81_FR_52025 81 FR 51874 - Alaska Gasline Development Corporation, BP Alaska LNG LLC, Conoco Phillips Alaska LNG Company, ExxonMobil Alaska LNG LLC; Supplemental Notice Requesting Comments on the Denali National Park and Preserve Alterative for the Planned Alaska LNG Project

81 FR 51874 - Alaska Gasline Development Corporation, BP Alaska LNG LLC, Conoco Phillips Alaska LNG Company, ExxonMobil Alaska LNG LLC; Supplemental Notice Requesting Comments on the Denali National Park and Preserve Alterative for the Planned Alaska LNG Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 151 (August 5, 2016)

Page Range51874-51876
FR Document2016-18580

Federal Register, Volume 81 Issue 151 (Friday, August 5, 2016)
[Federal Register Volume 81, Number 151 (Friday, August 5, 2016)]
[Notices]
[Pages 51874-51876]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-18580]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF14-21-000]


Alaska Gasline Development Corporation, BP Alaska LNG LLC, Conoco 
Phillips Alaska LNG Company, ExxonMobil Alaska LNG LLC; Supplemental 
Notice Requesting Comments on the Denali National Park and Preserve 
Alterative for the Planned Alaska LNG Project

    As previously noticed on March 4, 2015, the staff of the Federal 
Energy Regulatory Commission (FERC or Commission) is preparing an 
environmental impact statement (EIS) that will discuss the 
environmental impacts of the Alaska LNG Project that could result from 
construction and operation of facilities by Alaska Gasline Development 
Corporation; BP Alaska LNG LLC; Conoco Phillips Alaska LNG Company; and 
ExxonMobil Alaska LNG LLC (Applicants) in Alaska. This notice explains 
the additional scoping process that will be used to gather input from 
the public and interested agencies on a route alternative to be 
evaluated for crossing the Denali National Park and Preserve (DNPP).
    The route currently planned by Alaska LNG is closely aligned with 
the Parks Highway, but deviates from the highway where the Parks 
Highway passes through the DNPP entrance area (see figure in appendix 
1.\1\) In response to scoping comments, and in working with federal and 
state regulating agencies, as well as the local communities, Alaska LNG 
has identified an alternative route (the DNPP Alternative) that passes 
directly through the DNPP entrance area and is closely aligned with the 
Parks Highway (see figure in appendix 1). In this general area, the 
planned route would be 8.05 miles long and not enter the DNPP, while 
the corresponding segment of the DNPP Alternative would be 8.50 miles 
long (6.16 miles of which would pass through the DNPP).
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

    This Supplemental Notice announces the opening of a limited scoping 
period to gather input from the public and interested agencies on the 
DNPP Alternative route. You can make a difference by providing us with 
your specific comments or concerns about the DNPP Alternative route. 
Your comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. Your input will help the Commission staff determine what 
issues they need to evaluate in the EIS. To ensure that your comments 
are timely and properly recorded, please send your comments so that the 
Commission receives them in Washington, DC on or before September 25, 
2016.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should

[[Page 51875]]

notify their constituents of this planned project and encourage them to 
comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses 
a number of typically asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings.

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number (PF14-21-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or [email protected]. 
Please carefully follow these instructions so that your comments are 
properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(PF14-21-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.
    In addition, if you have questions regarding the FERC process and 
our review of the alternative, FERC staff will be available to answer 
questions on Tuesday, August 23, 2016, between 4:00 and 6:00 p.m. at 
the Murie Dining Hall within Denali National Park (next to the Murie 
Science and Learning Center),
    Please note this is not your only public input opportunity; please 
refer to the review process flow chart in appendix 2.

Summary of the Planned Project

    The Applicants are planning to transport and liquefy supplies of 
natural gas from the production fields at the Point Thomson and Prudhoe 
Bay Units (PTU and PBU, respectively) on Alaska's North Slope for 
export and potential in-state deliveries. To do this, the Alaska LNG 
Project would consist of a new Gas Treatment Plant (GTP) on the North 
Slope and associated pipelines to deliver the gas from the PTU and PBU 
to the GTP, as well as a pipeline to deliver natural gas processing 
byproducts from the GTP back to the PBU. The GTP would treat/process 
the natural gas for delivery to an approximately 800-mile-long, 42-
inch-diameter pipeline that would transport the natural gas to a new 
planned liquefaction facility on the eastern shore of Cook Inlet in the 
Nikiski area of the Kenai Peninsula. Alaska LNG anticipates starting 
construction in late 2019, with construction and startup taking 
approximately 8 years. On this basis, the full planned Project system 
would be placed into service about 2027.
    As previously described, the alternative we are scoping involves an 
alternative route directly through the DNPP entrance area and closely 
aligned with the Parks Highway (see figure in appendix 1). We are 
requesting input from stakeholders on both the DNPP Alternative route 
and the current route that is located outside the park.

The EIS Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EIS on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EIS. We will 
consider all filed comments during the preparation of the EIS.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EIS we will discuss impacts that could occur as a result of 
the construction and operation of the planned project under these 
general headings:
     Alternatives
     Geology and soils;
     Land use;
     Water resources, fisheries, and wetlands;
     Cultural resources;
     Vegetation and wildlife;
     Air quality and noise;
     Endangered and threatened species;
     Transportation;
     Socioeconomics;
     Public safety; and
     Cumulative impacts.
    We will also evaluate possible alternatives to the planned project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Although no formal application has been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders and to identify and resolve issues before 
the FERC receives an application. As part of our pre-filing review, we 
have already met with the Applicants, jurisdictional agencies, Alaska 
Native tribes, local officials, and other interested stakeholders to 
discuss the project and identify issues/impacts and concerns before the 
FERC receives an application.
    In October and November 2016, FERC conducted a total of 12 scoping 
meetings throughout Alaska. During the scoping meetings, we garnered 
feedback from the local communities, including residents, elected 
officials, tribal leaders, community leaders, and other interested 
stakeholders.
    Our independent analysis of the issues will be presented in the 
EIS. The draft EIS will be published and distributed for public review 
and comment. We will consider all timely comments and revise the 
document, as necessary, before issuing a final EIS. To ensure your 
comments are considered, please carefully follow the instructions in 
the Public Participation section of this notice.

[[Page 51876]]

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
planned project.
    Copies of the completed draft EIS will be sent to the environmental 
mailing list for public review and comment. If you would prefer to 
receive a paper copy of the document instead of the CD version or would 
like to remove your name from the mailing list, please return the 
attached Information Request (appendix 3).

Becoming an Intervenor

    Once the Applicants file their application with the Commission, you 
may want to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``efiling'' link on the Commission's Web 
site. Please note that the Commission will not accept requests for 
intervenor status at this time. You must wait until the Commission 
receives a formal application for the project.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., PF14-
21). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Further, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information. Finally, 
additional information about the project can be seen from the 
Applicant's Web site at http://ak-lng.com.

    Dated: July 27, 2016.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2016-18580 Filed 8-4-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                  51874                                    Federal Register / Vol. 81, No. 151 / Friday, August 5, 2016 / Notices

                                                  DEPARTMENT OF ENERGY                                                        e. Name of Project: Camp McDowell                                     Reference Room or may be viewed on
                                                                                                                           Project.                                                                 the Commission’s Web site at http://
                                                  Federal Energy Regulatory                                                   f. Location: On Clear Creek, near                                     www.ferc.gov using the ‘‘eLibrary’’ link.
                                                  Commission                                                               Nauvoo in Winston County, Alabama.                                       Enter the docket number excluding the
                                                  [Project No. 14793–000]
                                                                                                                           The project does not affect federal lands.                               last three digits in the docket number
                                                                                                                              g. Filed Pursuant to: Federal Power                                   field to access the document. For
                                                  The Domestic and Foreign Missionary                                      Act 16 U.S.C. 791(a)–825(r).                                             assistance, please contact FERC Online
                                                  Society of the Protestant Episcopal                                         h. Applicant Contact: Frazier Christy,
                                                                                                                           3621 Kingshill Road, Birmingham,                                         Support at FERCOnlineSupport@
                                                  Diocese of Alabama; Notice of                                                                                                                     ferc.gov, (866) 208–3676 (toll free), or
                                                  Application Tendered for Filing With                                     Alabama 35223.
                                                                                                                              i. FERC Contact: Michael Spencer,                                     (202) 502–8659 (TTY). A copy is also
                                                  the Commission and Establishing                                                                                                                   available for inspection and
                                                  Procedural Schedule for Licensing and                                    (202) 502–6093, michael.spencer@
                                                                                                                           ferc.gov.                                                                reproduction at the address in item (h)
                                                  Deadline for Submission of Final                                                                                                                  above.
                                                                                                                              j. This application is not ready for
                                                  Amendments
                                                                                                                           environmental analysis at this time.                                        m. You may also register online at
                                                    Take notice that the following                                            k. The proposed project would consist                                 http://www.ferc.gov/docs-filing/
                                                  hydroelectric application has been filed                                 of: (1) an Archimedean Screw installed                                   esubscription.asp to be notified via
                                                  with the Commission and is available                                     in the spillway of the dam; (2) a 10 acre                                email of new filings and issuances
                                                  for public inspection.                                                   reservoir; (3) a powerhouse containing a                                 related to this or other pending projects.
                                                    a. Type of Application: 10 Megawatt                                    generator with a total installed capacity                                For assistance, contact FERC Online
                                                  Exemption.                                                               of 140 kilowatts; and (4) a transmission
                                                                                                                                                                                                    Support.
                                                    b. Project No.: 14793–000.                                             line. The project is estimated to generate
                                                    c. Date filed: July 12, 2016.                                          an average of 950 megawatt-hours                                            n. Procedural schedule: The
                                                    d. Applicant: The Domestic and                                         annually.                                                                application will be processed according
                                                  Foreign Missionary Society of the                                           l. Locations of the Application: A                                    to the following preliminary Hydro
                                                  Protestant Episcopal Diocese of                                          copy of the application is available for                                 Licensing Schedule. Revisions to the
                                                  Alabama.                                                                 review at the Commission in the Public                                   schedule will be made as appropriate.

                                                                                                                                        Milestone                                                                                                  Target date

                                                  Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................                               October 2016.
                                                  Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ..............................................................                                          December 2016.
                                                  Commission issues EA .....................................................................................................................................................................     June 2017.
                                                  Comments on EA .............................................................................................................................................................................   July 2017.



                                                    o. Final amendments to the                                             impacts of the Alaska LNG Project that                                   the DNPP entrance area and is closely
                                                  application must be filed with the                                       could result from construction and                                       aligned with the Parks Highway (see
                                                  Commission no later than 30 days from                                    operation of facilities by Alaska Gasline                                figure in appendix 1). In this general
                                                  the issuance date of the notice of ready                                 Development Corporation; BP Alaska                                       area, the planned route would be 8.05
                                                  for environmental analysis.                                              LNG LLC; Conoco Phillips Alaska LNG                                      miles long and not enter the DNPP,
                                                    Dated: July 27, 2016.                                                  Company; and ExxonMobil Alaska LNG                                       while the corresponding segment of the
                                                  Kimberly D. Bose,
                                                                                                                           LLC (Applicants) in Alaska. This notice                                  DNPP Alternative would be 8.50 miles
                                                                                                                           explains the additional scoping process                                  long (6.16 miles of which would pass
                                                  Secretary.
                                                                                                                           that will be used to gather input from                                   through the DNPP).
                                                  [FR Doc. 2016–18579 Filed 8–4–16; 8:45 am]
                                                                                                                           the public and interested agencies on a                                     This Supplemental Notice announces
                                                  BILLING CODE 6717–01–P                                                   route alternative to be evaluated for                                    the opening of a limited scoping period
                                                                                                                           crossing the Denali National Park and                                    to gather input from the public and
                                                                                                                           Preserve (DNPP).                                                         interested agencies on the DNPP
                                                  DEPARTMENT OF ENERGY                                                       The route currently planned by                                         Alternative route. You can make a
                                                  Federal Energy Regulatory                                                Alaska LNG is closely aligned with the                                   difference by providing us with your
                                                  Commission                                                               Parks Highway, but deviates from the                                     specific comments or concerns about
                                                                                                                           highway where the Parks Highway                                          the DNPP Alternative route. Your
                                                  [Docket No. PF14–21–000]                                                 passes through the DNPP entrance area                                    comments should focus on the potential
                                                                                                                           (see figure in appendix 1.1) In response                                 environmental effects, reasonable
                                                  Alaska Gasline Development                                               to scoping comments, and in working
                                                  Corporation, BP Alaska LNG LLC,                                                                                                                   alternatives, and measures to avoid or
                                                                                                                           with federal and state regulating                                        lessen environmental impacts. Your
                                                  Conoco Phillips Alaska LNG Company,                                      agencies, as well as the local
                                                  ExxonMobil Alaska LNG LLC;                                                                                                                        input will help the Commission staff
                                                                                                                           communities, Alaska LNG has identified                                   determine what issues they need to
                                                  Supplemental Notice Requesting                                           an alternative route (the DNPP
                                                  Comments on the Denali National Park                                                                                                              evaluate in the EIS. To ensure that your
                                                                                                                           Alternative) that passes directly through                                comments are timely and properly
                                                  and Preserve Alterative for the Planned
                                                                                                                                                                                                    recorded, please send your comments so
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Alaska LNG Project                                                         1 The appendices referenced in this notice will
                                                                                                                                                                                                    that the Commission receives them in
                                                                                                                           not appear in the Federal Register. Copies of the
                                                    As previously noticed on March 4,                                      appendices were sent to all those receiving this                         Washington, DC on or before September
                                                  2015, the staff of the Federal Energy                                    notice in the mail and are available at www.ferc.gov                     25, 2016.
                                                  Regulatory Commission (FERC or                                           using the link called ‘‘eLibrary’’ or from the                              This notice is being sent to the
                                                                                                                           Commission’s Public Reference Room, 888 First
                                                  Commission) is preparing an                                              Street NE., Washington, DC 20426, or call (202)
                                                                                                                                                                                                    Commission’s current environmental
                                                  environmental impact statement (EIS)                                     502–8371. For instructions on connecting to                              mailing list for this project. State and
                                                  that will discuss the environmental                                      eLibrary, refer to the last page of this notice.                         local government representatives should


                                             VerDate Sep<11>2014        17:42 Aug 04, 2016         Jkt 238001      PO 00000       Frm 00035       Fmt 4703      Sfmt 4703      E:\FR\FM\05AUN1.SGM              05AUN1


                                                                                 Federal Register / Vol. 81, No. 151 / Friday, August 5, 2016 / Notices                                          51875

                                                  notify their constituents of this planned               Bose, Secretary, Federal Energy                       process is referred to as scoping. The
                                                  project and encourage them to comment                   Regulatory Commission, 888 First Street               main goal of the scoping process is to
                                                  on their areas of concern.                              NE., Room 1A, Washington, DC 20426.                   focus the analysis in the EIS on the
                                                    If you are a landowner receiving this                   In addition, if you have questions                  important environmental issues. By this
                                                  notice, a pipeline company                              regarding the FERC process and our                    notice, the Commission requests public
                                                  representative may contact you about                    review of the alternative, FERC staff will            comments on the scope of the issues to
                                                  the acquisition of an easement to                       be available to answer questions on                   address in the EIS. We will consider all
                                                  construct, operate, and maintain the                    Tuesday, August 23, 2016, between 4:00                filed comments during the preparation
                                                  planned facilities. The company would                   and 6:00 p.m. at the Murie Dining Hall                of the EIS.
                                                  seek to negotiate a mutually acceptable                 within Denali National Park (next to the                 In the EIS we will discuss impacts
                                                  agreement. However, if the Commission                   Murie Science and Learning Center),                   that could occur as a result of the
                                                  approves the project, that approval                       Please note this is not your only                   construction and operation of the
                                                  conveys with it the right of eminent                    public input opportunity; please refer to             planned project under these general
                                                  domain. Therefore, if easement                          the review process flow chart in                      headings:
                                                  negotiations fail to produce an                         appendix 2.                                              • Alternatives
                                                  agreement, the pipeline company could                                                                            • Geology and soils;
                                                  initiate condemnation proceedings                       Summary of the Planned Project
                                                                                                                                                                   • Land use;
                                                  where compensation would be                                The Applicants are planning to                        • Water resources, fisheries, and
                                                  determined in accordance with state                     transport and liquefy supplies of natural             wetlands;
                                                  law.                                                    gas from the production fields at the                    • Cultural resources;
                                                    A fact sheet prepared by the FERC                     Point Thomson and Prudhoe Bay Units                      • Vegetation and wildlife;
                                                  entitled ‘‘An Interstate Natural Gas                    (PTU and PBU, respectively) on                           • Air quality and noise;
                                                  Facility On My Land? What Do I Need                     Alaska’s North Slope for export and                      • Endangered and threatened species;
                                                  To Know?’’ is available for viewing on                  potential in-state deliveries. To do this,               • Transportation;
                                                  the FERC Web site (www.ferc.gov). This                  the Alaska LNG Project would consist of                  • Socioeconomics;
                                                  fact sheet addresses a number of                        a new Gas Treatment Plant (GTP) on the                   • Public safety; and
                                                  typically asked questions, including the                North Slope and associated pipelines to                  • Cumulative impacts.
                                                  use of eminent domain and how to                        deliver the gas from the PTU and PBU                     We will also evaluate possible
                                                  participate in the Commission’s                         to the GTP, as well as a pipeline to                  alternatives to the planned project or
                                                  proceedings.                                            deliver natural gas processing                        portions of the project, and make
                                                  Public Participation                                    byproducts from the GTP back to the                   recommendations on how to lessen or
                                                                                                          PBU. The GTP would treat/process the                  avoid impacts on the various resource
                                                     For your convenience, there are three                natural gas for delivery to an
                                                  methods you can use to submit your                                                                            areas.
                                                                                                          approximately 800-mile-long, 42-inch-                    Although no formal application has
                                                  comments to the Commission. In all                      diameter pipeline that would transport
                                                  instances, please reference the project                                                                       been filed, we have already initiated our
                                                                                                          the natural gas to a new planned                      NEPA review under the Commission’s
                                                  docket number (PF14–21–000) with                        liquefaction facility on the eastern shore
                                                  your submission. The Commission                                                                               pre-filing process. The purpose of the
                                                                                                          of Cook Inlet in the Nikiski area of the              pre-filing process is to encourage early
                                                  encourages electronic filing of                         Kenai Peninsula. Alaska LNG
                                                  comments and has expert staff available                                                                       involvement of interested stakeholders
                                                                                                          anticipates starting construction in late             and to identify and resolve issues before
                                                  to assist you at (202) 502–8258 or                      2019, with construction and startup
                                                  efiling@ferc.gov. Please carefully follow                                                                     the FERC receives an application. As
                                                                                                          taking approximately 8 years. On this                 part of our pre-filing review, we have
                                                  these instructions so that your                         basis, the full planned Project system
                                                  comments are properly recorded.                                                                               already met with the Applicants,
                                                                                                          would be placed into service about                    jurisdictional agencies, Alaska Native
                                                     (1) You can file your comments                       2027.
                                                  electronically using the eComment                                                                             tribes, local officials, and other
                                                                                                             As previously described, the                       interested stakeholders to discuss the
                                                  feature on the Commission’s Web site                    alternative we are scoping involves an
                                                  (www.ferc.gov) under the link to                                                                              project and identify issues/impacts and
                                                                                                          alternative route directly through the                concerns before the FERC receives an
                                                  Documents and Filings. This is an easy                  DNPP entrance area and closely aligned
                                                  method for submitting brief, text-only                                                                        application.
                                                                                                          with the Parks Highway (see figure in                    In October and November 2016, FERC
                                                  comments on a project;                                  appendix 1). We are requesting input
                                                     (2) You can file your comments                                                                             conducted a total of 12 scoping
                                                                                                          from stakeholders on both the DNPP                    meetings throughout Alaska. During the
                                                  electronically by using the eFiling
                                                                                                          Alternative route and the current route               scoping meetings, we garnered feedback
                                                  feature on the Commission’s Web site
                                                                                                          that is located outside the park.                     from the local communities, including
                                                  (www.ferc.gov) under the link to
                                                  Documents and Filings. With eFiling,                    The EIS Process                                       residents, elected officials, tribal
                                                  you can provide comments in a variety                                                                         leaders, community leaders, and other
                                                                                                            The National Environmental Policy
                                                  of formats by attaching them as a file                                                                        interested stakeholders.
                                                                                                          Act (NEPA) requires the Commission to
                                                  with your submission. New eFiling                       take into account the environmental                      Our independent analysis of the
                                                  users must first create an account by                   impacts that could result from an action              issues will be presented in the EIS. The
                                                  clicking on ‘‘eRegister.’’ If you are filing            whenever it considers the issuance of a               draft EIS will be published and
                                                  a comment on a particular project,                                                                            distributed for public review and
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                          Certificate of Public Convenience and
                                                  please select ‘‘Comment on a Filing’’ as                Necessity. NEPA also requires us 2 to                 comment. We will consider all timely
                                                  the filing type; or                                                                                           comments and revise the document, as
                                                                                                          discover and address concerns the
                                                     (3) You can file a paper copy of your                                                                      necessary, before issuing a final EIS. To
                                                                                                          public may have about proposals. This
                                                  comments by mailing them to the                                                                               ensure your comments are considered,
                                                  following address. Be sure to reference                   2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the          please carefully follow the instructions
                                                  the project docket number (PF14–21–                     environmental staff of the Commission’s Office of     in the Public Participation section of
                                                  000) with your submission: Kimberly D.                  Energy Projects.                                      this notice.


                                             VerDate Sep<11>2014   17:42 Aug 04, 2016   Jkt 238001   PO 00000   Frm 00036   Fmt 4703   Sfmt 4703   E:\FR\FM\05AUN1.SGM   05AUN1


                                                  51876                          Federal Register / Vol. 81, No. 151 / Friday, August 5, 2016 / Notices

                                                  Environmental Mailing List                              please contact FERC Online Support at                 excused for that portion of the meeting.1
                                                     The environmental mailing list                       FercOnlineSupport@ferc.gov or toll free               If you plan to attend this meeting,
                                                  includes federal, state, and local                      at (866) 208–3676, or for TTY, contact                please contact Dr. Frank Winchell at the
                                                  government representatives and                          (202) 502–8659. The eLibrary link also                Federal Energy Regulatory Commission.
                                                  agencies; elected officials;                            provides access to the texts of formal                He can be reached at (202) 502–6104.
                                                  environmental and public interest                       documents issued by the Commission,                     Dated: July 27, 2016.
                                                  groups; Native American Tribes; other                   such as orders, notices, and                          Kimberly D. Bose,
                                                  interested parties; and local libraries                 rulemakings.
                                                                                                                                                                Secretary.
                                                                                                             In addition, the Commission offers a
                                                  and newspapers. This list also includes                                                                       [FR Doc. 2016–18577 Filed 8–4–16; 8:45 am]
                                                                                                          free service called eSubscription which
                                                  all affected landowners (as defined in                                                                        BILLING CODE 6717–01–P
                                                                                                          allows you to keep track of all formal
                                                  the Commission’s regulations) who are
                                                                                                          issuances and submittals in specific
                                                  potential right-of-way grantors, whose
                                                                                                          dockets. This can reduce the amount of
                                                  property may be used temporarily for                                                                          DEPARTMENT OF ENERGY
                                                                                                          time you spend researching proceedings
                                                  project purposes, or who own homes
                                                                                                          by automatically providing you with                   Federal Energy Regulatory
                                                  within certain distances of aboveground
                                                                                                          notification of these filings, document               Commission
                                                  facilities, and anyone who submits
                                                                                                          summaries, and direct links to the
                                                  comments on the project. We will
                                                                                                          documents. Go to www.ferc.gov/docs-
                                                  update the environmental mailing list as                                                                      [Docket No. CP15–558–000]
                                                                                                          filing/esubscription.asp.
                                                  the analysis proceeds to ensure that we
                                                                                                             Further, public meetings or site visits
                                                  send the information related to this                                                                          PennEast Pipeline Company, LLC;
                                                                                                          will be posted on the Commission’s
                                                  environmental review to all individuals,                                                                      Notice of Motion
                                                                                                          calendar located at www.ferc.gov/
                                                  organizations, and government entities
                                                                                                          EventCalendar/EventsList.aspx along                      On June 15, 2016, the New Jersey
                                                  interested in and/or potentially affected
                                                                                                          with other related information. Finally,              Conservation Foundation and Stony
                                                  by the planned project.
                                                                                                          additional information about the project              Brook-Millstone Watershed Association
                                                     Copies of the completed draft EIS will
                                                                                                          can be seen from the Applicant’s Web                  (Movants), filed with the Federal Energy
                                                  be sent to the environmental mailing list
                                                                                                          site at http://ak-lng.com.                            Regulatory Commission (Commission) a
                                                  for public review and comment. If you
                                                  would prefer to receive a paper copy of                   Dated: July 27, 2016.                               pleading styled as a Rule 206 Complaint
                                                  the document instead of the CD version                  Kimberly D. Bose,                                     and Rule 212 Motion against PennEast
                                                  or would like to remove your name from                  Secretary.                                            Pipeline Company, LLC (PennEast),
                                                  the mailing list, please return the                                                                           alleging that PennEast’s application for
                                                                                                          [FR Doc. 2016–18580 Filed 8–4–16; 8:45 am]
                                                  attached Information Request (appendix                                                                        a Certificate of Public Convenience and
                                                                                                          BILLING CODE 6717–01–P
                                                  3).                                                                                                           Necessity does not contain substantial
                                                                                                                                                                evidence of public benefit, as required
                                                  Becoming an Intervenor                                                                                        by the Natural Gas Act.1 The pleading
                                                                                                          DEPARTMENT OF ENERGY
                                                     Once the Applicants file their                                                                             further requests the Commission initiate
                                                  application with the Commission, you                    Federal Energy Regulatory                             an evidentiary hearing to ‘‘garner
                                                  may want to become an ‘‘intervenor’’                    Commission                                            substantial evidence’’ and develop the
                                                  which is an official party to the                                                                             record upon which the Commission
                                                                                                          [Project No. 13318–003]                               would rely in making its ‘‘ultimate
                                                  Commission’s proceeding. Intervenors
                                                  play a more formal role in the process                  Swan Lake North Pumped Storage                        determination regarding PennEast’s
                                                  and are able to file briefs, appear at                  Project; Notice of Meeting                            certificate of public convenience and
                                                  hearings, and be heard by the courts if                                                                       necessity.’’
                                                  they choose to appeal the Commission’s                    Commission staff will meet with                        While styled as a complaint under
                                                  final ruling. An intervenor formally                    representatives of the Klamath Tribes                 Rule 206, the pleading, filed in the
                                                  participates in the proceeding by filing                (Tribes), the Oregon State Historic                   PennEast certificate proceeding, Docket
                                                  a request to intervene. Instructions for                Preservation Officer and other state and              No. CP15–558–000, seeks resolution of
                                                  becoming an intervenor are in the User’s                federal agencies (to the extent they wish             the issue pending before the
                                                  Guide under the ‘‘efiling’’ link on the                 to participate), and Swan Lake North                  Commission in that proceeding, i.e.,
                                                  Commission’s Web site. Please note that                 Hydro LLC regarding the proposed                      whether PennEast’s request for a
                                                  the Commission will not accept requests                 Swan Lake North Pumped Storage                        certificate of convenience and necessity
                                                  for intervenor status at this time. You                 Project (Project No. 13318–003). The                  is supported by substantial evidence.
                                                  must wait until the Commission                          meeting will be held at the location and              Accordingly, action on the Movants’
                                                  receives a formal application for the                   time listed below: Klamath Tribes,                    request for an evidentiary hearing, as
                                                  project.                                                Tribal Administration Building, 501                   well as consideration of the merits of
                                                                                                          Chiloquin Blvd., Chiloquin, OR 97624,                 the Movants’ allegations, will take place
                                                  Additional Information                                  Phone: (541) 783–2219, Thursday,                      in that forum.
                                                     Additional information about the                     August 11, 2016, 9:00 a.m. PDT.                         Dated: July 27, 2016.
                                                  project is available from the                             Members of the public and                           Kimberly D. Bose,
                                                  Commission’s Office of External Affairs,                intervenors in the referenced proceeding              Secretary.
                                                  at (866) 208–FERC, or on the FERC Web                   may attend this meeting; however,
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                                                                                [FR Doc. 2016–18578 Filed 8–4–16; 8:45 am]
                                                  site (www.ferc.gov) using the eLibrary                  participation will be limited to tribal
                                                                                                                                                                BILLING CODE 6717–01–P
                                                  link. Click on the eLibrary link, click on              representatives and agency personnel. If
                                                  ‘‘General Search’’ and enter the docket                 the Tribes decide to disclose
                                                                                                                                                                  1 Protection from public disclosure involving this
                                                  number, excluding the last three digits                 information about a specific location
                                                                                                                                                                kind of specific information is based upon 18 CFR
                                                  in the Docket Number field (i.e., PF14–                 which could create a risk or harm to an               4.32(b)(3)(ii) of the Commission’s regulations
                                                  21). Be sure you have selected an                       archeological site or Native American                 implementing the Federal Power Act.
                                                  appropriate date range. For assistance,                 cultural resource, the public will be                   1 15 U.S.C. 717f(e) (2012).




                                             VerDate Sep<11>2014   17:42 Aug 04, 2016   Jkt 238001   PO 00000   Frm 00037   Fmt 4703   Sfmt 9990   E:\FR\FM\05AUN1.SGM   05AUN1



Document Created: 2016-08-05 06:43:35
Document Modified: 2016-08-05 06:43:35
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 51874 

2025 Federal Register | Disclaimer | Privacy Policy