The Delaware River Basin Commission is amending its regulations to provide for the One Process/One Permit Program. The Program is intended to promote interagency cooperation and collaboration on shared mission objectives, achieve regulatory program efficiencies, avoid unnecessary duplication of effort, and reduce the potential for confusion on the part of regulated entities and the public regarding regulatory requirements applicable to projects.

Federal Register, Volume 81 Issue 22 (Wednesday, February 3, 2016)
[Federal Register Volume 81, Number 22 (Wednesday, February 3, 2016)]
[Rules and Regulations]
[Pages 5585-5589]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-02048]


=======================================================================
-----------------------------------------------------------------------

DELAWARE RIVER BASIN COMMISSION

18 CFR Part 401


Amendments to the Rules of Practice and Procedure To Allow Each 
Signatory Party and the Commission To Administer a Single Process for 
the Review and Adjudication of Projects

AGENCY: Delaware River Basin Commission.

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Delaware River Basin Commission is amending its 
regulations to provide for the One Process/One Permit Program. The 
Program is intended to promote interagency cooperation and 
collaboration on shared mission objectives, achieve regulatory program 
efficiencies, avoid unnecessary duplication of effort, and reduce the 
potential for confusion on the part of regulated entities and the 
public regarding regulatory requirements applicable to projects.

DATES: This final rule will be effective March 4, 2016.

FOR FURTHER INFORMATION CONTACT: Technical information: David Kovach,

[[Page 5586]]

609-477-7264. Legal information: Pamela Bush, 609-477-7203.

SUPPLEMENTARY INFORMATION:

Background

    The Delaware River Basin Commission (``DRBC'' or ``Commission'') is 
a federal-interstate compact agency charged with managing the water 
resources of the Delaware River Basin on a regional basis without 
regard to political boundaries. Its members are the governors of the 
four basin states--Delaware, New Jersey, New York and Pennsylvania--and 
the North Atlantic Division Commander of the U.S. Army Corps of 
Engineers, representing the federal government.
    Specifically, this final rule amends subchapter A--Administrative 
Manual, part 401--Rules of Practice and Procedure, subpart C--Project 
Review Under Section 3.8 of the Compact by the addition of a new 
section 401.42, providing for DRBC and each of the parties to the 
Delaware River Basin Compact (United States Pub. L. 87-328, Approved 
September 27, 1961, 75 U.S. Statutes at Large 688; 53 Delaware Laws, 
Chapter 71, Approved May 26, 1961; New Jersey Laws of 1961, Chapter 13, 
Approved May 1, 1961; New York Laws of 1961, Chapter 148, Approved 
March 17, 1961; and Pennsylvania Acts of 1961, Act No. 268, Approved 
July 7, 1961 (``the Compact''))--Delaware, New Jersey, New York, 
Pennsylvania and the federal government (``Signatory Parties'')--to 
coordinate and collaborate in the administration of a single process 
for the review and adjudication of certain projects, including, where 
appropriate, issuance of a single permit or other approval instrument.
    Currently, the sponsors of many water resource-related projects in 
the Delaware River Basin are required to apply to both the DRBC and a 
state agency, among others, for approvals. New section 401.42 provides 
for the DRBC and the administrative agencies of the Signatory Parties 
to identify regulatory programs that by mutual agreement will be 
managed through a single process that may result in one decision or 
approval. The program, known as One Process/One Permit (hereinafter, 
``the Program or ``One Permit'') is intended to promote interagency 
cooperation and collaboration on shared mission objectives, achieve 
regulatory program efficiencies, avoid unnecessary duplication of 
effort, and reduce the potential for confusion on the part of regulated 
entities and the public regarding regulatory requirements applicable to 
projects. Importantly, the rule expressly preserves the authorities of 
the DRBC and each of its Signatory Parties and effects no change to 
federal, state or DRBC substantive standards and requirements.
    In accordance with this final rule, administrative agreements 
between DRBC and Signatory Party agencies to implement the Program may 
be approved by the Commission after each such agreement undergoes a 
duly noticed public hearing. In accordance with Resolution No. 2015-4 
of the Commission, which was adopted on March 11, 2015 following a 
public hearing on March 10, 2015, an administrative agreement between 
the DRBC and the New Jersey Department of Environmental Protection 
(NJDEP) was executed, in part to demonstrate how the Program would 
operate in New Jersey. With adoption of the final rule, DRBC and NJDEP 
will fully implement their March 2015 agreement.
    Notably, each Signatory Party may choose whether and when to 
initiate an agreement or agreements with DRBC under the Program. No 
draft agreements with Signatory Party agencies other than the NJDEP to 
implement the Program have yet been published for comment.

Procedural Background

    The Commission introduced One Permit to the basin community during 
meetings with regulated entities, environmental organizations and other 
stakeholders on February 12 and March 3, 2015 and through publication 
on the DRBC Web site of a press release and a set of FAQs on February 
27, 2015. During the Commission's quarterly public meeting on March 10-
11, 2015, the Commission approved Resolution No. 2015-4, in part 
authorizing and directing the Executive Director to initiate rulemaking 
to amend DRBC's Rules of Practice and Procedure to provide specific 
authorization for and define the scope of the Program. Notice of the 
proposed amendments was published on the Commission's Web site on May 
17, 2015.
    Notice of the proposed amendments also appeared in the Federal 
Register at 80 FR 28567, May 19, 2015; in the Delaware Register of 
Regulations, 18 DE Reg. 1002, June 1, 2015; New Jersey Register, 47 
N.J.R. 1256, June 1, 2015; New York State Register, May 27, 2015 (page 
4); and Pennsylvania Bulletin, 45 Pa. B. 2611, May 30, 2015. The 
Commission held a public hearing on the proposal on June 9, 2015 and 
accepted written comments on the rule through July 1, 2015.

Rule Highlights

    Notable aspects of the final rule include the following:
     Section 401.42(b) provides that applications for approvals 
required by the Compact and Commission regulations, but not within the 
scope of the Program, must continue to be submitted to the Commission.
     To ensure continued public access to information on the 
status of all projects under review pursuant to the Delaware River 
Basin Compact, including those administered under One Permit, Sec.  
401.42(d)(2) establishes that participating Signatory Party agencies 
will notify DRBC at least once monthly of applications received under 
the Program; and Sec.  401.42(d)(5) establishes that the list that the 
Commission will maintain of projects being administered under One 
Permit will be posted on the Commission's Web site.
     Section 401.42(h) provides that DRBC's current Project 
Review Fee Schedule as set forth in Resolution No. 2009-2 will be the 
operative fee schedule for projects reviewed under the Program.
     Section 401.42(i) provides mechanisms for the efficient 
disposition of Commission dockets during the transition to One Permit. 
Section 401.42(i)(1) provides that for projects covered by the Program, 
the most recent docket will be deemed administratively continued when a 
renewal application is timely submitted to the Signatory Party Agency. 
Section 401.42(i)(2) provides that unless the Executive Director or the 
Commission otherwise directs, upon the Signatory Party Agency's final 
action on an application for a project subject to the Program, (a) any 
existing or administratively continued docket will terminate as to all 
of its provisions and conditions within the scope of the Signatory 
Party Agency approval; and (b) such docket will continue in effect as 
to any provisions and conditions outside the scope of the Signatory 
Party Agency approval, including for example, addition of a project to 
the Comprehensive Plan.
     The rule authorizes Signatory Party agencies, in 
accordance with an applicable administrative agreement, to issue in 
their approvals for projects to be administered under the Program the 
finding and determination required by section 3.8 of the Compact that a 
project subject to section 3.8 review does not substantially impair or 
conflict with the Commission's Comprehensive Plan (``the finding''). 
Section 401.42(d)(4) makes clear that where in accordance with an 
applicable administrative agreement implementing One Permit the finding 
continues to be made by the Commission, the Signatory Party agency may 
include the Commission's finding in the agency's approval, together 
with

[[Page 5587]]

any conditions identified by the Commission as necessary to support it, 
thereby achieving a unified permit.
     The final rule also makes clear (1) that participation in 
the program by Signatory Party agencies is voluntary; and (2) that the 
scope of a Signatory Party Agency's participation is defined by an 
administrative agreement between DRBC and the agency that has been duly 
adopted in accordance with Sec.  401.42(d).

Additional Materials

    Additional materials can be found on the Commission's Web site at 
www.drbc.net. These include DRBC Resolution No. 2015-9 approving the 
final rule, at http://www.nj.gov/drbc/library/documents/Res2015-09_OPOPwith-final-rule-text.pdf; and the Commission's detailed comment 
and response document, which identifies commenters, summarizes comments 
received on the proposal, and sets forth the Commission's responses, at 
http://www.nj.gov/drbc/library/documents/OPOP/comment-and-response_OPOP.pdf. The version of the Rules of Practice and Procedure 
that is currently posted on DRBC's Web site at http://www.nj.gov/drbc/library/documents/admin_manual.pdf uses DRBC's original numbering 
system, which is different from that of the CFR. In the original 
system, the One Permit Program rules are set forth at new section 
2.3.11. A list of the CFR units and corresponding DRBC units follows. A 
complete stand-alone version of the Rules of Practice and Procedure 
using the CFR system will be available on the DRBC Web site shortly.

------------------------------------------------------------------------
          CFR Unit                  DRBC Unit         Title or Caption
------------------------------------------------------------------------
Title 18 Conservation of
 Power and Water Resources.
Chapter III--Delaware River
 Basin Commission.
Subchapter A--Administrative  Administrative
 Manual.                       Manual [Part II]
Part 401--Rules of Practice   Rules of Practice
 and Procedure.                and Procedure
Subpart C--Project Review     Article 3--Project    ....................
 Under Section 3.8 of the      Review Under
 Compact.                      Section 3.8 of the
                               Compact.
401.42......................  2.3.11..............  One Permit Program.
401.42(a)...................  2.3.11 A............  Purpose.
401.42(b)...................  2.3.11 B............  Scope.
401.42(c)...................  2.3.11 C............  Regulatory programs.
401.42(d)...................  2.3.11 D............  Procedure.
401.42(e)...................  2.3.11 E............  Comprehensive Plan
                                                     projects.
401.42(f)...................  2.3.11 F............  Retention of
                                                     Commission review
                                                     and enforcement
                                                     authorities.
401.42(g)...................  2.3.11 G............  Exhaustion of
                                                     Signatory Party
                                                     administrative
                                                     remedies
                                                     prerequisite to
                                                     appeal.
401.42(h)...................  2.3.11 H............  Fees.
401.42(i)...................  2.3.11 I............  Effect of One Permit
                                                     Program on
                                                     Commission dockets.
401.42(j)...................  2.3.11 J............  Modification of
                                                     Rules of Practice
                                                     and Procedure to
                                                     conform to this
                                                     section.
401.42(k)...................  2.3.11 K............  No interference with
                                                     Supreme Court
                                                     decree.
------------------------------------------------------------------------

List of Subjects in 18 CFR Part 401

    Administrative practice and procedure, Project review, Water 
pollution control, Water resources.

    For the reasons set forth in the preamble, the Delaware River Basin 
Commission amends part 401 of title 18 of the Code of Federal 
Regulations as follows:

PART 401--RULES OF PRACTICE AND PROCEDURE

0
1. The authority citation for part 401 continues to read as follows:

    Authority:  Delaware River Basin Compact (75 Stat. 688), unless 
otherwise noted.

Subpart C--Project Review Under Section 3.8 of the Compact

0
2. Add Sec.  401.42 to read as follows:


Sec.  401.42  One Permit Program.

    (a) Purpose. The purpose of the One Permit Program set forth in 
this section is to provide the opportunity for the environmental agency 
and/or other administrative agency of a Signatory Party (``Signatory 
Party Agency'') and the Commission to coordinate and collaborate in the 
administration of a single process for the review and adjudication of 
projects. The One Permit Program allows the Signatory Party Agency and 
Commission to incorporate requirements and determinations of both 
entities in a single permit or other approval instrument, pursuant to a 
duly adopted Administrative Agreement under paragraph (d) of this 
section.
    (b) Scope. This section applies to all projects that:
    (1) Are reviewable under the Compact;
    (2) Meet the thresholds for review set forth in Sec.  401.35 of 
these Rules of Practice and Procedure;
    (3) Are subject to review by a Signatory Party Agency under its own 
statutory authorities; and
    (4) Are within regulatory programs that have been identified in a 
duly adopted Administrative Agreement between the Commission and a 
Signatory Party Agency under this section. For any project that 
requires an approval under the Compact that is outside the scope of the 
Signatory Party Agency's approval issued in accordance with an 
Administrative Agreement under this section, the project sponsor shall 
apply to the Commission in accordance with procedures established by 
the Commission.
    (c) Regulatory programs. Regulatory programs eligible for 
administration under the One Permit Program may include but are not 
limited to those concerning: Basin discharges, Basin water withdrawals, 
and Basin flood plain requirements.
    (d) Procedure. The categories of projects covered and the 
procedures for processing applications under the One Permit Program 
shall be set forth in one or more Administrative Agreements between the 
Commission and the Signatory Party Agency that have been adopted by the 
Commission following a duly noticed public hearing and are in form and 
substance acceptable to the Commission and the Signatory Party Agency, 
consistent with the following:

[[Page 5588]]

    (1) Except as provided in paragraphs (b) and (e) of this section or 
in an Administrative Agreement that has been duly executed by the 
Commission and the Signatory Party Agency under this section, an 
application for initial approval, renewal or revision of any project 
subject to the One Permit Program shall be filed only with the 
Signatory Party Agency.
    (2) To enable the Commission to compile and make available to the 
public a current list of pending applications for projects within the 
Basin subject to Commission jurisdiction, the Signatory Party Agency 
shall notify the Commission at least monthly of applications the 
Signatory Party has received during the preceding month that may be 
eligible for review under the One Permit Program.
    (3) For those categories of projects identified in the 
Administrative Agreement as requiring Commission input, the Commission 
staff shall provide the Signatory Party Agency with such input, 
including where specified by the Administrative Agreement, a 
recommendation as to any conditions of approval that may be necessary 
or appropriate to include in the project review determination under 
Section 3.8 of the Compact as to those regulatory programs identified 
in an Administrative Agreement in accordance with paragraph (b) of this 
section.
    (4) Unless the Signatory Party Agency disapproves the project or 
the Administrative Agreement provides for separate Commission action 
under Section 3.8 of the Compact, the Signatory Party Agency shall make 
the project review determination under Section 3.8 of the Compact, as 
specified in the Administrative Agreement, as to the regulatory program 
covered by the Signatory Party Agency's approval and include the 
determination and any associated conditions of approval within the 
permit or other approval instrument that it issues to the project 
sponsor. If in accordance with the applicable Administrative Agreement 
the determination under Section 3.8 of the Compact is made by the 
Commission, the Signatory Party Agency may include the determination 
together with any associated conditions of approval in its permit or 
other approval instrument covering the project.
    (5) The Commission will maintain on its Web site a list of all 
projects being administered pursuant to the Program.
    (e) Comprehensive Plan projects. Articles 11 and 13 of the Compact 
require certain projects to be included in the Comprehensive Plan. To 
add a project not yet included in the Comprehensive Plan, the project 
sponsor shall submit a separate application to the Commission. If 
following its review and public hearing the Commission approves the 
addition of the project to the Comprehensive Plan, the Commission's 
approval will include such project requirements as are necessary under 
the Compact and Commission regulations. All other project approvals 
that may be required from the Signatory Party Agency or the Commission 
under regulatory programs administered pursuant to this section may be 
issued through the One Permit Program. An application for renewal or 
modification of a project in the Comprehensive Plan that does not 
change the project so substantially as to render it a new and different 
project may be submitted only to the Signatory Party Agency unless 
otherwise specified in the Administrative Agreement.
    (f) Retention of Commission review and enforcement authorities. 
Notwithstanding any other provision of this section, any Commissioner 
or the Executive Director may designate for Commission review any 
project that is reviewable under the Compact. Nothing in this section 
shall limit the authority of the Commission to exercise its review 
authority under the Compact and applicable Commission regulations. 
Similarly, although Administrative Agreements executed pursuant to this 
section may include collaborative and cooperative compliance and 
enforcement procedures, nothing in this section shall limit the 
authority of the Commission to exercise its enforcement authority under 
the Compact and applicable regulations.
    (g) Exhaustion of Signatory Party administrative remedies 
prerequisite to appeal. Before commencing an action in a court of 
appropriate jurisdiction challenging any final action taken by a 
Signatory Party Agency under this section, the appellant must first 
exhaust its administrative remedies under the law of the Signatory 
Party whose agency issued the decision at issue.
    (h) Fees. The Commission shall establish and maintain a schedule of 
fees for any or all of the services it renders pursuant to this 
section. The applicable fee(s) for Commission services rendered 
pursuant to this section shall be those set forth in DRBC Resolution 
No. 2009-2 (available at http://www.nj.gov/drbc/library/documents/Res2009-2.pdf) for the review and renewal of project approvals. Project 
sponsors shall pay such fees, if any, directly to the Commission in 
accordance with the current schedule and applicable rules.
    (i) Effect of One Permit Program on Commission dockets.
    (1) Unless the Executive Director or Commission otherwise directs, 
if a docket holder submits, or has submitted, a timely application to a 
Signatory Party Agency for a project subject to review under an 
Administrative Agreement duly adopted under paragraph (d) of this 
section, the most recent docket for the project shall, upon expiration, 
be deemed administratively continued until final action is taken in 
accordance with paragraph (i)(2) of this section.
    (2) Unless the Executive Director or Commission otherwise directs, 
upon a Signatory Party Agency's final action on an application for a 
project subject to the One Permit Program:
    (i) Any existing or administratively continued docket for such 
project shall terminate as to all of its provisions and conditions that 
pertain to regulatory programs administered by the Signatory Party 
Agency under the Administrative Agreement (``the Covered Programs''); 
and
    (ii) The docket shall continue in effect as to any provisions and 
conditions not pertaining only to Covered Programs, including, as 
applicable, the incorporation of the project in the Commission's 
Comprehensive Plan.
    (j) Modification of rules of practice and procedure to conform to 
this section. Any project subject to review under an Administrative 
Agreement duly adopted under paragraph (d) of this section, shall be 
governed by this section and not Sec. Sec.  401.4, 401.5, 401.6, 401.8, 
401.34(a), (c) and (e), 401.37, 401.38 and 18 CFR part 401, subpart F, 
where they are inconsistent with the procedures provided in this 
section.
    (k) No interference with Supreme Court decree. In accordance with 
Sections 3.3(a) and 3.5 of the Compact, nothing in this section shall 
grant the authority to any Signatory Party Agency to impair, diminish 
or otherwise adversely affect the diversions, compensating releases, 
rights, conditions, obligations and provisions for administration 
thereof provided in the United States Supreme Court decree in New 
Jersey v. New York, 347 U.S. 995 (1954) (``Decree''). Any such action 
shall be taken only by the Commission with the unanimous consent of the 
parties to the Decree or upon unanimous consent of the members of the 
Commission following a declaration of a state of emergency in 
accordance with Section 3.3(a) of the Compact.


[[Page 5589]]


    Dated: January 15, 2016.
Pamela M. Bush,
Commission Secretary and Assistant General Counsel.
[FR Doc. 2016-02048 Filed 2-2-16; 8:45 am]
BILLING CODE 6360-01-P



                                                             Federal Register / Vol. 81, No. 22 / Wednesday, February 3, 2016 / Rules and Regulations                                                     5585

                                            February 26, 1979); and (3) does not                          Issued in Washington, DC, on December                     Authority: 49 U.S.C. 106(f), 106(g), 40103,
                                            warrant preparation of a regulatory                         31, 2015.                                                 40106, 40113, 40114, 40120, 44502, 44514,
                                            evaluation as the anticipated impact is                     John S. Duncan,                                           44701, 44719, 44721–44722.
                                            so minimal. For the same reason, the                        Director, Flight Standards Service.
                                                                                                                                                                  ■ 2. Part 97 is amended to read as
                                            FAA certifies that this amendment will                      Adoption of the Amendment                                 follows:
                                            not have a significant economic impact
                                                                                                          Accordingly, pursuant to the
                                            on a substantial number of small entities                                                                             §§ 97.23, 97.25, 97.27, 97.29, 97.31, 97.33,
                                                                                                        authority delegated to me, Title 14,                      97.35 [Amended]
                                            under the criteria of the Regulatory                        Code of Federal Regulations, Part 97, (14
                                            Flexibility Act.                                            CFR part 97), is amended by amending                        By amending: § 97.23 VOR, VOR/
                                            List of Subjects in 14 CFR Part 97                          Standard Instrument Approach                              DME, VOR or TACAN, and VOR/DME
                                                                                                        Procedures and Takeoff Minimums and                       or TACAN; § 97.25 LOC, LOC/DME,
                                               Air Traffic Control, Airports,                           ODPs, effective at 0901 UTC on the                        LDA, LDA/DME, SDF, SDF/DME;
                                            Incorporation by reference, Navigation                      dates specified, as follows:                              § 97.27 NDB, NDB/DME; § 97.29 ILS,
                                            (air).                                                                                                                ILS/DME, MLS, MLS/DME, MLS/RNAV;
                                                                                                        PART 97—STANDARD INSTRUMENT                               § 97.31 RADAR SIAPs; § 97.33 RNAV
                                                                                                        APPROACH PROCEDURES                                       SIAPs; and § 97.35 COPTER SIAPs,
                                                                                                                                                                  Identified as follows:
                                                                                                        ■ 1. The authority citation for part 97
                                                                                                        continues to read as follows:                             * * * Effective Upon Publication

                                               AIRAC date             State                 City                             Airport                 FDC No.      FDC date                   Subject

                                            4–Feb–16 ..........      ID        Blackfoot .....................     McCarley Fld ..............          5/7026         12/7/15   This NOTAM, published in TL
                                                                                                                                                                                   16–03, is hereby rescinded in
                                                                                                                                                                                   its entirety.
                                            4–Feb–16    ..........   TN        Oneida ........................     Scott Muni ...................       5/0865        12/18/15   RNAV (GPS) RWY 5, Amdt 1A.
                                            4–Feb–16    ..........   TN        Oneida ........................     Scott Muni ...................       5/0866        12/18/15   RNAV (GPS) RWY 23, Amdt 1A.
                                            4–Feb–16    ..........   TN        Oneida ........................     Scott Muni ...................       5/0867        12/18/15   VOR/DME–A, Amdt 5B.
                                            4–Feb–16    ..........   ID        Blackfoot .....................     McCarley Fld ..............          5/0898        12/23/15   RNAV (GPS)–A, Orig.
                                            4–Feb–16    ..........   KY        Mount Sterling ............         Mount Sterling-Mont-                 5/2877        12/18/15   RNAV (GPS) RWY 21, Orig-A.
                                                                                                                     gomery County.
                                            4–Feb–16 ..........      KY        Springfield ...................     Lebanon Springfield-                 5/4582        12/18/15   VOR/DME RWY 11, Amdt 4B.
                                                                                                                     George Hoerter
                                                                                                                     Field.
                                            4–Feb–16 ..........      GA        Atlanta .........................   Cobb County-MC                       5/5998        12/18/15   Takeoff Minimums and (Obsta-
                                                                                                                     Collum Field.                                                 cle) DP, Amdt 2.
                                            4–Feb–16 ..........      GA        Atlanta .........................   Cobb County-MC                       5/5999        12/18/15   ILS OR LOC RWY 27, Amdt 4C.
                                                                                                                     Collum Field.
                                            4–Feb–16 ..........      GA        Atlanta .........................   Cobb County-MC                       5/6001        12/18/15   RNAV (GPS) RWY 27, Amdt 4A.
                                                                                                                     Collum Field.
                                            4–Feb–16 ..........      GA        Atlanta .........................   Cobb County-MC                       5/6003        12/18/15   VOR/DME RWY 9, Amdt 2.
                                                                                                                     Collum Field.
                                            4–Feb–16 ..........      NY        New York ....................       Laguardia ....................       5/6013        12/18/15   ILS OR LOC RWY 4, Amdt 36C.
                                            4–Feb–16 ..........      GA        Atlanta .........................   Cobb County-MC                       5/6855        12/18/15   RNAV (GPS) RWY 9, Amdt 3.
                                                                                                                     Collum Field.
                                            4–Feb–16    ..........   AL        Brewton .......................     Brewton Muni ..............          5/7450        12/18/15   RNAV (GPS) RWY 6, Orig.
                                            4–Feb–16    ..........   AL        Brewton .......................     Brewton Muni ..............          5/7451        12/18/15   RNAV (GPS) RWY 24, Orig.
                                            4–Feb–16    ..........   WV        Moundsville .................       Marshall County ..........           5/8483        12/18/15   VOR/DME–A, Amdt 2A.
                                            4–Feb–16    ..........   NJ        Trenton .......................     Trenton Mercer ...........           5/9988        12/22/15   ILS OR LOC RWY 6, Amdt 10A.
                                            4–Feb–16    ..........   NJ        Trenton .......................     Trenton Mercer ...........           5/9989        12/22/15   VOR OR GPS–A, Amdt 11.
                                            4–Feb–16    ..........   NJ        Trenton .......................     Trenton Mercer ...........           5/9990        12/22/15   RNAV (GPS) Z RWY 6, Orig-A.
                                            4–Feb–16    ..........   NJ        Trenton .......................     Trenton Mercer ...........           5/9997        12/22/15   RNAV (GPS) Z RWY 24, Amdt
                                                                                                                                                                                   1A.



                                            [FR Doc. 2016–01858 Filed 2–2–16; 8:45 am]                  DELAWARE RIVER BASIN                                      to provide for the One Process/One
                                            BILLING CODE 4910–13–P                                      COMMISSION                                                Permit Program. The Program is
                                                                                                                                                                  intended to promote interagency
                                                                                                        18 CFR Part 401                                           cooperation and collaboration on shared
                                                                                                                                                                  mission objectives, achieve regulatory
                                                                                                        Amendments to the Rules of Practice                       program efficiencies, avoid unnecessary
                                                                                                        and Procedure To Allow Each                               duplication of effort, and reduce the
                                                                                                        Signatory Party and the Commission                        potential for confusion on the part of
                                                                                                        To Administer a Single Process for the                    regulated entities and the public
                                                                                                        Review and Adjudication of Projects                       regarding regulatory requirements
tkelley on DSK3SPTVN1PROD with RULES




                                                                                                        AGENCY:  Delaware River Basin                             applicable to projects.
                                                                                                        Commission.                                               DATES:This final rule will be effective
                                                                                                        ACTION: Final rule.                                       March 4, 2016.
                                                                                                        SUMMARY:The Delaware River Basin                          FOR FURTHER INFORMATION CONTACT:
                                                                                                        Commission is amending its regulations                    Technical information: David Kovach,


                                       VerDate Sep<11>2014    17:35 Feb 02, 2016   Jkt 238001    PO 00000      Frm 00013     Fmt 4700    Sfmt 4700   E:\FR\FM\03FER1.SGM   03FER1


                                            5586             Federal Register / Vol. 81, No. 22 / Wednesday, February 3, 2016 / Rules and Regulations

                                            609–477–7264. Legal information:                        of the DRBC and each of its Signatory                    • Section 401.42(b) provides that
                                            Pamela Bush, 609–477–7203.                              Parties and effects no change to federal,             applications for approvals required by
                                            SUPPLEMENTARY INFORMATION:                              state or DRBC substantive standards and               the Compact and Commission
                                                                                                    requirements.                                         regulations, but not within the scope of
                                            Background                                                In accordance with this final rule,                 the Program, must continue to be
                                               The Delaware River Basin                             administrative agreements between                     submitted to the Commission.
                                            Commission (‘‘DRBC’’ or                                 DRBC and Signatory Party agencies to                     • To ensure continued public access
                                            ‘‘Commission’’) is a federal-interstate                 implement the Program may be                          to information on the status of all
                                            compact agency charged with managing                    approved by the Commission after each                 projects under review pursuant to the
                                            the water resources of the Delaware                     such agreement undergoes a duly                       Delaware River Basin Compact,
                                            River Basin on a regional basis without                 noticed public hearing. In accordance                 including those administered under One
                                            regard to political boundaries. Its                     with Resolution No. 2015–4 of the                     Permit, § 401.42(d)(2) establishes that
                                            members are the governors of the four                   Commission, which was adopted on                      participating Signatory Party agencies
                                            basin states—Delaware, New Jersey,                      March 11, 2015 following a public                     will notify DRBC at least once monthly
                                            New York and Pennsylvania—and the                       hearing on March 10, 2015, an                         of applications received under the
                                            North Atlantic Division Commander of                    administrative agreement between the                  Program; and § 401.42(d)(5) establishes
                                            the U.S. Army Corps of Engineers,                       DRBC and the New Jersey Department of                 that the list that the Commission will
                                            representing the federal government.                    Environmental Protection (NJDEP) was                  maintain of projects being administered
                                               Specifically, this final rule amends                 executed, in part to demonstrate how                  under One Permit will be posted on the
                                            subchapter A—Administrative Manual,                     the Program would operate in New                      Commission’s Web site.
                                            part 401—Rules of Practice and                          Jersey. With adoption of the final rule,                 • Section 401.42(h) provides that
                                            Procedure, subpart C—Project Review                     DRBC and NJDEP will fully implement                   DRBC’s current Project Review Fee
                                            Under Section 3.8 of the Compact by the                 their March 2015 agreement.                           Schedule as set forth in Resolution No.
                                            addition of a new section 401.42,                         Notably, each Signatory Party may                   2009–2 will be the operative fee
                                            providing for DRBC and each of the                      choose whether and when to initiate an                schedule for projects reviewed under
                                            parties to the Delaware River Basin                     agreement or agreements with DRBC                     the Program.
                                            Compact (United States Pub. L. 87–328,                  under the Program. No draft agreements                   • Section 401.42(i) provides
                                            Approved September 27, 1961, 75 U.S.                    with Signatory Party agencies other than              mechanisms for the efficient disposition
                                            Statutes at Large 688; 53 Delaware Laws,                the NJDEP to implement the Program                    of Commission dockets during the
                                            Chapter 71, Approved May 26, 1961;                      have yet been published for comment.                  transition to One Permit. Section
                                            New Jersey Laws of 1961, Chapter 13,                                                                          401.42(i)(1) provides that for projects
                                            Approved May 1, 1961; New York Laws                     Procedural Background                                 covered by the Program, the most recent
                                            of 1961, Chapter 148, Approved March                       The Commission introduced One                      docket will be deemed administratively
                                            17, 1961; and Pennsylvania Acts of                      Permit to the basin community during                  continued when a renewal application
                                            1961, Act No. 268, Approved July 7,                     meetings with regulated entities,                     is timely submitted to the Signatory
                                            1961 (‘‘the Compact’’))—Delaware, New                   environmental organizations and other                 Party Agency. Section 401.42(i)(2)
                                            Jersey, New York, Pennsylvania and the                  stakeholders on February 12 and March                 provides that unless the Executive
                                            federal government (‘‘Signatory                         3, 2015 and through publication on the                Director or the Commission otherwise
                                            Parties’’)—to coordinate and collaborate                DRBC Web site of a press release and a                directs, upon the Signatory Party
                                            in the administration of a single process               set of FAQs on February 27, 2015.                     Agency’s final action on an application
                                            for the review and adjudication of                      During the Commission’s quarterly                     for a project subject to the Program, (a)
                                            certain projects, including, where                      public meeting on March 10–11, 2015,                  any existing or administratively
                                            appropriate, issuance of a single permit                the Commission approved Resolution                    continued docket will terminate as to all
                                            or other approval instrument.                           No. 2015–4, in part authorizing and                   of its provisions and conditions within
                                               Currently, the sponsors of many water                directing the Executive Director to                   the scope of the Signatory Party Agency
                                            resource-related projects in the                        initiate rulemaking to amend DRBC’s                   approval; and (b) such docket will
                                            Delaware River Basin are required to                    Rules of Practice and Procedure to                    continue in effect as to any provisions
                                            apply to both the DRBC and a state                      provide specific authorization for and                and conditions outside the scope of the
                                            agency, among others, for approvals.                    define the scope of the Program. Notice               Signatory Party Agency approval,
                                            New section 401.42 provides for the                     of the proposed amendments was                        including for example, addition of a
                                            DRBC and the administrative agencies                    published on the Commission’s Web                     project to the Comprehensive Plan.
                                            of the Signatory Parties to identify                    site on May 17, 2015.                                    • The rule authorizes Signatory Party
                                            regulatory programs that by mutual                         Notice of the proposed amendments                  agencies, in accordance with an
                                            agreement will be managed through a                     also appeared in the Federal Register at              applicable administrative agreement, to
                                            single process that may result in one                   80 FR 28567, May 19, 2015; in the                     issue in their approvals for projects to
                                            decision or approval. The program,                      Delaware Register of Regulations, 18 DE               be administered under the Program the
                                            known as One Process/One Permit                         Reg. 1002, June 1, 2015; New Jersey                   finding and determination required by
                                            (hereinafter, ‘‘the Program or ‘‘One                    Register, 47 N.J.R. 1256, June 1, 2015;               section 3.8 of the Compact that a project
                                            Permit’’) is intended to promote                        New York State Register, May 27, 2015                 subject to section 3.8 review does not
                                            interagency cooperation and                             (page 4); and Pennsylvania Bulletin, 45               substantially impair or conflict with the
                                            collaboration on shared mission                         Pa. B. 2611, May 30, 2015. The                        Commission’s Comprehensive Plan
                                            objectives, achieve regulatory program                  Commission held a public hearing on                   (‘‘the finding’’). Section 401.42(d)(4)
                                            efficiencies, avoid unnecessary                         the proposal on June 9, 2015 and                      makes clear that where in accordance
tkelley on DSK3SPTVN1PROD with RULES




                                            duplication of effort, and reduce the                   accepted written comments on the rule                 with an applicable administrative
                                            potential for confusion on the part of                  through July 1, 2015.                                 agreement implementing One Permit the
                                            regulated entities and the public                                                                             finding continues to be made by the
                                            regarding regulatory requirements                       Rule Highlights                                       Commission, the Signatory Party agency
                                            applicable to projects. Importantly, the                  Notable aspects of the final rule                   may include the Commission’s finding
                                            rule expressly preserves the authorities                include the following:                                in the agency’s approval, together with


                                       VerDate Sep<11>2014   17:35 Feb 02, 2016   Jkt 238001   PO 00000   Frm 00014   Fmt 4700   Sfmt 4700   E:\FR\FM\03FER1.SGM   03FER1


                                                                 Federal Register / Vol. 81, No. 22 / Wednesday, February 3, 2016 / Rules and Regulations                                                                            5587

                                            any conditions identified by the                                           www.drbc.net. These include DRBC                                         posted on DRBC’s Web site at http://
                                            Commission as necessary to support it,                                     Resolution No. 2015–9 approving the                                      www.nj.gov/drbc/library/documents/
                                            thereby achieving a unified permit.                                        final rule, at http://www.nj.gov/drbc/                                   admin_manual.pdf uses DRBC’s
                                              • The final rule also makes clear (1)                                    library/documents/Res2015-09_                                            original numbering system, which is
                                            that participation in the program by                                       OPOPwith-final-rule-text.pdf; and the                                    different from that of the CFR. In the
                                            Signatory Party agencies is voluntary;                                     Commission’s detailed comment and                                        original system, the One Permit Program
                                            and (2) that the scope of a Signatory                                      response document, which identifies                                      rules are set forth at new section 2.3.11.
                                            Party Agency’s participation is defined                                    commenters, summarizes comments                                          A list of the CFR units and
                                            by an administrative agreement between
                                                                                                                       received on the proposal, and sets forth                                 corresponding DRBC units follows. A
                                            DRBC and the agency that has been duly
                                                                                                                       the Commission’s responses, at http://                                   complete stand-alone version of the
                                            adopted in accordance with § 401.42(d).
                                                                                                                       www.nj.gov/drbc/library/documents/                                       Rules of Practice and Procedure using
                                            Additional Materials                                                       OPOP/comment-and-response_                                               the CFR system will be available on the
                                              Additional materials can be found on                                     OPOP.pdf. The version of the Rules of                                    DRBC Web site shortly.
                                            the Commission’s Web site at                                               Practice and Procedure that is currently

                                                                        CFR Unit                                                                 DRBC Unit                                                     Title or Caption

                                            Title 18 Conservation of Power and Water Re-
                                               sources.
                                            Chapter III—Delaware River Basin Commission.
                                            Subchapter A—Administrative Manual ...............                         Administrative Manual [Part II]
                                            Part 401—Rules of Practice and Procedure ......                            Rules of Practice and Procedure
                                            Subpart C—Project Review Under Section 3.8                                 Article 3—Project Review Under Section 3.8
                                               of the Compact.                                                           of the Compact.
                                            401.42 .................................................................   2.3.11 ...............................................................   One Permit Program.
                                            401.42(a) ............................................................     2.3.11 A ............................................................    Purpose.
                                            401.42(b) ............................................................     2.3.11 B ............................................................    Scope.
                                            401.42(c) ............................................................     2.3.11 C ...........................................................     Regulatory programs.
                                            401.42(d) ............................................................     2.3.11 D ...........................................................     Procedure.
                                            401.42(e) ............................................................     2.3.11 E ............................................................    Comprehensive Plan projects.
                                            401.42(f) .............................................................    2.3.11 F ............................................................    Retention of Commission review and enforce-
                                                                                                                                                                                                  ment authorities.
                                            401.42(g) ............................................................     2.3.11 G ...........................................................     Exhaustion of Signatory Party administrative
                                                                                                                                                                                                  remedies prerequisite to appeal.
                                            401.42(h) ............................................................     2.3.11 H ...........................................................     Fees.
                                            401.42(i) .............................................................    2.3.11 I .............................................................   Effect of One Permit Program on Commission
                                                                                                                                                                                                  dockets.
                                            401.42(j) .............................................................    2.3.11 J ............................................................    Modification of Rules of Practice and Proce-
                                                                                                                                                                                                  dure to conform to this section.
                                            401.42(k) ............................................................     2.3.11 K ............................................................    No interference with Supreme Court decree.



                                            List of Subjects in 18 CFR Part 401                                        administrative agency of a Signatory                                     section. For any project that requires an
                                              Administrative practice and                                              Party (‘‘Signatory Party Agency’’) and                                   approval under the Compact that is
                                            procedure, Project review, Water                                           the Commission to coordinate and                                         outside the scope of the Signatory Party
                                            pollution control, Water resources.                                        collaborate in the administration of a                                   Agency’s approval issued in accordance
                                                                                                                       single process for the review and                                        with an Administrative Agreement
                                              For the reasons set forth in the                                         adjudication of projects. The One Permit                                 under this section, the project sponsor
                                            preamble, the Delaware River Basin                                         Program allows the Signatory Party                                       shall apply to the Commission in
                                            Commission amends part 401 of title 18                                     Agency and Commission to incorporate                                     accordance with procedures established
                                            of the Code of Federal Regulations as                                      requirements and determinations of                                       by the Commission.
                                            follows:                                                                   both entities in a single permit or other                                  (c) Regulatory programs. Regulatory
                                                                                                                       approval instrument, pursuant to a duly                                  programs eligible for administration
                                            PART 401—RULES OF PRACTICE AND
                                                                                                                       adopted Administrative Agreement                                         under the One Permit Program may
                                            PROCEDURE
                                                                                                                       under paragraph (d) of this section.                                     include but are not limited to those
                                            ■ 1. The authority citation for part 401                                     (b) Scope. This section applies to all                                 concerning: Basin discharges, Basin
                                            continues to read as follows:                                              projects that:                                                           water withdrawals, and Basin flood
                                                                                                                         (1) Are reviewable under the                                           plain requirements.
                                              Authority: Delaware River Basin Compact                                                                                                             (d) Procedure. The categories of
                                                                                                                       Compact;
                                            (75 Stat. 688), unless otherwise noted.
                                                                                                                         (2) Meet the thresholds for review set                                 projects covered and the procedures for
                                            Subpart C—Project Review Under                                             forth in § 401.35 of these Rules of                                      processing applications under the One
                                            Section 3.8 of the Compact                                                 Practice and Procedure;                                                  Permit Program shall be set forth in one
                                                                                                                         (3) Are subject to review by a                                         or more Administrative Agreements
                                            ■   2. Add § 401.42 to read as follows:                                    Signatory Party Agency under its own                                     between the Commission and the
tkelley on DSK3SPTVN1PROD with RULES




                                                                                                                       statutory authorities; and                                               Signatory Party Agency that have been
                                            § 401.42       One Permit Program.                                           (4) Are within regulatory programs                                     adopted by the Commission following a
                                               (a) Purpose. The purpose of the One                                     that have been identified in a duly                                      duly noticed public hearing and are in
                                            Permit Program set forth in this section                                   adopted Administrative Agreement                                         form and substance acceptable to the
                                            is to provide the opportunity for the                                      between the Commission and a                                             Commission and the Signatory Party
                                            environmental agency and/or other                                          Signatory Party Agency under this                                        Agency, consistent with the following:


                                       VerDate Sep<11>2014        17:35 Feb 02, 2016         Jkt 238001      PO 00000       Frm 00015       Fmt 4700       Sfmt 4700      E:\FR\FM\03FER1.SGM         03FER1


                                            5588             Federal Register / Vol. 81, No. 22 / Wednesday, February 3, 2016 / Rules and Regulations

                                               (1) Except as provided in paragraphs                 project not yet included in the                         (i) Effect of One Permit Program on
                                            (b) and (e) of this section or in an                    Comprehensive Plan, the project                       Commission dockets.
                                            Administrative Agreement that has been                  sponsor shall submit a separate                         (1) Unless the Executive Director or
                                            duly executed by the Commission and                     application to the Commission. If                     Commission otherwise directs, if a
                                            the Signatory Party Agency under this                   following its review and public hearing               docket holder submits, or has
                                            section, an application for initial                     the Commission approves the addition
                                                                                                                                                          submitted, a timely application to a
                                            approval, renewal or revision of any                    of the project to the Comprehensive
                                                                                                                                                          Signatory Party Agency for a project
                                            project subject to the One Permit                       Plan, the Commission’s approval will
                                            Program shall be filed only with the                    include such project requirements as are              subject to review under an
                                            Signatory Party Agency.                                 necessary under the Compact and                       Administrative Agreement duly adopted
                                               (2) To enable the Commission to                      Commission regulations. All other                     under paragraph (d) of this section, the
                                            compile and make available to the                       project approvals that may be required                most recent docket for the project shall,
                                            public a current list of pending                        from the Signatory Party Agency or the                upon expiration, be deemed
                                            applications for projects within the                    Commission under regulatory programs                  administratively continued until final
                                            Basin subject to Commission                             administered pursuant to this section                 action is taken in accordance with
                                            jurisdiction, the Signatory Party Agency                may be issued through the One Permit                  paragraph (i)(2) of this section.
                                            shall notify the Commission at least                    Program. An application for renewal or                  (2) Unless the Executive Director or
                                            monthly of applications the Signatory                   modification of a project in the                      Commission otherwise directs, upon a
                                            Party has received during the preceding                 Comprehensive Plan that does not                      Signatory Party Agency’s final action on
                                            month that may be eligible for review                   change the project so substantially as to             an application for a project subject to
                                            under the One Permit Program.                           render it a new and different project                 the One Permit Program:
                                               (3) For those categories of projects                 may be submitted only to the Signatory
                                            identified in the Administrative                        Party Agency unless otherwise specified                 (i) Any existing or administratively
                                            Agreement as requiring Commission                       in the Administrative Agreement.                      continued docket for such project shall
                                            input, the Commission staff shall                          (f) Retention of Commission review                 terminate as to all of its provisions and
                                            provide the Signatory Party Agency                      and enforcement authorities.                          conditions that pertain to regulatory
                                            with such input, including where                        Notwithstanding any other provision of                programs administered by the Signatory
                                            specified by the Administrative                         this section, any Commissioner or the                 Party Agency under the Administrative
                                            Agreement, a recommendation as to any                   Executive Director may designate for                  Agreement (‘‘the Covered Programs’’);
                                            conditions of approval that may be                      Commission review any project that is                 and
                                            necessary or appropriate to include in                  reviewable under the Compact. Nothing                   (ii) The docket shall continue in effect
                                            the project review determination under                  in this section shall limit the authority             as to any provisions and conditions not
                                            Section 3.8 of the Compact as to those                  of the Commission to exercise its review              pertaining only to Covered Programs,
                                            regulatory programs identified in an                    authority under the Compact and                       including, as applicable, the
                                            Administrative Agreement in                             applicable Commission regulations.                    incorporation of the project in the
                                            accordance with paragraph (b) of this                   Similarly, although Administrative                    Commission’s Comprehensive Plan.
                                            section.                                                Agreements executed pursuant to this
                                               (4) Unless the Signatory Party Agency                section may include collaborative and                   (j) Modification of rules of practice
                                            disapproves the project or the                          cooperative compliance and                            and procedure to conform to this
                                            Administrative Agreement provides for                   enforcement procedures, nothing in this               section. Any project subject to review
                                            separate Commission action under                        section shall limit the authority of the              under an Administrative Agreement
                                            Section 3.8 of the Compact, the                         Commission to exercise its enforcement                duly adopted under paragraph (d) of
                                            Signatory Party Agency shall make the                   authority under the Compact and                       this section, shall be governed by this
                                            project review determination under                      applicable regulations.                               section and not §§ 401.4, 401.5, 401.6,
                                            Section 3.8 of the Compact, as specified                   (g) Exhaustion of Signatory Party                  401.8, 401.34(a), (c) and (e), 401.37,
                                            in the Administrative Agreement, as to                  administrative remedies prerequisite to               401.38 and 18 CFR part 401, subpart F,
                                            the regulatory program covered by the                   appeal. Before commencing an action in                where they are inconsistent with the
                                            Signatory Party Agency’s approval and                   a court of appropriate jurisdiction                   procedures provided in this section.
                                            include the determination and any                       challenging any final action taken by a                 (k) No interference with Supreme
                                            associated conditions of approval                       Signatory Party Agency under this
                                                                                                                                                          Court decree. In accordance with
                                            within the permit or other approval                     section, the appellant must first exhaust
                                                                                                                                                          Sections 3.3(a) and 3.5 of the Compact,
                                            instrument that it issues to the project                its administrative remedies under the
                                                                                                                                                          nothing in this section shall grant the
                                            sponsor. If in accordance with the                      law of the Signatory Party whose agency
                                                                                                    issued the decision at issue.                         authority to any Signatory Party Agency
                                            applicable Administrative Agreement
                                                                                                       (h) Fees. The Commission shall                     to impair, diminish or otherwise
                                            the determination under Section 3.8 of
                                            the Compact is made by the                              establish and maintain a schedule of                  adversely affect the diversions,
                                            Commission, the Signatory Party                         fees for any or all of the services it                compensating releases, rights,
                                            Agency may include the determination                    renders pursuant to this section. The                 conditions, obligations and provisions
                                            together with any associated conditions                 applicable fee(s) for Commission                      for administration thereof provided in
                                            of approval in its permit or other                      services rendered pursuant to this                    the United States Supreme Court decree
                                            approval instrument covering the                        section shall be those set forth in DRBC              in New Jersey v. New York, 347 U.S. 995
                                            project.                                                Resolution No. 2009-2 (available at                   (1954) (‘‘Decree’’). Any such action shall
                                               (5) The Commission will maintain on                  http://www.nj.gov/drbc/library/                       be taken only by the Commission with
tkelley on DSK3SPTVN1PROD with RULES




                                            its Web site a list of all projects being               documents/Res2009-2.pdf) for the                      the unanimous consent of the parties to
                                            administered pursuant to the Program.                   review and renewal of project                         the Decree or upon unanimous consent
                                               (e) Comprehensive Plan projects.                     approvals. Project sponsors shall pay                 of the members of the Commission
                                            Articles 11 and 13 of the Compact                       such fees, if any, directly to the                    following a declaration of a state of
                                            require certain projects to be included                 Commission in accordance with the                     emergency in accordance with Section
                                            in the Comprehensive Plan. To add a                     current schedule and applicable rules.                3.3(a) of the Compact.


                                       VerDate Sep<11>2014   17:35 Feb 02, 2016   Jkt 238001   PO 00000   Frm 00016   Fmt 4700   Sfmt 4700   E:\FR\FM\03FER1.SGM   03FER1


                                                             Federal Register / Vol. 81, No. 22 / Wednesday, February 3, 2016 / Rules and Regulations                                        5589

                                              Dated: January 15, 2016.                              names for specific FDA offices. The                   172.864, 172.886, 173.375, 177.1345,
                                            Pamela M. Bush,                                         amendments are as follows:                            177.1585, 177.1637, 178.1010, 184.1007,
                                            Commission Secretary and Assistant General                 • We are revising §§ 73.165, 73.585,               184.1257, 184.1259, 184.1282, 184.1293,
                                            Counsel.                                                165.110, and 173.300 to update the                    184.1472, 184.1530, 184.1699, 184.1979,
                                            [FR Doc. 2016–02048 Filed 2–2–16; 8:45 am]              library address from ‘‘Center for Food                184.1979a, 184.1979b, and 184.1979c to
                                            BILLING CODE 6360–01–P
                                                                                                    Safety and Applied Nutrition’s Library,               update the library address from ‘‘Center
                                                                                                    5100 Paint Branch Pkwy., College Park,                for Food Safety and Applied Nutrition’s
                                                                                                    MD’’ to ‘‘Food and Drug                               Library, Food and Drug Administration,
                                                                                                    Administration’s Main Library, 10903                  5100 Paint Branch Pkwy., College Park,
                                            DEPARTMENT OF HEALTH AND                                New Hampshire Ave., Bldg. 2, Third                    MD 20740’’ to ‘‘Food and Drug
                                            HUMAN SERVICES                                          Floor, Silver Spring, MD 20993, 301–                  Administration’s Main Library, 10903
                                                                                                    796–2039’’.                                           New Hampshire Ave., Bldg. 2, Third
                                            Food and Drug Administration                               • We are revising §§ 101.4,                        Floor, Silver Spring, MD 20993, 301–
                                                                                                    101.81(c)(2)(ii)(A) introductory text and             796–2039’’.
                                            21 CFR Parts 73, 101, 118, 165, 172,                    (B)(1) and (2), 101.83, 165.110, 172.155,
                                            173, 177, 178, 184, 189, 589, and 700                                                                            • We are revising §§ 172.167 and
                                                                                                    172.785, 172.833, 173.25, 173.45,                     173.356 to update the library address
                                                                                                    173.340, 173.357, 173.370, 177.1350,                  from ‘‘Center for Food Safety and
                                            [Docket No. FDA–2015–N–0011]
                                                                                                    177.1360, 177.1390, 177.1520, 177.2600,               Applied Nutrition’s Library, Food and
                                            Center for Food Safety and Applied                      178.3297, 184.1063, 184.1148, 184.1150,               Drug Administration, 5100 Paint Branch
                                            Nutrition Library Address; Technical                    184.1250, 184.1387, 184.1420, 184.1444,               Pkwy., College Park, MD 20740, 301–
                                            Amendments                                              184.1866, 189.5, 589.2001, and 700.27                 436–2163’’ to ‘‘Food and Drug
                                                                                                    to update the library address from                    Administration’s Main Library, 10903
                                            AGENCY:    Food and Drug Administration,                ‘‘Center for Food Safety and Applied                  New Hampshire Ave., Bldg. 2, Third
                                            HHS.                                                    Nutrition’s Library, 5100 Paint Branch                Floor, Silver Spring, MD 20993, 301–
                                                  Final rule; technical
                                            ACTION:                                                 Pkwy., College Park, MD 20740’’ to                    796–2039’’.
                                                                                                    ‘‘Food and Drug Administration’s Main
                                            amendments.                                                                                                      • We are revising § 172.736 to update
                                                                                                    Library, 10903 New Hampshire Ave.,
                                                                                                                                                          the library address from ‘‘in the library
                                            SUMMARY:   The Food and Drug                            Bldg. 2, Third Floor, Silver Spring, MD
                                                                                                                                                          at the Center for Food Safety and
                                            Administration (FDA or we) is                           20993, 301–796–2039’’.
                                                                                                       • We are revising § 101.80 to update               Applied Nutrition, 5100 Paint Branch
                                            amending certain regulations to update
                                                                                                    the library address from ‘‘Center for                 Pkwy., College Park, MD 20740’’ to ‘‘at
                                            the location of references cited in our
                                                                                                    Food Safety and Applied Nutrition’s                   the Food and Drug Administration’s
                                            food regulations. We are taking this
                                                                                                    Library, Harvey W. Wiley Federal                      Main Library, 10903 New Hampshire
                                            action to reflect the transfer of those
                                                                                                    Building, 5100 Paint Branch Pkwy.,                    Ave., Bldg. 2, Third Floor, Silver Spring,
                                            references from our facility in College
                                                                                                    College Park, MD’’ to ‘‘Food and Drug                 MD 20993, 301–796–2039’’.
                                            Park, MD, to our library at our main
                                                                                                    Administration’s Main Library, 10903                     • We are revising § 172.829 to update
                                            campus in Silver Spring, MD. We also
                                                                                                    New Hampshire Ave., Bldg. 2, Third                    the library address from ‘‘Center for
                                            are updating certain regulations to
                                                                                                    Floor, Silver Spring, MD 20993, 301–                  Food Safety and Applied Nutrition’s
                                            reflect the current names for specific
                                                                                                    796–2039’’.                                           Library, 5100 Paint Branch Pkwy., rm.
                                            FDA offices.
                                                                                                       • We are revising                                  1C–100, College Park, MD 20740’’ to
                                            DATES: This rule is effective February 3,                                                                     ‘‘Food and Drug Administration’s Main
                                            2016.                                                   § 101.81(c)(2)(ii)(A)(5) to update the
                                                                                                    library address from ‘‘Center for Food                Library, 10903 New Hampshire Ave.,
                                            FOR FURTHER INFORMATION CONTACT:                                                                              Bldg. 2, Third Floor, Silver Spring, MD
                                                                                                    Safety and Applied Nutrition Library,
                                            Philip L. Chao, Center for Food Safety                  5100 Paint Branch Pkwy., College Park,                20993, 301–796–2039’’.
                                            and Applied Nutrition (HFS–024), Food                   MD 20740’’ to ‘‘Food and Drug                            • We are revising § 173.325 to update
                                            and Drug Administration, 5100 Paint                     Administration’s Main Library, 10903                  the library address from ‘‘Center for
                                            Branch Pkwy., College Park, MD 20740–                   New Hampshire Ave., Bldg. 2, Third                    Food Safety and Applied Nutrition’s
                                            3835, 240–402–2112.                                     Floor, Silver Spring, MD 20993, 301–                  Library, 5100 Paint Branch Pkwy.,
                                            SUPPLEMENTARY INFORMATION: Various                      796–2039’’.                                           College Park, MD 20740 20204–0001’’ to
                                            regulations pertaining to human food                       • We are revising §§ 118.8 and                     ‘‘Food and Drug Administration’s Main
                                            have incorporated materials by                          165.110 to update the library address                 Library, 10903 New Hampshire Ave.,
                                            reference. In general, the regulations                  from ‘‘Center for Food Safety and                     Bldg. 2, Third Floor, Silver Spring, MD
                                            have identified a library at the Center                 Applied Nutrition’s Library, 5100 Paint               20993, 301–796–2039’’.
                                            for Food Safety and Applied Nutrition                   Branch Pkwy., College Park, MD, 301–                     • We are revising § 184.1311 to
                                            (CFSAN), which was (at the time the                     436–2163’’ to ‘‘Food and Drug                         update the library address from ‘‘Center
                                            regulations were published) located in                  Administration’s Main Library, 10903                  for Food Safety and Applied Nutrition’s
                                            Washington, DC, or in College Park, MD.                 New Hampshire Ave., Bldg. 2, Third                    library, 5100 Paint Branch Pkwy.,
                                            We recently consolidated our library                    Floor, Silver Spring, MD 20993, 301–                  College Park, MD 20740’’ to ‘‘Food and
                                            holdings at our main campus in Silver                   796–2039’’.                                           Drug Administration’s Main Library,
                                            Spring, MD. Consequently, we are                           • We are revising § 165.110 to update              10903 New Hampshire Ave., Bldg. 2,
                                            making technical amendments to our                      the library address from ‘‘Center for                 Third Floor, Silver Spring, MD 20993,
                                            regulations at parts 73, 101, 118, 165,                 Food Safety and Applied Nutrition’s                   301–796–2039’’.
                                            172, 173, 177, 178, 184, 189, 589, and                  Library, 200 C St. NW., Washington DC’’                  • We are revising
tkelley on DSK3SPTVN1PROD with RULES




                                            700 (21 CFR parts 73, 101, 118, 165,                    to ‘‘Food and Drug Administration’s                   § 101.83(c)(2)(ii)(A)(2) and
                                            172, 173, 177, 178, 184, 189, 589, and                  Main Library, 10903 New Hampshire                     (c)(2)(ii)(B)(2), to remove the words
                                            700) to state that the materials can be                 Ave., Bldg. 2, Third Floor, Silver Spring,            ‘‘Office of Nutritional Products,
                                            found at the FDA Library in Silver                      MD 20993, 301–796–2039’’.                             Labeling, and Dietary Supplements,
                                            Spring, MD. We also are updating                           • We are revising §§ 165.110,                      Division of Nutrition Science and
                                            certain regulations to reflect the current              172.723, 172.736, 172.804, 172.809,                   Policy,’’ and in their place add ‘‘Office


                                       VerDate Sep<11>2014   17:35 Feb 02, 2016   Jkt 238001   PO 00000   Frm 00017   Fmt 4700   Sfmt 4700   E:\FR\FM\03FER1.SGM   03FER1



Document Created: 2016-02-03 00:40:11
Document Modified: 2016-02-03 00:40:11
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionFinal rule.
DatesThis final rule will be effective March 4, 2016.
ContactTechnical information: David Kovach, 609-477-7264. Legal information: Pamela Bush, 609-477-7203.
FR Citation81 FR 5585 
CFR AssociatedAdministrative Practice and Procedure; Project Review; Water Pollution Control and Water Resources