-U.S. citizens or foreign-appointed U.S.           Regulation.
                                                proposed to permit the transfer of Luminant             citizens serving as either directors or               [FR Doc. 2016–12051 Filed 5–20–16; 8:45 am]
                                                Power as possessor, owner, and operator. It             executive officers of Reorganized TCEH, the           BILLING CODE 7590–01–P
                                                also concludes that the transfer of the                 ultimate parent, and intermediate parents of
                                                licenses are otherwise consistent with the              CP LLC and OpCo LLC shall not seek access
                                                applicable provisions of law, regulations, and          to any classified information or to special
                                                                                                                                                              NUCLEAR REGULATORY
                                                orders issued by the NRC, pursuant thereto,             nuclear material in the custody of the CPNPP
                                                subject to the conditions set forth below. The          licensees and shall not participate in or seek        COMMISSION
                                                NRC staff has further found that the                    to influence operational decisions by the             [Docket Nos. 50–272 and 50–311; NRC–
                                                application for the proposed license                    licensees regarding nuclear safety or security        2016–0102]
                                                amendments complies with the standards                  matters.
                                                and requirements of the Atomic Energy Act                  4. CP LLC and OpCo LLC shall provide               PSEG Nuclear LLC; Salem Nuclear
                                                of 1954, as amended, and the Commission’s               satisfactory documentary evidence to the              Generating Station, Unit Nos. 1 and 2
                                                rules and regulations set forth in 10 CFR               Director of the Office of Nuclear Reactor
                                                Chapter I; the facilities will operate in               Regulation that, as of the date of the license        AGENCY:  Nuclear Regulatory
                                                conformity with the application, the                    transfer, the licensees reflected in the              Commission.
                                                provisions of the Act and the rules and                 amended licenses have obtained the                    ACTION: License amendment application;
                                                regulations of the Commission; there is                 appropriate amount of insurance required of           opportunity to comment, request a
                                                reasonable assurance that the activities                a licensee under 10 CFR part 140 and 10C FR
                                                authorized by the proposed license                      50.54(w).
                                                                                                                                                              hearing, and petition for leave to
sradovich on DSK3TPTVN1PROD with NOTICES




                                                amendments can be conducted without                        IT IS FURTHER ORDERED that after                   intervene.
                                                endangering the health and safety of the                receipt of all required regulatory approvals of
                                                                                                                                                              SUMMARY:   The U.S. Nuclear Regulatory
                                                public and that such activities will be                 the proposed transfer action, Luminant
                                                conducted in compliance with the                        Power shall inform the Director of the Office         Commission (NRC) is considering
                                                Commission’s regulations; the issuance of the           of Nuclear Reactor Regulation in writing of           issuance of amendments to Facility
                                                proposed license amendments will not be                 such receipt within 5 business days, and of           Operating License Nos. DPR–70 and 75,
                                                inimical to the common defense and security             the date of the closing of the direct transfer        issued to PSEG Nuclear LLC (PSEG or
                                                or to the health and safety of the public; and          no later than 7 business days before the date         the licensee) for operation of the Salem


                                           VerDate Sep<11>2014   18:25 May 20, 2016   Jkt 238001   PO 00000   Frm 00078   Fmt 4703   Sfmt 4703   E:\FR\FM\23MYN1.SGM   23MYN1


                                                32352                           Federal Register / Vol. 81, No. 99 / Monday, May 23, 2016 / Notices

                                                Nuclear Generating Station (Salem),                     (ADAMS): You may obtain publicly-                     spring 2017 (2R22) outage to align with
                                                Unit Nos. 1 and 2. The proposed                         available documents online in the                     the outages for the replacement of the
                                                amendments would extend the                             ADAMS Public Documents collection at                  source range and intermediate range
                                                implementation period for Salem, Unit                   http://www.nrc.gov/reading-rm/                        detectors.
                                                No. 1, License Amendment No. 311, and                   adams.html. To begin the search, select                  Before any issuance of the proposed
                                                Salem, Unit No. 2, License Amendment                    ‘‘ADAMS Public Documents’’ and then                   license amendments, the NRC will need
                                                No. 292, from July 5, 2016 (120 days                    select ‘‘Begin Web-based ADAMS                        to make the findings required by the
                                                from the March 7, 2016, date of issuance                Search.’’ For problems with ADAMS,                    Atomic Energy Act of 1954, as amended
                                                of the amendments), to prior to Mode 6                  please contact the NRC’s Public                       (the Act), and the NRC’s regulations.
                                                entry for the Salem, Unit No. 1, fall 2017              Document Room (PDR) reference staff at                   The NRC has made a proposed
                                                (1R25) outage and prior to Mode 6 entry                 1–800–397–4209, 301–415–4737, or by                   determination that the license
                                                for the Salem, Unit No. 2, spring 2017                  email to pdr.resource@nrc.gov. The                    amendment request involves no
                                                (2R22) outage to align with the outages                 ADAMS accession number for each                       significant hazards consideration. Under
                                                for the replacement of the source range                 document referenced (if it is available in            the NRC’s regulations in § 50.92 of title
                                                and intermediate range detectors.                       ADAMS) is provided the first time that                10 of the Code of Federal Regulations
                                                DATES: Submit comments by June 22,                      it is mentioned in the SUPPLEMENTARY                  (10 CFR), this means that operation of
                                                2016. Requests for a hearing or petition                INFORMATION section of this document.                 the facility in accordance with the
                                                for leave to intervene must be filed by                    • NRC’s PDR: You may examine and                   proposed amendments would not (1)
                                                July 22, 2016.                                          purchase copies of public documents at                involve a significant increase in the
                                                                                                        the NRC’s PDR, Room O1–F21, One                       probability or consequences of an
                                                ADDRESSES: You may submit comments
                                                                                                        White Flint North, 11555 Rockville                    accident previously evaluated; or (2)
                                                by any of the following methods (unless                 Pike, Rockville, Maryland 20852.                      create the possibility of a new or
                                                this document describes a different                                                                           different kind of accident from any
                                                method for submitting comments on a                     B. Submitting Comments
                                                                                                                                                              accident previously evaluated; or (3)
                                                specific subject):                                        Please include Docket ID NRC–2016–                  involve a significant reduction in a
                                                   • Federal Rulemaking Web site: Go to                 0102 in your comment submission.                      margin of safety. As required by 10 CFR
                                                http://www.regulations.gov and search                     The NRC cautions you not to include                 50.91(a), the licensee has provided its
                                                for Docket ID NRC–2016–0102. Address                    identifying or contact information that               analysis of the issue of no significant
                                                questions about NRC dockets to Carol                    you do not want to be publicly                        hazards consideration, which is
                                                Gallagher; telephone: 301–415–3463;                     disclosed in your comment submission.                 presented below:
                                                email: Carol.Gallagher@nrc.gov. For                     The NRC posts all comment
                                                technical questions, contact the                                                                                1. Do the proposed changes involve a
                                                                                                        submissions at http://                                significant increase in the probability or
                                                individual listed in the FOR FURTHER                    www.regulations.gov as well as entering               consequences of an accident previously
                                                INFORMATION CONTACT section of this                     the comment submissions into ADAMS.                   evaluated?
                                                document.                                               The NRC does not routinely edit                         Response: No.
                                                   • Mail comments to: Cindy Bladey,                    comment submissions to remove                           The proposed amendment implementation
                                                Office of Administration, Mail Stop:                    identifying or contact information.                   schedule extension is administrative in
                                                OWFN–12–H08, U.S. Nuclear                                 If you are requesting or aggregating                nature and does not require any
                                                Regulatory Commission, Washington,                      comments from other persons for                       modifications to or change in operation of
                                                DC 20555–0001.                                                                                                plant systems or components. The extension
                                                                                                        submission to the NRC, then you should                of the amendment implementation period
                                                   For additional direction on obtaining                inform those persons not to include                   does not increase the probability or
                                                information and submitting comments,                    identifying or contact information that               consequences of an accident previously
                                                see ‘‘Obtaining Information and                         they do not want to be publicly                       evaluated in the Updated Final Safety
                                                Submitting Comments’’ in the                            disclosed in their comment submission.                Analysis (UFSAR). Current Technical
                                                SUPPLEMENTARY INFORMATION section of                    Your request should state that the NRC                Specification (TS) 3.9.2 requirements will
                                                this document.                                          does not routinely edit comment                       continue to ensure the plant is operated
                                                                                                        submissions to remove such information                consistent with the UFSAR accident analysis
                                                FOR FURTHER INFORMATION CONTACT:                                                                              for a boron dilution event.
                                                Thomas J. Wengert, Office of Nuclear                    before making the comment                               Therefore, the proposed change does not
                                                Reactor Regulation, U.S. Nuclear                        submissions available to the public or                involve a significant increase in the
                                                Regulatory Commission, Washington,                      entering the comment submissions into                 probability or consequences of an accident
                                                DC 20555–0001; telephone: 301–415–                      ADAMS.                                                previously evaluated.
                                                4037, email: Thomas.Wengert@nrc.gov.                                                                            2. Do the proposed changes create the
                                                                                                        II. Introduction                                      possibility of a new or different kind of
                                                SUPPLEMENTARY INFORMATION:                                                                                    accident from any accident previously
                                                                                                           The NRC is considering issuance of
                                                I. Obtaining Information and                            amendments to Facility Operating                      evaluated?
                                                                                                        License Nos. DPR–70 and 75, issued to                   Response: No.
                                                Submitting Comments
                                                                                                                                                                The proposed amendment implementation
                                                                                                        PSEG Nuclear LLC for operation of                     schedule extension is administrative in
                                                A. Obtaining Information
                                                                                                        Salem, Unit Nos. 1 and 2, located in                  nature. The extension of the amendment
                                                  Please refer to Docket ID NRC–2016–                   Salem County, New Jersey.                             implementation does not require any
                                                0102 when contacting the NRC about                         The proposed amendments would                      physical plant modifications, does not alter
                                                the availability of information for this                extend the implementation period for                  any plant systems or components, and does
                                                action. You may obtain publicly-                        Salem, Unit No. 1, License Amendment                  not change the operation of the plant. Current
sradovich on DSK3TPTVN1PROD with NOTICES




                                                available information related to this                   No. 311, and Salem, Unit No. 2, License               TS 3.9.2 requirements will continue to
                                                action by any of the following methods:                 Amendment No. 292, from July 5, 2016                  ensure the plant is operated consistent with
                                                                                                                                                              the UFSAR accident analysis for a boron
                                                  • Federal rulemaking Web site: Go to                  (120 days from March 7, 2016, date of                 dilution event.
                                                http://www.regulations.gov and search                   issuance of the amendments), to prior to                Therefore, the proposed change does not
                                                for Docket ID NRC–2016–0102.                            Mode 6 entry for the Salem, Unit No. 1,               create the possibility of a new or different
                                                  • NRC’s Agencywide Documents                          fall 2017 (1R25) outage and prior to                  kind of accident from any previously
                                                Access and Management System                            Mode 6 entry for the Salem, Unit No. 2,               evaluated.



                                           VerDate Sep<11>2014   18:25 May 20, 2016   Jkt 238001   PO 00000   Frm 00079   Fmt 4703   Sfmt 4703   E:\FR\FM\23MYN1.SGM   23MYN1


                                                                                Federal Register / Vol. 81, No. 99 / Monday, May 23, 2016 / Notices                                             32353

                                                  3. Do the proposed changes involve a                  subject facility operating licenses or                to rely to establish those facts or expert
                                                significant reduction in a margin of safety?            combined license. Requests for a                      opinion. The petition must include
                                                  Response: No.                                         hearing and a petition for leave to                   sufficient information to show that a
                                                  Margin of safety is related to the                    intervene shall be filed in accordance                genuine dispute exists with the
                                                confidence in the ability of the fission
                                                product barriers to perform their intended
                                                                                                        with the Commission’s ‘‘Agency Rules                  applicant on a material issue of law or
                                                functions. These barriers include the fuel              of Practice and Procedure’’ in 10 CFR                 fact. Contentions shall be limited to
                                                cladding, the reactor coolant system pressure           part 2. Interested person(s) should                   matters within the scope of the
                                                boundary, and the containment. The                      consult a current copy of 10 CFR 2.309,               amendments under consideration. The
                                                proposed TS change is administrative in                 which is available at the NRC’s PDR,                  contention must be one which, if
                                                nature and does not affect any of these                 located at One White Flint North, Room                proven, would entitle the requestor/
                                                barriers. Current TS 3.9.2 requirements will            O1–F21, 11555 Rockville Pike (first                   petitioner to relief. A requestor/
                                                continue to ensure the plant is operated                floor), Rockville, Maryland 20852. The                petitioner who fails to satisfy these
                                                consistent with the UFSAR accident analysis             NRC’s regulations are accessible                      requirements with respect to at least one
                                                for a boron dilution event.                             electronically from the NRC Library on                contention will not be permitted to
                                                  Therefore, the proposed change does not
                                                involve a significant reduction in the margin
                                                                                                        the NRC’s Web site at http://                         participate as a party.
                                                of safety.                                              www.nrc.gov/reading-rm/doc-                              Those permitted to intervene become
                                                                                                        collections/cfr/. If a request for a hearing          parties to the proceeding, subject to any
                                                   The NRC staff has reviewed the                       or petition for leave to intervene is filed           limitations in the order granting leave to
                                                licensee’s analysis and, based on this                  within 60 days, the Commission or a                   intervene, and have the opportunity to
                                                review, it appears that the three                       presiding officer designated by the                   participate fully in the conduct of the
                                                standards of 10 CFR 50.92(c) are                        Commission or by the Chief                            hearing with respect to resolution of
                                                satisfied. Therefore, the NRC staff                     Administrative Judge of the Atomic                    that person’s admitted contentions,
                                                proposes to determine that the license                  Safety and Licensing Board Panel, will                including the opportunity to present
                                                amendment request involves a no                         rule on the request and/or petition; and              evidence and to submit a cross-
                                                significant hazards consideration.                      the Secretary or the Chief                            examination plan for cross-examination
                                                   The NRC is seeking public comments                   Administrative Judge of the Atomic                    of witnesses, consistent with NRC
                                                on this proposed determination that the                 Safety and Licensing Board will issue a               regulations, policies and procedures.
                                                license amendment request involves no                   notice of a hearing or an appropriate                    Petitions for leave to intervene must
                                                significant hazards consideration. Any                  order.                                                be filed no later than 60 days from the
                                                comments received within 30 days after                     As required by 10 CFR 2.309, a                     date of publication of this notice.
                                                the date of publication of this notice                  petition for leave to intervene shall set             Requests for hearing, petitions for leave
                                                will be considered in making any final                  forth with particularity the interest of              to intervene, and motions for leave to
                                                determination.                                          the petitioner in the proceeding, and                 file new or amended contentions that
                                                   Normally, the Commission will not                    how that interest may be affected by the              are filed after the 60-day deadline will
                                                issue the amendments until the                          results of the proceeding. The petition               not be entertained absent a
                                                expiration of 60 days after the date of                 should specifically explain the reasons               determination by the presiding officer
                                                publication of this notice. The                         why intervention should be permitted                  that the filing demonstrates good cause
                                                Commission may issue the license                        with particular reference to the                      by satisfying the three factors in 10 CFR
                                                amendments before expiration of the 60-                 following general requirements: (1) The               2.309(c)(1)(i)–(iii).
                                                day notice period if the Commission                     name, address, and telephone number of                   If a hearing is requested, and the
                                                concludes the amendments involve no                     the requestor or petitioner; (2) the                  Commission has not made a final
                                                significant hazards consideration. In                   nature of the requestor’s/petitioner’s                determination on the issue of no
                                                addition, the Commission may issue the                  right under the Act to be made a party                significant hazards consideration, the
                                                amendments prior to the expiration of                   to the proceeding; (3) the nature and                 Commission will make a final
                                                the 30-day comment period if                            extent of the requestor’s/petitioner’s                determination on the issue of no
                                                circumstances change during the 30-day                  property, financial, or other interest in             significant hazards consideration. The
                                                comment period such that failure to act                 the proceeding; and (4) the possible                  final determination will serve to decide
                                                in a timely way would result, for                       effect of any decision or order which                 when the hearing is held. If the final
                                                example, in derating or shutdown of the                 may be entered in the proceeding on the               determination is that the amendment
                                                facility. If the Commission takes action                requestor’s/petitioner’s interest. The                request involves no significant hazards
                                                prior to the expiration of either the                   petition must also set forth the specific             consideration, the Commission may
                                                comment period or the notice period, it                 contentions which the requestor/                      issue the amendments and make them
                                                will publish in the Federal Register a                  petitioner seeks to have litigated at the             immediately effective, notwithstanding
                                                notice of issuance. If the Commission                   proceeding.                                           the request for a hearing. Any hearing
                                                makes a final no significant hazards                       Each contention must consist of a                  held would take place after issuance of
                                                consideration determination, any                        specific statement of the issue of law or             the amendments. If the final
                                                hearing will take place after issuance.                 fact to be raised or controverted. In                 determination is that the amendment
                                                The Commission expects that the need                    addition, the requestor/petitioner shall              request involves a significant hazards
                                                to take this action will occur very                     provide a brief explanation of the bases              consideration, then any hearing held
                                                infrequently.                                           for the contention and a concise                      would take place before the issuance of
                                                                                                        statement of the alleged facts or expert              any amendments unless the
                                                III. Opportunity To Request a Hearing                   opinion which support the contention                  Commission finds an imminent danger
sradovich on DSK3TPTVN1PROD with NOTICES




                                                and Petition for Leave To Intervene                     and on which the requestor/petitioner                 to the health or safety of the public, in
                                                   Within 60 days after the date of                     intends to rely in proving the contention             which case it will issue an appropriate
                                                publication of this notice, any person(s)               at the hearing. The requestor/petitioner              order or rule under 10 CFR part 2.
                                                whose interest may be affected by this                  must also provide references to those                    A State, local governmental body,
                                                action may file a request for a hearing                 specific sources and documents of                     Federally-recognized Indian Tribe, or
                                                and a petition to intervene with respect                which the petitioner is aware and on                  agency thereof, may submit a petition to
                                                to issuance of the amendments to the                    which the requestor/petitioner intends                the Commission to participate as a party


                                           VerDate Sep<11>2014   18:25 May 20, 2016   Jkt 238001   PO 00000   Frm 00080   Fmt 4703   Sfmt 4703   E:\FR\FM\23MYN1.SGM   23MYN1


                                                32354                           Federal Register / Vol. 81, No. 99 / Monday, May 23, 2016 / Notices

                                                under 10 CFR 2.309(h)(1). The petition                  hearing.docket@nrc.gov, or by telephone               Time on the due date. Upon receipt of
                                                should state the nature and extent of the               at 301–415–1677, to request (1) a digital             a transmission, the E-Filing system
                                                petitioner’s interest in the proceeding.                identification (ID) certificate, which                time-stamps the document and sends
                                                The petition should be submitted to the                 allows the participant (or its counsel or             the submitter an email notice
                                                Commission by July 22, 2016. The                        representative) to digitally sign                     confirming receipt of the document. The
                                                petition must be filed in accordance                    documents and access the E-Submittal                  E-Filing system also distributes an email
                                                with the filing instructions in the                     server for any proceeding in which it is              notice that provides access to the
                                                ‘‘Electronic Submissions (E-Filing)’’                   participating; and (2) advise the                     document to the NRC’s Office of the
                                                section of this document, and should                    Secretary that the participant will be                General Counsel and any others who
                                                meet the requirements for petitions for                 submitting a request or petition for                  have advised the Office of the Secretary
                                                leave to intervene set forth in this                    hearing (even in instances in which the               that they wish to participate in the
                                                section, except that under § 2.309(h)(2)                participant, or its counsel or                        proceeding, so that the filer need not
                                                a State, local governmental body, or                    representative, already holds an NRC-                 serve the documents on those
                                                Federally-recognized Indian Tribe, or                   issued digital ID certificate). Based upon            participants separately. Therefore,
                                                agency thereof does not need to address                 this information, the Secretary will                  applicants and other participants (or
                                                the standing requirements in 10 CFR                     establish an electronic docket for the                their counsel or representative) must
                                                2.309(d) if the facility is located within              hearing in this proceeding if the                     apply for and receive a digital ID
                                                its boundaries. A State, local                          Secretary has not already established an              certificate before a hearing request/
                                                governmental body, Federally-                           electronic docket.                                    petition to intervene is filed so that they
                                                recognized Indian Tribe, or agency                         Information about applying for a                   can obtain access to the document via
                                                thereof may also have the opportunity to                digital ID certificate is available on the            the E-Filing system.
                                                participate under 10 CFR 2.315(c).                      NRC’s public Web site at http://                         A person filing electronically using
                                                   If a hearing is granted, any person                  www.nrc.gov/site-help/e-submittals/                   the NRC’s adjudicatory E-Filing system
                                                who does not wish, or is not qualified,                 getting-started.html. System                          may seek assistance by contacting the
                                                to become a party to the proceeding                     requirements for accessing the E-                     NRC Meta System Help Desk through
                                                may, in the discretion of the presiding                 Submittal server are detailed in the                  the ‘‘Contact Us’’ link located on the
                                                officer, be permitted to make a limited                 NRC’s ‘‘Guidance for Electronic                       NRC’s public Web site at http://
                                                appearance pursuant to the provisions                   Submission,’’ which is available on the               www.nrc.gov/site-help/e-
                                                of 10 CFR 2.315(a). A person making a                   agency’s public Web site at http://                   submittals.html, by email to
                                                limited appearance may make an oral or                  www.nrc.gov/site-help/e-                              MSHD.Resource@nrc.gov, or by a toll-
                                                written statement of position on the                    submittals.html. Participants may                     free call at 1–866–672–7640. The NRC
                                                issues, but may not otherwise                           attempt to use other software not listed              Meta System Help Desk is available
                                                participate in the proceeding. A limited                on the Web site, but should note that the             between 8 a.m. and 8 p.m., Eastern
                                                appearance may be made at any session                   NRC’s E-Filing system does not support                Time, Monday through Friday,
                                                of the hearing or at any prehearing                     unlisted software, and the NRC Meta                   excluding government holidays.
                                                conference, subject to the limits and                   System Help Desk will not be able to                     Participants who believe that they
                                                conditions as may be imposed by the                     offer assistance in using unlisted                    have a good cause for not submitting
                                                presiding officer. Persons desiring to                  software.                                             documents electronically must file an
                                                make a limited appearance are                              If a participant is electronically                 exemption request, in accordance with
                                                requested to inform the Secretary of the                submitting a document to the NRC in                   10 CFR 2.302(g), with their initial paper
                                                Commission by July 22, 2016.                            accordance with the E-Filing rule, the                filing requesting authorization to
                                                                                                        participant must file the document                    continue to submit documents in paper
                                                IV. Electronic Submissions (E-Filing)                   using the NRC’s online, Web-based                     format. Such filings must be submitted
                                                  All documents filed in NRC                            submission form. In order to serve                    by: (1) First class mail addressed to the
                                                adjudicatory proceedings, including a                   documents through the Electronic                      Office of the Secretary of the
                                                request for hearing, a petition for leave               Information Exchange System, users                    Commission, U.S. Nuclear Regulatory
                                                to intervene, any motion or other                       will be required to install a Web                     Commission, Washington, DC 20555–
                                                document filed in the proceeding prior                  browser plug-in from the NRC’s Web                    0001, Attention: Rulemaking and
                                                to the submission of a request for                      site. Further information on the Web-                 Adjudications Staff; or (2) courier,
                                                hearing or petition to intervene, and                   based submission form, including the                  express mail, or expedited delivery
                                                documents filed by interested                           installation of the Web browser plug-in,              service to the Office of the Secretary,
                                                governmental entities participating                     is available on the NRC’s public Web                  Sixteenth Floor, One White Flint North,
                                                under 10 CFR 2.315(c), must be filed in                 site at http://www.nrc.gov/site-help/e-               11555 Rockville Pike, Rockville,
                                                accordance with the NRC’s E-Filing rule                 submittals.html.                                      Maryland, 20852, Attention:
                                                (72 FR 49139; August 28, 2007). The E-                     Once a participant has obtained a                  Rulemaking and Adjudications Staff.
                                                Filing process requires participants to                 digital ID certificate and a docket has               Participants filing a document in this
                                                submit and serve all adjudicatory                       been created, the participant can then                manner are responsible for serving the
                                                documents over the Internet, or in some                 submit a request for hearing or petition              document on all other participants.
                                                cases to mail copies on electronic                      for leave to intervene. Submissions                   Filing is considered complete by first-
                                                storage media. Participants may not                     should be in Portable Document Format                 class mail as of the time of deposit in
                                                submit paper copies of their filings                    (PDF) in accordance with NRC guidance                 the mail, or by courier, express mail, or
                                                unless they seek an exemption in                        available on the NRC’s public Web site                expedited delivery service upon
sradovich on DSK3TPTVN1PROD with NOTICES




                                                accordance with the procedures                          at http://www.nrc.gov/site-help/e-                    depositing the document with the
                                                described below.                                        submittals.html. A filing is considered               provider of the service. A presiding
                                                  To comply with the procedural                         complete at the time the documents are                officer, having granted an exemption
                                                requirements of E-Filing, at least 10                   submitted through the NRC’s E-Filing                  request from using E-Filing, may require
                                                days prior to the filing deadline, the                  system. To be timely, an electronic                   a participant or party to use E-Filing if
                                                participant should contact the Office of                filing must be submitted to the E-Filing              the presiding officer subsequently
                                                the Secretary by email at                               system no later than 11:59 p.m. Eastern               determines that the reason for granting


                                           VerDate Sep<11>2014   18:25 May 20, 2016   Jkt 238001   PO 00000   Frm 00081   Fmt 4703   Sfmt 4703   E:\FR\FM\23MYN1.SGM   23MYN1


                                                                                Federal Register / Vol. 81, No. 99 / Monday, May 23, 2016 / Notices                                             32355

                                                the exemption from use of E-Filing no                   unwarranted invasion of personal                      NUCLEAR REGULATORY
                                                longer exists.                                          privacy.                                              COMMISSION
                                                   Documents submitted in adjudicatory                    The agenda for the subject meeting                  [NRC–2015–0285]
                                                proceedings will appear in the NRC’s                    shall be as follows:
                                                electronic hearing docket which is                                                                            Containment Shell or Liner Moisture
                                                available to the public at http://                      Wednesday, June 8, 2016—12:00 p.m.
                                                                                                                                                              Barrier Inspection
                                                ehd1.nrc.gov/ehd/, unless excluded                      Until 1:00 p.m.
                                                pursuant to an order of the Commission,                                                                       AGENCY:  Nuclear Regulatory
                                                                                                           The Subcommittee will discuss                      Commission.
                                                or the presiding officer. Participants are
                                                                                                        proposed ACRS activities and related
                                                requested not to include personal                                                                             ACTION: Regulatory issue summary;
                                                                                                        matters. The Subcommittee will gather
                                                privacy information, such as social                                                                           issuance.
                                                                                                        information, analyze relevant issues and
                                                security numbers, home addresses, or
                                                                                                        facts, and formulate proposed positions               SUMMARY:    The U.S. Nuclear Regulatory
                                                home phone numbers in their filings,
                                                                                                        and actions, as appropriate, for                      Commission (NRC) is issuing Regulatory
                                                unless an NRC regulation or other law
                                                                                                        deliberation by the Full Committee.                   Issue Summary (RIS) 2016–07,
                                                requires submission of such
                                                information. However, in some                              Members of the public desiring to                  ‘‘Containment Shell or Liner Moisture
                                                instances, a request to intervene will                  provide oral statements and/or written                Barrier Inspection.’’ This RIS reiterates
                                                require including information on local                  comments should notify the Designated                 the NRC staff’s position regarding
                                                residence in order to demonstrate a                     Federal Official (DFO), Quynh Nguyen                  American Society of Mechanical
                                                proximity assertion of interest in the                  (Telephone 301–415–5844 or Email:                     Engineers (ASME) code inservice
                                                proceeding. With respect to copyrighted                 Quynh.Nguyen@nrc.gov) five days prior                 inspection requirements for moisture
                                                works, except for limited excerpts that                 to the meeting, if possible, so that                  barriers. The NRC’s regulations require,
                                                serve the purpose of the adjudicatory                   arrangements can be made. Thirty-five                 in part, that licensees implement the
                                                filings and would constitute a Fair Use                 hard copies of each presentation or                   inservice inspection program for
                                                application, participants are requested                 handout should be provided to the DFO                 pressure retaining components and their
                                                not to include copyrighted materials in                 thirty minutes before the meeting. In                 integral attachments of metal
                                                their submission.                                       addition, one electronic copy of each                 containments and metallic liners of
                                                   For further details with respect to this             presentation should be emailed to the                 concrete containments in accordance
                                                action, see the application for license                 DFO one day before the meeting. If an                 with the ASME Code. If a material
                                                amendment dated May 10, 2016                            electronic copy cannot be provided                    prevents moisture from contacting
                                                (ADAMS Accession No. ML16131A555).                      within this timeframe, presenters                     inaccessible areas of the containment
                                                   Attorney for licensee: Jeffrie J. Keenan,            should provide the DFO with a CD                      shell or liner, especially if the material
                                                PSEG Nuclear LLC—N21, P.O. Box 236,                     containing each presentation at least                 is being relied upon in lieu of
                                                Hancocks Bridge, NJ 08038.                              thirty minutes before the meeting.                    augmented examinations of a
                                                   NRC Branch Chief: Douglas A.                         Electronic recordings will be permitted               susceptible location, the material must
                                                Broaddus.                                               only during those portions of the                     be inspected as a moisture barrier. The
                                                                                                        meeting that are open to the public.                  applicable ASME Code sections require
                                                  Dated at Rockville, Maryland, this 17th day           Detailed procedures for the conduct of                licensees to inspect 100 percent of
                                                of May 2016.
                                                                                                        and participation in ACRS meetings                    accessible moisture barriers during each
                                                  For the Nuclear Regulatory Commission.                were published in the Federal Register                inspection period.
                                                Andrew Hon,                                             on October 21, 2015 (80 FR 63846).                    DATES: The RIS is available as of May
                                                Acting Chief, Plant Licensing Branch I–2,                                                                     23, 2016.
                                                Division of Operating Reactor Licensing,                   Information regarding changes to the
                                                Office of Nuclear Reactor Regulation.                   agenda, whether the meeting has been                  ADDRESSES: Please refer to Docket ID
                                                [FR Doc. 2016–12054 Filed 5–20–16; 8:45 am]
                                                                                                        canceled or rescheduled, and the time                 NRC–2015–0285 when contacting the
                                                                                                        allotted to present oral statements can               NRC about the availability of
                                                BILLING CODE 7590–01–P
                                                                                                        be obtained by contacting the identified              information regarding this document.
                                                                                                        DFO. Moreover, in view of the                         You may obtain publicly-available
                                                NUCLEAR REGULATORY                                      possibility that the schedule for ACRS                information related to this document
                                                COMMISSION                                              meetings may be adjusted by the                       using any of the following methods:
                                                                                                        Chairman as necessary to facilitate the                  • Federal Rulemaking Web site: Go to
                                                Advisory Committee on Reactor                           conduct of the meeting, persons                       http://www.regulations.gov and search
                                                Safeguards (ACRS); Meeting of the                       planning to attend should check with                  for Docket ID NRC–2015–0285. Address
                                                ACRS Subcommittee on Planning and                       the DFO if such rescheduling would                    questions about NRC dockets to Carol
                                                Procedures; Notice of Meeting                           result in a major inconvenience.                      Gallagher; telephone: 301–415–3463;
                                                                                                           If attending this meeting, please enter            email: Carol.Gallagher@nrc.gov. For
                                                   The ACRS Subcommittee on Planning                    through the One White Flint North                     technical questions, contact the
                                                and Procedures will hold a meeting on                   building, 11555 Rockville Pike,                       individual listed in the FOR FURTHER
                                                June 8, 2016, Room T–2B3, 11545                         Rockville, MD. After registering with                 INFORMATION CONTACT section of this
                                                Rockville Pike, Rockville, Maryland.                    security, please contact Mr. Theron                   document.
                                                   The meeting will be open to public                   Brown (240–888–9835) to be escorted to                   • NRC’s Agencywide Documents
                                                attendance with the exception of a                                                                            Access and Management System
sradovich on DSK3TPTVN1PROD with NOTICES




                                                                                                        the meeting room.
                                                portion that may be closed pursuant to                                                                        (ADAMS): You may obtain publicly-
                                                5 U.S.C. 552b(c)(2) and (6) to discuss                    Dated: May 11, 2016.                                available documents online in the
                                                organizational and personnel matters                    Mark L. Banks,                                        ADAMS Public Documents collection at
                                                that relate solely to the internal                      Chief, Technical Support Branch, Advisory             http://www.nrc.gov/reading-rm/
                                                personnel rules and practices of the                    Committee on Reactor Safeguards.                      adams.html. To begin the search, select
                                                ACRS, and information the release of                    [FR Doc. 2016–12052 Filed 5–20–16; 8:45 am]           ‘‘ADAMS Public Documents’’ and then
                                                which would constitute a clearly                        BILLING CODE 7590–01–P=                               select ‘‘Begin Web-based ADAMS


                                           VerDate Sep<11>2014   18:25 May 20, 2016   Jkt 238001   PO 00000   Frm 00082   Fmt 4703   Sfmt 4703   E:\FR\FM\23MYN1.SGM   23MYN1



Document Created: 2018-02-07 15:07:31
Document Modified: 2018-02-07 15:07:31
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionLicense amendment application; opportunity to comment, request a hearing, and petition for leave to intervene.
DatesSubmit comments by June 22, 2016. Requests for a hearing or petition for leave to intervene must be filed by July 22, 2016.
ContactThomas J. Wengert, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-4037, email: [email protected]