81_FR_53286 81 FR 53131 - Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications; Shell Energy North America (US), L.P.

81 FR 53131 - Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications; Shell Energy North America (US), L.P.

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 155 (August 11, 2016)

Page Range53131-53132
FR Document2016-19070

Federal Register, Volume 81 Issue 155 (Thursday, August 11, 2016)
[Federal Register Volume 81, Number 155 (Thursday, August 11, 2016)]
[Notices]
[Pages 53131-53132]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-19070]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14795-000]


Notice of Preliminary Permit Application Accepted for Filing and 
Soliciting Comments, Motions To Intervene, and Competing Applications; 
Shell Energy North America (US), L.P.

    On July 26, 2016, Shell Energy North America (US), L.P., filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act, proposing to study the feasibility of the Hydro 
Battery Pearl Hill Project (Pearl Hill Project or project) to be 
located on the Columbia River and Rufus Woods Lake, near Bridgeport, 
Douglas County, Washington. The sole purpose of a preliminary permit, 
if issued, is to grant the permit holder priority to file a license 
application during the permit

[[Page 53132]]

term. A preliminary permit does not authorize the permit holder to 
perform any land-disturbing activities or otherwise enter upon lands or 
waters owned by others without the owners' express permission.
    The proposed pumped storage project would consist of the following: 
(1) 215-foot-diameter, 40-foot-high corrugated steel tank (upper 
reservoir) having a total storage capacity of 29 acre-feet and a usable 
capacity of 26.7 acre-feet; (2) 6,025-foot-long, 36-inch-diameter steel 
and high density polyethylene penstock extending between the upper 
reservoir and the pump/turbines below; (3) 400-foot-long, 100-foot-
wide, 40-foot-deep polyurea membrane stretched over a framed plastic 
structure (lower reservoir) having a total storage capacity of 29 acre-
feet and a usable capacity of 26.7 acre-feet; (4) 80-foot-long, 50-
foot-wide pontoon barge floating on Rufus Woods Lake containing: Two 
Pelton turbine-motor/generator units rated for 2.5 megawatts each at 
1,310 feet of net head; up to 8 pumps; and a substation; (5) an 
overhead 2,500-foot-long, 24.9-kilovolt transmission line extending 
from the project substation to an existing distribution line owned by 
Douglas County Public Utility District (the point of interconnection); 
and (6) appurtenant facilities. The estimated annual generation of the 
Pearl Hill Project would be 10.9 gigawatt-hours.
    Applicant Contact: Mr. Brian Johansen, Vice President Power Trading 
West, Shell Energy North America (US), L.P., 601 W. 1st Ave., Suite 
1700, Spokane, Washington 99201; phone: (509) 688-6000.
    FERC Contact: Ryan Hansen, email: [email protected]; phone: 
(202) 502-8074.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14795-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14795) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: August 4, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-19070 Filed 8-10-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                            Federal Register / Vol. 81, No. 155 / Thursday, August 11, 2016 / Notices                                                 53131

                                                Docket No. RP16–618, Algonquin Gas                      service to customers. Natural estimates               the date of issuance of the Commission
                                                  Transmission, LLC                                     the cost of the project to be $268,000, all           staff’s FEIS or EA.
                                                Docket No. ER12–1650, Emera Maine                       as more fully set forth in the application               Persons who wish to comment only
                                                Docket No. ER14–1409, ISO-New                           which is on file with the Commission                  on the environmental review of this
                                                  England Inc.                                          and open to public inspection. The                    project should submit an original and
                                                Docket No. ER14–1639, ISO New                           filing may also be viewed on the web at               two copies of their comments to the
                                                  England Inc. and New England Power                    http://www.ferc.gov using the                         Secretary of the Commission.
                                                  Pool Participants Committee                           ‘‘eLibrary’’ link. Enter the docket                   Environmental commenters will be
                                                Docket No. ER13–2266, ISO New                           number excluding the last three digits in             placed on the Commission’s
                                                  England Inc.                                          the docket number field to access the                 environmental mailing list, will receive
                                                Docket No. ER15–1429, Emera Maine                       document. For assistance, please contact              copies of the environmental documents,
                                                Docket No. ER16–551, ISO New England                    FERC Online Support at                                and will be notified of meetings
                                                  Inc.                                                  FERCOnlineSupport@ferc.gov or toll                    associated with the Commission’s
                                                Docket No. ER16–1301, ISO New                           free at (866) 208–3676, or TTY, contact               environmental review process.
                                                  England Inc. and Emera Maine                          (202) 502–8659.                                       Environmental commenters will not be
                                                Docket No. ER16–1041, ISO New                              Any questions concerning this                      required to serve copies of filed
                                                  England Inc.                                          application may be directed to Bruce H.               documents on all other parties.
                                                Docket No. ER16–1904, ISO New                           Newsome, Vice President, Regulatory                   However, the non-party commenters,
                                                  England Inc.                                          Products and Services, Natural Gas                    will not receive copies of all documents
                                                Docket No. ER16–2126, ISO New                           Pipeline Company of America, LLC,                     filed by other parties or issued by the
                                                  England Inc. and New England Power                    3250 Lacey Road, Suite 700, Downers                   Commission (except for the mailing of
                                                  Pool Participants Committee                           Drove, Illinois 60515–7918, by                        environmental documents issued by the
                                                Docket No. ER16–2215, ISO New                           telephone at (630) 725–3070, or by                    Commission) and will not have the right
                                                  England Inc.                                          email at bruce_newsome@                               to seek court review of the
                                                Docket No. ER16–2283, Genbright LLC                     kindermorgan.com.                                     Commission’s final order.
                                                  For more information, contact                            Any person or the Commission’s staff                  The Commission strongly encourages
                                                Michael Cackoski, Office of Energy                      may, within 60 days after issuance of                 electronic filings of comments, protests
                                                Market Regulation, Federal Energy                       the instant notice by the Commission,                 and interventions in lieu of paper using
                                                Regulatory Commission at (202) 502–                     file pursuant to Rule 214 of the                      the ‘‘eFiling’’ link at http://
                                                6169 or Michael.Cackoski@ferc.gov.                      Commission’s Procedural Rules (18 CFR                 www.ferc.gov. Persons unable to file
                                                  Dated: August 4, 2016.                                385.214) a motion to intervene or notice              electronically should submit an original
                                                                                                        of intervention and pursuant to section               and seven copies of the protest or
                                                Nathaniel J. Davis, Sr.,
                                                                                                        157.205 of the regulations under the                  intervention to the Federal Energy
                                                Deputy Secretary.
                                                                                                        NGA (18 CFR 157.205), a protest to the                Regulatory Commission, 888 First Street
                                                [FR Doc. 2016–19068 Filed 8–10–16; 8:45 am]                                                                   NE., Washington, DC 20426.
                                                                                                        request. If no protest is filed within the
                                                BILLING CODE 6717–01–P
                                                                                                        time allowed therefore, the proposed                    Dated: August 4, 2016.
                                                                                                        activity shall be deemed to be                        Nathaniel J. Davis, Sr.,
                                                DEPARTMENT OF ENERGY                                    authorized effective the day after the                Deputy Secretary.
                                                                                                        time allowed for filing a protest. If a
                                                                                                                                                              [FR Doc. 2016–19067 Filed 8–10–16; 8:45 am]
                                                Federal Energy Regulatory                               protest is filed and not withdrawn
                                                                                                                                                              BILLING CODE 6717–01–P
                                                Commission                                              within 30 days after the allowed time
                                                                                                        for filing a protest, the instant request
                                                [Docket No. CP16–485–000]                               shall be treated as an application for                DEPARTMENT OF ENERGY
                                                                                                        authorization pursuant to section 7 of
                                                Notice of Request Under Blanket
                                                                                                        the NGA.                                              Federal Energy Regulatory
                                                Authorization: Natural Gas Pipeline
                                                Company of America, LLC                                    Pursuant to section 157.9 of the                   Commission
                                                                                                        Commission’s rules, 18 CFR 157.9,
                                                                                                        within 90 days of this Notice the                     [Project No. 14795–000]
                                                   Take notice that on July 29, 2016,
                                                Natural Gas Pipeline Company of                         Commission staff will either: Complete                Notice of Preliminary Permit
                                                America, LLC (Natural), 3250 Lacey                      its environmental assessment (EA) and                 Application Accepted for Filing and
                                                Road, Suite 700, Downers Grove, Illinois                place it into the Commission’s public                 Soliciting Comments, Motions To
                                                60515, filed in Docket No. CP16–485–                    record (eLibrary) for this proceeding, or             Intervene, and Competing
                                                000 a prior notice request pursuant to                  issue a Notice of Schedule for                        Applications; Shell Energy North
                                                sections 157.205 and 157.216 of the                     Environmental Review. If a Notice of                  America (US), L.P.
                                                Commission’s regulations under the                      Schedule for Environmental Review is
                                                Natural Gas Act (NGA), requesting                       issued, it will indicate, among other                    On July 26, 2016, Shell Energy North
                                                authorization to plug and abandon the                   milestones, the anticipated date for the              America (US), L.P., filed an application
                                                Karcher 9 injection/withdrawal well                     Commission staff’s issuance of the final              for a preliminary permit, pursuant to
                                                and abandon and remove related meter                    environmental impact statement (FEIS)                 section 4(f) of the Federal Power Act,
                                                and surface facilities as well as a related             or EA for this proposal. The filing of the            proposing to study the feasibility of the
                                                lateral and tap at Natural’s Herscher                   EA in the Commission’s public record                  Hydro Battery Pearl Hill Project (Pearl
sradovich on DSK3GMQ082PROD with NOTICES




                                                Galesville Storage Field located in                     for this proceeding or the issuance of a              Hill Project or project) to be located on
                                                Kankakee County, Illinois. Natural                      Notice of Schedule for Environmental                  the Columbia River and Rufus Woods
                                                states that, as a result of the proposed                Review will serve to notify federal and               Lake, near Bridgeport, Douglas County,
                                                abandonment project, there will be no                   state agencies of the timing for the                  Washington. The sole purpose of a
                                                impact on the Herscher Galesville                       completion of all necessary reviews, and              preliminary permit, if issued, is to grant
                                                Storage Field’s certificate parameters                  the subsequent need to complete all                   the permit holder priority to file a
                                                and that there will be no decrease in                   federal authorizations within 90 days of              license application during the permit


                                           VerDate Sep<11>2014   17:44 Aug 10, 2016   Jkt 238001   PO 00000   Frm 00014   Fmt 4703   Sfmt 4703   E:\FR\FM\11AUN1.SGM   11AUN1


                                                53132                       Federal Register / Vol. 81, No. 155 / Thursday, August 11, 2016 / Notices

                                                term. A preliminary permit does not                     (TTY). In lieu of electronic filing, please           Procedure (18 CFR 385.211 and
                                                authorize the permit holder to perform                  send a paper copy to: Secretary, Federal              385.214). Protests will be considered by
                                                any land-disturbing activities or                       Energy Regulatory Commission, 888                     the Commission in determining the
                                                otherwise enter upon lands or waters                    First Street NE., Washington, DC 20426.               appropriate action to be taken, but will
                                                owned by others without the owners’                     The first page of any filing should                   not serve to make protestants parties to
                                                express permission.                                     include docket number P–14795–000.                    the proceeding. Any person wishing to
                                                   The proposed pumped storage project                     More information about this project,               become a party must file a notice of
                                                would consist of the following: (1) 215-                including a copy of the application, can              intervention, or motion to intervene, as
                                                foot-diameter, 40-foot-high corrugated                  be viewed or printed on the ‘‘eLibrary’’              appropriate. The Respondent’s answer
                                                steel tank (upper reservoir) having a                   link of Commission’s Web site at http://              and all interventions, or protests must
                                                total storage capacity of 29 acre-feet and              www.ferc.gov/docs-filing/elibrary.asp.                be filed on or before the comment date.
                                                a usable capacity of 26.7 acre-feet; (2)                Enter the docket number (P–14795) in                  The Respondent’s answer, motions to
                                                6,025-foot-long, 36-inch-diameter steel                 the docket number field to access the                 intervene, and protests must be served
                                                and high density polyethylene penstock                  document. For assistance, contact FERC                on the Complainants.
                                                extending between the upper reservoir                   Online Support.                                          The Commission encourages
                                                and the pump/turbines below; (3) 400-                                                                         electronic submission of protests and
                                                                                                          Dated: August 4, 2016.
                                                foot-long, 100-foot-wide, 40-foot-deep                                                                        interventions in lieu of paper using the
                                                polyurea membrane stretched over a                      Nathaniel J. Davis, Sr.,
                                                                                                                                                              ‘‘eFiling’’ link at http://www.ferc.gov.
                                                framed plastic structure (lower                         Deputy Secretary.
                                                                                                                                                              Persons unable to file electronically
                                                reservoir) having a total storage capacity              [FR Doc. 2016–19070 Filed 8–10–16; 8:45 am]
                                                                                                                                                              should submit an original and 5 copies
                                                of 29 acre-feet and a usable capacity of                BILLING CODE 6717–01–P
                                                                                                                                                              of the protest or intervention to the
                                                26.7 acre-feet; (4) 80-foot-long, 50-foot-                                                                    Federal Energy Regulatory Commission,
                                                wide pontoon barge floating on Rufus                                                                          888 First Street NE., Washington, DC
                                                Woods Lake containing: Two Pelton                       DEPARTMENT OF ENERGY
                                                                                                                                                              20426.
                                                turbine-motor/generator units rated for                                                                          This filing is accessible on-line at
                                                2.5 megawatts each at 1,310 feet of net                 Federal Energy Regulatory
                                                                                                        Commission                                            http://www.ferc.gov, using the
                                                head; up to 8 pumps; and a substation;                                                                        ‘‘eLibrary’’ link and is available for
                                                (5) an overhead 2,500-foot-long, 24.9-                  [Docket No. EL16–104–000]                             review in the Commission’s Public
                                                kilovolt transmission line extending                                                                          Reference Room in Washington, DC
                                                from the project substation to an                       HORUS Central Valley Solar 1, LLC,                    There is an ‘‘eSubscription’’ link on the
                                                existing distribution line owned by                     HORUS Central Valley Solar 2, LLC v.                  Web site that enables subscribers to
                                                Douglas County Public Utility District                  California Independent System                         receive email notification when a
                                                (the point of interconnection); and (6)                 Operator Corporation; Notice of                       document is added to a subscribed
                                                appurtenant facilities. The estimated                   Complaint                                             docket(s). For assistance with any FERC
                                                annual generation of the Pearl Hill                                                                           Online Service, please email
                                                Project would be 10.9 gigawatt-hours.                      Take notice that on July 29, 2016,
                                                                                                        pursuant to sections 206 and 306 of the               FERCOnlineSupport@ferc.gov, or call
                                                   Applicant Contact: Mr. Brian
                                                                                                        Federal Power Act, 16 U.S.C. 824e and                 (866) 208–3676 (toll free). For TTY, call
                                                Johansen, Vice President Power Trading
                                                                                                        825e and Rule 206 of the Federal Energy               (202) 502–8659.
                                                West, Shell Energy North America (US),
                                                L.P., 601 W. 1st Ave., Suite 1700,                      Regulatory Commission‘s (Commission)                     Comment Date: 5:00 p.m. Eastern
                                                Spokane, Washington 99201; phone:                       Rules of Practice and Procedure 18 CFR                Time on August 18, 2016.
                                                (509) 688–6000.                                         385.206, HORUS Central Valley Solar 1,                  Dated: August 1, 2016.
                                                   FERC Contact: Ryan Hansen, email:                    LLC and HORUS Central Valley Solar 2,                 Nathaniel J. Davis, Sr.,
                                                ryan.hansen@ferc.gov; phone: (202)                      LLC (collectively, HORUS), filed a                    Deputy Secretary.
                                                502–8074.                                               formal complaint against California                   [FR Doc. 2016–19079 Filed 8–10–16; 8:45 am]
                                                   Deadline for filing comments, motions                Independent System Operator
                                                                                                                                                              BILLING CODE 6717–01–P
                                                to intervene, competing applications                    Corporation (Respondent or CAISO)
                                                (without notices of intent), or notices of              alleging violation of the CAISO Open
                                                intent to file competing applications: 60               Access Transmission Tariff and                        DEPARTMENT OF ENERGY
                                                days from the issuance of this notice.                  requesting that the Commission (1)
                                                Competing applications and notices of                   direct the CAISO to stop interfering                  Federal Energy Regulatory
                                                intent must meet the requirements of 18                 with HORUS’ compliance with the                       Commission
                                                CFR 4.36.                                               interconnection procedures of Western
                                                   The Commission strongly encourages                   Area Power Administration (Western)                   Combined Notice of Filings #1
                                                electronic filing. Please file comments,                for its direct interconnection with
                                                motions to intervene, notices of intent,                Western as an energy-only resource, and                  Take notice that the Commission
                                                and competing applications using the                    (2) stop CAISO from requiring HORUS                   received the following electric rate
                                                Commission’s eFiling system at http://                  to go through a second set of                         filings:
                                                www.ferc.gov/docs-filing/efiling.asp.                   interconnection procedures and studies                   Docket Numbers: ER16–13–003.
                                                Commenters can submit brief comments                    under the CAISO tariff even though                       Applicants: Southwest Power Pool,
                                                up to 6,000 characters, without prior                   HORUS is an energy-only resource and                  Inc.
                                                registration, using the eComment system                 Western is a non-participating                           Description: Compliance filing:
sradovich on DSK3GMQ082PROD with NOTICES




                                                at http://www.ferc.gov/docs-filing/                     transmission owner under the CAISO                    Compliance Filing in ER16–13—
                                                ecomment.asp. You must include your                     tariff for the HORUS project, as more                 Revisions to Att AE re Annual ARR
                                                name and contact information at the end                 fully explained in the complaint.                     Allocation to be effective 1/28/2016.
                                                of your comments. For assistance,                          Any person desiring to intervene or to                Filed Date: 8/4/16.
                                                please contact FERC Online Support at                   protest this filing must file in                         Accession Number: 20160804–5119.
                                                FERCOnlineSupport@ferc.gov, (866)                       accordance with Rules 211 and 214 of                     Comments Due: 5 p.m. ET 8/25/16.
                                                208–3676 (toll free), or (202) 502–8659                 the Commission’s Rules of Practice and                   Docket Numbers: ER16–1649–004.


                                           VerDate Sep<11>2014   17:44 Aug 10, 2016   Jkt 238001   PO 00000   Frm 00015   Fmt 4703   Sfmt 4703   E:\FR\FM\11AUN1.SGM   11AUN1



Document Created: 2018-02-09 11:27:13
Document Modified: 2018-02-09 11:27:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 53131 

2025 Federal Register | Disclaimer | Privacy Policy