81_FR_33621 81 FR 33519 - Rio Grande LNG, LLC, Rio Bravo Pipeline Company, LLC; Notice of Application

81 FR 33519 - Rio Grande LNG, LLC, Rio Bravo Pipeline Company, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 102 (May 26, 2016)

Page Range33519-33520
FR Document2016-12414

Federal Register, Volume 81 Issue 102 (Thursday, May 26, 2016)
[Federal Register Volume 81, Number 102 (Thursday, May 26, 2016)]
[Notices]
[Pages 33519-33520]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-12414]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP16-454-000, CP16-455-000, PF15-14-000]


Rio Grande LNG, LLC, Rio Bravo Pipeline Company, LLC; Notice of 
Application

    Take notice that on May 5, 2016, Rio Grande LNG, LLC (Rio Grande), 
3 Water-way Square Place, Suite 400, The Woodlands, Texas 77380, filed 
an application, in Docket No. CP16-454-000, pursuant to section 3(a) of 
the Natural Gas Act (NGA) and Part 153 of the Commission's Regulations, 
requesting authorization to site, construct, modify, and operate a 
natural gas liquefaction facility and liquefied natural gas export and 
truck loading terminal, located in Cameron County, Texas.
    Also, take notice that on May 5, 2016, Rio Bravo Pipeline Company, 
LLC (Rio Bravo), 3 Waterway Square Place, Suite 400, The Woodlands, 
Texas 77380, filed an application pursuant to Section 7(c) of the NGA, 
and Parts 157 and 284 of the Commission's regulations, an application 
in Docket No. CP16-455-000 for (1) a certificate of public convenience 
and necessity (i) authorizing Rio Bravo to construct, own, and operate 
a natural gas pipeline system, (ii) approving a pro forma Tariff, and 
(iii) approving the proposed initial rates for service; (2) a Part 157, 
Subpart F blanket certificate authorizing Rio Bravo to engage in 
certain self-implementing routine activities; and (3) a Part 284, 
Subpart G blanket certificate authorizing Rio Bravo to transport 
natural gas, on an open access and self-implementing basis.
    These filings may be viewed on the web at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-
free (886) 208-3676 or TYY (202) 502-8659.
    Any questions regarding this application should be directed to 
Shaun Davison, Senior Vice President, Rio Grande LNG, LLC/Rio Bravo 
Pipeline Company, LLC, 3 Waterway Square Place, Suite 400, The 
Woodlands, Texas

[[Page 33520]]

77380, (832) 403-3040, shaun@riobravopipeline.com, or Erik J.A. 
Swenson, Norton Rose Fulbright US LLP, 799 9th Street NW., Suite 1000, 
Washington, DC 20001-4501, (202) 662-4555, 
erik.j.a.swenson@nortonrosefulbright.com, with written and electronic 
correspondence copied to Krysta De Lima, General Counsel, Rio Grande 
LNG, LLC/Rio Bravo Pipeline Company, LLC, 3 Waterway Square Place, 
Suite 400, The Woodlands, Texas 77380, krysta@riobravopipeline.com.
    Specifically, Rio Grande proposes to construct an LNG export 
terminal on the Port of Brownsville ship channel. The terminal will 
consist of six liquefaction trains with a total capacity of 3.6 Bcf per 
day, four LNG tanks capable of storing 15.26 Bcf of LNG, marine and 
truck loading facilities, and all necessary ancillary and support 
facilities.
    Rio Bravo proposes to construct 139.4 miles of pipeline, three 
compressor stations and two booster stations totaling 600,000 hp, and 
associated facilities to deliver up to 4.5 Bcf per day of natural gas 
from the Agua Dulce Market area to the Rio Grande terminal. The 
facilities will be located in Jim Wells, Kleberg, Kenedy, Willacy and 
Cameron Counties, Texas. The pipeline facilities cost an estimated 
$2,173,362,909.
    On April 13, 2015, the Commission staff granted Rio Grande/Rio 
Bravo's request to use the National Environmental Policy Act (NEPA) 
Pre-Filing Process and assigned Docket No. PF15-20-000 to staff 
activities involving the proposed facilities. Now, as of the filing of 
this application on May 5, 2016, the NEPA Pre-Filing Process for this 
project has ended. From this time forward, this proceeding will be 
conducted in Docket Nos. CP16-454-000 and CP16-455-000, as noted in the 
caption of this Notice.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule will serve to 
notify federal and state agencies of the timing for the completion of 
all necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 5 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    Motions to intervene, protests and comments may be filed 
electronically via the internet in lieu of paper; see, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. The Commission strongly encourages 
electronic filings.
    Comment Date: 5:00 p.m. Eastern Time May 9, 2016.

    Dated: May 19, 2016.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2016-12414 Filed 5-25-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 81, No. 102 / Thursday, May 26, 2016 / Notices                                                  33519

                                                comments must be filed with the                         particular application, a competing                     Dated: May 20, 2016.
                                                Commission: 105 days from the                           development application, or a notice of               Kimberly D. Bose,
                                                issuance of this notice.                                intent to file such an application.                   Secretary.
                                                   The Commission strongly encourages                   Submission of a timely notice of intent               [FR Doc. 2016–12412 Filed 5–25–16; 8:45 am]
                                                electronic filing. Please file comments,                allows an interested person to file the               BILLING CODE 6717–01–P
                                                motions to intervene, and protests using                competing development application no
                                                the Commission’s eFiling system at                      later than 120 days after the specified
                                                http://www.ferc.gov/docs-filing/                        deadline date for the particular                      DEPARTMENT OF ENERGY
                                                efiling.asp. Commenters can submit                      application. Applications for
                                                brief comments up to 6,000 characters,                  preliminary permits will not be                       Federal Energy Regulatory
                                                without prior registration, using the                   accepted in response to this notice.                  Commission
                                                eComment system at http://                                 o. Protests or Motions to Intervene—               [Docket Nos. CP16–454–000, CP16–455–
                                                www.ferc.gov/docs-filing/                               Anyone may submit a protest or a                      000, PF15–14–000]
                                                ecomment.asp. You must include your                     motion to intervene in accordance with
                                                name and contact information at the end                 the requirements of Rules of Practice                 Rio Grande LNG, LLC, Rio Bravo
                                                of your comments. For assistance,                       and Procedure, 18 CFR 385.210,                        Pipeline Company, LLC; Notice of
                                                please contact FERC Online Support at                   385.211, and 385.214. In determining                  Application
                                                FERCOnlineSupport@ferc.gov, (866)                       the appropriate action to take, the
                                                208–3676 (toll free), or (202) 502–8659                                                                          Take notice that on May 5, 2016, Rio
                                                                                                        Commission will consider all protests                 Grande LNG, LLC (Rio Grande), 3
                                                (TTY). In lieu of electronic filing, please             filed, but only those who file a motion
                                                send a paper copy to: Secretary, Federal                                                                      Water-way Square Place, Suite 400, The
                                                                                                        to intervene in accordance with the                   Woodlands, Texas 77380, filed an
                                                Energy Regulatory Commission, 888                       Commission’s Rules may become a
                                                First Street NE., Washington, DC 20426.                                                                       application, in Docket No. CP16–454–
                                                                                                        party to the proceeding. Any protests or              000, pursuant to section 3(a) of the
                                                The first page of any filing should                     motions to intervene must be received
                                                include docket number P–14776–000.                                                                            Natural Gas Act (NGA) and Part 153 of
                                                                                                        on or before the specified deadline date              the Commission’s Regulations,
                                                   The Commission’s Rules of Practice
                                                                                                        for the particular application.                       requesting authorization to site,
                                                and Procedure require all intervenors
                                                filing documents with the Commission                       p. All filings must (1) bear in all                construct, modify, and operate a natural
                                                to serve a copy of that document on                     capital letters the title ‘‘PROTEST,’’                gas liquefaction facility and liquefied
                                                each person on the official service list                ‘‘MOTION TO INTERVENE,’’                              natural gas export and truck loading
                                                for the project. Further, if an intervenor              ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’                     terminal, located in Cameron County,
                                                files comments or documents with the                    ‘‘RECOMMENDATIONS,’’ ‘‘TERMS                          Texas.
                                                Commission relating to the merits of an                 AND CONDITIONS,’’ or                                     Also, take notice that on May 5, 2016,
                                                issue that may affect the responsibilities              ‘‘PRESCRIPTIONS;’’ (2) set forth in the               Rio Bravo Pipeline Company, LLC (Rio
                                                of a particular resource agency, they                   heading, the name of the applicant and                Bravo), 3 Waterway Square Place, Suite
                                                must also serve a copy of the document                  the project number of the application to              400, The Woodlands, Texas 77380, filed
                                                on that resource agency.                                which the filing responds; (3) furnish                an application pursuant to Section 7(c)
                                                   l. Description of the project: The                   the name, address, and telephone                      of the NGA, and Parts 157 and 284 of
                                                proposed C.C. Cragin Raw Water Supply                   number of the person protesting or                    the Commission’s regulations, an
                                                Line Small Conduit Hydroelectric                        intervening; and (4) otherwise comply                 application in Docket No. CP16–455–
                                                Project would consist of: (1) A proposed                with the requirements of 18 CFR                       000 for (1) a certificate of public
                                                powerhouse containing one proposed                      385.2001 through 385.2005. All                        convenience and necessity (i)
                                                generating unit with an installed                       comments, recommendations, terms and                  authorizing Rio Bravo to construct, own,
                                                capacity of 200 kilowatts placed in the                 conditions or prescriptions must set                  and operate a natural gas pipeline
                                                18-inch-diameter water supply pipeline;                 forth their evidentiary basis and                     system, (ii) approving a pro forma
                                                and (2) appurtenant facilities. The                     otherwise comply with the requirements                Tariff, and (iii) approving the proposed
                                                applicant estimates the project would                   of 18 CFR 4.34(b). Agencies may obtain                initial rates for service; (2) a Part 157,
                                                have an average annual generation of                    copies of the application directly from               Subpart F blanket certificate authorizing
                                                1.256 gigawatt-hours.                                   the applicant. Any of these documents                 Rio Bravo to engage in certain self-
                                                   m. This filing is available for review               must be filed by providing the original               implementing routine activities; and (3)
                                                and reproduction at the Commission in                   and seven copies to: The Secretary,                   a Part 284, Subpart G blanket certificate
                                                the Public Reference Room, Room 2A,                     Federal Energy Regulatory Commission,                 authorizing Rio Bravo to transport
                                                888 First Street NE., Washington, DC                    888 First Street NE., Washington, DC                  natural gas, on an open access and self-
                                                20426. The filing may also be viewed on                 20426. An additional copy must be sent                implementing basis.
                                                the web at http://www.ferc.gov/docs-                    to Director, Division of Hydropower                      These filings may be viewed on the
                                                filing/elibrary.asp using the ‘‘eLibrary’’              Administration and Compliance, Office                 web at http://www.ferc.gov using the
                                                link. Enter the docket number, P–14776,                 of Energy Projects, Federal Energy                    ‘‘eLibrary’’ link. Enter the docket
                                                in the docket number field to access the                Regulatory Commission, at the above                   number excluding the last three digits in
                                                document. For assistance, call toll-free                address. A copy of any protest or motion              the docket number field to access the
                                                1–866–208–3676 or email                                 to intervene must be served upon each                 document. For assistance, contact FERC
                                                FERCOnlineSupport@ferc.gov. For TTY,                    representative of the applicant specified             at FERCOnlineSupport@ferc.gov or call
                                                call (202) 502–8659. A copy is also                     in the particular application. A copy of              toll-free (886) 208–3676 or TYY (202)
sradovich on DSK3TPTVN1PROD with NOTICES




                                                available for review and reproduction at                all other filings in reference to this                502–8659.
                                                the address in item h above.                            application must be accompanied by                       Any questions regarding this
                                                   n. Development Application—Any                       proof of service on all persons listed in             application should be directed to Shaun
                                                qualified applicant desiring to file a                  the service list prepared by the                      Davison, Senior Vice President, Rio
                                                competing application must submit to                    Commission in this proceeding, in                     Grande LNG, LLC/Rio Bravo Pipeline
                                                the Commission, on or before the                        accordance with 18 CFR 4.34(b) and                    Company, LLC, 3 Waterway Square
                                                specified deadline date for the                         385.2010.                                             Place, Suite 400, The Woodlands, Texas


                                           VerDate Sep<11>2014   18:47 May 25, 2016   Jkt 238001   PO 00000   Frm 00061   Fmt 4703   Sfmt 4703   E:\FR\FM\26MYN1.SGM   26MYN1


                                                33520                         Federal Register / Vol. 81, No. 102 / Thursday, May 26, 2016 / Notices

                                                77380, (832) 403–3040, shaun@                           complete all federal authorizations                   to seek court review of the
                                                riobravopipeline.com, or Erik J.A.                      within 90 days of the date of issuance                Commission’s final order.
                                                Swenson, Norton Rose Fulbright US                       of the Commission staff’s FEIS or EA.                    Motions to intervene, protests and
                                                LLP, 799 9th Street NW., Suite 1000,                       There are two ways to become                       comments may be filed electronically
                                                Washington, DC 20001–4501, (202) 662–                   involved in the Commission’s review of                via the internet in lieu of paper; see, 18
                                                4555, erik.j.a.swenson@                                 this project. First, any person wishing to            CFR 385.2001(a)(1)(iii) and the
                                                nortonrosefulbright.com, with written                   obtain legal status by becoming a party               instructions on the Commission’s Web
                                                and electronic correspondence copied to                 to the proceedings for this project                   site under the ‘‘e-Filing’’ link. The
                                                Krysta De Lima, General Counsel, Rio                    should, on or before the comment date                 Commission strongly encourages
                                                Grande LNG, LLC/Rio Bravo Pipeline                      stated below, file with the Federal                   electronic filings.
                                                Company, LLC, 3 Waterway Square                         Energy Regulatory Commission, 888                        Comment Date: 5:00 p.m. Eastern
                                                Place, Suite 400, The Woodlands, Texas                  First Street NE., Washington, DC 20426,               Time May 9, 2016.
                                                77380, krysta@riobravopipeline.com.                     a motion to intervene in accordance                     Dated: May 19, 2016.
                                                   Specifically, Rio Grande proposes to                 with the requirements of the                          Kimberly D. Bose,
                                                construct an LNG export terminal on the                 Commission’s Rules of Practice and                    Secretary.
                                                Port of Brownsville ship channel. The                   Procedure (18 CFR 385.214 or 385.211)
                                                terminal will consist of six liquefaction                                                                     [FR Doc. 2016–12414 Filed 5–25–16; 8:45 am]
                                                                                                        and the Regulations under the NGA (18
                                                trains with a total capacity of 3.6 Bcf per             CFR 157.10). A person obtaining party
                                                                                                                                                              BILLING CODE 6717–01–P
                                                day, four LNG tanks capable of storing                  status will be placed on the service list
                                                15.26 Bcf of LNG, marine and truck                      maintained by the Secretary of the
                                                loading facilities, and all necessary                                                                         DEPARTMENT OF ENERGY
                                                                                                        Commission and will receive copies of
                                                ancillary and support facilities.                       all documents filed by the applicant and
                                                   Rio Bravo proposes to construct 139.4                                                                      Federal Energy Regulatory
                                                                                                        by all other parties. A party must submit             Commission
                                                miles of pipeline, three compressor                     5 copies of filings made with the
                                                stations and two booster stations                       Commission and must mail a copy to                    Combined Notice of Filings #1
                                                totaling 600,000 hp, and associated
                                                                                                        the applicant and to every other party in
                                                facilities to deliver up to 4.5 Bcf per day                                                                      Take notice that the Commission
                                                                                                        the proceeding. Only parties to the
                                                of natural gas from the Agua Dulce                                                                            received the following exempt
                                                                                                        proceeding can ask for court review of
                                                Market area to the Rio Grande terminal.                                                                       wholesale generator filings:
                                                                                                        Commission orders in the proceeding.
                                                The facilities will be located in Jim                                                                            Docket Numbers: EG16–105–000.
                                                Wells, Kleberg, Kenedy, Willacy and                        However, a person does not have to                    Applicants: Portal Ridge Solar B, LLC.
                                                Cameron Counties, Texas. The pipeline                   intervene in order to have comments                      Description: Self-Certification of
                                                facilities cost an estimated                            considered. The second way to                         Exempt Wholesale Generator Status of
                                                $2,173,362,909.                                         participate is by filing with the                     Portal Ridge Solar B, LLC.
                                                   On April 13, 2015, the Commission                    Secretary of the Commission, as soon as                  Filed Date: 5/20/16.
                                                staff granted Rio Grande/Rio Bravo’s                    possible, an original and two copies of                  Accession Number: 20160520–5121.
                                                request to use the National                             comments in support of or in opposition                  Comments Due: 5 p.m. ET 6/10/16.
                                                Environmental Policy Act (NEPA) Pre-                    to this project. The Commission will                     Take notice that the Commission
                                                Filing Process and assigned Docket No.                  consider these comments in                            received the following electric rate
                                                PF15–20–000 to staff activities                         determining the appropriate action to be              filings:
                                                involving the proposed facilities. Now,                 taken, but the filing of a comment alone                 Docket Numbers: ER10–1819–015;
                                                as of the filing of this application on                 will not serve to make the filer a party              ER10–1820–018; ER10–1818–013;
                                                May 5, 2016, the NEPA Pre-Filing                        to the proceeding. The Commission’s                   ER10–1817–014.
                                                Process for this project has ended. From                rules require that persons filing                        Applicants: Northern States Power
                                                this time forward, this proceeding will                 comments in opposition to the project                 Company, a Minnesota corporation,
                                                be conducted in Docket Nos. CP16–454–                   provide copies of their protests only to              Northern States Power Company, a
                                                000 and CP16–455–000, as noted in the                   the party or parties directly involved in             Wisconsin corporation, Public Service
                                                caption of this Notice.                                 the protest.                                          Company of Colorado, Southwestern
                                                   Pursuant to section 157.9 of the                        Persons who wish to comment only                   Public Service Company.
                                                Commission’s rules, 18 CFR 157.9,                       on the environmental review of this                      Description: Notice of Change in
                                                within 90 days of this Notice the                       project should submit an original and                 Status of Northern States Power
                                                Commission staff will either: complete                  two copies of their comments to the                   Company, a Minnesota corporation, et
                                                its environmental assessment (EA) and                   Secretary of the Commission.                          al.
                                                place it into the Commission’s public                   Environmental commenters will be                         Filed Date: 5/19/16.
                                                record (eLibrary) for this proceeding, or               placed on the Commission’s                               Accession Number: 20160519–5213.
                                                issue a Notice of Schedule for                          environmental mailing list, will receive                 Comments Due: 5 p.m. ET 6/9/16.
                                                Environmental Review. If a Notice of                    copies of the environmental documents,                   Docket Numbers: ER14–1485–007.
                                                Schedule for Environmental Review is                    and will be notified of meetings                         Applicants: PJM Interconnection,
                                                issued, it will indicate, among other                   associated with the Commission’s                      L.L.C.
                                                milestones, the anticipated date for the                environmental review process.                            Description: Compliance filing:
                                                Commission staff’s issuance of the final                Environmental commenters will not be                  Compliance filing per 4/22/2016 order
                                                environmental impact statement (FEIS)                   required to serve copies of filed                     in Docket Nos. EL15–18, ER14–1485 et
sradovich on DSK3TPTVN1PROD with NOTICES




                                                or EA for this proposal. The filing of the              documents on all other parties.                       al to be effective 12/31/9998.
                                                EA in the Commission’s public record                    However, the non-party commenters                        Filed Date: 5/20/16.
                                                for this proceeding or the issuance of a                will not receive copies of all documents                 Accession Number: 20160520–5070.
                                                Notice of Schedule will serve to notify                 filed by other parties or issued by the                  Comments Due: 5 p.m. ET 6/10/16.
                                                federal and state agencies of the timing                Commission (except for the mailing of                    Docket Numbers: ER16–829–001.
                                                for the completion of all necessary                     environmental documents issued by the                    Applicants: Southwest Power Pool,
                                                reviews, and the subsequent need to                     Commission) and will not have the right               Inc.


                                           VerDate Sep<11>2014   18:47 May 25, 2016   Jkt 238001   PO 00000   Frm 00062   Fmt 4703   Sfmt 4703   E:\FR\FM\26MYN1.SGM   26MYN1



Document Created: 2016-05-26 01:14:14
Document Modified: 2016-05-26 01:14:14
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time May 9, 2016.
FR Citation81 FR 33519 

2025 Federal Register | Disclaimer | Privacy Policy